10
Affordability in Shipbuilding Affordability in Shipbuilding M. W. Toner M. W. Toner October 21, 2008 October 21, 2008

Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

Affordability in ShipbuildingAffordability in ShipbuildingM. W. TonerM. W. Toner

October 21, 2008October 21, 2008

Page 2: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

2

Summary of Key PointsDescribe the Design Build Process and its impact on affordabilityDescribe actions to facilitate affordability

Design BuildCollaborative environment

ExamplesVIRGINIA – Cost PlusT-AKE – Fixed PriceCommercial Ships –Fixed Price

Page 3: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

3

Design-Build ObjectivesDesign high quality, low cost, mission-ready ships which meet the operational requirements of the NavyEstablish a cost effective process that ensures the design is complete, material is available and work packages are developed prior to construction startDevelop a cost effective ship construction plan

Increase ModularizationReduce construction labor and cost –Goal: Achieve 3rd ship learning curve on the lead shipReduce design changes identified by trades during construction

VIRGINIA Class Submarine

Lewis and Clark Class Dry Cargo/Ammunition Auxiliary

Arleigh Burke Class Destroyer

Page 4: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

4

Detail Design

Traditional Acquisition Strategy Limited Collaboration, Maximum Cost and Schedule Risk

Phase II Period Characterized By:End of competition typically results in significant design changes

Impacts schedule – causes shipbuilder to revisit early decisions, delays detail designImpacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk

Must expedite functional design to start detail design and support LLTM OrderWorld shipbuilding boom – LLTM in excess of 32 monthsForces design decisions that fail to optimize total cost

Significant Overlap between functional and detail design – reworkSignificant Overlap between detail design and start of construction

Lack of a mature design at SOC results in poor cost and schedule performanceBuild strategy is sub-optimized – construction sequence is sacrificed

CA OE CA IBR PRR

Remaining Functional Design

Long Lead Time Material – Manufacturing and Delivery Lead Time

Detail Design Arrangements and Key Plans

Modeling

Installation Drawings

Production Info

Work Packs

Construction SOC K Float Out TrialsD

CD

Year 1 Year 4 Year 5Year 3Year 2 Year 6 Year 7

Concept Design and Trade Studies

Phase I Period Characterized By:• Competition – Limited Communication

& Collaboration• Limited Funding – Can’t Complete Functional Design• FFP estimate based on incomplete information – growth likely• Interruption in Design Flow While Awaiting Competitive Down Select

Detail Design

Page 5: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

5

Concept Requirements

Definition

Concept Requirements

Definition

Functional DesignFunctional Design

Build StrategyBuild Strategy

Detail DesignDetail Design

Planning andProduction Information

Planning andProduction Information

Lead Ship ConstructionLead Ship

Construction

Follow Ship ConstructionFollow Ship Construction

Accrue input from all relevant stakeholders and requirement sets

CFREPAIMO

Navy/MIL StdsABSSUPSHIP

Facility LimitationsUSPH/FDA

ProductionSuppliers

Procure LLTM for follow ships

Work instructions (detailed work packages)

must be substantially complete prior to construction start

Purchase LLTM for lead ship

Co-Located Design Build Teams to complete design prior to start of

construction

Integrated Master Schedule

Lower Cost

Higher Cost

Cost ModelCost Uncertainty Range

Design Build Acquisition Strategy Establishes Potential for Success

For US Shipbuilding to be affordable, a paradigm shift must take placeCreate Govt/Shipbuilder partnership early enough to maximize impact of collaboration and design for producibility considerations in future shipbuilding programs

MLP-006

Cost Reduction Potential

Cost to Change

Specification Engineering Fabrication Delivery

Cost

Design Construction

Page 6: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

6

-

1,000

2,000

4,000

5,000

1 2 3 4 5 6 7 8 9 10

Traditional Acquisition Strategy Approach

Design BuildApproach

Hull Number

Labo

r Hou

rs in

100

0's

2,0582,069102,0912,13292,1292,20582,1732,29172,2242,39562,2872,5235

Total 2,1802,3662,69044492,4712,92136522,628,3,2802

1,0792,9214,0001

Potential 3 Ship Class Savings

Design Build Approach

Traditional ApproachHull

2,0582,069102,0912,13292,1292,20582,1732,29172,2242,39562,2872,5235

Total 2,1802,3662,69044492,4712,92136522,628,3,2802

1,0792,9214,0001

Potential 3 Ship Class Savings

Design Build Approach

Traditional ApproachHull

3,000

2,921

Traditional Versus Design Build Approach Lead Ship at Third Ship Cost

Notional 10-ship ClassTraditional Approach: 4M Hour Lead ShipDesign Build Approach: ~30% ReductionArea Between Curves: > 2M Hours (3-ship Class)

Notional 10-ship ClassTraditional Approach: 4M Hour Lead ShipDesign Build Approach: ~30% ReductionArea Between Curves: > 2M Hours (3-ship Class)

Page 7: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

7

Design Build in Practice SEAWOLF and VIRGINIA Submarine Programs

Perc

ent

SEAWOLF VIRGINIA

100

90

80

70

0

60

50

40

30

20

10

100

90

80

70

0

60

50

40

30

20

10

68,056

73%

40%

~50%

~6%

~1% 12,000

80K

70K

60K

50K

0

40K

30K

20K

10K

Num

ber o

f Cha

nges

Percent Design Complete at SOC

Percent Planning Complete at SOC

Percentage of Construction Manhours Comparison

Number of Trade Identified Construction Changes at Delivery

Page 8: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

8

Perc

ent

T-AKE 1 T-AKE 3

100

90

80

70

0

60

50

40

30

20

10

100

90

80

70

0

60

50

40

30

20

10

~16%~1%

9,267

70%

1,083

80K

70K

60K

50K

0

40K

30K

20K

10K

Num

ber o

f Cha

nges

Percent Design Complete at SOC

Percent Planning Complete at SOC

Percentage of Construction Manhours Comparison

Number of Trade Identified Construction Changes at Delivery

Design Maturity at SOC Reduces Cost T-AKE 3 Represents a 30% Reduction in Cost

Page 9: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

9

Design Maturity at SOC Reduces Cost Commercial Shipbuilding Examples

Percent Design Complete at SOC

Percentage Planning Complete at SOC

Percentage of Construction Manhours Comparison

Number of Trade Identified Construction Changes at Delivery

Perc

ent

TOTE 1

100

90

80

70

0

60

50

40

30

20

10

100

90

80

70

0

60

50

40

30

20

10

79%

~12%15%

12K

10K

8K

6K

0

4K

2K

Num

ber o

f Cha

nges

BP 1 PC 1

TOTE

1

TOTE

2

4,920

~13%8%

BP

1

BP

4

10,03973%

Hul

l 501

Bid

Hul

l 501

Per

form

ance

to D

ate

~1,300

Page 10: Affordability in Shipbuilding · 2017-05-19 · Impacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk. ¾. Must expedite functional design to start

10

ConclusionsThe Government/Shipbuilder Team must Change the Navy AcquisitionStrategy to Achieve the Desired Outcome

Realistic Cost EstimatingPredictable Schedule Performance High Quality, Mission Ready Ships

Shipbuilder Focus:Early Requirements DefinitionEarly Functional Design CompletionWork Paper ready at SOC

Government Focus:Short Competition for Good IdeasMaximize Opportunities for Collaboration Before the Start of Detail Design

Design-Build Represents the Way Ahead –Results are Well Established

VCS Program – 27% reduction in lead ship labor hoursPC-1 Program – Lead ship on schedule, under budget, minimal design change