Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Michael Pacholok Director
Purchasing and Materials Management Division City Hall, 18th Floor, West Tower 100 Queen Street West Toronto, Ontario M5H 2N2
Allison Phillips Manager Professional Services
1
November 24, 2015 Posted via PDF (7 pages + 10 attachments)
ADDENDUM NO. 3
REQUEST FOR TENDER NO. 273-2015 CONTRACT NO. 15ECS-M1-02AB
FOR: ASHBRIDGES BAY TREATMENT PLANT – WASTE GAS BURNER FACILITY
EXPANSION IN THE CITY OF TORONTO
CLOSING DATE: DECEMBER 4, 2015, 12:00 NOON (LOCAL TIME)
Please refer to the above Request for Tender (RFT) document in your possession and be advised of the following: I. CORRECTION TO ADDENDUM NO. 2
1. Addendum 2 (dated November 19, 2015), Q19/A19 Revised as follows:
"Q19 In the Schedule of Prices of Section 3 (page 3-12), price 13 is for "Sodding &
Seeding". The price varies significantly between the two, please clarify which we are to price.
A19 Refer to Section II – Revised Price Form, Item 1 above"
II. REVISED SPECIFICATIONS 1. 15450 Add the following sections: 2.03 Mixing Valve 2.04 Face/Eyewash 2. 15450 Replace the existing sentence with the following:
"2.01.A. Provide one vertical hot water heater as follows:
1. Capacity 75 litre (20USGAL)
2
2. No. Heaters Per Tank 3 3. Capacity, kW 5 4. Electric 208VAC/3Ph/60Hz 4. Classification Class I Division I Group D 5. Thermostat Range 49-68oC"
3. 16140 Insert the following paragraph:
"2.02. C. Explosion proof disconnect type receptacle with mechanical interlock, 600VAC,
3PH, 4W, 30A, pin & sleeve, Cl. I Div. 1, Group D, Crouse Hinds FSQC c/w matching plug."
4. 13010 Revise the panel tag as follows:
"1.03.C.10 New Heating and Ventilation Control Panel TAB-ACC-CP-4902"
5. 15225 Replace the current specification with the updated specification (attached).
III. REVISED DRAWINGS
1. Drawing Sheet No. G10 2. Drawing Sheet No E7 3. Drawing Sheet No E10 4. Drawing sheet No E13 5. Drawing Sheet No S4 6. Drawing Sheet No S8
IV. QUESTIONS Please be advised of the following questions that were submitted to the City and the relevant responses: Q1 Ref. Dwg. # E7(3) - What is the detail for mounting to roof, light fixture (AS) shown
mounted to light post on G9(A)? A1 Refer to revised Drawing Sheets E7, S4 and S8 included in this Addendum. Q2 Specification section 15255 clause 3.08 Outdoor Duct insulation material is to be
mineral-fibre board. A note on drawing M8 in detail 4 states that mineral board insulation is to be used for the round outdoor duct. Board insulation is not typically used for round duct as it is not able to be installed correctly because of the rigidity. Please clarify what type of insulation is to be used for the round supply ductwork.
A2 The insulation specification is correct. The Contractor is to follow industrial standard in
scoring insulation to suit diameter of duct.
3
Q3 Specification section 15255 clause 3.08 Outdoor Duct states that a corrugated aluminum is to be used as the jacketing material. This application creates two probable issues. Because the duct is outside the water will sit on the ductwork and will not shed off. Additionally, a corrugated aluminum elbow is not readily available and installing a flat stock elbow would likely compromise the weather tight seal. Please clarify what type of jacket is intended to be used for the outdoor ductwork.
A3 Contractor must use stucco embossed aluminum secured with stainless steel banding. Q4 Will the cold water line need to be operational for the startup of phase one of the
project? A4 No. Q5 Concrete - Structural drawing S-1 only specified concrete strength to be 35MPa, could
consultant provide related concrete classes of exposure also? A5 Concrete exposure as follows: General (non-exposed) concrete interior slabs walls and beams: N Exposed concrete slabs, walls and columns: F-2 Exterior slab on grade, side walk: C-2 Foundation, grade beam: N Q6 The description under Tie Points 25, 26, 27 and 28 on drawing P4 list the size of the
valve and spool to be 300mm. Please confirm that the butterfly valves V-9021 and V-9024 are to be 350mm in size, as shown on drawing P4 and the valve schedule.
A6 The correct size is 350mm. Q7 Cash allowance for testing & inspection – there are no cash allowances in tender form
for testing & inspection, please clarify it. A7 The Contractor is required to pay for all testing associated with his own quality control plan
and as specified in Section 01451. The City has its own testing and inspection services which the City pays for directly.
Q8 Cost for test & inspection – Section 01451 clause 1.01.B & 1.03E shows “All costs
associated with quality control plan shall be included in contractor’s bid & all tests shall be paid for by contractor”, usually it is city to assign the testing company & allow a cash allowance amount to cover the inspection & test cost, please clarify it.
A8 Refer to Q/A7 above. Q9 Digester gas piping welding radiographic NDE examination – Please clarify if this NDE
test will be paid by cash allowance amount. A9 Contractor must pay for all NDE testing as required by the specifications and TSSA. Q10 On drawing M10 there is an eyewash shown–we cannot locate a specification for the
eyewash? A10 Refer to the revised Specification Section 15450 (added sections 2.03 and 2.04) included in
this Addendum.
4
Q11 The manufacturer of the hot water heater (Section 15450) indicates the specified hot water heater will not have enough capacity to feed an eyewash.
A11 Increase size of hot water heater to 75litre (20 USGAL), 5kW 208V/3Phase/60Hz.
Refer to the revised Specification Section 15450 and revised Drawing Sheet E13 attached to this Addendum.
Q12 What is the extent of new asphalt paving, section 2430? A12 Refer to the revised Drawing Sheet G6 included in Addendum 2 (dated November 19, 2015). Q13 Where is the Excavation Shoring System required? Specification 2150. A13 No shoreline protection is required. Refer to Q/A1 in Addendum 2 (dated November 19,
2015). Q14 Section 07555 Item 2.04.C calls for tapered glass fibre insulation. This product has not
been made for at least 15 years. What type of tapered insulation should we use? A14 Polyisocyanurate foam insulation faced with black glass/felt facers on one side and meeting
the requirements of CAN/ULC-S704. Q15 Stahl crane – section 14330 calls for stahl crane from Richard Wilcox, but when I
contacted Richard Wilcox they indicated not bidding for this project, could consultant specify anther crane system for this project?
A15 Contact Brent Ball at (905) 523-7727 (office) or (905) 981-8293 (cell). Q16 We notice there is a conflict between Drwg G4, Note 6 and Specification 01510 2.04.
The drawings states that a trailer for the administrator is required while the specification says no trailer is required. We assume a trailer is not required since the consultant has their own trailer compound already set up. Please clarify.
A16 No trailer is required for the Consultant/Contract Administrator. Q17 In Section 3, Tender Submission Package, Schedule of Prices, Item 4, it doesn’t make
any sense, can’t have addition and deduction in one chart, and total them up. Please revise.
A17 Refer to specification Section 02351, Item 1.03. Q18 The section 033000 makes reference to the CSA A23.1 of 1994. More than 20 years old!!.
We don't keep this old version in our files and it is not clear what class of exposure A, B or C were described at that time. Also drawings on general notes ask to use the latest codes edition and encourage to report discoveries or discrepancies. We require an updated section 033000 reflecting the latest CSA A23.1. Otherwise we will not be able to submit proper pricing reflecting this project.
A18 Refer to Q/A 5 above. Q19 Drawing P5 shows valves V-7001 and V-7002 on a 500mm pipe header, but valve list
15110.1 calls these valves out as 600mm. Drawing P13 shows the valves and header but there is no indication of size. Please verify size of valves V-7001 and V-7002 and size of header on drawing P13.
5
A19 The correct size is 600mm. Refer to Q/A34 in Addendum 2 (dated November 19, 2015). Q20 Would it be possible to schedule a second site visit? A20 No second site visit will be scheduled. Q21 Bridge Crane Section 14330 1.01 B. calls for electric motors for the trolley, hoist and
bridge to be Class 1 Division 1. According to the supplier, the acceptable Manufacturer “Stahl crane Systems” does not provide a Class 1 Division 1 crane which is the old NEC500 standard. They do provide a Class 1 Zone 1 which is the new NEC505 standard. Is this acceptable?
A21 Class 1 Zone 1 is acceptable. Q22 The drawings call 75mm Rigid Insulation (min. RSI 5.28). The specified material is
Roofmate and 3” has an RSI of 2.64 or an R-value of 15.0. An RSI of 5.28 would be an R-value of 30.0 which would require 2 layers of 3” Roofmate. Please confirm if the thickness or RSI is correct.
A22 The insulation thickness is 3mm with an R-value of 15. Q23 Provide diameter and specification for the Thermal Valves not included in the process
valve list. (V-7203/7204/7303/7304/7403/7404/7503/7504/7603/7604) A23 Thermal Valve sizes are as per drawings. These valves are part of the Waste Gas Burner
vendor’s scope of supply as per specification Sections 11566 section 2.06. Q24 Provide diameter and specification for the Flame Arrestor (FX-7201/7202/ 7301/ 7302/7401/7402/7501/7502/7601/7602). A24 Flame arrestor sizes are as per drawings. These devices are part of the Waste Gas Burner
vendors scope of supply as per specification Sections 11566, Item 2.06 and Q/A34 of Addendum 2 (dated November 19, 2015).
Q25 Provide a detail showing the piping reduction from 600mm to 500mm on the digester
gas incoming line (600-DG-007-202 & 500-008-202) which is not shown on the drawings A25 Refer to Q/A34 in Addendum 2 (dated November 19, 2015). Q26 Section 07555, page 5, item 2.04 C. Calls for tapered glass fibre roof insulation. Please
be advised that this product was discontinued a number of years ago. Since the tapered is being used in an inverted system, perhaps a tapered fiberboard could be considered (has a lower thermal value to minimize the possibility of dew pointing). Also, under the same section, page 7, item 3.04 A. it calls for the slope to be 1%. This slope cannot be used and hit the elevations shown on roof drawing. On drawing A1, +50 is shown at all perimeters. Please be advised that a constant thickness at the roof perimeters cannot be maintained (the runs from the roof drain to the roof perimeters vary). Usually tapered is specified as a particular slope eg. 1%, 2% and thickness are not given. Please clarify as soon as possible.
A26 Refer to Q/A14 above concerning insulation. The drawing shows the design intent and the
Contractor is free to offer alternates using common and customized slopes, mitred panels, etc. to drain the roof. The roof design will be reviewed and commented on as a shop drawing submission.
6
Q27 Specification #13510, Paragraph 2.06: This item describes the installation of a Category
3 Backbone 24 pair Telephone cable between the telephone patch panel in the telecom enclosure and the BIX block in the entrance facility. Please define “Entrance Facility” and where is this location in relation to the new Waste Gas Burner Facility. The “Entrance Facility” is not identified on the Lan campus Layout Drawing.
A27 This is the City standard LAN specification and paragraph 2.06 does not apply to this project.
Refer to drawing sheet E34 and specification Section 16516 for project specific phone and PA requirements.
Q28 In terms of life safety is there fire alarm for protecting the new expansion? E.g. smoke
detectors, pull stations etc. I noticed on drawing E4 the engineer noted a fire alarm panel within the electrical room but I didn’t see any FA devices for the field or a section under the Div.16 Index for fire alarm.
A28 No fire alarm is required. Q29 We require more detailed routing for fiber cable tray that runs from blower building
control room to new burner facility control room? The routing is shown on Drawing I19. Specifically the routing of the tray within the Blower Building.
A29 Contractor to confirm on site the effort required to install fibre optic cable. Q30 Are two fiber cables required to meet specifications Section 13510 Item # 1.01.E for
redundant requirement? A30 This is the City standard LAN specification and this project requires only one cable as
detailed on drawing sheet I19. Q31 There is a 600V 30A Receptacle that is referenced as TAB-EL3-WR-6371/6372. .Please
provide the actual catalogue number of the receptacle that is required. A31 Refer to revised specification Section 16140 attached to this Addendum. Use Crouse-Hinds FSQC2430 c/w matching plug. Q32 New Heating and Ventilation Panel referenced in general specification division 13010
Item # 10 on page 4 of 17 is labelled as TAB-ACC-CP-6372 however this same Heating and Ventilation panel is labelled as TAB-ACC-CP-4902 in drawing E35. Are they identical control panels or are they different? Please confirm which Tab # we are to use.
A32 These are the same control panel and the correct tag number is TAB-ACC-CP-4902. Q33 There is a Temperature Control Panel TAB-ACC-V-4902 shown on Drawing E35.
Please provide a schematic and layout? A33 Refer to Drawing Sheet E22 for schematic and layout. Q34 Is local control valve station TAB-DIG-V-6751 shown on drawing I58 a new panel or an
existing one? It is not referenced in general specification division 13 process control. Please confirm if it is new and we are to supply. Note: If it is new we will require a schematic and a layout.
A34 This panel is new and is detailed on drawing sheet I58.
7
Q35 Can we get the schematic drawing for existing RPU Control Panel TAB-DIG-RPU-1204 that is referenced in Section 13010 Item # 13 on Page 5 of 17. We require the drawing to do our modifications.
A35 Refer to Drawing Sheets I56 and I57 for the scope of work. Q36 Drawing # E10, Note #4: This note refers to a reference Drawing #148 for installation
details, but this drawing does not relate in any way to the scope item described in Note #4. Please clarify.
A36 The referenced drawing sheet should be I49 not I48. Refer to revised drawing sheet E10
within this Addendum. Q37 Drawing # E34, Detail #1, Conduits from PA Speakers & Telephone. Are these cables
(which are not identified on this detail) to be supplied & installed by the contractor? If so, please provide details of cabling required.
A37 Refer to specification Section 13150 for details.
Should you have any questions regarding this addendum contact Patricia Vasquez, Senior Corporate Buyer at (416) 392-6808 or by email at [email protected]. Please attach this addendum to your Tender document and be governed accordingly. Bidders must acknowledge receipt of all addenda in their Tender in the space provided on the Tender Submission Form as per Appendix A, Section 4 - Addenda of the Tender document or your response will be declared non-compliant and will not be considered. All other aspects of the Tender remain the same.
Yours truly, Allison Phillips, Manager Professional Services
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – PLUMBING FIXTURES AND TRIM
SECTION 15450 - Page 1 of 4
PART 1 -- GENERAL
1.01 Work of this Section
A. The WORK of this Section includes the supply and installation of combination safety
shower and eyewash stations complete with mixing valve, and hot water heater.
B. Conform to Division 1 - General Requirement and Section 15010 - Basic Mechanical
Requirements.
C. Related Sections
Plumbing and Drainage Section 15400
Mechanical Division 15
Electrical Division 16
1.02 References
A. Ontario Plumbing Code
B. Ontario Boiler and Pressure Vessel Act
1.03 Shop Drawings
A. Submit shop drawings, manuals, parts lists, etc. in accordance with the Contract Documents.
B. The shop drawings to include the following information:
1. Dimensions
2. Materials
3. Overall weight
4. Installation requirements
5. Required certificates, labelling and listing
4. Installation requirements
5. Required certificates, labelling and listing
1.04 Quality Assurance
A. Fabricate and label hot water heater to comply with ASME Boiler and Pressure Vessel Code Section VIII, Division 1.
B. Hot water heater to meet ASHRAE 90.1
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – PLUMBING FIXTURES AND TRIM
SECTION 15450 - Page 2 of 4
1.04 Scheduling
A. Order and delivery schedule shall be consistent with project completion date and
account for equipment manufacturer’s production and shipping terms.
PART 2 – PRODUCTS
2.01 Electric Hot Water Heater
A. Provide one vertical hot water heater as follows:
1. Capacity 75 litre (20USGAL)
2. No. Heaters Per Tank 3
3. Capacity, kW 5
4. Electric 208VAC/3Ph/60Hz
4. Classification Class I Division I Group D
5. Thermostat Range 49-68oC
B. The tank shall be of ASME welded steel construction, for a working pressure of not less
than 1035kPa, with magnesium anode, glass-lining, minimum 50mm foam insulation,
enameled steel jacket, and feet.
C. The heaters shall be of the electric immersion type, incoloy sheathed.
D. Provide the following:
1. cold and hot water connections
2. 20mm drain valve piped to drain 3. 20mm (min.) ASME temperature and pressure relief valve, 99
oC, 1035kPa, piped to
sink or drain
4. aquastat
E. Water heaters shall include nameplates of stainless steel shall be engraved or stamped
and fastened to the equipment in accessible locations. Nameplates shall contain the
manufacturer's name, model, serial number, size, characteristics, and appropriate data
describing the machine performance ratings.
F. Manufacturers
1. Hubbell Heaters
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – PLUMBING FIXTURES AND TRIM
SECTION 15450 - Page 3 of 4
2.02 Service Sink, Floor Mounted
A. Fixture:
. 1. Stern Williams #SB-90 precast terrazzo basin with stainless steel cap on all exposed
surfaces
2. 600mm by 600mm by 300mm deep
B. Trim:
1. Chicago Faucet #305 VB-R-RCF-XK-HOSE
2. 200mm centres
3. solid brass cast body, lead free, with ceramic disc cartridges
4. metal lever handles
5. hose end vacuum breaker integral stop
6. 915mm hose with hanger
C. Drain:
1, Cast brass
2. Stainless steel strainer
3. “P”trap
2.03 Mixing Valve
A. Supply and install thermostatic mixing valve providing tempered water to the
combination safety shower and eyewash stations.
B. Certified to meet requirements of ANSI Z358.1 complete with cold water bypass.
C. Mixed flowrate 1.95 L/s (min) at 206kPa.
D Inlet hot water temperature 60 oC.
Inlet cold water temperature 4oC.
E. Manufacturers
1. Haws Model 9201E
2. Bradley Navigator series
2.04 Face/Eyewash
A. Supply and install pedestal type eye and face wash station, complete with stay open
valve and in-line strainer, were indicated on the Contract Drawings.
B. Certified by CSA to meet the requirements of ANSI Z358.1.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – PLUMBING FIXTURES AND TRIM
SECTION 15450 - Page 4 of 4
C. Provide hinged stainless steel dust cover and stainless steel foot control assembly.
D. Manufacturers
1. Haws Model 7777 with all stainless steel components
2. Bradley
E. Mechanically install eyewash station flow switch provided by Division 13 with wiring
by Division 16.
PART 3 -- EXECUTION
3.01 Installation
A. Installed items in in accordance with the manufacturer's printed recommendations and
the Ontario Plumbing Code.
END OF SECTION
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 16 Electrical
ELECTRICAL – WIRING DEVICES
SECTION 16140 - Page 1 of 2
PART 1 – GENERAL
1.01 General
A. Comply with the requirements of Division 1 – General Requirements and Section 16010 –
General Electrical Provisions.
PART 2 – PRODUCTS
2.01 Wall Switches
A. 15 A, 20 A, 120 V, single pole switches as indicated or where required, manually operated, toggle, specification grade (colour to be advised).
B. Provide switches of one manufacturer through project where possible.
C. Acceptable manufacturers:
1. Pass & Seymour 2. Arrow Hart 3. Bryant 4. Hubbell 5. Pass & Seymour 6. Slater 7. Smith & Stone
2.02 Receptacles
A. Duplex receptacles, CSA Type 5-15R, 125 Volt, 15A, u-ground, colour to be advised, weather proof where indicated on drawings.
B. Disconnect type receptacle with mechanical interlock, 600VAC, 3PH, 4W, 20HP rated, pin & sleeve, NEMA 4X, Pass & Seymour Cat. No. PS430MIR5-W
C. Explosion proof disconnect type receptacle with mechanical interlock, 600VAC, 3PH,
4W, 30A, pin & sleeve, Cl. I Div. 1, Group D, Crouse Hinds FSQC c/w matching plug.
D. Receptacles of one manufacturer throughout projects, where possible.
E. Acceptable Manufacturers:
1. Pass & Seymour 2. Arrow Hart
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 16 Electrical
ELECTRICAL – WIRING DEVICES
SECTION 16140 - Page 2 of 2
3. Bryant 4. Hubbell 5. Pass & Seymour 6. Slater 7. Smith & Stone 8. Crouse Hinds
2.03 Coverplates
A. Coverplates for wiring devices in finished areas: stainless steel, type 302 alloy, 0.035 satin finish.
B. Coverplates from one manufacturer throughout project.
C. Coverplates for surface mount wiring devices and blank: Scepter PVC type.
D. Weatherproof duplex receptacle covers: Hubbell Cast Aluminum, Cat. No. 5205 UO.
E. Coverplates for wiring devices in finished areas in Operations Centre; Smith and Stone "The Designer Series": single gang, white Cat No. 6-0311-5.
F. All coverplates below grade to be NEMA 4 (watertight).
PART 3 - EXECUTION
3.01 Installation
A. All 120VAC and 208VAC wiring devices shall be labeled. The labels shall indicate Lighting Panel tag and circuit breaker number to which they are connected.
B. All 600VAC receptacles to be tagged as noted in Sections 13040 and 13040.1.
END OF SECTION
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 1 of 17
PART 1 - GENERAL
1.01 Intent
A. This Section contains General and Specific Requirements for process control and instrumentation for the Ashbridges Bay Treatment Plant (ABTP) – Waste Gas Burner
Facility Expansion project.
B. The work in this Section generally consists of the supply of all labour, tools, services, provision of all products required, for a complete, integrated, operational
instrumentation and control system.
C. Comply with the requirements of Division 1.
D. Refer to Divisions 11 Process, 15 Mechanical and 16 Electrical for additional requirements.
E. Wherever there is a discrepancy between information provided in this document and on a drawing, the drawing shall take precedence.
F. The Contractor will retain services of City approved System Integrator to undertake commissioning of the upgraded glycol heating system.
G. The approved System Integrators are:
1. IBI-MAAK Technologies 2. Summa Engineering 3. Hatch Mott McDonald (HMM) 4. Real Time Systems 5. Eramosa
H. The Integrator is responsible for all PLC and SCADA programming in accordance with latest City of Toronto Process Control System Implementation Manual and Section
13010.1, 13010.2 and 13010.3.
1.02 References
A. Comply with the requirements of Division 1. Be responsible for all the requirements of
this Section and of Division 1. No additional cost will be considered for non-
coordination between this Section and the other Sections in the Specification.
B. Refer to other sections of the Division 15 for instructions that apply to the Work of
Section 13010.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 2 of 17
C. Refer to other sections of the Division 16 for instructions that apply to the Work of
Section 13010.
D. Refer to applicable sections for contractors in the latest City of Toronto Process Control
System Implementation Manual.
E. Have the material, equipment, installation and workmanship also meet the latest edition
and requirements of the following:
1. Ontario Electrical Safety Code
2. Canadian Standards Association (CSA)
3. Canadian Electrical Manufacturers Association (CEMA)
4. Institute of Electrical and Electronics Engineers (IEEE)
5. National Electrical Manufacturers Association (NEMA)
6. Electrical and Electronic Manufacturers Association of Canada (EEMAC)
7. International Society for Measurement and Control (Formerly the Instrument Society of America, ISA)
8. Electronic Industries Association / Telecommunications Industries Association
(EIAITIA 606)
9. National Fire Code, National Fire Protection Association (NFPA): 820, Fire
Protection in Wastewater Treatment Plants.
10. Underwriters Laboratory, Ic. (UL): 508, Standards for Safety, Industrial Control
Equipment
11. Deutsche Industrie - Norm (DIN); VDE0611, Specification for modular terminal blocks for connection to copper conductors up to 1,000 VAC and up to 1,200VDC..
1.03 Scope of Work
A. In general, the work involves the supply, installation, modification, reconnection, testing, start-up and commissioning of the necessary instrumentation and controls as
indicated in the specifications under Division 13 and on the Contract Drawings.
B. Division 16 will field mount/install the control panels, closets and workstation provided
by Division 13 (after successful FAT testing) and will supply and install all conduits,
field wiring and cables for power and control systems. Division 16 will leave wiring
pigtails of sufficient length in the control panels for termination by Division 13. Division
16 will terminate all analogue and digital wiring in motorized valves and field
instrumentation.
C. The following is a summary of the major work:
1. New RPU Control Panel TAB-DIG-RPU-1032
a. Provide and install new RPU Control Panel as detailed in the specification and
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 3 of 17
drawings.
b. Terminate all digital and analogue I/O.
c. Provide PLC and SCADA programming.
d. Provide FAT and SAT services.
2. Existing SCADA Workstation TAB-SPC-CPU-0006
a. Remove existing Waste Gas Burner SCADA programming including all the
relevant screens, trends, alarms and database points.
b. Develop new Waste Gas Burner process graphics, sub-pictures, devices sub-
pictures, set points, trends, alarm pages, run-hour graphs, HMI database and
menus, as required for the Waste Gas Burner Facility Expansion.
c. Provide SCADA User’s Manual for the scope of work under this contract
including any necessary updates required to existing SCADA Users’ Manual as
impacted by this contract.
d. Provide FAT and SAT services.
4. New Waste Gas Burner Control Panels TAB-DIG-BU-7200, -7300, -7400, -7500
and -7600
a. Terminate all discrete and analogue I/O to the equipment vendor supplied burner
control panels as shown on the Contract Drawings.
5. Existing RPU control panel TAB-ACC-RPU-1408
a. Provide and install GE Fanuc expansion rack, communication card, discrete and
analogue I/O cards, and all necessary hardware as shown on the Contract
Drawings.
b. Terminate all analogue, discrete, network inputs and outputs to the PLC as
shown on the Contract Drawings and Instrument List.
c. Download copy of existing program logic for the plant wide heating system as
directed by the City for updating. Program revised ladder logic to follow intent
of the program logic of existing secondary and tertiary space heating systems
and applicable sections for contractors in the latest City of Toronto Process
Control System Implementation Manual.
d. Provide FAT and SAT services.
6. New Glycol Pumps Control Panel TAB-ACC-CP-4901
a. Provide and install Control Panel TAB-ACC-CP-4901 as shown on the Contract
Drawings.
b. Terminate all wiring as shown on the Contract Drawings.
c. Provide FAT and SAT services.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 4 of 17
7 New Termination Panel and New Telecom Enclosure
a. Provide, test and commission Termination Panel TAB-ITS-COM-5601 as
shown on the Contract Drawings.
b. Provide, test and commission Telecom Enclosure TAB-ITS-COM-5600 as
shown on the Contract Drawings. Supply and install all necessary patch cords.
Comply with 13510 Process Control System Standard Local Area Network.
Also refer applicable sections for contractors in the latest City of Toronto
Process Control System Implementation Manual at the time of the contract
award.
8. New Valve Control Panels
a. Provide and install all valve control panels as shown on the Contract Drawings.
Note that valves are supplied by Divisions 11 and 15.
b. Terminate all discrete and analogue wiring as shown on the Contract Drawings.
c. Provide FAT and SAT services.
9. New Lighting Control Panel TAB-EL3-CP-6371
a. Provide and install new lighting control panel and new door lighting control
stations as shown on the Contract Drawings.
b. Terminate all wiring as shown on the Contract Drawings.
c. Provide FAT and SAT services.
10. New Heating and Ventilation Control Panel TAB-ACC-CP-4902
a. Provide and install new heating and ventilation control panel as shown on the
Contract Drawings.
b. Terminate all wiring as shown on the Contract Drawings.
c. Provide FAT and SAT services.
11. New Gas Monitoring Control Panel TAB-DIG-CP-7100
a. Provide and install new gas monitoring control panel, new door control stations
and new door audible alarms as shown on the Contract Drawings.
b. Terminate all wiring as shown on the Contract Drawings.
c. Provide FAT and SAT services.
12. Plant Wide Heating and Ventilation SCADA System
a. Download the existing program, in the SCADA server, for the plant wide heating system as directed by the City for updating.
b. Follow the program logic and screen features for the existing secondary and
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 5 of 17
tertiary space heating systems in developing new process graphics, sub-pictures,
devices sub-pictures, set points, trends, alarm pages, run-hour graphs, HMI
database and menus, as required for the work under this Contract. Carry out FAT
testing and upload revised program. Complete SAT testing.
c. The Integrator is also responsible to produce SCADA Users Manual for the scope of work under this contract including any necessary updates required to
existing SCADA Users Manual as impacted by this contract.
13. Existing RPU control panel TAB-DIG-RPU-1204
a. Provide and install GE Fanuc discrete I/O cards, and all necessary hardware as
shown on the Contract Drawings.
b. Terminate all discrete inputs and outputs to the PLC as shown on the Contract
Drawings.
c. Modify PLC and SCADA programming.
d. Provide FAT and SAT services.
e. The Integrator is also responsible to produce SCADA User’s Manual for the
scope of work under this contract including any necessary updates required to
existing SCADA User’s Manual as impacted by this contract.
14. Existing RPU control panel TAB-DIG-RPU-1031A
a. Terminate all discrete inputs to the PLC as shown on the Contract Drawings.
c. Modify PLC and SCADA programming.
d. Provide FAT and SAT services.
e. The Integrator is also responsible to produce SCADA User’s Manual for the
scope of work under this contract including any necessary updates required to
existing SCADA User’s Manual as impacted by this contract.
15. Existing RPU control panel TAB-DIG-RPU-1037
a. Terminate all discrete inputs to the PLC as shown on the Contract Drawings.
c. Modify PLC and SCADA programming.
d. Provide FAT and SAT services.
e. The Integrator is also responsible to produce SCADA User’s Manual for the
scope of work under this contract including any necessary updates required to
existing SCADA User’s Manual as impacted by this contract.
16. Network:
a. Provide, configure, test and commission new local network and integrate into
the existing ABTP networks. Comply with 13510 Process Control System
Local Area Network. Also refer applicable sections for contractors in the latest
City of Toronto Process Control System Implementation Manual at the time of
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 6 of 17
the contract award.
17. Field Devices:
a. Supply all field instrumentation as listed in the Instrument List, and all
peripheral devices necessary. Test, site calibrate and commission all instruments
and control valves in cooperation with Divisions 11, 15 and 16.
b. Provide all field device tags and panel labels listed in the specification and
Contract Drawings.
c. Provide configuration and programming for all microprocessor based
instruments and other intelligent instruments.
d. Provide qualified manufacturer's service for installation, setup, calibration,
testing and commissioning and guarantee and warranty period activities.
18. Commissioning and Training:
a. Comply with the requirements in Division 1 Sections 01650 and 01850, and
applicable Division 13 sections following.
b. Demonstrate loop checks for the I/O identified by this scope of work. Before
requesting witnessed loop checks, carry out Contractor's own field and loop
check tests to verify that the equipment operates as intended in cooperation with
Division 16. Correct any problems or deficiencies prior to requesting witnessed
checks.
c. On site loop check must exercise the entire loop, including the field equipment
and SCADA screens. Coordinate this work with the Consultant/Integrator. Each
loop check must be witnessed by, and successfully demonstrated to the Contract
Administrator for sign-off approval.
d. Provide testing and commissioning services including those associated with
testing software prepared by the Consultant/Integrator. Assign qualified staff
when the Consultant/Integrator requires it during RPU and SCADA software
testing. Allow in the Contract Price, for any additional time deemed necessary
to meet the testing and commission requirements.
e. Provide Factory Acceptance Test (FAT) as defined in Section 13921.
f. Provide Site Acceptance Test (SAT) as defined in Section 13933.
13. General:
a. Maintain record drawings (as-builts) for all tender drawings and create new
drawings as required to document installed equipment and system under this
contract.
b. Refer to the Contract Drawings to ensure completeness of installation for all
items and that these items are compatible with the control and operational intent
of the design of this project.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 7 of 17
c. Without limitation to the following sections of this division, the equipment
supplied shall be complete with all accessory items, whether specifically
mentioned or not, so as to provide completeness of installation, controls and
operation as intended. All equipment installation shall be as recommended by
the equipment manufacturer or as described in the installation drawing.
d. Process control equipment and wiring as specified, or as shown on the drawings,
are sized for the process, electrical and mechanical equipment as specified, or as
may be necessary in the future. Any additional expense incurred because of
approved substituted process control equipment from that specified shall be
borne by the Contractor.
14. Meetings:
a. Conduct meetings with Plant/PCS staff as indicated in Section 01200 - Project
Meetings.
1.04 Related Sections
Division 1 General Requirements
Division 11 Equipment
Division 15 Mechanical
Division 16 Electrical
1.05 Submittals
A. Submittal to be in accordance with the Section 01300 - Submittals and requirements in this Section. Instrument submittal requirements are in Section 13105.
B. Drawing Index: Prepare a clear, typed index listing the number and title of all proposed
Purpose-made drawings and submit for review within fourteen (14) days after award of
contract.
C. Prepare and submit a proposed schedule of instrumentation and control work to the
General Contractor, indicating the following major milestones as a minimum, for
incorporation in Commissioning Plan outlined in Section 01650.
1. Hardware shop drawings submission - including initial issue of Product Data
Sheets;
2. Panel inspection and earliest date for Factory Acceptance Testing (FAT);
3. Signed calibration sheet or report on each field instrument;
4. Final submission and sign-off of Product Data Sheets;
5. Report on proper site installation, inspection, and loop checks;
6. Earliest date of Site Acceptance Testing (SAT); and
7. Maintenance training sessions on field instruments.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 8 of 17
D. Unless otherwise specified or indicated, submit detail design drawings, shop
drawings, specifications sheets or product data sheets for all instruments, devices
and panels. All dimensions, rating, curves, etc. to be in SI units.
E. Product Data Sheets:
1. Product Data Sheets specifying instruments and equipment form part of this document. Complete the standard forms found in ISA S20.
2. Initial submission for review to accompany Shop Drawings:
a. the product manufacturer and the supplier or representative;
b. the complete model or catalogue number(s) including any special options;
c. the available adjustment range(s) and the project operating range(s).
3. Second Submission during pre-commissioning, testing and calibration period:
a. serial numbers, part numbers, dates of installation and calibration;
b. any special procedures required to duplicate calibration;
c. this submission is for signature by the Contractor and the Consultant following
acceptance of the operation of each instrument.
4. Final Submission of signed-off Product Data Sheets included with Operating and Maintenance Instruction Manuals:
a. all of the above information; and;
b. phone and fax numbers of contact person for product support/service.
5. Where there is any discrepancy, the description provided on the Product Data Sheet takes precedence over the model number given in the data sheet.
6. Completed WMS Sheets.
G. Purpose-made Drawings:
1. Prepare Purpose-made drawings neatly and accurately by means of the latest version of AutoCAD or as otherwise advised. Do not use external references or customized
file extensions. Provide fully portable electronic file copies of all drawings.
2. Make submissions on legal-size paper, complete with a title block containing the Contractor’s Engineer's stamp, your project number and company logo, a drawing
and project title as stated in the Contract drawings, and a referenced drawing number
(related to a file name if applicable). Provide tabular columns to record the original
submission date, a revision number, date and reason for subsequent revisions, and
signature of authorized issuing staff member.
3. Submit, as a minimum, the following Purpose-made drawings:
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 9 of 17
a. Scaled, referenced, front of panel layouts, and general arrangement drawings;
b. Scaled, referenced, internal panel layouts (may be combined with the above);
c. Equipment and/or panel block wiring diagrams showing termination
identification at each item of equipment, inter-wiring and cable numbering, all
peripheral equipment, any RTU module DIP switch settings, pin assignments
for D-shell connectors, plugs and jacks, and instrument/equipment tag
numbers;
d. Submit, prior to the installation or fabrication of the instruments and panels,
complete loop wiring diagrams showing all the wiring between instruments
and devices;
e. Submit, prior to installation, layout drawings of each Control Panel showing
construction details, materials and construction, bill of materials, location of
instruments and devices, dimensions, etc.;
f. Where issued, loop drawings are typical for guidance only. Submit itemized
instrument wiring arm drawings for all analogue process loops and discrete
connections, generally in accordance with ISA S5.4 format and as a minimum
incorporating the following details: RTU terminal numbers, Control Cabinet
terminal numbers, field terminal numbers, wire numbers, contact orientation,
power source identifications and equipment numbers. The "AutoCAD" files for
these drawings are to be edited with "Record Drawing" detail and made
accessible to the Contract Administrator during the project;
g. List of expendable materials and quantities;
h. List of Instrument, Equipment and Panel Identification Nameplates.
H. Vendor Equipment Shop Drawings,
1. Submit Shop Drawings for all field and panel mounted instruments, controllers,
gauges and similar products. Manufacturers' documentation will be accepted only if
the following information is clearly indicated and highlighted for the equipment
proposed. Submit the following:
a. an itemized quotation from the proposed instrument or equipment vendor,
(prices removed), including tag numbers, quantities, options being provided and
a full description and performance data;
b. installation details depicting mounting assemblies, physical dimensions, process
connection sizes (e.g. flange ratings & styles);
c. termination details clearly indicating the type and lengths of external wiring
required and electrical' connections;
d. power supply rating, input and output signal ranges, maximum measured process
range and calibrated scale, physical, electrical and environmental requirements;
e. exact catalogue model numbers for each piece of equipment and its accessory
options, and clearly referenced by the respective instrument or equipment tag
name given in this document (improperly tagged items shall be rejected);
f. a separate sheet with manufacturers' recommended list of spare parts including
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 10 of 17
individual pricing with the shop drawings
2. Contractor shall note compliance and variance in writing or the specification shall
have precedence over approved vendor drawings. Stamp the shop drawings
submitted in accordance with Section 01300 - Submittals. Describe deviations
exactly and indicate how they impact the specified duty of the component. The
Contract Administrator will assess acceptability of submission.
I. Submission Format:
1. A complete set of Purpose-made Drawings, Shop Drawings, and the initial submission of the Product Data Sheets shall be bound into one volume and issued
for approval before the commencement of work.
1.06 Operating and Maintenance Manuals
A. In addition to requirements for operating and maintenance instruction manuals specified
in Section 01300, include the following as per PCS Guidelines, Appendix C, PCS
Documentation (EDOCSLIB-#9108-v2):
a. SCADA Operations Manual b. Contractor Equipment Operation and Maintenance Manual, including the following:
a. Control System Hardware Manuals b. Software User`s Manual c. Configuration Manual d. Custom Software Manuals e. Source Materials f. Drawings - Copies g. Drawings - Reproducible
c. Manufacturer's hardware manuals; d. Special instructions or procedures, including trouble-shooting techniques; e. Recommendations on equipment maintenance and suggested spare parts; f. Final Shop Drawings and signed-off Product Data Sheets as defined in this
Specification;
g. Copies of Record drawings of all Purpose-made Drawings; h. Name(s), addresses) and telephone number(s) for local qualified system and/or
product service representatives;
i. Calibration certificates from the manufacturers for each calibrated instrument.
to be provided to the General Contractor for inclusion in the overall manual binder.
PART 2 - PRODUCTS
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 11 of 17
2.01 Instrument Panel Requirements
A. In addition to specific panel requirements set out in the Sections 13310, 13311, 13312,
13320, 13325, 13340 and 13350 for control panels and enclosures include:
1. Protect each instrument power circuit with a panel mounted terminal block type circuit breaker sized to suit.
2. Provide lamicoid nameplates for all equipment, both door mounted and panel
mounted
3. Provide all wall-mounted panels with 50mm stainless steel spacers.
4. Do not allow panel floor mounted equipment (i.e. UPS) to block access to the panel
back plane mounted equipment.
5. Provide surge suppressers to protect process instrumentation against damage due to
electrical transients induced in interconnecting lines by lightning and nearby
electrical systems.
2.02 Control Processors - RPU etc.
A. Comply with Section 13400-Programmable Logic Controller for RPU hardware
requirements.
B. Provide all cables, line extenders and connection devices required for the connection
of the system and for connection of any associated programming or operator interface
devices. Provide double insulated cables unless otherwise specified. Select and
provide connectors with electrical contact surfaces gold-plated, and D-shell
connectors with metal or metalized plastic (shielded type) hoods.
C. Provide a written confirmation from the manufacturer of each product stating that it is a
current product and that it will be supported (spare parts, software drivers, service, etc.)
for a period of not less than 5 years from the date of purchase. Submit confirmation with
Shop Drawings.
D. For all motor Start/Stop commands and actuator Open/Close commands use only
individually isolated relay output modules.
E. Always use signal isolators for VFD analogue signals as required.
2.03 Programming Requirements
A. Programming is the responsibility of the Consultant/Integrator in accordance with the
latest City of Toronto Process Control System Implementation Manual.
2.04 Terminal Blocks
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 12 of 17
A. Refer Section 13320- Panel Wiring for terminal blocks specifications.
2.05 Wire and Cable
A. Refer to Section 13320 for panel wiring.
B. All wire and cable must be sized and installed in accordance with the Ontario Electrical
Safety Code Requirements. No control wire smaller than # 14 gauge shall be used
except where so indicated on the drawings or as specified in other Sections.
C. Field wiring (Section 13305) is installed by Division 16 with final termination of
discrete, analogue, communication and power 120VAC and below within control panels
is the responsibility of Division 13.
D. Provide adequate slack on cable harnesses to permit easy removal of I/O and other
printed circuit cards and/or modules and instruments during service or repair.
E. All wiring for signal system shall be identified as to circuit numbers with approved
markers on the cables at all panels and terminal strips. Where hand written markers are
necessary, use the manufacturer's recommended indelible marker pen. Printing must be
neat, capital alpha characters. Refer specification 16120 Wire and Cables for approved
markers.
2.06 Network
A. All network products must comply with the applicable specification sections and
Contract Drawings.
B. All networks must be sized and installed in accordance with the applicable specification
sections and drawings. Also refer to applicable sections for contractors in the latest City
of Toronto Process Control System Implementation Manual at the time of the contract
award.
PART 3 - EXECUTION
3.01 Coordination
A. Carefully examine and monitor for compatibility, any instrumentation and control work
provided as part of the Work of Sections of the Specification other than the Sections
governed by this Section, or the City of Toronto, and ensure that all trades involved are
aware of any coordination problems or details.
B. Incompatible work, such as instrument process connections, mounting of equipment,
analog, discrete or communication wiring, voltages, or inconsistencies resulting from
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 13 of 17
insufficient coordination of other related work, is to be satisfactorily resolved at no
additional cost to the Contract.
C. When scheduling site inspection, FAT, commissioning, or SAT with the Contract
Administrator, allow at least 10 working days advance notice.
3.02 Manufacturer's Services and Installation Certification
A. Comply with the requirements of the Section 01650-Start-up, Testing and
Commissioning.
B. Allow in the tender for all the necessary services and expenses of a trained, qualified
manufacturer's representative for each device as specified in the specification, to ensure
correctness of installation, testing, start-up, commissioning and training. The qualified
representative is to:
1. Provide onsite supervision of installation for the initial and critical stages of the work as agreed to with the manufacturer/supplier and as required by the Contract
Administrator.
2. Supervise testing and calibration of equipment. Supervise retesting and recalibration of equipment at no additional cost to the Owner.
3. Provide written certification stating that the work has been completed satisfactorily.
4. Provide a complete Installation, Start-up Checklist and sign off on the start-up work
completed.
5. Provide operation and maintenance instruction to the Owner's operating staff
C. Provide supervision of installation as required by the manufacturers for all equipment in
this Division. The Owner/Contract Administrator may order additional supervision at no
cost to the Owner if, in their opinion, installation procedures are compromised.
D. Provide all materials, labour and equipment to make any adjustments to the installation
as required by the manufacturer or the Contract Administrator to effect performance.
E. On completion of installation and testing, obtain certification from the manufacturers
that the equipment is installed correctly, is in full operating condition, and is operating in
accordance with its design rating. Submit the original certificate to the Contract
Administrator.
F. Include the service of the trained personnel to inspect and commission the equipment
when ready for starting and to instruct the operating personnel in the operation and
maintenance of the equipment. Time spent on site by the trained personnel must be
witnessed by the Contract Administrator.
G. As a minimum requirement allow the following days for the service of a manufacturer's
representative. Not all days will necessarily be concurrent. If additional days are
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 14 of 17
required to complete the work, include these additional days and trips at no additional
cost to the project.
1. Pressure/Temperature/Flow Transmitter 1/2 day
2. Uninterruptible Power Supplies 1/2 day
3. PLC 2 days
4. Pressure/Temperature/Flow Switches 1 day
5. Equipment not mentioned 1/2 day
3.03 Panel Inspection and Factory Acceptance Testing (FAT)
A. Panel inspection and FAT testing shall follow Sections 13921. Also refer to applicable
sections for contractors in the latest City of Toronto Process Control System
Implementation Manual.
B. Make all necessary arrangements with equipment supplier(s) and the
Consultant/Integrator for panel inspection and FAT prior to delivery.
3.04 General Installation Requirements
A. Provide all necessary installation detail drawings and sufficient supervision to ensure
that the installation of the instrument and the control system components is done to the
satisfaction of the Contract Administrator as work progresses.
B. Provide all necessary adjusting, field calibration, testing and check-out of all equipment
and control loops. After loop check-out, submit written test results to the Contract
Administrator. All instrument calibration procedures to be witnessed by the Contract
Administrator.
C. Supply any materials and/or test facilities necessary for commissioning. The use of the
City of Toronto's facilities, if suitable, may be considered upon written request.
D. All tag labeling of the existing wiring to be maintained, and be consistent with the
current City of Toronto's tagging standard, Section 13040 Equipment Tag Standard
EDOCLIB-#6454-v2A.
E. Install the instrumentation and auxiliary devices such that they are accessible for
operation and maintenance.
F. Advise the Contract Administrator in sufficient time to avoid delays to the Project of any
perceived problems regarding implementation of installation details or standard
practices for the particular application or if any requirements of this Specification, or a
drawing detail, contradicts the equipment manufacturer's instructions or
recommendations in a manner, which could be detrimental to its operation, including the
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 15 of 17
possibility of inducing adverse side effects elsewhere.
G. Locate and install controller and panels so as to be easily accessible for maintenance and
readability of displays.
H. Displays and keyboards are to be protected during the construction and commissioning
period, but remain readily accessible on the panel's exterior.
I. Following Site Acceptance, provide to the Contract Administrator a minimum of six
identified control panel keys for each panel.
J. Follow the Manufacturer's recommendations for loading resistors on digital outputs to
limit the affect of leakage currents through triac and relay outputs.
K. Follow the Manufacturer's recommendations for surge suppression on inductive loads.
L. Once RPU Control Panels are installed and sufficient field wiring is in place to power
up the RTUs, immediately install keepers on any lighting panel or MCC circuit breaker
feeding the RPU Control Panel. Unless otherwise authorized by the Contract
Administrator, the RPU Control Panel and PLC to remain powered up at all times.
3.05 System Wiring Requirements
A. Provide all required panel wiring as per Section 13320. All wiring shall conform to the
latest revision of the O.E.S.C. and to the Electrical Area Classification for Hazardous
Locations where applicable.
B. Where specific wiring types are not specified (except AC power wiring) provide types of
wiring as recommended by the system component manufacturers.
C. Communication and analog signal conductor shields must be isolated and taped back at
one end and terminated at a single ground point at the other (normally at the RPU) as
shown on the loop drawings. If the correct grounding information is unclear, confirm
exact shield termination and isolation details with the equipment manufacturer and the
Contract Administrator.
D. Using suitable permanent wire markers and terminal block tags, number all control
panel terminal blocks as indicated on the drawings.
E. Install lightning and surge protection on all analog signal cabling entering or exiting
buildings. Provide two spare units.
F. Confirm all conduit terminations are sealed to prevent moisture penetration.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 16 of 17
G. Install signal isolators (24VDC externally powered if not loop-powered devices) on all
analog loops with signal cabling running outside buildings, speed control signals into
variable frequency drives, and any situation where potential EMF could damage
electronic equipment. Provide two spare isolators.
H. Comply with Section 18 of the O.E.S.C., and NFPA 820 for devices and wires installed
in classified areas.
3.07 Identification and Tagging
A. All equipment and wiring identification and tagging shall comply with Sections 13040
and 13320.
B. Submit with the Shop Drawings, a typed list indicating all nameplate wording as well as
proposed types, sizes and styles.
C. Prior to installation of new items, apply identification nameplates to each instrument,
panel, telemetry device and controller. Where existing instruments are re-used, or
connected into the new system/control panel(s), provide identification nameplates for
these instruments also.
D. Wiring:
1. Identify all RTU I/O signals on field terminal rails with appropriate tag.
2. Identify all wiring at both ends with appropriate, permanent wire markers.
3.08 Site Acceptance Testing (SAT)
A. SAT Testing shall follow Section 13933.
3.09 Training
A. Comply with the requirements of Section 01850 Training. Also refer to applicable
sections for contractors in the latest City of Toronto Process Control System
Implementation Manual.
3.10 Process Performance Operation
A. Provide all labor and materials necessary to support the process and the instrumentation and control system for the duration of the contract performance run. During this
operation all equipment is expected to run in automatic mode.
3.11 Warranty and Guarantee Period Activities
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 13 Process Control
PROCESS CONTROL- GENERAL
SECTION 13010 - Page 17 of 17
A. During the warranty period, hardware service should be provided by a factory trained
service representative who shall be on-site within 24 hours of a service request, 7
days/week, including weekends and holidays. The service representative shall be
equipped with all necessary tools, testing equipment, spare parts, and expertise to
perform the service in one visit.
1. For each service call submit a report giving the following information:
a. part numbers, description and prices for items replaced
b. revised hard copy/soft copy listings of program changes
c. hours worked by maintenance personnel
d. reason for the service call, and whether preventative, unscheduled or
corrective maintenance was carried out
e. name of Owner's technician present during repairs. Explain the problem and
solutions to the Owner's technician
f. description of problem as discovered on arrival at site and itemized report of
activities performed to isolate and correct problem
g. identification of any required actions to prevent similar future occurrence
h. name of attending operations representative, time of call and time of arrival
on site
2. A single contact point shall be provided for all hardware such that the Owner's representative need only call a single phone number irrespective of which piece of
hardware has failed.
3. Spare Components
a. The supplier should have access to a dedicated spare parts inventory for each
component provided. Parts shall be available within 24 hours of a service parts
request, 7 days/week.
b. Include key spare parts that are not normally available immediately from stock,
in the Recommended Spare Parts List.
END OF SECTION
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 1 of 9
PART 1- GENERAL
1.01 General
A. The requirements of Section 15250 apply to and form part of all sections of Division 15
Mechanical.
B. This Section includes rigid, semirigid and flexible duct, and plenum insulation;
insulating cements; field-applied jackets; accessories and attachments; and sealing
compounds.
C. Thermal insulation is indicated on the Drawings by symbols.
D. Related Sections
1. Air Distribution Section 15885
E. Asbestos containing materials shall not be used.
1.02 Standards
A. ASTM:
1. C 553, Standard Specification for Mineral Fiber Blanket Thermal Insulation for
Commercial and Industrial Applications
2. C 612, Mineral Fibre Block and Board Thermal Insulation
3. C 795, Thermal Insulation for Use in Contact with Austenitic Stainless Steel
4. C916, Standard Specification for Adhesives for Duct Thermal Insulation
5. C 1071, Standard Specification for Fibrous Glass Duct Lining Insulation
6. E 84, Standard Test Method for Surface Burning Characteristics of Building
Materials
B. National Fire Protection Association (NFPA):
1. 90A, Standard for the Installation of Air Conditioning and Ventilating Systems.
2. 190B, Standard for the Installation of Warm Air Heating and Air Conditioning
Systems.
3. 255, Standard Method of Test of Surface Burning Characteristics of Building
Materials.
4. 259, Standard Test Method for Potential Heat of Building Materials.
C. North American Insulation Manufacturers Association (NAIMA)
D. SMACNA, HVAC Duct Construction Standards Metal and Flexible
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 2 of 9
E. Underwriters' Laboratories, Inc. (UL): 723, UL Standard for Safety Test for Surface
Burning Characteristics of Building Materials.
F. TIAC, Thermal Insulation Association of Canada- Standards Manual for Mechanical
Insulation.
G. CAN/ULC-S 1 02, Standard Method & Test for Surface Burning Characteristics of
Building Materials and Assemblies.
1.03 Submittals
A. Submit product data in accordance with Section 01300 and to include the following
information:
1. Thermal conductivity
2. Thickness
3. Jacket material
4. Installation requirements
5. Required certificates, labelling and listing
B. Submit material test reports from a qualified testing agency indicating, interpreting,
and certifying test results for compliance of insulation materials, sealers, attachments,
cements, and jackets with requirements of this Section. Include dates of tests.
1.04 Quality Assurance
A. Fire-Test-Response Characteristics 1. Insulation Installed Indoors: Flame-spread rating of 25 or less, and smoke-
developed rating of 50 or less.
2. Insulation Installed Outdoors: Flame-spread rating of 75 or less, and smoke-
developed rating of 150 or less.
B. Factory label insulation and jacket materials and sealer and cement material containers with appropriate markings of applicable testing and inspecting agency certifying above
characteristics.
1.05 Delivery, Storage, and Handling
A. Manufacturer's Stamp or Label:
1. Every package or standard container of insulation, jackets, cements, adhesives and
coatings delivered to Project site for use must have manufacturer's stamp or label
attached, giving name of manufacturer, brand, and description of material.
2. Insulation packages and containers shall be marked "asbestos-free."
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 3 of 9
B. Protect insulation from weather and construction traffic, dirt, water, chemical, and
mechanical damage, by storing in original wrapping.
1.06 Coordination
A. Coordinate clearance requirements with ductwork sub contractor for insulation
application.
B. Schedule insulation application after testing duct systems. Insulation application may
begin on segments of ducts that have satisfactory test results.
PART 2 – PRODUCTS
2.01 General
A. For each insulation application, an acceptable material is specified with corresponding K value. If alternative insulation materials are proposed having K values different from
specified materials, adjust thickness to provide overall heat loss not greater than the
specified material.
1. Minimum acceptable insulation thickness is 25mm.
B. Fire hazard ratings for insulation systems: 1. Insulation Installed Indoors: Flame-spread rating of 25 or less, and smoke-
developed rating of 50 or less.
2. Insulation Installed Outdoors: Flame-spread rating of 75 or less, and smoke-
developed rating of 150 or less.
C. Attachment systems: Materials and methods in accordance with manufacturer's instructions.
2.02 Manufacturers
A. Provide products by one of the following:
1. Knauf Insulation Ltd
2. Owens-Corning Canada
3. Johns-Manvill Canada
2.03 Insulation Materials
A. Rigid Mineral-Fibre Board
1. Thermal insulation consisting of glass fibres bonded with a thermosetting resin and
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 4 of 9
complying with ASTM C 612 Type IB with factory applied FSK facing.
2. K =0.034W/m°C at 24°C.
3. Density of 96kg/m3 (6 lb/ft
3).
B. Semi-Rigid Mineral-Fibre Board
1. Thermal insulation consisting of glass fibres bonded with a thermosetting resin and
complying with ASTM C 612 Type IB with factory applied FSK facing.
2. K =0.034W/m°C at 24°C.
3. Density of 48kg/m3 (3 lb/ft
3).
C. Mineral-Fibre Blanket
1. Thermal insulation consisting of glass fibres bonded with a thermosetting resin and
complying with ASTM C 553 Type II with factory applied FSK facing.
2. K =0.036W/m°C at 24°C.
3. Density of 24kg/m3 (1.5 lb/ft3).
2.04 Field Applied Jackets
A. Foil and Paper Jacket: Laminated, glass-fibre-reinforced, flame-retardant kraft paper
and aluminum foil.
B. Canvas: 220gm/m2 cotton, plain weave, treated with dilute fire retardant lagging
adhesive to ASTM C921.
C. Aluminum Jacket: 0.40mm thick sheet manufactured from aluminum alloy complying
with ASTM B 209 and having an integrally bonded moisture barrier over entire surface
in contact with insulation.
1. Finish: Stucco embossed
2. Moisture Barrier: 0.254mm thick, heat-bonded polyethylene and kraft paper
3. Jacket banding and mechanical seals: 12mm wide, 0.5mm thick stainless steel.
D. Stainless steel: 0.25mm thick sheet manufactured from 304 or 316 stainless steel (where
shown on Contract Drawings)
1. Finish: Corrugated or stucco embossed.
2. Jacket banding and mechanical seals: 12mm wide, 0.5 mm thick stainless steel.
2.05 Accessories and Attachments
A. Glass Cloth and Tape: Comply with MIL-C-20079H, Type I for cloth and Type II for
tape. Tape width: 100mm.
B. Bands: 12mm wide, 0.5 mm thick stainless steel.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 5 of 9
C. Wire: 2mm, nickel-copper alloy; 1.5mm, soft-annealed, stainless steel.
D. Adhesive-Attached Anchor Pins and Speed Washers: Galvanized steel plate, pin, and washer manufactured for attachment to duct and plenum with adhesive. Pin length
sufficient for insulation thickness indicated. The adhesive to be recommended by the
anchor pin manufacturer as appropriate for surface temperatures of ducts, and plenums,
and to achieve a holding capacity of 445N for direct pull perpendicular to the adhered
surface.
2.06 Vapour Retarders
A. Indoor
1. Vinyl emulsion type acrylic, compatible with insulation.
B. Outdoor
1. Mastics as recommended by insulation material manufacturer that is compatible
with insulation materials, jackets, and substrates.
2. Reinforcing fabric: Fibrous glass, untreated 305g/m2.
PART 3 – EXECUTION
3.01 Examination
A. Examine substrates and conditions for compliance with requirements for installation and other conditions affecting performance of insulation application.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.02 Preparation
A. Clean and dry surfaces to receive insulation. Remove materials that will adversely affect insulation application.
3.03 General Application Requirements
A. Install in accordance with TIAC National Standards.
B. Apply materials in accordance with manufacturer’s instructions and as indicated; with smooth, straight, and even surfaces; and free of voids throughout the length of ducts and
fittings
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 6 of 9
C. Use two layers with staggered joints when required nominal thickness exceeds 75mm. Stagger seams.
D. Apply insulation with the least number of joints practical.
E. At supports apply high compressive strength insulation where insulation may be
compressed by weight of ductwork.
F. Fasteners: At 300mm oc in horizontal and vertical directions, minimum two rows
each side.
G. Keep insulation materials dry during application and finishing.
H. Apply insulation over fittings and specialties, with continuous thermal and vapour-
retarder integrity, unless otherwise indicated.
I. Hangers and Anchors: Where vapor retarder is indicated, seal penetrations in insulation
at hangers, supports, anchors, and other projections with vapour-retarder mastic. Apply
insulation continuously through hangers and around anchor attachments.
J. Insulation Terminations: For insulation application where vapor retarders are indicated, seal
ends with a compound recommended by the insulation material manufacturer to maintain vapor
retarder.
K. Cut insulation according to manufacturer's written instructions to prevent compressing
insulation to less than 75 percent of its nominal thickness.
L. Roof Penetrations: Apply insulation for interior applications to a point even with top of
roof flashing.
1. Seal penetrations with vapour-retarder mastic. 2. Apply insulation for exterior applications tightly joined to interior insulation ends. 3. Seal insulation to roof flashing with vapour-retarder mastic.
M. Interior Wall and Partition Penetrations: Apply insulation continuously through walls
and partitions, except fire-rated walls and partitions.
N. Fire-Rated Wall and Partition Penetrations: Terminate insulation at fire/smoke damper
sleeves for fire-rated wall and partition penetrations.
O. Floor Penetrations: Terminate insulation at underside of floor assembly and at floor
support at top of floor. For insulation indicated to have vapor retarders, taper
termination and seal insulation ends with vapour-retarder mastic.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 7 of 9
3.04 Duct System Applications
A. Insulation materials and thicknesses are specified in schedules at the end of this Section.
B. Insulate the following plenums and duct systems: 1. Indoor concealed supply-, return-, and outside-air ductwork. 2. Indoor exposed supply-, return-, and outside-air ductwork. 3. Outdoor exposed supply and return ductwork.
C. Unless otherwise indicated, do not apply insulation to the following systems, materials, and equipment:
1. Metal ducts with duct liner. 2. Factory-insulated flexible ducts. 3. Factory-insulated plenums, casings, terminal boxes, and filter boxes and sections. 4. Flexible connectors. 5. Vibration-control devices. 6. Testing agency labels and stamps. 7. Nameplates and data plates. 8. Access panels and doors in air-distribution systems.
3.05 Indoor Duct and Plenum Application Schedule
A. Service: Round, supply-air ducts, concealed. 1. Material: Mineral-fibre blanket. 2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Foil and paper. 5. Vapor Retarder Required: Yes.
B. Service: Round, return-air ducts, concealed. 1. Material: Mineral-fibre blanket. 2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Foil and paper. 5. Vapor Retarder Required: Yes.
C. Service: Round, outside-air ducts, concealed. 1. Material: Mineral-fibre blanket. 2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Foil and paper. 5. Vapor Retarder Required: Yes.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 8 of 9
D. Service: Rectangular, supply-air ducts, concealed. 1. Material: Mineral-fibre blanket. 2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Foil and paper. 5. Vapor Retarder Required: Yes.
E. Service: Rectangular, return-air ducts, concealed. 1. Material: Mineral-fibre blanket 2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Foil and paper. 5. Vapor Retarder Required: Yes.
F. Service: Rectangular, outside-air ducts, concealed. 1. Material: Mineral-fibre blanket. 2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Foil and paper. 5. Vapor Retarder Required: Yes.
G. Service: Round, supply-air ducts, exposed. 1. Material: Mineral-fibre board below 2400mm above floor, mineral-fibre blanket
above 2400mm above floor.
2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Glass cloth on rigid board, foil and paper on fibre blanket. 5. Vapor Retarder Required: Yes.
H. Service: Round, return-air ducts, exposed. 1. Material: Mineral-fibre board below 2400mm above floor, mineral-fibre blanket
above 2400mm above floor.
2. Thickness: 38mm inches. 3. Number of Layers: One. 4. Field-Applied Jacket: Glass cloth on rigid board, foil and paper on fibre blanket. 5. Vapor Retarder Required: Yes.
I. Service: Round, outside-air ducts, exposed. 1. Material: Mineral-fibre board below 2400mm above floor, mineral-fibre blanket
above 2400mm above floor.
2. Thickness: 38mm. 3. Number of Layers: One.
City of Toronto - Engineering and Construction Services ASHBRIDGES BAY TREATMENT PLANT
WASTE GAS BURNER FACILITY EXPANSION Contract No. 15ECS-MI-02AB
Specification Division 15 Mechanical
MECHANICAL – DUCT INSULATION
SECTION 15255 - Page 9 of 9
4. Field-Applied Jacket: Glass cloth on rigid board, foil and paper on fibre blanket. 5. Vapor Retarder Required: Yes.
J. Service: Rectangular, supply-air ducts, exposed. 1. Material: Mineral-fibre board below 2400mm above floor, mineral-fibre blanket
above 2400mm above floor.
2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Glass cloth on rigid board, Foil and paper on fibre blanket. 5. Vapor Retarder Required: Yes.
K. Service: Rectangular, return-air ducts, exposed. 1. Material: Mineral-fibre board below 2400mm above floor, mineral-fibre blanket
above 2400mm above floor.
2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Glass cloth on rigid board, foil and paper on fibre blanket. 5. Vapor Retarder Required: Yes.
L. Service: Rectangular, outside-air ducts, exposed. 1. Material: Mineral-fibre board. 2. Thickness: 38mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Glass cloth. 5. Vapor Retarder Required: Yes
3.06 Outdoor Duct and Plenum Application Schedule
A. Service: Supply-air ducts or return-air ducts. 1. Material: Mineral-fibre board. 2. Thickness: 50mm. 3. Number of Layers: One. 4. Field-Applied Jacket: Aluminum. Seal all joints and make water tight with
approved material guaranteed for 10 years.
5. Vapor Retarder Required: Yes.
END OF SECTION