4
CASE STUDY TUNNEL RELINE ALUMINUM TUNNEL LINER PLATE RELINE Due to the high costs of replacing failing infrastructure, interest is growing for the rehabilitation of existing steel and concrete structures in a variety of different geometries. Relines with Tunnel Liner Plate offer superior solutions because they are often constructed more quickly than other building alternatives, can provide significant cost savings in locations where structures have a high amount of ground cover, and cause the least amount of disruption to the general public. Owner Public Works Canada Contractors General - J-1 Contracting Ltd. Sub - S&H Construction Consultants Meridian Engineering Location Terra Nova National Park, Newfoundland THE HOST MULTI-PLATE STRUCTURE WITH ALUMINUM TUNNEL LINER PLATES LAID AT OPENING

ALUMNUMI TUNNEL LINER PLATE RELINE - Armtec · CASE STUDY TUNNEL RELINE ALUMNUMI TUNNEL LINER PLATE RELINE Due to the high costs of replacing failing infrastructure, interest is growing

Embed Size (px)

Citation preview

CASE STUDY

TUNNEL RELINE

ALUMINUM TUNNEL LINER PLATE RELINE

Due to the high costs of replacing failing infrastructure, interest is growing for the rehabilitation of existing steel and concrete structures in a variety of different geometries. Relines with Tunnel Liner Plate offer superior solutions because they are often constructed more quickly than other building alternatives, can provide significant cost savings in locations where structures have a high amount of ground cover, and cause the least amount of disruption to the general public.

OwnerPublic Works Canada

ContractorsGeneral - J-1 Contracting Ltd. Sub - S&H Construction

ConsultantsMeridian Engineering

LocationTerra Nova National Park, Newfoundland

THE HOST MULTI-PLATE STRUCTURE WITH ALUMINUM TUNNEL LINER PLATES LAID AT OPENING

BACKGROUND

In the Fall of 2012, Armtec was asked by Public Works Canada to visit a site in Terra Nova National Park in Eastern Newfoundland and assess the possibility of rehabilitating a 47-year old structure, installed in 1965 using Armtec Multi-Plate. At the site meeting it was determined that a rehabilitation with Tunnel Liner Plate would be the right solution and aluminum plate was selected because of the long service life it would provide. Because of its location at the bottom of a steep embankment, accessibility to the existing culvert was a challenge. The portability of the product made it a great solution for the unique geography of the project. Tunnel Liner Plate, which only Armtec manufactures in Canada, could be shipped to the site and hand-carried in segments weighing only 9-14kg through the length of the existing host structure for erection. The alternative choice would have been to incur significant construction costs in building the access infrastructure, which could also negatively impact the park’s environmentally sensitive area.

DESIGN

After Public Works Canada determined that Tunnel Liner Plate would be most suitable for the installation, Armtec’s engineering team quickly prepared a detailed set of drawings and specifications for Public Works Canada to review. In the summer of 2013, a tender was called for the work which included Armtec’s drawings and specifications in the tender package.

INSTALLATION

As the only manufacturer of Tunnel Liner Plate in Canada, Armtec’s Newfoundland team secured the business in late 2013, began installation of the structure in May 2014, and completed the project the following month. The work involved relining the existing 2,430mm diameter Armtec Multi-Plate which was installed under 8m of cover with a new 2,250mm diameter Aluminum Tunnel Liner Plate. During construction, the site was visited by a number of parties such as Engineering Consultants, Department of Transportation Engineers, and Public

Works Engineers. Given the unique challenges posed by the project, there was tremendous interest in Armtec’s solution, so much so that one worker proposed (tongue-in-cheek of course) charging every visitor a toll to see the project! Feedback from visitors to the site was overwhelmingly positive and Armtec’s products generated a substantial amount of interest.

The installation of Armtec’s Aluminum Tunnel Liner Plate was a successful project for Public Works Canada and caused little disruption to the visitors of Terra Nova National Park. More importantly, there was little environmental impact to the area.

To learn more about this project or for more information on Armtec’s various Tunnel Liner Plate options, please speak with an Armtec Representative or visit our website at www.armtec.com.

“Given the unique challenges posed by the project, there was tremendous interest in Armtec’s [Tunnel Liner] solution, so much so that one worker proposed (tongue-in-cheek of course) charging every visitor a toll to see the project!”

Rick Hobbs, Owner, S&H Construction

ALUMINUM TUNNEL LINER PLATE RELINE

THREADED GROUT PORT

PROJECT OVERVIEW

1) 10” pump at upstream end, allowed Multi-Plate to be completely dewatered.

2) Existing Multi-Plate was cleaned of all debris and rocks.

3) Plates were placed in bundles at upstream end of culvert by excavator.

4) Plates were brought into the structure by hand, according to plate layout per ring.

5) Crew of 3 assembled 5 plates inside structure. Final top plate was then put into position to complete the first ring.

6) 2x4 was used as blocking to ensure uniform spacing and proper alignment.

7) Second ring was assembled with 5 plates and moved into place next to first ring. Once in place, final top plate was placed into position. Each ring was bolted to the previous ring through an inward projecting vertical flange. This allowed assembly to be completed from inside the host structure.

8) After three days, crew of three was able to complete 20 rings per day.

9) Once all rings were completed, bolts were tightened to the specified torque of 115-135 foot pounds.

10) Grouting was completed using a portable concrete pump. The grout mixture was a freely flowing mixture with an approximate 6” slump that was pumped through 2” grout plugs located throughout the structure. Grout was placed in 3 uniform lifts along both sides of the pipe while ensuring the design diameter of the reline pipe was held at all times.

11) Grout was injected into the grout ports and the ABS plug was secured to prevent the grout from flowing out.

12) Sand bags were placed around the structure inlet and outlet ends to prevent grout from flowing out at the ends.

STATS

Plate Weight: 9-14kgs

Ring Width: 500mm

Total Rings Used: 87

MONITORING THE GROUT PROCESS

INJECTING GROUT INTO THE GROUT PORTS

INSTALLATION COMPLETE

1-877-5-ARMTEC | ARMTEC.COM

Armtec is a leading Canadian infrastructure and construction materials company combining creative engineered solutions, relevant advice, dedicated people, proven products and a national presence with a local focus on exceptional customer service.

Armtec / Case Study / Aluminum Tunnel Liner Plate Reline | 2014–01

ALUMINUM TUNNEL LINER PLATE RELINE

MORE ABOUT TERRA NOVA NATIONAL PARK:

Terra Nova National Park is located in eastern Newfoundland, approximately 200km west of St. John’s and 60km east of Gander, NL. Abundant natural resources, such as fish and sea mammals, have attracted people to the Terra Nova area for at least 5,000 years. Prehistoric peoples and European settlers depended on the rich resources of the sea and land, as do many people in the region today. The significance of the area’s natural and cultural heritage was officially recognized in 1957 when Terra Nova became Newfoundland’s first national park. Today, people continue to be attracted to this land because of the abundant wildlife, exceptional scenery and array of recreational activities.*

TERRA NOVA NATIONAL PARK

TERRA NOVA NATIONAL PARK

*SOURCE: Parks Canada http://www.pc.

gc.ca/eng/pn-np/nl/terranova/natcul.aspx