Upload
kenneth-shaw
View
215
Download
1
Embed Size (px)
Citation preview
2008
SSEPD Energy storage projects
2010
2011
2012
100 kW Flow Battery
1 MW NaS Battery 2 MW Lithium Battery
3 x 25 kW Lithium Batteries
Installed 1 MW / 6 MWh NaS battery
• Significant safety incident in Japan has halted progress• Currently awaiting results of detailed investigation before making a decision on project status
Project drivers
• The uptake of low carbon technologies is already having an impact on how we operate our LV networks:
- Solar PV- Heat pumps- Electric vehicles
• Traditional solution is to replace cable / associated plant
• Can energy storage be used to mitigate these effects?
• Is there an operational / economic case over existing solutions?
Overview
• Small array to prove functionality• 3x single phase, 25kVA batteries
connected at 230V
• Located towards the end of the circuit for SSE Zero Carbon Homes project
• Determine operational issues and benefits:• Peak lopping demand &
generation• Voltage support from real /
reactive power• Aggregated reduction in peak
demand and phase balancing
• Presently have a comms fault internal to the battery in two of the
units
• Working with manufactured to resolve situation
• Basic test programme started July 2012 – moving into detailed
testing of the units to flatten demand and manipulate voltage
• Learning will feed into the larger project rollout under Tier 2
Next steps
• Project within timescales / budget
• Safety case / risk assessment completed
• All three battery units successfully installed
• Manufacturer commissioning and G59 compliance completed
• Radio communications working as intended
• Enmac integration complete
• Test programme to run for 2 years
• Formal learning report released 2014
Summary
Orkney battery - Service Based Contract
• Battery not owned or operated by network business• Service procured – Constraint management• Battery owner free to trade across multiple markets