Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Affordability in ShipbuildingAffordability in ShipbuildingM. W. TonerM. W. Toner
October 21, 2008October 21, 2008
2
Summary of Key PointsDescribe the Design Build Process and its impact on affordabilityDescribe actions to facilitate affordability
Design BuildCollaborative environment
ExamplesVIRGINIA – Cost PlusT-AKE – Fixed PriceCommercial Ships –Fixed Price
3
Design-Build ObjectivesDesign high quality, low cost, mission-ready ships which meet the operational requirements of the NavyEstablish a cost effective process that ensures the design is complete, material is available and work packages are developed prior to construction startDevelop a cost effective ship construction plan
Increase ModularizationReduce construction labor and cost –Goal: Achieve 3rd ship learning curve on the lead shipReduce design changes identified by trades during construction
VIRGINIA Class Submarine
Lewis and Clark Class Dry Cargo/Ammunition Auxiliary
Arleigh Burke Class Destroyer
4
Detail Design
Traditional Acquisition Strategy Limited Collaboration, Maximum Cost and Schedule Risk
Phase II Period Characterized By:End of competition typically results in significant design changes
Impacts schedule – causes shipbuilder to revisit early decisions, delays detail designImpacts cost performance – Phase II FFP bid inadequate, shipbuilder financial risk
Must expedite functional design to start detail design and support LLTM OrderWorld shipbuilding boom – LLTM in excess of 32 monthsForces design decisions that fail to optimize total cost
Significant Overlap between functional and detail design – reworkSignificant Overlap between detail design and start of construction
Lack of a mature design at SOC results in poor cost and schedule performanceBuild strategy is sub-optimized – construction sequence is sacrificed
CA OE CA IBR PRR
Remaining Functional Design
Long Lead Time Material – Manufacturing and Delivery Lead Time
Detail Design Arrangements and Key Plans
Modeling
Installation Drawings
Production Info
Work Packs
Construction SOC K Float Out TrialsD
CD
Year 1 Year 4 Year 5Year 3Year 2 Year 6 Year 7
Concept Design and Trade Studies
Phase I Period Characterized By:• Competition – Limited Communication
& Collaboration• Limited Funding – Can’t Complete Functional Design• FFP estimate based on incomplete information – growth likely• Interruption in Design Flow While Awaiting Competitive Down Select
Detail Design
5
Concept Requirements
Definition
Concept Requirements
Definition
Functional DesignFunctional Design
Build StrategyBuild Strategy
Detail DesignDetail Design
Planning andProduction Information
Planning andProduction Information
Lead Ship ConstructionLead Ship
Construction
Follow Ship ConstructionFollow Ship Construction
Accrue input from all relevant stakeholders and requirement sets
CFREPAIMO
Navy/MIL StdsABSSUPSHIP
Facility LimitationsUSPH/FDA
ProductionSuppliers
Procure LLTM for follow ships
Work instructions (detailed work packages)
must be substantially complete prior to construction start
Purchase LLTM for lead ship
Co-Located Design Build Teams to complete design prior to start of
construction
Integrated Master Schedule
Lower Cost
Higher Cost
Cost ModelCost Uncertainty Range
Design Build Acquisition Strategy Establishes Potential for Success
For US Shipbuilding to be affordable, a paradigm shift must take placeCreate Govt/Shipbuilder partnership early enough to maximize impact of collaboration and design for producibility considerations in future shipbuilding programs
MLP-006
Cost Reduction Potential
Cost to Change
Specification Engineering Fabrication Delivery
Cost
Design Construction
6
-
1,000
2,000
4,000
5,000
1 2 3 4 5 6 7 8 9 10
Traditional Acquisition Strategy Approach
Design BuildApproach
Hull Number
Labo
r Hou
rs in
100
0's
2,0582,069102,0912,13292,1292,20582,1732,29172,2242,39562,2872,5235
Total 2,1802,3662,69044492,4712,92136522,628,3,2802
1,0792,9214,0001
Potential 3 Ship Class Savings
Design Build Approach
Traditional ApproachHull
2,0582,069102,0912,13292,1292,20582,1732,29172,2242,39562,2872,5235
Total 2,1802,3662,69044492,4712,92136522,628,3,2802
1,0792,9214,0001
Potential 3 Ship Class Savings
Design Build Approach
Traditional ApproachHull
3,000
2,921
Traditional Versus Design Build Approach Lead Ship at Third Ship Cost
Notional 10-ship ClassTraditional Approach: 4M Hour Lead ShipDesign Build Approach: ~30% ReductionArea Between Curves: > 2M Hours (3-ship Class)
Notional 10-ship ClassTraditional Approach: 4M Hour Lead ShipDesign Build Approach: ~30% ReductionArea Between Curves: > 2M Hours (3-ship Class)
7
Design Build in Practice SEAWOLF and VIRGINIA Submarine Programs
Perc
ent
SEAWOLF VIRGINIA
100
90
80
70
0
60
50
40
30
20
10
100
90
80
70
0
60
50
40
30
20
10
68,056
73%
40%
~50%
~6%
~1% 12,000
80K
70K
60K
50K
0
40K
30K
20K
10K
Num
ber o
f Cha
nges
Percent Design Complete at SOC
Percent Planning Complete at SOC
Percentage of Construction Manhours Comparison
Number of Trade Identified Construction Changes at Delivery
8
Perc
ent
T-AKE 1 T-AKE 3
100
90
80
70
0
60
50
40
30
20
10
100
90
80
70
0
60
50
40
30
20
10
~16%~1%
9,267
70%
1,083
80K
70K
60K
50K
0
40K
30K
20K
10K
Num
ber o
f Cha
nges
Percent Design Complete at SOC
Percent Planning Complete at SOC
Percentage of Construction Manhours Comparison
Number of Trade Identified Construction Changes at Delivery
Design Maturity at SOC Reduces Cost T-AKE 3 Represents a 30% Reduction in Cost
9
Design Maturity at SOC Reduces Cost Commercial Shipbuilding Examples
Percent Design Complete at SOC
Percentage Planning Complete at SOC
Percentage of Construction Manhours Comparison
Number of Trade Identified Construction Changes at Delivery
Perc
ent
TOTE 1
100
90
80
70
0
60
50
40
30
20
10
100
90
80
70
0
60
50
40
30
20
10
79%
~12%15%
12K
10K
8K
6K
0
4K
2K
Num
ber o
f Cha
nges
BP 1 PC 1
TOTE
1
TOTE
2
4,920
~13%8%
BP
1
BP
4
10,03973%
Hul
l 501
Bid
Hul
l 501
Per
form
ance
to D
ate
~1,300
10
ConclusionsThe Government/Shipbuilder Team must Change the Navy AcquisitionStrategy to Achieve the Desired Outcome
Realistic Cost EstimatingPredictable Schedule Performance High Quality, Mission Ready Ships
Shipbuilder Focus:Early Requirements DefinitionEarly Functional Design CompletionWork Paper ready at SOC
Government Focus:Short Competition for Good IdeasMaximize Opportunities for Collaboration Before the Start of Detail Design
Design-Build Represents the Way Ahead –Results are Well Established
VCS Program – 27% reduction in lead ship labor hoursPC-1 Program – Lead ship on schedule, under budget, minimal design change