ADA Transition Project2016
Purpose• Collect inventory of non-compliant ADA ramps and sidewalks• Bring non-compliant ramps to be compliant ADA ramps• Conduct ADA Transition Plan
Materials
• Smart Tool• Measuring Tape• iPad
Materials: Smart Tool
• Slope in Percentage %• Calibrating
– Instructions: • SmartTool Calibration• Video: Calibration Demo
Process
• ODOT Form– Extra information we do
not need– Only use a few standards
ODOT ADA InspectionForm
Process (Continue)What component of the ramp was measured
• Running Slope (1,2,3)• Cross Slope (1,2,3)• Landing Width (X,Y)• Clear Width• Counter Slope• Differential Slope • Wing (Left, Right)
Process (Continue)
• iPad– Modified ODOT form– GIS location tracking
Process (Continue)
• Google Maps– To locate and verify
ramps before making trip
– Street view– Aerial view
Process (Continue)• GIS Field Data Map
– Blue icon= Ramps not completed
– Red icon= Ramps completed
– Blue circle icon =Comment
Process (Continue)
• GIS Field Data Map– Plot existing ramps– Simplify trips– Inventory of all the
ramps in the county– Know how many ramps
are completed
Process (Continue)
iPad Demonstration
GIS Maps
GIS Maps (Continue)
Development Plan
• Requirements for Plan1. List of barriers (GIS Map)2. Outline of methods to remove barriers3. Schedule for removal4. Name of official responsible for plan
Development Plan
• Comparing cities plan– City of Portland– City of Eugene (Best)
• Time line• Complete new GIS map (End of August)• Complete written Transition Plan (October 31, 2016)
Benefits
• Obtain the county’s ramp inventory• Develop ADA Transition Plan• Begin constructing new ramps
How to improve
• Google and GIS Field Data Map- sync
• Prevent Application Crash
• 2 workers