1
Above: Energy deposition in the superconducting magnet and the tungsten- carbide shield inside them. Approximately 2.4 MW must be dissipated in the shield. See also THPEC092. Above: A major challenge is incorporation of the Inside the superconducting magnet cryostat. The pool can serve as this dump. A 4-MW TARGET STATION FOR A MUON COLLIDER OR NEUTRINO FACTORY (WEPE101, IPAC10) While the principle of a liquid-metal jet target inside a 20-T solenoid has been validated by the MERIT experiment (WEPE101) for beam pulses equivalent to 4-MW beam power at 50 Hz, substantial effort is still required to turn this concept into a viable engineering design. We are embarking on a several-year program of simulation and technical design for a 4-MW target station in preparation for the Muon Collider Design Feasibility Study and the International Design Study for a Neutrino Factory. Above: Baseline Parameters for the target system. Concept of a continuous mercury jet target for an intense proton beam. The jet and beam are tilted by ~ 100 mrad and ~ 70 mrad, respectively, with respect to a 20-T solenoid magnet that conducts low-momentum pions into a decay channel. H.G. Kirk,* BNL, Upton, NY 11973, USA X. Ding, UCLA, Los Angeles, CA 90095, USA V.B. Graves, ORNL, Oak Ridge, TN 37831, USA K.T. McDonald, Princeton University, Princeton, NJ 08544, USA C.J. Densham, P. Loveridge, RAL, Chilton, OX11 0QX, UK F. Ladeinde, Y. Zhan , SUNY Stony Brook, Stony Brook, NY 11794, USA J.J. Back, U. Warwick, Coventry CV4 7AL, UK Above : The major cost driver of the target system is the civil construction of the target vault – with hot cells and remote handling manipulators. Above: Splash mitigation options for the mercury collection pool/beam dump, which will be disrupted by both the proton beam and mercury jet. Iron Plug Proton Beam Nozzle Tube SC-1 SC-2 SC-3 SC-4 SC-5 Window Mercury Drain Mercury Pool Water-cooled Tungsten Shield Mercury Jet Resistive Magnet Splash Mitigator Item Neutrino Factory IDS / Muon Collider Comments Beam Power 4 MW No existing target system will survive at this power E p 8 GeV yield for fixed beam power peaks at ~ 8 GeV Rep Rate 50 Hz Lower rep rate could be favorable Bunch width ~ 3 ns Very challenging for proton driver Bunches/pulse 3 3-ns bunches easier if 3 bunches per pulse Bunch spacing ~ 100 s Disruption of liquid target takes longer than 200 s Beam dump < 5 m from target Very challenging for target system Capture system 20-T Solenoid High field solenoid “cools” rms emittance Capture energy 40 < T < 300 MeV Much lower energy than for Superbeams Target geometry Free liquid jet Moving target, replaced every pulse Target velocity 20 m/s Target moves by 50 cm ~ 3 int. lengths per pulse Target material Hg High-Z favored; could also be Pb-Bi eutectic Target radius 4 mm Proton beam r = 0.3 of target radius = 1.2 mm Beam angle 80 mrad Thin target at angle to capture axis maximizes ’s Jet angle 100 mrad Beam/jet angle 30 mrad, 2 int. lengths Dump material Hg Hg pool serves as dump and jet collector Magnet shield W-C beads + water Shield must dissipate 2.4 MW; could be Hg (See also THPEC092) 0 30 60 90 120 120 cm 0 300 600 600 cm 10 −3 10 −4 10 −5 10 −6 10 −7 10 −8 10 −9 10 −10 10 −11 10 −12 10 −13 10 −14 10 −15 10 −16 10 −17 10 −18 10 −19 4.2e−04 0

Above: Energy deposition in the superconducting magnet and the tungsten-carbide shield inside them. Approximately 2.4 MW must be dissipated in the shield

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Above: Energy deposition in the superconducting magnet and the tungsten-carbide shield inside them. Approximately 2.4 MW must be dissipated in the shield

Above: Energy deposition in the superconducting magnet and the tungsten-carbide shield inside them. Approximately 2.4 MW must be dissipated in the shield. See also THPEC092.

Above: A major challenge is incorporation of the proton beam dumpInside the superconducting magnet cryostat. The mercury collectionpool can serve as this dump.

A 4-MW TARGET STATION FOR A MUON COLLIDEROR NEUTRINO FACTORY

(WEPE101, IPAC10)

While the principle of a liquid-metal jet target inside a 20-T solenoid has been validated by the MERIT experiment (WEPE101) for beam pulses equivalent to 4-MW beam power at 50 Hz, substantial effort is still required to turn this concept into a viable engineering design.We are embarking on a several-year program of simulation and technical design for a 4-MW target station in preparation for the Muon Collider Design Feasibility Study and the International Design Study for a Neutrino Factory.

Above: Baseline Parameters for the target system.

Concept of a continuous mercury jet target for an intense proton beam. The jet and beam are tilted by ~ 100 mrad and ~ 70 mrad, respectively, with respect to a 20-T solenoid magnet that conducts low-momentum pions into a decay channel.

H.G. Kirk,* BNL, Upton, NY 11973, USAX. Ding, UCLA, Los Angeles, CA 90095, USA

V.B. Graves, ORNL, Oak Ridge, TN 37831, USAK.T. McDonald, Princeton University, Princeton, NJ 08544, USA

C.J. Densham, P. Loveridge, RAL, Chilton, OX11 0QX, UKF. Ladeinde, Y. Zhan , SUNY Stony Brook, Stony Brook, NY 11794, USA

J.J. Back, U. Warwick, Coventry CV4 7AL, UK

Above : The major cost driver of the target system is the civil construction of the target vault – with hot cells and remote handling manipulators.

Above: Splash mitigation options for the mercury collection pool/beam dump, which will be disrupted by both the proton beam and mercury jet.

IronPlug

ProtonBeam

NozzleTube

SC-1 SC-2 SC-3 SC-4 SC-5Window

MercuryDrain

MercuryPool

Water-cooledTungsten Shield

MercuryJet

ResistiveMagnet

SplashMitigator

Item Neutrino Factory IDS / Muon Collider

Comments

Beam Power 4 MW No existing target system will survive at this power

Ep 8 GeV yield for fixed beam power peaks at ~ 8 GeV

Rep Rate 50 Hz Lower rep rate could be favorable

Bunch width ~ 3 ns Very challenging for proton driver

Bunches/pulse 3 3-ns bunches easier if 3 bunches per pulse

Bunch spacing ~ 100 s Disruption of liquid target takes longer than 200 s

Beam dump < 5 m from target Very challenging for target system

Capture system 20-T Solenoid High field solenoid “cools” rms emittance

Capture energy 40 < T < 300 MeV Much lower energy than for Superbeams

Target geometry Free liquid jet Moving target, replaced every pulse

Target velocity 20 m/s Target moves by 50 cm ~ 3 int. lengths per pulse

Target material Hg High-Z favored; could also be Pb-Bi eutectic

Target radius 4 mm Proton beam r = 0.3 of target radius = 1.2 mm

Beam angle 80 mrad Thin target at angle to capture axis maximizes ’s

Jet angle 100 mrad Beam/jet angle 30 mrad, 2 int. lengths

Dump material Hg Hg pool serves as dump and jet collector

Magnet shield W-C beads + water

Shield must dissipate 2.4 MW; could be Hg

(See also THPEC092)

0

30

60

90

120120

cm

0 300 600600cm

10−3

10−4

10−5

10−6

10−7

10−8

10−9

10−10

10−11

10−12

10−13

10−14

10−15

10−16

10−17

10−18

10−19

4.2e−04 0