Analysis for Building

Embed Size (px)

Citation preview

  • 8/13/2019 Analysis for Building

    1/51

    2.32

    Code Description Unit Quantity Rate Amount

    Details of cost for 100 sqm.

    Labour

    0114 Beldars Day 0.60 135.00 81.00

    0115 Coolies Day 0.25 125.00 31.25

    9999 Sundries L.S. 1.82 1.26 2.29

    Total 114.54

    Add 1% for water charges 1.15

    Total 115.69

    Add 15% for contractors profit

    and overheads 17.35

    Cost of 100 sqm. 133.04

    Cost of 1 sqm. 1.33

    2.35.1.1

    2.35.2

    Code Description Unit Quantity Rate Amount

    Details of cost for 10 metres

    Materials:

    Chlorpyriphos 1%

    concentration =10.0x0.30x7.5 =

    22.5 litres7022 Chlorpyriphos 20% E.C.

    required 22.5/20 = litre 1.125 to

    be 0.001.125 litres. Supplied free of

    costLabour

    0114 Beldars (for excavating

    channel ) rodding in chemical

    spraying the emulssion and

    refilling the same Day 0.33

    135.25 44.63 Day 0.33 135.00 44.55

    9999 Sundries and rent of

    sprayer etc L.S. 13.52 1.00

    13.52 L.S 13.52 1.26 17.04

    TOTAL 61.59

    Add 1% for water charges 0.62TOTAL 62.20

    Add 15% for C.P. and

    overheads 9.33

    Cost of 10 sqm 71.53

    Cost of 1 sqm. 7.152.35 :

    2.35.2 :

    2.35.2.1 : With Chlorpyriphos/Lindane E.C. 20% with 1% concentration.

    Clearing grass and removal of the rubbish up to a distance of 50 m

    Outside the periphery of the area cleared.

    Along external wall where the apron is not provided using chemical

    emulsion @ 7.5 litres / sqm of the vertical surface of the substructure to a

    With Chlorpyriphos/Lindane E.C. 20% with 1% concentration

    Diluting and injecting chemica emulsion for POST-CONSTRUCTIONAL anti-

    Along the external wall below concrete or masonry apron using chemical

  • 8/13/2019 Analysis for Building

    2/51

    Code Description Unit Quantity Rate Amount

    Details of cost for 10 metres

    Materials:

    7022Chlorpyriphos 1% concentration =

    10x2.25 =22.5 litres litre 1.125

    to be supplied

    free of cost0.000

    Chlorpyriphos 20% required =

    22.5/20 = 1.125 litres

    Labour:

    0114Beldar (for drilling holes and

    injecting chemical) Day 0.40 135.00 54

    9,999

    Sundries and rent of a sprayer and

    mortar and making good the holes

    L.S. 35.88 1.26 45.21TOTAL 99.21

    Add 1 % for water charges 0.99TOTAL 100.20

    Add for contractors profit and

    overheads @ 15% 15.03Cost for 10 metres 115.23

    Cost for 1 metre 11.52

    Details of Cost for 100 Cum.

    Labour

    (i) Mistry Nos 0.16 200.00 32.00

    (ii) Beldar Nos 13.33 135.00 1799.55

    (iii) Coolies Nos 5.00 125.00 625.00

    (iv) Black smith for sharpening of

    tools etc. Nos 0.16 190.00 30.40

    (v) Sundries Nos 0.00 0.00

    Total 2486.95

    373.04Total 2859.99

    28.60

    2.34

    2.34.1

    Code Description Unit Quantity Rate Amount

    Details of cost of 100 litres

    7022 Chlorpyriphos E.C. 20% Litre 100.00 150.00 15000.00

    2342 Carriage of chemical quintal 1.00 5.32 5.32

    Total 15005.32

    Add 1% for water charges 150.05Total 15155.37

    Add for contractors profit and

    overheads @ 15% 2273.31

    Cost for 100 litres 17428.68

    Cost for 01 litres 174.29

    Say 174.30

    2.27

    Filling availble excatvated earth (Excluding rock) in trenches plinth side of

    Add 15 % C.P

    Cost of 1 cum

    Supplying chemical emulsion in sealed containers including delivery as spe

    Chlorpyriphos/ Lindane emulsifiable concentrate of 20%

    Supplying and filling in plinth with Jamuna sand under floors including,

  • 8/13/2019 Analysis for Building

    3/51

    Code Description Unit Quantity Rate Amount

    Details of cost for 10 cum.

    Materials

    6501 Jamuna sand cum 10.00 247.00 2470.00

    2335 Carriage of Jamuna sand cum 10.00 0.00 0.00

    Labour

    0114 Beldars Day 0.89 135.00 120.15

    0115 Coolies Day 1.07 125.00 133.75

    0101 Bhishti Day 0.35 160.00 56.00

    Total 2779.90

    Add for water charge @ 1 % 27.80

    Total 2807.70

    Add for contractors profit and

    over-heads @ 15% 421.15

    Cost of 10 cum. 3228.85

    Cost of 1 cum. 322.89

    4.1.8

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 1 Cum.

    MATERIALS

    Stone aggregate 40 mm Cum 0.65 1220.00 793.00

    Stone aggregate 20 mm Cum 0.24 1270.00 304.80

    Coarse Sand Cum 0.47 1150.00 540.50

    Cement 0.2833 Cum. Tonne 0.17 5060.00 860.20

    LABOUR

    Mason Each 0.10 190.00 19.00

    Beldar Each 1.63 135.00 220.05

    Bhisti Each 0.70 160.00 112.00

    Mixer Each 0.07 400.00 28.00

    Vibrator Each 0.07 200.00 14.00

    Sundries L.S. 13.52 1.26 17.04

    TOTAL 2908.59

    Add 1% For water charges 29.09

    TOTAL 2937.67

    Add 15 % For contractor profit 440.65

    3378.32

    4.17

    Code Description Unit QTY. Rate Amount

    Details of cost for 10 sqm

    Materials

    0287 Brick aggregate 40 mm size cum 0.75 360.00 270.00

    2260 Carriage of brick aggregate cum 0.75 0.00

    0983 Fine sand 60 cu.dm. per 10

    sqm

    cum 0.06 247.00 14.82

    2261 Carriage of Fine sand cum 0.06 0.00

    watering, ramming consolidating and dressing complete.

    1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal

    Making plinth protection 50mm thick of cement concrete 1:3:6 (1 cement

  • 8/13/2019 Analysis for Building

    4/51

    Dressing the ground including

    cutting and filling up to 15 cm

    0114 Beldar Day 0.16 135.00 21.60

    0114 Coolie Day 0.11 125.00 13.75

    Cement concrete 1:3:6 Qty. of

    cement

    concrete 1:3:6 on 10 sqmarea = 0.5 cum

    Materials (for C.C. 1:3:6)

    0295 Stone aggregate 20 mm

    nominal size

    cum 0.35 1270.00 444.50

    0297 Stone aggregate 10 mm

    nominal size

    cum 0.12 1270.00 152.40

    2202 Carriage of stone aggregate cum 0.47 0.00 0.00

    0982 Coarse sand cum 0.23 1150.00 264.50

    2203 Carriage of Coarse sand cum 0.23 0.00 0.00

    367 Cement tonne 0.11 5060.00 556.60

    2209 Carriage of cement tonne 0.11 0.00 0.00 Labour (for C.C. 1:3:6)

    0114 Beldar Day 1.00 135.00 135.00

    0155 Mason Day 0.05 190.00 9.50

    0101 Bhishti Day 0.33 160.00 52.80

    9999 Hire and runing charges of

    mechanical mixer

    L.S. 13.39 1.26 16.87

    9999 Sundries 6.76 1.26 8.52

    Labour

    0155 Mason Day 0.27 190.00 51.30

    0114 Beldar Day 1.08 135.00 145.80

    0115 Coolie Day 1.08 125.00 135.00

    TOTAL 2292.96

    Add 1% for water charges 22.93

    TOTAL 2315.89

    Add 15% for C.P. and

    overheads

    347.38

    Cost for 10 sqm 2663.27

    Cost for 1 sqm 266.33

    5.33

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 1.00 Cum.

    MATERIALSStone aggregate 20 mm Cum 0.57 1270.00 723.90

    Stone aggregate 10 mm Cum 0.28 1270.00 355.60

    Coarse Sand Cum 0.425 1150.00 488.75

    Cement 0.2833 Cum. Tonne 0.41 5060.00 2074.60

    Plasticizer 0.50% of cement 2.05 30.00 61.50

    Production cost of concrete by

    batch mix plant. 1.00 200.00 200.00

    Providing and laying in position machine batched, machine mixed and machine

  • 8/13/2019 Analysis for Building

    5/51

    Pumping charges of concrete.1.00 80.00 80.00

    LABOUR

    Mason Each 0.17 190.00 32.30

    Beldar Each 2.00 135.00 270.00

    Bhisti Each 0.90 160.00 144.00

    0.07 Vibrator Each 0.07 200.00 14.00

    Sundries L.S. 13.00 1.26 16.38TOTAL 4461.03

    Add 1% For water charges 44.61

    TOTAL 4505.64

    Add 15 % For contractor profit 675.85

    5181.49

    5.9

    5.9.1

    Code Description Unit Quantity Rate Amount

    Details of cost for footing size

    2.70 m x 2.70 m x 1.00 m

    Contact area = 10.80 Sqm.

    Materials :

    Assuming shuttering material will

    become

    unserviceable after use of 40

    times

    Adding for maintenance @ 10

    % of cost

    Taking salvage value after full

    use of material

    @ 25 % of cost7319 Wall form panel 1250x500mm each 0.34 980.00 333.20

    Qty taken for cost of using once

    =16x0.85/40 = 0.34

    7326 Corner angle ( 1.50 m long ) each 0.085 280.00 23.80

    Qty taken for cost of using once

    =4x0.85/40 = 0.085

    7327 100mm channel shoulders 2.5 m

    long

    each 0.17 1000.00 170.00

    Qty taken for cost of using once

    =8x0.85/40 = 0.17

    7328 Double clip ( bridge clip ) each 0.34 75.00 25.50

    Qty taken for cost of using once=16x0.85/40 = 0.34

    7329 Single clip each 0.17 60.00 10.20

    Qty taken for cost of using once

    =8x0.85/40 = 0.17

    7330 MS tube 40 mm = 4x2.70m =

    10.80 m

    metre 0.2295 225.00 51.64

    Qty taken for cost of using

    once=10.8x0.85/40=0.2295

    Centering and shuttering including strutting, propping etc. and removal of form

    Foundations, footings, bases of columns, etc. for mass concrete.

  • 8/13/2019 Analysis for Building

    6/51

    9999 Assembly nuts & bolts L.S. 22.10 1.26 27.85

    Qty taken for cost of using

    once=1040x0.85/40=22.10

    9999 Carriage L.S. 78.00 1.26 98.28

    Labour :

    0116 Fitter Grade-I Day 0.75 150.00 112.50

    0114 Beldar Day 1.50 135.00 202.50

    9999 Shuttering oil L.S. 52.00 1.26 65.529999 Sundries L.S. 26.00 1.26 32.76

    TOTAL 1153.74

    Add 1% for water charges 11.54

    TOTAL 1165.28

    Add 15% for C.P. and

    overheads

    174.79

    Cost of 10.80 Sqm 1340.07

    Cost of 1 Sqm 124.08

    Say 124.08

    5.9

    5.9.3

    Code Description Unit Quantity Rate Amount

    Details of cost for a room

    4.50x3 = 13.50 sqm, height 3.50

    m

    Materials :

    Adding for maintenance @ 10

    % of cost

    Taking salvage value after full

    use of material @ 25 % of cost 1. Plates ( size 0.75x0.60 )

    Angle 40x40x5mm

    2x0.75 = 1.50 m

    2x0.60 = 1.20 m

    =2.70 m @ 3.00 kg/m = 8.10 kg

    sheet 1.60 mm thick

    0.75x0.60 =0.45 sqm

    0.45 sqm @ 12.55 kg/sqm

    =5.65 kg

    Weight of one plate =13.75 kg

    Add for wastage @ 5% = 0.69kg

    Total weight of all plates = 5x 6 x

    14.44 = 433.20 kg

    Qty taken for cost of using once =

    433.20 x 0.85 / 40 =9.2055 kg

    kg 9.2055 42.64 392.52

    Centering and shuttering including strutting, propping etc. and removal of form

    Suspended floors, roofs, landings, balconies and access platform.

  • 8/13/2019 Analysis for Building

    7/51

    7342 2. Adjustable span- ESOSI ( 2.35

    3.40m ) Qty taken for cost of

    using once=5x0.85/40=0.1063

    each 0.1063 1600.00 170.08

    7343 3. Adjustable telscopi prop

    3m(2.02-3.75m)

    each 0.1275 1000.00 127.50

    Qty taken for cost of using

    once=6x0.85/40=0.12759999 4. Assembly Nuts & bolts etc. L.S. 22.10 1.26 27.85

    Qty taken for cost of using

    once=1040x0.85/40=22.10

    9999 Carriage L.S. 130.00 1.26 163.80

    Labour :

    0116 Fitter Grade-I Day 3.00 150.00 450.00

    0114 Beldar Day 6.00 135.00 810.00

    9999 Shuttering oil L.S. 78.00 1.26 98.28

    9999 Sundries L.S. 50.02 1.26 63.03

    TOTAL 2303.05

    Add 1% for water charges

    except on 'X'

    19.11

    TOTAL 2322.16

    Add 15% for C.P. and

    overheads except on 'X'

    289.45

    Cost of 13.50 Sqm 2611.60

    Cost of 1 Sqm 193.45

    Say 193.45

    5.9

    5.9.5

    Code Description Unit Quantity Rate Amount

    Consider a beam of 6.0m clear

    span, 0.50 m deep

    0.30 m wide and height 3.50 m

    from floor

    6.60x0.50x0.30 =0.99 cum

    1x1.30x6.00 =7.80 sqm

    Materials :

    Assuming shuttering will become

    unserviceable after use of 40

    times Adding for maintenance @

    10% of cost of material Less

    salvage value of material after @25 % of cost of material full use

    1. Steel plates for sides and

    bottom

    ( plate size 1.20x0.50 )

    Angle 40x40x5mm

    2x1.20 = 2.40 m , 3x0.50 = 1.50

    m

    Lintels, beams, plinth beams, girders, bressumers and cantilevers.

    Centering and shuttering including strutting, propping etc. and removal of form

  • 8/13/2019 Analysis for Building

    8/51

    Total 3.90 m @ 3.00 kg/m =

    11.70 kg

    sheet 1.60 mm thick

    1.20x0.50 =0.60 sqm

    0.45 sqm @ 12.55 kg/sqm

    =7.53 kg

    Weight of one plate =19.23 kg +

    Add for wastage @ 5% = 0.96 kgTotal =20.19 Kg

    Total weight of all plates

    3x5x20.19 = 302.85 Kg or 3.03 q

    Qty taken for cost of using

    once=302.85x0.85/40

    =6.4356 kg

    (X) Rate as per item no 10.1 kg 6.4356 42.64 274.41

    7343 (ii) Adjustable telscopi prop

    3m(2.02-3.75m)

    each 0.1275 1000.00 127.50

    Qty taken for cost of using

    once=6x0.85/40=0.12757344 (iii) Beam clamp 300-380 mm

    (450-1070mm)

    each 0.1063 375.00 39.86

    Qty taken for cost of using

    once=5x0.85/40=0.1063

    set

    9999 4. Assembly Nuts & bolts etc. L.S. 22.10 1.26 27.85

    Qty taken for cost of using

    once=1040x0.85/40=22.10

    9999 Carriage L.S. 78.00 1.26 98.28

    Labour :

    0116 Fitter Grade-I Day 1.25 150.00 187.50

    0114 Beldar Day 2.50 135.00 337.50

    9999 Shuttering oil L.S. 39.00 1.26 49.14

    9999 Sundries,paper tape etc. L.S. 24.61 1.26 31.01

    TOTAL 1173.05

    Add 1% for water charges

    except on 'X'

    8.99

    TOTAL 1182.04

    Add 15% for C.P. and

    overheads except on 'X'

    136.14

    Cost of 7.80 Sqm 1318.18

    Cost of 1 Sqm 169.00

    Say 169.00

    5.9

    5.9.6

    Code Description Unit Quantity Rate Amount

    Details of cost for

    Size of column 450x450 mm and

    2.50 m high

    Centering and shuttering including strutting, propping etc. and removal of form

    Columns, Pillars, Piers, Abutments, Posts and Struts.

  • 8/13/2019 Analysis for Building

    9/51

  • 8/13/2019 Analysis for Building

    10/51

    (i) Cost of plank 38 mm (2nd

    class kail wood )

    Waist 2.69x1.30 =3.50 sqm.

    Side shuttering of steps and side

    of waist-Steps

    =8x1.30x1.15 = 1.56 sqm.

    face of landing 1x1.30x0.15

    =0.20 sqm.Side of waist 2.69x0.13

    =0.35 sqm

    Side of steps

    8x0.50x0.30x0.15 = 0.18 sqm

    Total = 5.79 sqm.

    Wastage 5% =0.29 sqm.

    Total = 6.08 sqm.

    Cubical content = 6.08x0.038=

    0.231cum=231 dm3

    1198 Qty taken for cost of using

    once=231/8=28.875dm3

    10 dm3 28.875 178.00 513.98

    (ii) Batten 100 mm X 75 mm

    ( 2nd class kail wood in scantling

    )

    4x1.30x0.100x0.075 = 0.039 cum

    =39 dm3

    1197 Qty taken for cost of using once =

    39 / 8 = 4.875 dm3

    10 dm3 4.875 160.00 78.00

    (iii) Safeda Ballies 125 mm dia

    2 x 4 x 0.80 = 6.40m

    302 Qty taken for cost of using once=

    6.40/8 = 0.80 m

    metre 0.80 29.00 23.20

    Carriage of timber- Planks = 0.231 cum.

    Battens = 0.039 cum

    Ballies 6.4x3.142/4x(0.125)2

    =

    0.079 cum.

    Total = 0.349 cum

    2204 Qty taken for cost of using

    once=0.349/8=.04363m3

    cum 0.04363 60.81 2.65

    Labour

    For assembling, erection,

    dismantling & cleaning

    0112 Carpenter 2nd class Day 1.75 190.00 332.50

    0114 Beldar Day 1.00 135.00 135.00

    9999 Sundries L.S. 16.12 1.26 20.31

    TOTAL 1105.64

    Add 1% for water charges 11.06

    TOTAL 1116.70

    Add 15% for C.P. and

    overheads

    167.50

    Cost of 5.79Sqm 1284.20

  • 8/13/2019 Analysis for Building

    11/51

    Cost of 1 Sqm 221.80

    Say 221.80

    5.9

    5.9.16

    5.9.16.1 Under 20 cm wide

    Code Description Unit Quantity Rate Amount

    Under 20 cm wide

    Consider a 3mx3m slab 15 cm

    thick

    12m edge length

    Assuming that the timber will

    become

    unserviceable after being used 8

    times.

    (i) Planks 30mm thick(2nd class

    kail wood or

    equivalent local soft wood)

    4x3 x 0.15 x0.030 = 0.054 cum

    Wastage @ 5% =0.003 cum

    Total = 0.057 cum. Or 57 cudm

    1198 Qty taken for cost of using

    once=57/8=7.125 cudm10 dm

    3 7.125 178.00 126.83

    (ii)Battens 75mmx100mm(2nd

    class Kail wood)

    Horizontal 2x4x0.075x0.10x0.50

    =0.030

    Horizontal 2x4x0.075x0.10x1.50

    =0.090

    (iii)Vertical battens

    16 x 0.15 x 0.075 x 0.03 M =

    0.0054

    (iv) Struts

    16 x 0.25 x 0.075 x 0.075 =

    0.0225

    Total 0.1479 cum

    Wastage @ 5% =0.0074 cum

    Total = 0.1553 cum = 155 cudm

    1197 Qty taken for cost of using

    once=155/8= 19.375dm3

    10 dm3 19.375 160.00 310.00

    Carriage of timber

    Planks = 0.057 cum

    Battens = 0.155 cum

    Total = 0.212 cum

    2204 Qty taken for cost of using

    once=0.212/8=

    cum 0.0265 60.81 1.61

    Centering and shuttering including strutting, propping etc. and removal of form

    Edges of slabs and breaks in floors and walls

  • 8/13/2019 Analysis for Building

    12/51

    0.0265 cum

    Labour

    For assembling, erection,

    dismantling & cleaning

    0112 Carpenter 2nd class Day 0.81 190.00 153.90

    0114 Mazdoor(Male) Day 0.54 135.00 72.90

    9999 Sundries L.S. 5.2 1.26 6.55

    TOTAL 671.79 Add 1% for water charges 6.72

    TOTAL 678.51

    Add 15% for C.P. and

    overheads

    101.78

    Cost of 12 metres 780.28

    Cost of one metre 65.02

    5.11

    5.11.1

    Code Description Unit Quantity Rate Amount

    Details of cost for a room of size

    6mx4.8m =

    28.80 sqm

    Materials

    Assuming that shuttering material

    will become

    unserviceable after use 40 times

    Less salvage value of material

    after full use @

    25% of cost of materials

    Add 10% of cost of material for

    maintenance

    1. Prop 4 m

    7345 Qty taken for cost of using

    once=21x0.85/40=

    each 0.4463 1030.00 459.69

    0.4463

    1. Prop 3 m

    7343 Qty taken for cost of using

    once=21x0.85/40=

    each 0.4463 1000.00 446.30

    0.4463

    Diffrence of rate between 4 m prop

    and 3 m prop 7 x 3

    2.Bracing

    M.S. tube 40 mm

    7 x 4.80 m = 33 60 m

    3 x 6.0 m = 18.00 m

    Total = 51.60 m

    7330 Qty taken for cost of using

    once=51.60x0.85/40=

    metre 1.0965 225.00 246.71

    1.0965

    Extra for additional height in centering, shuttering where ever required with

    Suspended floors, roofs, landing, beams and balconies (Plan area to be

  • 8/13/2019 Analysis for Building

    13/51

    3. Double coupler ( 40 x 40 )

    7346 Qty taken for cost of using

    once=21x0.85/40=

    each 0.4463 45.00 20.08

    0.4463

    9999 Carriage L.S. 65.00 1.26 81.90

    Labour

    0116 Fitter Grade-I Day 3.00 150.00 450.00

    0114 Beldar Day 6.00 135.00 810.009999 Sundries L.S. 130.00 1.26 163.80

    TOTAL 2678.49

    Add 1% for water charges 26.78

    TOTAL 2705.27

    Add 15% for C.P. and

    overheads

    405.79

    Cost for 28.80 sqm 3111.06

    Cost per sqm 108.02

    5.28

    Code Description Unit Qty Rate Amount

    Details of cost for joint 100m long

    10cm deep and 12 mm thick

    Materials

    0339 (i) Impregnated fibre board sqm 7.50 279.00 2092.50

    1 x 100 x 0.075 = 7.50sqm.

    0316 (ii) Primere 80m/litre 100m=

    100/80 x1 =1.25 lit

    Ltrs. 1.25 28.00 35.00

    0314 (iii) Sealing compound @ 3 per

    litre for

    100m = 100/3 x1 =33.33 litres+

    Wastage @ 5% =

    1.67 = 35.00 litre ( 1 litre = 0.90

    Kg ) =

    Kg 31.50 20.00 630.00

    35.00 x 0.90 = 31.50 Kg

    9999 Carriage L.S. 26.91 1.26 33.91

    Labour :

    0123 Mason 1st class Day 0.12 200.00 24.00

    0124 Mason 2nd class Day 0.12 190.00 22.80

    0114 Beldar Day 0.25 135.00 33.75

    9999 Sundries L.S. 26.91 1.26 33.91

    TOTAL 2905.86

    Add 1% for water charges 29.06

    TOTAL 2934.92Add 15% for C.P. and

    overheads

    440.24

    Cost of 100 m long 10 cm deep 3375.16

    Cost per cm depth per 100m 337.52

    Say 337.52

    5.29 Providing and fixing sheet covering over expansion joints with iron screws as per

    Providing and fixing in position 12mm thick bitumen impregnated fibre board

  • 8/13/2019 Analysis for Building

    14/51

    5.29.2 Aluminium fluted strips 3.15mm

    thick.

    5.29.2.1 150mm wide

    Code Description Unit Qty Rate Amount

    Details of cost for 1.0m length

    Materials :

    2391 3.15mm thick aluminium flutedstrips.

    metre 1.00 216.00 216.00

    1m x15 cm wide.

    0639 Iron screws 25 mm 100 Nos 6.00 15.00 0.90

    9999 Carriage of materials L.S. 1.04 1.26 1.31

    Labour :

    0112 Carpenter 2nd class Day 0.067 190.00 12.73

    0114 Beldar Day 0.067 135.00 9.05

    9999 Sundries L.S. 1.82 1.26 2.29

    TOTAL 242.28

    Add 1% for water charges 2.42

    TOTAL 244.70

    Add 15% for C.P. and

    overheads

    36.71

    Cost for 1.00 m 281.41

    Say 281.41

    5.30

    Code Description Unit Qty Rate Amount

    Details of cost for 30 metre long

    throating or

    plaster or moulding-

    Labour :

    0123 Mason 1st class Day 0.50 200.00 100

    0124 Mason 2nd class Day 0.50 190.00 95.00

    0115 Coolie Day 1.00 125.00 125

    9999 Add for materials ( cement

    mortar etc.)

    L.S. 26.91 1.26 33.91

    TOTAL 353.91

    Add 1% for water charges 3.54

    TOTAL 357.45

    Add 15% for C.P. and

    overheads

    53.62

    Cost for 30 metre 411.06

    Cost for per metre 13.70

    6.4.2

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 1.00 Cum.

    MATERIALS

    Brick work with F.P.S. bricks of

    class designation 150 1000 Nos. 494 2800.00 1383.20

    Cement mortar 1:6(1 cement :6

    coarse sand) CUM. 0.25 2658.89 664.72

    Add or deduct for plaster drip course/ groove in plastered surface or

    Cement mortar 1:6 (1 cement :6 coarse sand)

  • 8/13/2019 Analysis for Building

    15/51

    Sundries L.S. 2.73 1.26 3.44

    LABOUR

    Mason Ist Class Each 0.47 200.00 94.00

    Mason IInd Class Each 0.47 190.00 89.30

    Coolie Each 1.80 125.00 225.00

    Bhisti Each 0.20 160.00 32.00

    Scaffolding L.S. 22.36 1.26 28.17

    Extra for Coolie Each 1.13 125.00 141.25TOTAL 2661.09

    Add 1% For water charges 19.96

    TOTAL 2681.05

    Add 15 % For contractor profit 402.16

    3083.21

    6.1.2

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 1.00 Cum.

    MATERIALS

    Brick work with F.P.S. bricks of class designation 75

    1000 Nos.494 2800.00 1383.20

    Cement mortar 1:6(1 cement :6

    coarse sand) CUM. 0.25 2658.89 664.72

    Sundries L.S. 2.73 1.26 3.44

    LABOUR 0.00

    Mason Ist Class Each 0.36 200.00 72.00

    Mason IInd Class Each 0.36 190.00 68.40

    Coolie Each 1.37 125.00 171.25

    Bhisti Each 0.20 160.00 32.00

    TOTAL 2395.01

    Add 1% For water charges 23.95

    TOTAL 2418.96Add 15 % For contractor profit 362.84

    2781.81

    6.13

    6.13.2DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 10 sqm.

    Materials :

    Brick of class designation 75 1 000 Nos 565 2800.00 1582

    Cement mortar 1:4 (Rate as

    per item No. 3.9) cum 0.28 3316.69 928.67

    Carriage of bricks 1 000 Nos 565 0.00Sundries & Scaffolding L.S 13.52 1.26 17.04

    LABOUR: 0.00

    Mason 1st class Day 0.6 200.00 120.00

    Mason 2nd class Day 0.6 190.00 114.00

    Coolie Day 2 125.00 250.00

    Bhishti Day 0.7 160.00 112.00

    Extra labour for lifting materials:

    0.00

    Half brick masonry with F.P.S. bricks of class designation 75 in

    Cement mortar 1:4 (1 cement :4 coarse sand)

    Cement mortar 1:6 (1 cement : 6 coarse sand)

  • 8/13/2019 Analysis for Building

    16/51

    Coolie Day 1.29 125.00 161.25

    10 x 0.115 x 0.75 x1.5

    TOTAL 3284.96

    Add 1% for water charges 32.85

    TOTAL 3317.81

    Add for contractors profit and

    overheads @ 15% 497.67

    Cost for 10 sqm. 3815.48Cost for 1 sqm. 381.55

    6.15

    Code Description Unit Qty Rate Amount

    Details of cost for 10 sqm

    1002 (a) 6 mm dia. M.S. bars

    (round) 2 Nos. @ 30

    meter/10sqm. = 60 meter

    @0.22kg/m =13.2 kg

    quintal 0.132 3650.00 481.80

    2205 (b) Carriage of M.S. Bars tonne 0.0132 0.00 0.00

    9999 Sundries L.S. 1.82 1.26 2.29

    TOTAL 484.09

    Add 1% for water charges 4.84

    TOTAL 488.93

    Add 15% for C.P. and

    overheads

    73.34

    Cost for 10 sqm 562.27

    Cost for 1 sqm 56.23

    Say 56.23

    8.2

    8.2.28.2.2.2

    Code Description Unit Qty Rate Amount

    Details of cost for 2.00 sqm

    Mirror polished granite = 2.00

    sqm + Wastage 5%, 0.10sqm =

    2.10 sqm

    7297 Granite 18 mm thick slab,

    above 0.50 sqm

    sqm 2.10 3286.00 6900.60

    Cement morter 1:4 (1 cement

    : 4 coarse sand) (Rate as per

    item no 3.9)

    cum 0.027 3316.69 89.55

    Labour :

    0123 Mason (brick layer) 1st class Day 2.80 200.00 560.00

    0114 Beldar Day 1.30 135.00 175.50

    0115 Coolie Day 1.30 125.00 162.50

    9999 Moulding and edge polishig L.S. 78.00 1.26 98.28

    9999 Sundries apoxy resin & cutting

    machine etc.

    L.S. 65.00 1.26 81.90

    TOTAL 8068.33

    Area of slab above 0.50 sqm.

    Extra for providing and placing in position 2 Nos. 6mm dia. M.S. bars at

    Providing and fixing 18mm thick gang saw cut mirror polished premoulded

    Granite of any colour and shade

  • 8/13/2019 Analysis for Building

    17/51

    Add 1% for water charges 80.68

    TOTAL 8149.01

    Add 15% for C.P. and

    overheads

    1222.35

    Cost for 2.00 sqm 9371.37

    Cost for 1.00 sqm 4685.68

    8.3

    8.3.2 Granite work.

    Code Description Unit Quantity Rate Amount

    Details of cost for 10.00 m

    Labour:

    0019 Hand Grinder for mirror polish Day 2.50 100.00 250.00

    0114 Beldar Day 3.50 135.00 472.50

    9999 Sundries Blades & Polish etc. L.S. 117.00 1.26 147.42

    TOTAL 869.92

    Add 1 % for water charges 8.70TOTAL 878.62

    Add 15% for contractors profit

    and overheads 131.79

    Cost for 10 metre 1010.41

    Cost per metre 101.04

    Say 97.60

    9.20

    9.20.1Code Description Unit Quantity Rate Amount

    Details of cost for 2.20 sqm.Materials-

    0713 35mm thick door shutters sqm 2.20 1100.00 2420.00

    9999 Carriage of door L.S. 29.64 1.26 37.35

    8220Stainless steel butt hinges (heavy

    weight) 10 Nos 6.00 185.00 111.00

    100x60x2.5 mm IS : 12817

    marked 0.00

    8211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36

    Labour-

    For fixing shutter and fittings

    0156 Carpenter (Average) Day 0.55 190.00 104.50

    0114 Beldar Day 0.55 135.00 74.25TOTAL 2822.46

    Add 1% for water charges 28.22

    TOTAL 2850.68

    Add 15% forcontractors profit and

    overheads 427.60

    Cost for 2.2 sqm. 3278.28

    Cost of 1 sqm. 1490.13

    9.21

    Providing and fixing ISI marked flush door shutters conforming to IS: 2202

    35 mm thick including ISl marked Stainless Steel butt hinges with

    Providing and fixing lSl marked flush door shutters conforming to IS: 2202

    Extra for providing edge moulding to 18mm thick marble stone counters,

  • 8/13/2019 Analysis for Building

    18/51

    9.21.2

    Code Description Unit Qty Rate Amount

    Details of cost for 2.2 sqm.

    Materials-

    0718 30mm thick door shutters sqm 2.20 610.00 1,342.00

    9999 Carriage of door L.S 29.64 1.26 37.35

    fittings - for a door 2.2x1.0m =

    2.20 sqm

    8220 Stainless steel but hinges

    (heavy weight)

    10 Nos 6.00 195.00 117.00

    100x60x2.5mm IS : 12817

    marked

    8211 Stainless steel scres 40mm 100 Nos 48.00 157.00 75.36

    Labour-

    For fixing shutter and fittings.

    0156 Carpenter (Average) Day 0.55 190.00 104.50

    0114 Beldar Day 0.55 135.00 74.25

    Total 1,750.46Add 1% for water charges 17.50

    Total 1,767.96

    Add 15% for contractors profit

    and overheads

    265.19

    Cost for 2.2 sqm. 2,033.16

    Cost of 1 sqm. 924.16

    9.96

    9.96.2 250x16 mm

    Code Description Unit Qty Rate Amount

    Details of cost for 10 Nos.

    Materials-

    0697 Aluminium sliding bolt

    250x16mm

    each 10.00 104.00 1,040.00

    0588 C.P.brass screws 25mm 100 Nos 40.00 83.00 33.20

    9999 Carriage of materials L.S 5.46 1.26 6.88

    Labour-

    0111 Carpenter 1st class Day 0.50 200.00 100.00

    Total 1,180.08

    Add for water charges @ 1% 11.80

    Total 1,191.88

    Add for contractors profit andoverheads @ 15%

    178.78

    Cost of 10 sliding bolts 1,370.66

    Cost of 1 sliding bolt 137.07

    9.100

    9.100.1 125 mm

    Code Description Unit Qty Rate Amount

    Details of cost for 10 Nos.

    30 mm thick including ISI marked Stainless Steel butt hinges with

    Providing and fixing aluminium sliding door bolts ISI marked anodised

    Providing and fixing aluminium handles ISI marked anodised (anodic

  • 8/13/2019 Analysis for Building

    19/51

    Materials-

    0703 Aluminium handeles 125mm 10 Nos 10.00 375.00 375.00

    0588 C.P.brass screws 25mm 100 Nos 40.00 83.00 33.20

    9999 Carriage of materials L.S 2.73 1.26 3.44

    Labour-

    0111 Carpenter 1st class Day 0.060 200.00 12.00

    Total 423.64

    Add for water charges @ 1% 4.24Total 427.88

    Add for contractors profit and

    overheads @ 15%

    64.18

    Cost of 10 handeles 492.06

    Cost of 1 handeles 49.21

    9.100

    9.100.2 100 mm

    Code Description Unit Qty Rate AmountDetails of cost for 10 Nos.

    Materials-

    0704 Aluminium handeles 100mm 10 Nos 10.00 260.00 260.00

    0588 C.P.brass screws 25mm 100 Nos 40.00 83.00 33.20

    9999 Carriage of materials L.S 1.82 1.26 2.29

    Labour-

    0111 Carpenter 1st class Day 0.060 200.00 12.00

    Total 307.49

    Add for water charges @ 1% 3.07

    Total 310.57

    Add for contractors profit andoverheads @ 15% 46.59

    Cost of 10 handeles 357.15

    Cost of 1 handeles 35.72

    9.97

    9.97.2 250x10mm

    Code Description Unit Qty Rate Amount

    Details of cost for 10 Nos.

    Materials-

    0700 Aluminium tower bolt(barrel

    type) 250x10mm

    10 Nos 10.00 440.00 440.00

    0587 C.P.brass screws 30mm 100 Nos 80.00 90.00 72.00

    9999 Carriage of materials L.S 2.73 1.26 3.44

    Labour-

    0111 Carpenter 1st class Day 0.125 200.00 25.00

    Total 540.44

    Add for water charges @ 1% 5.40

    Total 545.84

    Providing and fixing aluminium handles ISI marked anodised (anodic

    Providing and fixing aluminium tower bolts ISI marked anodised (anodic

  • 8/13/2019 Analysis for Building

    20/51

    Add for contractors profit and

    overheads @ 15%

    81.88

    Cost of 10 tower bolts 627.72

    Cost of 1 tower bolts 62.77

    Say 66.90

    9.97

    9.97.4 150x10mm

    Code Description Unit Qty Rate Amount

    Details of cost for 10 Nos.

    Materials-

    0701 Aluminium tower bolt(barrel

    type) 150x10mm

    10 Nos 10.00 281.00 281.00

    0587 C.P.brass screws 30mm 100 Nos 80.00 90.00 72.00

    9999 Carriage of materials L.S 2.73 1.26 3.44

    Labour-

    0111 Carpenter 1st class Day 0.080 200.00 16.00Total 372.44

    Add for water charges @ 1% 3.72

    Total 376.16

    Add for contractors profit and

    overheads @ 15%

    56.42

    Cost of 10 tower bolts 432.59

    Cost of 1 tower bolts 43.26

    9.76 :

    Code Description Unit Qty Rate AmountDetails of cost for 1 No.

    Materials-

    0413100 mm mortice latch & lock with

    6 levers each 1.00 257.00 257.00Labour- -

    0111 Carpenter 1st class Day 0.17 200.00 34.00

    9999Sundries (screws, carriage etc.)

    L.S. 3.64 1.26

    4.59

    TOTAL 295.59

    Add for water charge @ 1 % 2.96

    TOTAL 298.54

    Add for contractors profit andoverheads @15% 44.78

    Cost of 1 mortice latch and lock 343.32

    9.101

    9.101.2 Twin rubber stopper

    Code Description Unit Qty Rate Amount

    Details of cost for 10 Nos.

    Materials-

    Providing and fixing aluminium tower bolts ISI marked anodised (anodic

    Providing and fixing bright finished brass 100 mm mortice latch and lock with 6

    Providing and fixing aluminium hanging floor door stopper ISI marked

  • 8/13/2019 Analysis for Building

    21/51

    7059 Aluminium hanging floor door

    stopper with

    each 10.00 44.00 440.00

    twin rubber stoper

    0588 C.P.brass screws 25mm 100 Nos 20.00 83.00 16.60

    9999 Carriage of materials L.S 2.73 1.26 3.44

    Labour-

    0111 Carpenter 1st class Day 0.030 200.00 6.00

    Total 466.04Add for water charges @ 1% 4.66

    Total 470.70

    Add for contractors profit and

    overheads @ 15%

    70.61

    Cost of 10 door stopers 541.31

    Cost of 1 door stopers 54.13

    11.26

    11.26.1 25 mm thick

    Code Description Unit Quantity Rate Amount

    Details of cost for 10 sqm.

    Materials;

    1168

    25mm thick kota stone slabs

    polished including sqm 11.50 323.95 3725.43

    15%wastage

    2216 Carriage of slabs tonne 0.67 0.00 0.00

    cement mortar 1:4 ( Rate as

    per item no 3.9)

    cum 0.22 3316.69 742.94

    0367

    cement for slurry -(i) for

    bedding = 44 kg + (ii) for joints

    = 20 kg total = 64 kg or 0.064

    tonne tonne 0.06 5060.00 323.84

    2209 Carriage of cement tonne 0.06 0.00 0.00

    0874 Dark shade pigment kilogram 4.50 42.00 189.00

    Labour

    0124 Mason 2nd class Day 1.20 190.00 228.00

    0114 Beldar Day 1.00 135.00 135.00

    0115 Coolie Day 1.00 125.00 125.00

    0139

    Beldar for rubbing and poishing

    (special rate) Day 5.00 135.00 675.00

    0013 Machine Day 4.00 200.00 800.009999 Sundries L.S 208.13 1.26 262.24

    Total 7206.45

    Add 1% for water charges 72.06

    Total 7278.51

    Add 15% for contractors profit

    and overheads 1091.78

    Cost for 10 sqm. 8370.29

    Cost for 1 sqm. 837.03

    Kota stone slab flooring over 20 mm (average) thick base laid over and

  • 8/13/2019 Analysis for Building

    22/51

    Say 837.03

    11.31

    Code Description Unit Quantity Rate Amount

    Details of cost for 10m

    Labour-

    0126 Stone mason (ornamental) Day 1.50 200.00 300

    Total 300

    Add 1% for water charges 3.00

    Total 303.00

    Add 15% for contractors profit

    and overheads 45.45

    Total 348.45

    Cost for 10 sqm. 348.45

    Cost for 1 sqm. 34.85

    Say 34.85

    11.36

    Code Description Unit Qty Rate Amount

    Details of cost for 1 sqm

    materials

    Ceramic Glazed tiles = 1.00

    sqm

    Add for wastage & bradkage @

    2.5 % = 0.025

    sqm = 1.025 sqm

    7800

    Vitrified tiles 600 x 600 mm wall

    tiles sqm 1.025 385.00 394.63

    9999 Carriage of tiles L.S 6.24 0.00 0.00

    12mm thick cement mortar 1:3

    ( 1 cement : 3 coarse sand

    (Rate as oper item no 3.8) cum 0.014 3974.39 55.64

    9999

    Mortar for pointing in white

    cement L.S 40.43 1.26 50.94

    0367

    Cement for slurry over bed @

    3.3 kg per sqm tonne 0.0033 5060.00 16.70

    Labour0123 mason 1st class Day 0.25 200.00 50.00

    0115 Coolie Day 0.25 125.00 31.25

    9999

    Sundries including carriage of

    cement etc L.S 26.91 1.26 33.91

    Total 633.06

    Add for water charges @ 1% 6.33

    Total 639.39

    Extra for pre finished nosing in treads of steps of Kota stone /sand stone

    slab.

    Providing and fixing 1st quality ceramic glazed wall tiles conforming toIS:15622 (thickness to be specified by the manufacturer ) of approved

    make in all colours, shades except burgundy, bottle green, black of any

    size as approved by Engineer-in-Charge in skirting, risers of steps and

  • 8/13/2019 Analysis for Building

    23/51

    Add for contractors profit and

    overhaeds @ 15% 95.91

    Cost for 1 sqm 735.30

    11.37 :

    Code Description Unit Quantity Rate AmountDetails of cost for 1 sqm

    Materials-

    Glazed Ceramic floor tiles

    300x300 mm size =

    1.00 sqm

    Add for wastage & breakage @

    2.5 % = 0.025

    sqm = Total 1.025 sqm

    7801 Tiles Sq.m. 1.025 320.00 328.00

    9999 Carriage of tiles L.S. 6.24 1.26 7.86

    20 mm thick cement mortar 1:4(1

    cement: 4 coarse sand) (Rate asper item No. 3.9) cum 0.024 3316.69 79.60

    9999Mortar for pointing in white cement

    L.S. 20.20 1.26 25.45

    0367Cement for slurry over bed @ 3.3

    kg per sqm tonne 0.0033 5060 16.70

    Labour: 0.00

    0123 Mason 1st class Day 0.20 200.00 40.00

    0115 Coolie Day 0.20 125 25.00

    9999Sundries including carriage of

    cement etc L.S. 26.91 1.26 33.91

    TOTAL 556.52

    Add for water charges @ 1% 5.57TOTAL 562.08

    Add for contractors profit and

    overheads @ 15% 84.31

    Cost for 1 sqm 646.40

    11.41.1 Size of Tile 50x50 cm

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 1Sqm.

    MATERIALS

    Porcelain floor tiles 30x30 cmsize = 1.00 Sqm.

    Add for wastage & breakage @

    2.5%=0.025 Sqm

    Total = 1.025 Sqm. Sqm. 1.025 896.15 918.55

    Carriage of tile L.S 6.240 1.26 7.86

    20 mm thick cement mortar 1:4

    ( 1Cement : 4 Coarse sand )

    Cum 0.024 3316.69 79.60

    Providing and laying Ceramic glazed floor tiles 300x300 mm (thickness to be

    Mortar 1:4 (1 Cement : 4 Coarse sand) including pointing the joints with white

    Providin and la in vitrified floor tiles in different sizes thickness to be

  • 8/13/2019 Analysis for Building

    24/51

    Mortar for pointing in white

    cement L.S 3.64 1.26 4.59

    Cement slurry over bed @

    3.3Kg./ sqm. Tonne 0.0033 5060.00 16.70

    LABOUR 0.00

    Mason 1st class Day 0.20 200.00 40.00

    Coolie Day 0.20 125.00 25.00

    Sundries L.S 26.91 1.26 33.91TOTAL 1126.21

    Add 1% For water charges 11.26

    TOTAL 1137.47

    Add 15 % For contractor profit 170.62

    1308.09

    12.22

    Description Unit Qty Rate Amount

    Details of cost for 1 no.

    0295

    Stone aggregate (Single size):

    20mm cum 0.0067 1270.00 8.51

    nominal size

    0297

    Stone aggregate (Single size):

    10mm cum 0.0022 1270.00 2.79

    nominal size

    2202

    Carriage of stone aggregate

    below 40mm cum 0.0089 0.00 0.00

    nominal size

    0982 Coarse sand cum 0.0044 1150.00 5.06

    2203 Carriage of coase sand cum 0.0044 0.00 0.00

    367 Portland cement tonne 0.0032 5060.00 16.19

    2209 Carriage of cement tonne 0.0032 0.00 0.00

    0114 Beldar Day 0.0090 135.00 1.22

    0115 Coolie Day 0.0060 125.00 0.75

    0101 Bhisti Day 0.0027 160.00 0.43

    0123 Mason 1st class Day 0.0005 200.00 0.10

    0124 Mason 2nd class Day 0.0005 200.00 0.100128 Mate Day 0.0004 140.00 0.06

    9999

    Hire and running charge of

    mechnanical mixer L.S 0.26 1.26 0.33

    9999 Sundries L.S 0.13 1.26 0.16

    3002 PVC sheet 400 micron thick sqm 1.00 26.00 26.00

    Cement mortar 1:3 ( 1 cement :

    3 coarse sand cum 0.0041 3974.49 16.30

    (Rate as per item No 3.8)

    Making khurras 45x45 cm with average minimum thickness of 5 cm cement

    concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 20 mm

    nominal size) over P.V.C. sheet lmxlmx400micron, finished with 12mm cement

    plaster 1:3 (1 cement: 3 coarse sand) and a coat of neat cement rounding the

    edge sand making and finishing the outlet complete.

  • 8/13/2019 Analysis for Building

    25/51

    0155 Mason Day 0.0235 190.00 4.47

    0115 Coolie Day 0.0235 125.00 2.94

    0101 Bhisti Day 0.0078 160.00 1.25

    9999 Sundries L.S 0.3900 1.26 0.49

    0367 Portland cement tonne 0.0006 5060.00 3.04

    2209 Carriage of cement tonne 0.0006 0.00 0.00

    0155 Mason Day 0.008 190.00 1.52

    0115 Coolie Day 0.008 125.00 1.00

    9999

    Rounding of edges and making

    outlet L.S 0.26 1.26 0.33

    9999 Sundries L.S 13.52 1.26 17.04

    Total 110.06

    Add 1% for water charges 1.10

    Total 111.16

    Add 15% for contractors profit

    and overheads 16.67

    Cost of 1 no. 127.83

    Say

    13.16 6 mm cement plaster of mix

    13.16.1 1:3 (1 cement : 3 fine sand)

    Code Description Unit Quantity Rate Amount

    Detail of cost for 10 sqm

    MATERIALS

    Cement mortar - 1:3 Cum 0.072 3,008.28 216.60

    (Rate as per item no. 3.3)

    LABOUR

    0155 Mason Day 0.51 190.00 96.90

    0115 Coolie Day 0.75 125.00 93.75

    0101 Bhisti Day 0.92 160.00 147.209999 Extra for removing burrs,

    cleaning with wire brushes,

    pock making with pointed tool

    etc. complete. L.S 13.39 1.26 16.87

    9999 Scaffolding and sundries L.S 11.7 1.26 14.74

    Total 586.06

    Add 1% for water charges 5.86

    TOTAL 591.92

    Add 15% for contract's profit

    and overheads 88.79

    Cost of 10.00 sqm 680.71

    Cost of 1.00 sqm 68.07

    12 MM PLASTER

    13.4.2

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Cost for 10 sqm.

    Cement mortar 1:6 CUM. 0.144 2658.89 382.88

    1:6 (1Cement : 6 Coarse sand)

  • 8/13/2019 Analysis for Building

    26/51

    Labour :

    Mason Day 0.67 190.00 127.30

    Coolie Day 0.75 125.00 93.75

    Bhisti Day 0.92 160.00 147.20

    Scaffolding and sundries L.S 12.61 1.26 15.89

    767.02

    Add 1% For water charges 7.67

    TOTAL 774.69

    Add 15 % For contractor profit 116.20

    890.89

    Cost for 1sqm. 89.09

    13.5.2

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Cost for 10 sqm.

    Cement mortar 1;6 CUM. 0.172 2658.89 457.33

    Labour :Mason DAY 0.8 190.00 152.00

    Coolie DAY 0.88 125.00 110.00

    Bhisti DAY 0.99 160.00 158.40

    Scaffolding and sundries L.S 12.61 1.26 15.89

    893.62

    Add 1% For water charges 8.94

    TOTAL 902.55

    Add 15 % For contractor profit

    135.38

    1037.94

    Cost for 1sqm. 103.79

    13.37

    13.37.1

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Detail of cost for 10 sqm

    MATERIALS

    Detail of cost for 10 sqm

    MATERIALS

    Dehradun white lime Qtl. 0.03 295.00 8.85

    Carriage of lime L.S 0.91 1.26 1.15

    LABOUR 0White Washer Day 0.20 160.00 32.00

    Coolie Day 0.10 125.00 12.50

    Indigo gum etc L.S 4.42 1.26 5.57

    Sundries ladders etc L.S 2.73 1.26 3.44

    TOTAL 63.51

    Add 1% For water charges 0.64

    TOTAL 64.14

    White washing with lime to give an even shade:

    New work (three or more coats)

    15 mm cement plaster on rough side of single or half brick wall of mix:

    1:6 (1Cement : 6 Coarse sand)

  • 8/13/2019 Analysis for Building

    27/51

    Add 15 % For contractor profit

    9.62

    73.76

    Cost for 1sqm. 7.38

    13.41

    13.41.1

    Code Description Unit Qty Rate AmountDetail of cost for 10 sqm

    MATERIALS

    Cement primer litre 0.70 70.00 49.00

    Brushes, putty etc L.S. 7.15 1.26 9.01

    Sundries including Carriage L.S. 8.06 1.26 10.16

    Dry distemper kilogram 1.50 40.00 60.00

    Carriage of material L.S. 4.42 1.26 5.57

    Brushes, sand paper and putty

    for filling holes L.S. 11.70 1.26 14.74

    LABOUR 0.00

    Painter Day 1.00 200.00 200.00Coolie Day 0.50 125.00 62.50

    Sundries L.S. 8.06 1.26 10.16

    TOTAL 421.13

    Add 1% For water charges 4.21

    TOTAL 425.34

    Add 15 % For contractor profit

    63.80

    489.14

    Cost for 1sqm. 48.91

    13.45

    13.45.1

    Code Description Unit Quantity Rate Amount

    Detail of cost for 10 sqm

    MATERIALS

    8507 Textured exterior paint litre 3.28 183.00 600.24

    0851 Water proofing cement paint kilogram 2.20 36.00 79.2

    9999 Carriage of material L.S 1.56 1.26 1.9656

    LABOUR 0

    0131 Painter Day 0.60 200.00 120

    0115 Coolie Day 0.30 125.00 37.5

    0101 Bhisti Day 0.05 160.00 8.00

    Brushes, sand paper etc L.S 7.02 1.26 8.8452

    Sundries L.S 8.06 1.26 10.1556

    TOTAL 865.91

    Add 1 % for water charges 8.66TOTAL 874.57

    Add 15% forcontractors profit and

    overheads 131.18Cost of 10.00 sqm 1005.75

    Cost of 1.00 sqm 100.58

    Distempering with oil bound washable distemper of approved brand and

    New work (two or more coats) over and including priming coat with

    Finishing walls with textured exterior paint of required shade :

    New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including

  • 8/13/2019 Analysis for Building

    28/51

    13.47

    13.47.1

    Code Description Unit Quantity Rate Amount

    Detail of cost for 10 sqm

    MATERIALS

    8506 Premium Acrylic exterior paint litre 1.43 202.00 288.86

    0851 Water proofing cement paint kilogram 2.20 36.00 79.20

    9999 Carriage of material L.S 1.56 1.26 1.97LABOUR 0.00

    0131 Painter Day 0.6 200.00 120.00

    0115 Coolie Day 0.30 125.00 37.50

    0101 Bhisti Day 0.05 160.00 8.00

    9999 Brushes, sand paper etc L.S 7.15 1.26 9.01

    9999 Sundries L.S 8.06 1.26 10.16

    TOTAL 554.69

    Add 1% for water charges 5.55

    TOTAL 560.24

    Add 15% or contractors profit and overheads 84.04

    Cost of 10.00 sqm 644.27

    Cost of 1.00 sqm 64.43

    22.7

    22.7.1

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Detail of cost for 10 sqm

    i) Cement slurryCement Tonne 0.0275 5060.00 139.15

    ii) Cement mortar 1:5 (1 cement: 5

    coarse 0.00

    sand) (Rate as per item no.3.10) Cum. 0.224 2962.49 663.60

    iii) Roof treatment with brick bats

    and cement mortar 0.00

    Materials: 0.00

    Brick bats/ brick aggregate Cum. 0.94 350.00 329.00

    Cement mortar 1:5 (Rate as per

    item no.3.10) Cum. 0.5 2962.49 1481.25

    Labour 0.00

    Beldar Day 1.75 135.00 236.25Bhishti Day 0.28 160.00 44.80

    Mason 1 st class Day 0.05 200.00 10.00

    Mason 2 nd class Day 0.05 190.00 9.50

    Mate Day 0.04 140.00 5.60

    Extra labour for ramming 0.00

    Beldar Day 0.25 135.00 33.75

    Sundries L.S 13.65 1.26 17.20

    iv) Cement slury 0.00

    With average thickness of 120mm and minimum thickness at khurra as 65 mm.

    Providing and laying integral cement based water proofing treatment including

    A)Applying a slurry coat of neat cement using 2.75 kg/sqm. of cement admixed

    B)Laying brick bats with mortar using broken bricks/brick bats 25 mm to 115mm

    C)After two days of proper curing applying a second coat of cement slurry using

    E) The whole terrace so finished shall be flooded with water for a minimum

    D) Finishing the surface with 20 mm thick jointless cement mortar of mix 1:4 (1

    Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives

    New work (Two or more coats applied @ 1.43 ltr/ 10 sqm. over and including

  • 8/13/2019 Analysis for Building

    29/51

    Cement Tonne 0.0275 5060.00 139.15

    Beldar Day 0.20 135.00 27.00

    A

    v) 20 mm cement plaster 1:4(1

    cement: 4 coarse sand)(Rate as

    per item no 13.6.1 of SH :

    Finishing) Sqm. 10.00 144.13 1441.30

    vi) Water proofing compound 0.00

    27.50+27.50+69.40+124.00 =248.40 kg @ 1 kg per bag of

    cement Kg. 5.00 30.00 150.00

    Extra for making chequers for

    10 sqm 0.00

    Fibre glass tissue reinforcement

    Type II Grade I Sqm. 10.50 55.00 577.50

    Mason 2nd class Day 0.36 190.00 68.40

    Beldar Day 0.36 135.00 48.60

    Chequer plate L.S 13.65 1.26 17.20

    Add labour for laying 20 mm bed

    mortar 0.00

    Mason 2nd class Day 0.54 190.00 102.60

    Beldar Day 0.54 135.00 72.90

    Bhishti Day 0.45 160.00 72.00

    Total 5686.74

    Add for water charges @ 1% on

    all except A 42.45

    Total 5729.20

    Add for contractors profit and

    overheads @ 15% on all except

    A 643.18

    Cost of 10 Sqm. 6372.38

    Cost per Sqm. 637.24

    22.3

    Code Description Unit Qty Rate Amount

    Details of cost for 10 sqm

    MATERIAL

    0367

    Cement slurry @ 4.4 kg/sqm =

    44.00 kg or tonne 0.044 5060.00 222.64

    0.044 t 0.00

    2209 Carriage tonne 0.044 0 0.00

    Cement plaster 1:3 (20 mm

    thick) 0.00

    Materials : 0.00

    (iv) IVth course of 400 micron thick PVC sheet. (Overlaps at joints of PVC

    Providing and laying water proofing treatment to vertical and horizontal

    (i) 1st course of applying cement slurry @ 4.4 Kg/sqm mixed with water

    (ii) Ilnd course of 20mm cement plaster 1:3 (1 cement : 3 coarse sand)

    (iii) Illrd course of applying blown or residual bitumen applied hot at 1.7

  • 8/13/2019 Analysis for Building

    30/51

    Cement mortar1:3 (Rate as per

    items no.3.8) cum 0.224 3974.49 890.29

    Labour 0.00

    0155 Mason Day 0.94 190.00 178.60

    0115 Coolie Day 1.02 125.00 127.50

    0101 Bhisti Day 1.10 160.00 176.00

    9999 Scafolding and sundries L.S 12.61 1.26 15.89

    Bitumen blown or/and residualbitumen 0.00

    0313 = 10x1.70= 17 kg = 0.017 t tonne 0.017 25000.00 425.00

    2211 Carriage tonne 0.017 0 0.00

    3002 PVC 400 micron thick sheet sqm 10.00 26.00 260.00

    9999 Carriage L.S 13.00 1.26 16.38

    Water proofing compound @ 1

    kg per 50 kg of cement used 0.00

    Cement slurry = 44 kg 0.00

    Cement plaster 1:3 0.00

    10x(13.62xl00)/100= 136.2 kg 0.00

    1213 Total = 180.2 kg/50 = 3.60 kg kilogram 3.60 20.00 72.00LABOUR 0.00

    0131 Painter Day 0.20 200.00 40.00

    0114 Beldar Day 1.33 135.00 179.55

    0130 Mistry Day 0.06 190.00 11.40

    9999 Sundries L.S 7.28 1.26 9.17

    TOTAL 2624.42

    Add 1% for water charges 26.24

    TOTAL 2650.66

    Add 15% for contractors profit

    and overheads 397.5992

    Cost for 10 sqm 3048.26

    Cost for 1 sqm 304.83

    5.22 :

    5.22.6 :

    Code Description Unit Quantity Rate Amount

    Details of cost for 1 quintal-

    Materials:

    Deformed twisted steel bars =

    1.00 q

    Add 5% wastage =0.05

    1005 Total =1.05q quintal 1.05 3629.85 3811.34

    2205 Carriage of steel 1.05/10 = 0.105ttonne 0.105 0 0.00

    9999 Cover block L.S. 26.00 1.26 32.76

    Labour: 0

    For straightening, cutting, bending,

    binding and placing in position-

    0

    0102 Blacksmith 1 st class Day 1.00 190.00 190

    0114 Beldar Day 1.00 135.00 135

    Reinforcement for R.C.C. work including straightening, cutting, bending, placing

    Thermo-Mechanically Treated bars.

  • 8/13/2019 Analysis for Building

    31/51

    9999 Sundries L.S 26.91 1.26 33.91

    TOTAL 4203.01

    Add 1% for water charges 42.03

    TOTAL 4245.04

    Add 15% forcontractors profit and

    overheads 636.76

    Cost of one quintal 4881.80

    Cost of 1 Kg. 48.82AS ON 03 Sept. 2010

    10.25

    10.25.1

    Code Description Unit Quantity Rate Amount

    Consider a flight of staircase of 2.8m height with tread and riser of

    200mm & 0.60m wide.

    Materials-

    (i) Unequal angles as stringers-

    75x50x6mm

    4x12.69x5.6 = 284.25 Kg.

    Add wastage @ 5% =14.21 Kg.

    = 298.46kg. Say 2.985q

    (ii) unequal angles at sides

    50x30x5mm

    2xl4x0.2x3.00=I6.8kg.

    Add wastage @ 5% = 0.84kg.= 17.64 kg. Say 0.176q = 3.161q

    1007 Unequal angles quintal 3.161 3349.50 10587.77

    (iii) plate for tread 8mm thick

    14x7.5= 105.00kg+

    Add wastage @ 5% = 5.25kg.

    = 110.25kg. Say 1.103q

    1010 Plate for tread quintal 1.103 3400.00 3750.20

    (iv) G. pipe for railing 40mm

    2xl2.69m = 25.38m+

    Add wastage @ 5% = 1.27m =

    26.65m

    1549 G.I. Pipe for railing metre 26.65 160.00 4264.00(v) M.S. round bars 16mm dia.

    15x0.75x2xl.58 = 35.55kg.+

    Add wastage @ 5% = 1.78kg.

    = 37.33 Kg. Say O.373q

    1003 M.S. round bars quintal 0.373 3349.50 1249.36

    Carriage of steel

    2205(3.I61 + 1.103+0.373)=4.637q =

    0.4637 tonne tonne 0.373 0 0.00

    Steel work welded in built up section/framed work including cutting, hoisting,

    fixing in position and applying a priming coat of approved steel primer using steel

    etc. as required.

    In stringers, treads, landing etc. of stair cses including use of chequered plate

    wher-ever required, all complete.

  • 8/13/2019 Analysis for Building

    32/51

    2271 Carriage of g.I. Pipe approx. wt. tonne 0.0991 47.59 4.72

    3.72x26.65=99.14kg.

    1215Welding charge (electric) 23.20m

    cm 2320.00 1.00 2320.00

    Labour :

    0102 Blacksmith 1st class day 1.85 200.00 370.00

    0114 Beldar day 1.25 135.00 168.75

    0100 Bandhani day 0.60 135.00 81.00Applying priming coat

    (i) steps 2.4x 14 = 33.60sqm.+

    (ii) angles 4x 12.69x0.25 =

    12.69sqm.+

    (iii) Bars and other components =

    2.00 sqm.

    (L.S.)

    (A) (Rate as per item no. 13.50.3)

    sqm 48.29 14.35 692.96

    9999 Sundries L.S. 110.89 1.26 139.72

    TOTAL 23628.482

    Add for water charges @ 1% onall except A 229.36

    TOTAL 23857.84Add for contractors profit and

    overheads @15% on all except A 3474.73

    Cost of 5.331 qunital 27332.57

    Cost per kg 51.27

    21.3 Providing and fixing glazing in aluminium door, window, ventilator shutters and

    partitions etc. with PVC/neoprene gasket etc. complete as per the architectural

    drawings and the directions of engineer-in-charge . (Cost of aluminium snap

    beading shall be paid in basic item):

    21.3.1 With float glass panes of 4.0 mm thickness

    Code Description Unit Quantity Rate Amount

    Details of cost for 1.00 sqm

    MATERIAL

    FloatGlass panes 4.00 mm thick 1.00 sqm

    Add for waistage and brecakage 10%-0.10 sqm.

    2406 Total =1.10 sqm. sqm 1.10 248.00 272.80

    9999 Carriage of glass L.S. 2.42 1.26 3.0492

    7390 Neoprene/ PVC gasket metre 6.00 22.00 132

    LABOUR: 0

    0112 Glazier Day 0.23 160.00 36.8

    0114 Beldar Day 0.23 135.00 31.05

    9999 Sundries and carriage of gasket L.S. 6.89 1.26 8.6814

    TOTAL 484.38

    Add 1% for water charges 4.843806

    TOTAL 489.22

    Add 15% for contractors profit and overheads 73.38

    Cost for 1 sqm 562.61

    13.26 Providing and applying plaster of paris putty of 2 mm thickness over

  • 8/13/2019 Analysis for Building

    33/51

    Code Description Unit Quantity Rate Amount

    Detail of cost for 10 sqm

    MATERIALS

    Plaster of paris 10x0.002x1121 =

    22.42kg

    Add 20% wastage= 0.45kg

    Total = 22.45kg Say23kg

    0869 Plaster of Paris kilogram 23.00 2.50 57.509999 Carriage of plaster of paris L.S 1.50 1.26 1.89

    LABOUR 0.00

    0122 Mason special Day 0.91 200.00 182.00

    0144 Beldar Day 0.91 135.00 122.85

    9999 Scaffolding and sundries L.S 83.98 1.26 105.81TOTAL 470.05

    Add 1 % for water charges 4.70TOTAL 474.76

    Add 15% forcontractors profit and

    overheads 71.21Cost of 10.00 sqm 545.97Cost of 1.00 sqm 54.60

    9.29 Providing and fixing 30mm thick wire gauge shutters using galvanised M.S. wire

    gauge of average width of aperture 1.4mm with wire of dia. 0.63 mm for doors,

    windows and clerestory windows including ISI marked Stainless Steel butt

    hinges with necessary screws :

    9.29.1 Second class teak wood.

    Code Description Unit Quantity Rate Amount

    Details of cost for door shutters

    2.00x1.08m = 2.16 sqm.

    Materials -

    Teak wood (2nd class)

    Styles 4x209x9.5x3cm = 0.023

    cum+

    Top Rail - 1x110.5x9.5x3cm =

    0.003cum+

    Lock and bottom rail

    2x110.5xl9.7x3cm = 0.013 cum+

    Beadings -

    (2x312+2x150)x(1.2)x(1.2)cm =

    0.001 cum.

    Total = 0.040 cum+

    Add for wastage @ 10% = 0.004

    cum.

    = 0.044 cum.

    Say 44 cudm.

    1190 Teak wood (2nd class) 10 cudm 44.00 378.00 1663.20

    2204 Carriage of timber cum 0.044 2.68

    Wire gauge 2xl60x40cm = 1.28

    sqm.+

  • 8/13/2019 Analysis for Building

    34/51

    Add wastage @ 10% = 0.13 sqm.

    Total= 1.41 sqm.

    7029 Wire gauge sqm 1.41 142.00 200.22

    8221Stainless steel butt hinges (heavy

    weight) 10 Nos 6.00 155.00 93

    75x50x2.5 mm IS : 12817 marked

    08211 Stainless steel screws 40 mm 100 Nos 48.00 157.00 75.36

    Labour- 0

    0111 Carpenter 1st class Day 1.20 200.00 240

    0112 Carpenter 2nd class Day 0.80 190.00 152

    0114 Beldar Day 0.95 135 128.25

    0130 Mistry Day 0.08 190.00 15.2

    9999 Sundries L.S . 33.80 1.26 42.59

    TOTAL 2612.50

    Add 1% for water charges 26.12

    TOTAL 2638.62

    Add 15% forcontractors profit and

    overheads 395.79Cost of 2.16 sqm. 3034.42

    Cost of 1 sqm. 1404.82

    Say 1422.15

  • 8/13/2019 Analysis for Building

    35/51

    19.2

    19.2.1 100 mm diameter S. W. pipe

    Code Description Unit Quantity Rate Amount

    Details of cost for 10 metre

    Area = W x (W/2) + 112x (3.14/4 x

    W2) -(3.14/4 xd2)

    = W2 x {A1/2 + 1/2 x (3.14/4)} -

    (3.14/4 x d2)

    Where W = D + X

    D = 100 + 12 + 12 = 124 mm or 12.4

    cm

    X = 300 mm as trench depth is less

    than 1200

    mm

    Area = (30.0 + 12.4)2 (0.5 + 3.14x1/8) -

    3.14x/4X(12.4)2

    = (42.4)2 (0.5 + 3.14/8) -

    3.14/4x(12.4)2

    = (1797.76) (0.89) - 0.7854x153.76

    = 1600.01-120.76 = 1479.2 sq.cm.

    = 0.1479 sqm Say 0.148 sqm

    For 10 m length qty. of concrete reqd.

    = 1.48

    cum

    Rate as per item no 4.1.10 of SH :

    Concrete cum 1.48 3143.23 4651.98

    Work

    Cost of 10 metres 4651.98

    Cost per metre 465.20

    19.4 :

    19.4.1: 100x100 mm size P type

    19.4.1.2:

    Code Description Unit Quantity Rate AmountDetails of cost of one gully trap

    1900 100x100 mm Gully trap P type each 1.00 55.00 55.00

    1364 C.I. grating .100x100 mm each 1.00 10.00 10.00

    1352

    C.l. cover with frame 300x300mm inside

    each 1.00 265.00 265.00

    9999 Carriage of materials L.S. 4.50 1.26 5.67

    Cement concrete 1:5:10 ( 1 cement: 5 fine

    Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10

    graded stone aggregate 40 mm nominal size) alround S.W. pipes including bed

    concrete as per standard design:

    Providing and fixing square-mouth S.W. gully trap grade A complete with C.I. grating

    brick masonry chamber with water tight C.I. cover with frame of 300 x300 mm size

    (inside) the weight of cover to be not less than 4.50 kg and frame to be not less than

    2.70 kg as per standard design :

    With Sewer bricks conforming to IS : 4885

  • 8/13/2019 Analysis for Building

    36/51

    sand : 10 graded stone aggregate 40 mm

    nominal size)

    0.68x0.68x0.10 m = 0.046 cum

    Concrete around trap

    0.30x0.30x0.675 m = 0.061 cum

    =0.107 cum

    Deduct:0.345/3x[0.09+0.01+(0.09x0.01)l/2] =

    0.015

    cum

    3.14/4x(0.124)2x0.47 = 0.006 cum

    = 0.021 cum

    Net quantity 0.107 cum (-) 0.021 cum

    = 0.086 cum say 0.09 cum

    (Rate as per item 4.1.11 of S.H. :

    Concrete) cum 0.09 2643.62 237.93

    Brick work with sewer bricksconforming to

    IS:4885 in cement mortar 1:4(1 cement: 4

    coarse sand)1.66x0.115x0.675 m = 0.129 cum say 0.13

    cum

    Rate as per item no 6.36.1 of SH : Brick

    Work cum 0.13 3,187.69 414.40

    Cement concrete 1:2:4 ( 1 cement: 2

    coarse sand : 4 graded stone aggregate

    20 mm nominal size)

    1.66x0.115x0.04 m = 0.008 cum

    (Rate as per item 4.2.3 of S.H. : concrete

    cum 0.008 4600.71 36.81

    12 mm cement plaster 1:3 (1 cement: 3

    coarse sand) finished with floating coat ofneat cement:

    [l/2x0.358x(l.20+0.40)] = 0.286 sqm say

    0.29 sqm

    (Rate as per item no.13.9.1 of S.H. :

    finishing) sqm 0.29 133.50 38.72

    TOTAL 1063.52

    Add 1 % for water charges on (A) 3.36

    TOTAL 1066.87

    Add 15% for contractors profit and

    overheads on (A+B) 50.85

    Cost for 1 trap 1117.73

    19.7

    19.7.1

    19.7.1.1

    Code Description Unit Quantity Rate Amount

    Details of cost for 1 manhole

    MATERIALS

    Constructing brick masonry manhole in cement mortar 1:4 (1 cement 4 coarse sand)

    Inside size 90x80 cm and 45cm deep including CI. cover with frame (light duty)

    With F.P.S. bricks with class designation 75

  • 8/13/2019 Analysis for Building

    37/51

    Cement concrete 1:4:8 (1 cement: 4

    coarse sand : 8 graded stone aggregate

    40 mm nominal size)

    1.51x1.41x0.20=0.426 cum Say 0.43 cun.

    Rate as per item no 4.1.8 of SH : Concrete

    Work cum 0.43 3378.32 1452.678

    Brick work with bricks of class designation150 in foundation & plinth in cement

    mortar 1:4 (1cement: 4 coarse sand)

    0

    4.32x0.23x0.35 m = 0.348 cum 0

    Less for pipe 2x3.14/4x(0.15m)2x0.23m =

    (-)0.008 cum

    0

    = 0.340 cum 0

    Rate as per item no 6.1.1 of SH : Brick

    Work cum 0.34 2972.82 1010.759

    Cement concrete 1:2:4 (1 cement: 2

    coarsesand : 4 graded stone aggregate 20mm nominal size) for benching 0

    2x0.90x(0.80/2) x (0.30+0.20)/2 = 0.18

    cum 0

    Less for pipe 1x0.90x3.14/4x(0.15 m)2 = (-

    ) 0

    0.02 cum 0

    = 0.16 cum 0

    Rate as per item no 4.1.3 of SH : Concrete

    Work cum 0.16 4265.40 682.464

    12 mm cement plaster 1:3 (1 cement: 3

    coarse sand) finished with floating coat of

    neat cement 03.40mx0.05m = 0.17 sqm 0

    2x1/2x0.80x0.10m = 0.08 sqm 0

    = 0.25 sqm 0

    Rate as per item no.13.9.1 of SH :

    Finishing sqm 0.25 133.50 33.375

    Reinforced cement concrete 1:2:4 (1

    cement:2 coarse sand : 4 graded stone

    aggregate 20mm nominal size) 0

    For slab: 1.36x1.26x0.15m = 0.257 cum

    0

    Less for cover 0.61x0.455x0.15m = (-)

    0.042cum 0= 0.215 cum Say 0.22 cum 0

    Rate as per item no 5.3 of SH : RCC Work

    cum 0.22 4680.11 1029.62

    Mild steel reinforcement for slab : 0

    0.22 cum @ 48.06 kg/cum = 10.57 kg 0

    Rate as per item no 5.22.1 of SH: RCC

    Work kg 10.57 48.80 515.816

    Form work = 0.90x0.80= 0.72 sqm 0

  • 8/13/2019 Analysis for Building

    38/51

    Less cover = 0.61x0.45m = (-) 0.278 sqm

    0

    =0.42 sqm. say 0.44 sqm. 0

    Rate as per item no 5.9.3 of SH : RCC

    Work sqm 0.44 194.03 85.3732

    LABOUR 0

    Extra labour for making channel: 0.00

    0123 A Mason 1st class Day 0.06 200.00 12.000124 A Mason 2nd class Day 0.06 190.00 11.40

    1354 B

    C.I. Cover with frame 455x610 mm

    (inside) each 1.00 1395.00 1395.00

    B Carriage of C.I. cover & frame L.S. 6.76 1.26 8.52

    B

    Painting of C.I. cover & frame with coal tar

    L.S. 6.76 1.26 8.52

    B Sundries L.S. 13.52 1.26 17.04

    TOTAL 6262.56

    Add 1% for water charges on (A+B) 14.52

    TOTAL 6277.08

    Add 15% for contractors profit and

    overheads on (A+B+C) 217.87Cost of one manhole 6494.95

    19.8 Extra for depth for manholes

    19.8.1 Size 90x80 cm

    19.8.1.1

    Code Description Unit Quantity Rate Amount

    Details of cost for one meter

    MATERIALS

    Brick work with bricks of class designation

    75 in cement mortar 1:4(1 cement : 4

    coarse sand)4.32x0.23x1.00 = 0.994 cum Say 0.99

    Rate as per item no. 6.1.1 of S.H : brick

    work cum 0.99 2972.82 2943.09

    12 mm cement plaster 1:3 (1 cement: 3

    coarse sand) finished with floating coat of

    neat cement

    3.40x1 m = 3.40 sqm

    Rate as per item no. 13.9.1 of SH :

    Finishing sqm 3.40 133.50 453.90

    TOTAL 3396.992

    Cost for one metre 3396.99

    19.27:

    19.27.1: With F.P.S. bricks

    Code Description Unit Quantity Rate Amount

    Details of cost for one chamber

    MATERIALS

    With F.P.S. bricks class designation 75

    Constructing brick masonry road gully chamber 50x45x60 cm with bricks of class

  • 8/13/2019 Analysis for Building

    39/51

    Cement concrete 1:5:10 (1 cement: 5 fine

    sand : 10 graded stone aggregate 40 mm

    nominal size) 1.11x1.06x0.15=0.176 say

    0.18cum

    Rate as per item no 4.1.11of SH :

    Concrete work cum 0.18 2643.62 475.85

    Brick work in bricks of clas designation 75

    in cement mortar 1:4(1 cement: 4 coarsesand) 0.00

    2.82 m x 0.23m x0.45 m = 0.29 cum 0.00

    Rate as per item no 6.1.1 of SH : Brick

    Work cum 0.29 2972.82 862.12

    12 mm cement plaster 1:3(1 cement: 3 0.00

    coarse sand) finished with floating coat of

    neat 0.00

    cement 0.00

    Wall: 1.90x0.45 m = 0.855 sqm r 0.00

    Bed : 0.45x0.50 m = 0.225 sqm - 0.00

    Total= 1.080 sqm 0.00

    Rate as per item no 13.9.1 of SH :Finishing sqm 1.08 133.50 144.18

    Cement concrete 1:2:4 ( 1 cement: 2

    coarse sand : 4 graded stone aggregate

    20 mm nominal size) 0.00

    2.82x0.23x0.15 m = 0.097 cum Say 0.10

    cum 0.00

    Rate as per item no.4.2.3 of SH:Concrete

    work cum 0.10 4600.77 460.08

    Form work 0

    3.50x0.15 m = 0.525 sqm Say 0.53 sqm

    0

    Rate as per item no 5.9.2 of SH : RCCwork sqm 0.53 184.35 97.71

    7380

    Precast R.C.C.gully grating with frame

    500x450 mm each 1.00 533.00 533.00

    9999 Carriage of R.C.C. grating L.S. 7.15 1.26 9.01

    9999 Fixing R.C.C. grating L.S. 5.33 1.26 6.72

    TOTAL 2588.66

    Add 1% for water charges on (A) 5.49

    TOTAL 2594.14

    Add 15% for contractors profit and

    overheads on (A+B) 83.13

    Cost of one chamber 2677.28

    19.31

    19.31.1 For 455x610 mm size

    19.31.1.1 With F.P.S. bricks

    Code Description Unit Quantity Rate Amount

    Details of cost for one metre

    Extra for depth beyond 45 cm of brick masonry chamber :

  • 8/13/2019 Analysis for Building

    40/51

    Brick work in bricks of clas designation 75

    in

    cement mortar 1:4(1 cement: 4 coarse

    sand)

    3.05 x 0.23m x 1.00m = 0.70 cum

    Rate as per item no. 6.1.1 cum 0.70 2972.82 2080.97

    12mm cement plaster1:3 (1 cement: 3

    coarse 0.00sand finished with floating coat of neat

    cement 0.00

    Wall: 2.13x1.00 m = 2.13 sqm 0.00

    Rate as per item no 13.9.1 of SH :

    Finishing sqm 2.13 133.50 284.36

    TOTAL 2365.329

    Cost per metre 2365.33

    18.4

    18.4.1 PN-16 Pipe, 16 mm OD

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 10 metreMATERIALS

    A) 3 layer PP-R pipe (PN-16/SDR 7.4)

    16mm outer dia Rmt. 10.00 29.00 290.00

    Add 30% for fitting and wastage etc.

    on (A) 87.00

    Cement, sand and grit L.S. 2.73 1.26 3.44

    LABOUR 0.00

    Fitter Day 0.33 150.00 49.50

    Asstt. Fitter Day 0.66 140.00 92.40

    Beldar Day 0.66 135.00 89.10

    611.44Add 1% For water charges 6.11

    TOTAL 617.55

    Add 15 % For contractor profit 92.63

    710.19

    Cost for 1sqm. 71.02

    18.4

    (Internal work - exposed on wall)

    18.4.2 : PN-16 Pipe, 20 mm OD

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 10 metreMATERIALS

    A) 3 layer PP-R pipe (PN-16/SDR 7.4)

    20 mm outer dia Rmt. 10.00 44.00 440.00

    Add 30% for fitting and wastage etc.

    on (A) 132.00

    Cement, sand and grit L.S. 2.73 1.26 3.44

    LABOUR 0.00 0.00

    Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes

    Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes

  • 8/13/2019 Analysis for Building

    41/51

    Fitter Day 0.33 150.00 49.50

    Asstt. Fitter Day 0.82 140.00 114.80

    Beldar Day 0.66 135.00 89.10

    828.84

    Add 1% For water charges 8.29

    TOTAL 837.13

    Add 15 % For contractor profit 125.57

    962.70Cost for 1sqm. 96.27

    18.4

    18.4.3 : PN - 16 Pipe, 25 mm OD

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Details of cost for 10 metre

    MATERIALS

    A) 3 layer PP-R pipe (PN-16/SDR 7.4)

    25 mm outer dia Rmt. 10.00 68.00 680.00

    Add 30% for fitting and wastage etc.

    on (A) 204.00Cement, sand and grit L.S. 2.73 1.26 3.44

    LABOUR 0.00 0.00

    Fitter Day 0.33 150.00 49.50

    Asstt. Fitter Day 0.98 140.00 137.20

    Beldar Day 0.66 135.00 89.10

    1163.24

    Add 1% For water charges 11.63

    TOTAL 1174.87

    Add 15 % For contractor profit 176.23

    1351.10

    Cost for 1sqm. 135.11

    18.5 :18.5.1 PN- 16 Pipe, 16 mm OD

    Code Description Unit Quantit Rate AmountDetails of cost for 10 metre

    MATERIALS

    8625

    (A) 3 layer PP-R pipe (PN-16/SDR 7.4) 16

    mm outer dia metre 10.00 29.00 290.00

    Add 75% for fitting clamps and wastage

    etc on (A) 217.50

    Making chases upto 7.5 x 7.5 cm. in walls

    and making good the same(B) Rate as per item no. 18.78 metre 10.00 43.48 434.80

    LABOUR

    0116 Fitter Day 0.33 150.00 49.50

    0117 Asstt. Fitter Day 0.66 140.00 92.40

    0114 Beldar Day 0.66 135.00 89.10

    TOTAL 1173.30

    Add 1% for water charges on all except

    (B) 7.39

    Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes

    Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes

  • 8/13/2019 Analysis for Building

    42/51

    TOTAL 1180.69

    Add 15% for contractors profit and

    overheads on all except (B) 111.88

    Cost for 10 metre 1292.57

    Cost for 1 metre 129.26

    18.5 :18.5.2: PN-16 Pipe, 20 mm OD

    Code Description Unit Quantity Rate Amount

    Details of cost for 10 metre

    MATERIALS

    8626

    (A) 3 layer PP-R pipe (PN-16/SDR 7.4) 20

    mm outer dia metre 10.00 44.00 440.00

    Add 75% for fitting, clamps and wastage

    etc on (A) 330.00

    Making chase upto 7.5 x 7.5 cm. in walls

    and making good the same

    (B) Rate as per item no. 18.78 metre 10.00 43.48 434.80

    LABOUR0116 Fitter Day 0.33 150.00 49.50

    0117 Asstt. Fitter Day 0.66 140.00 92.40

    0114 Beldar Day 0.66 135 89.10

    TOTAL 1435.80

    Add 1% for water charges on all except

    (B) 10.01

    TOTAL 1445.81

    Add 15% for contractors profit and

    overheads on all except (B) 151.65

    Cost for 10 metre 1597.46

    Cost for 1 metre 159.75

    18.6 :

    18.6.3: PN - 16 Pipe, 25 mm OD

    Code Description Unit Quantity Rate Amount

    Details of cost for 10 metre

    MATERIALS

    8627

    (A) 3 layer PP-R pipe (PN-16/SDR 7.4) 25

    mm outer dia metre 10.00 68.00 680.00Add 30% for fitting and wastage etc on (A)

    204.00

    LABOUR

    0116 Fitter Day 0.12 150.00 18.00

    0114 Beldar Day 0.25 135.00 33.75

    Trenching and refilling etc. 0.00

    0114 Beldar Day 0.66 135.00 89.10

    0115 Coolie Day 0.66 125.00 82.50

    TOTAL 1107.35

    Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR 7.4

    Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes U V

    stabilized & anti - microbial fusion welded, having thermal stability for hot & cold water

    supply including all PP - R plain & brass threaded polypropylene random fittings

    including trenching refill ing & testing of joints complete as per direction of Engineer in

    Charge.

  • 8/13/2019 Analysis for Building

    43/51

    Add 1% for water charges 11.0735

    TOTAL 1118.42

    Add 15% for contractors profit and

    overheads 167.76

    Cost for 10 metre 1286.19

    Cost for 1 metre 128.62

    18.1818.18.1 High or low pressure with plastic floats:

    18.18.1.3 25 mm nominal bore

    Code Description Unit Quantity Rate Amount

    Details of cost for one no.

    Materials :-

    1924 25mm ball valve each 1.00 300.00 300.00

    9999

    Carriage of materials and fixing charges

    L.S. 32.24 1.26 40.62

    TOTAL 340.62

    Add 1 % for water charges 3.41

    TOTAL 344.03

    Add 15% for contractors profit andoverheads 51.60

    Cost of one no. 395.63

    18.32.1 With F.P.S. bricks

    Code Description Unit Quantity Rate Amount

    Details of cost for one chamber

    Materials :-

    (i) Earth work in excavation including

    refilling

    and disposal of surplus earth

    0.68x0.68x0.65m=0.301cum.

    (Rate as per item No. 2.8.1) cum 0.30 58.35 17.51

    (Rate as per item No. 2.25) cum 0.30 28.60 8.58

    (ii) Cement concrete 1:5:10 (1 Cement:

    5 fine sand : 10 graded stone

    aggregate 40mm nominal size) 0.00

    0.68x0.68x0.075m=0.035cum. Say

    0.04 cum. 0.00

    (Rate as per item No.4.1.11) cum 0.04 2643.62 105.74

    (iii) Second class brick work in cement

    mortar 1:4 (1 Cement: 4 coarse sand)

    in foundations and plinth0.00

    1.66mx0.115x0.50m=0.095cum. Say

    0.10 cum. 0.00

    (Rate as per item no 6.1.1 of SH :

    Brick Work) cum 0.10 2972.82 297.28

    (iv) 12mm cement plaster 1:3 (1

    Cement: 3Coarse sand) finished with a

    floating coat of neat cement. 0.00

    Providing and fixing ball valve (brass) of approved quality complete :

    Constructing masonry Chamber 30x30x50 cm, inside with 75 class designation

  • 8/13/2019 Analysis for Building

    44/51

    1.20x0.50=0.60sqm. 0.00

    0.30x0.30=0.09sqm. 0.00

    =0.69sqm. Say 0.70sqm. 0.00

    (Rate as per item no .13.9.1) sqm 0.70 133.50 93.45

    1304

    (A) (v) C.I. surface box with hinged

    cover each 1.00 72.00 72.00

    100x100x75mm (inside) 0.00

    9999 (A)(vi) Carriage of C.I. surface box L.S. 1.43 1.26 1.80(vii) Cement concrete 1:2:4 (1 Cement:

    2 Coarse sand ; 4 graded stone

    aggregate 20mm nominal size) 0.00

    in slab = 0.53mx0.53mx0.075m =

    0.02107cum. 0.00

    Less surface box 0.112 x 0.112 x

    0.076' = (-)0.00094 cum. 0.00

    = 0.0201 cum. Say 0.02cum. 0.00

    (Rate as per item No.5.3) cum 0.02 4680.11 93.60

    (A) (viii) Sundries L.S. 4.16 1.26 5.24

    TOTAL 695.21(B) Add for water charges @ 1 % on A 0.72

    TOTAL 695.93

    Add 15% for contractors profit and

    overheadson (A + B) 10.91

    Cost of one chamber 706.84

    18.41 Providing and filling sand of grading zone V or coarser grade alround the G.I.

    pipes in external work.

    18.41.3 25 mm diameter pipe

    Code Description Unit Quantity Rate Amount

    Details of cost of sand filling alround

    25mmdia. pipe 10 metre long.

    Width of sand filling = 300mm

    Depth of sand filling under the pipe=75mm

    Above the pipe = 150mm

    Max. external dia of pipe = 34.2mm

    = 259.2 Say 259mm

    Quantity of sand = 10x0.30x0.259 = 0.777

    cum.

    Less for pipe 3.142/4 (0.0342)2 x 10 =

    (-)0.009cum.= 0.768 Say 0.77 cum.

    Cost of sand filling for 10 metre pipe

    Rate as in Item No 18.41.1 marked (A) cum 0.77 316.97 244.07

    TOTAL 244.07

    Cost of 10 metre 244.07

    Cost of one metre 24.41

    17.7 Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32 mm

  • 8/13/2019 Analysis for Building

    45/51

    17.7.1

    Code Description Unit Quantity Rate Amount

    Details of cost for one no.

    MATERIALS

    1947

    630x450 mm flat back wash basin of white

    vitreous china each 1.00 585.00 585.00

    1885 15 mm C.P. brass piller taps each 2.00 103.00 206.00

    195132 mm diameter C.P. brass waste of standardpattern each 1.00 48.00 48.00

    1309 C.I./M.S. brackets pair 1.00 48.00 48.00

    9999 Red lead, white lead and gasket L.S. 16.12 1.26 20.31

    9999 Cement, sand and grit etc. L.S. 13.39 1.26 16.87

    9999 Painting of brackets, fittings etc. L.S. 26.91 1.26 33.91

    9999 Carriage of materials L.S. 13.52 1.26 17.04

    LABOUR 0.00

    0116 Fitter 1st class Day 0.33 150.00 49.50

    0123 Mason 1st class Day 0.33 200.00 66.00

    0114 Beldar Day 0.67 135.0 90.45

    TOTAL 1,181.07

    Add 1% for water charges 11.81TOTAL 1,192.89

    Add 15% for contractors profit and

    overheads 178.93

    Cost for one no 1,371.82

    18.48

    Code Description Unit Quantity Rate Amount

    Details of cost for 500 litres, tank 1 no.

    Materials:

    1649 Polyethylene water storage tank per litre 500.00 4.00 2000.009999 Carriage to site L.S. 179.40 1.26 226.04

    9999 Placing at terrace L.S. 89.70 1.26 113.02

    TOTAL 2339.07

    Add for water charges @ 1 % 23.39

    TOTAL 2362.46

    Add for contractors profit and over

    head @15% 354.37

    Cost for 500 litre 2716.83

    Cost per litre 5.43

    18.17

    Providing and fixing gun metal gate valvewith C.I. wheel of approved quality

    (screwed end):

    18.17.1 25 mm nominal bore

    Code Description Unit Quantity Rate Amount

    Details of cost for one no.

    Materials :-

    1927

    25mm dia. Gun metal gate valve with

    wheel each 1.00 235.00 235.00

    Providing and placing on terrace (at all floor levels) polyethylene water storage

    White Vitreous China Wash basin size 630x450 mm with a pair of 15 mm C.P. brass

  • 8/13/2019 Analysis for Building

    46/51

    9999

    Carriage of materials and fixing charges

    L.S. 10.79 1.26 13.60

    TOTAL 248.60

    Add 1 % for water charges 2.485954

    TOTAL 251.08

    Add 15% for contractors profit and

    overheads 37.6622

    Cost of one no. 288.74

    17.3

    17.3.1 W.C. pan with ISI marked white solid plastic seat and lid.

    Code Description Unit Quantity Rate Amount

    Details of cost for one pan

    MATERIALS

    1875

    White solid plastic seat and lid with C.P.

    brass hinges and rubber buffers complete

    each 1.00 275.00 275.00

    1955 White glazed pedestal type W.C. pan each 1.00 554.00 554.00

    7006

    10 litre white glazed vitreous china low

    level flushing cistern with fitting andbracket and 40 mm white C.P. flush bend

    each 1.00 1,390.00 1390.00

    9999

    Overflow arrangement and specials for

    oveflow pipe L.S. 62.79 1.26 79.12

    1350

    Mosquito proof coupling of the approved

    municipal design each 1.00 23.00 23.00

    9,999 Plugs,screws etc. L.S. 13.52 1.26 17.04

    9,999 Red lead, white lead and gasket L.S. 16.12 1.26 20.31

    9,999 Cement, sand and grit etc. L.S. 26.91 1.26 33.91

    9,999 Carriage of materials L.S. 26.91 1.26 33.91

    LABOUR 0.00

    0116 Fitter 1st class Day 1.00 150.00 150.000123 Mason 1st class Day 1.00 200.00 200.00

    0114 Beldar Day 1.00 135.00 135.00

    TOTAL 2,911.28

    Add 1% for water charges 29.11

    TOTAL 2,940.39

    Add 15% for contractors profit and

    overheads 441.0582

    Cost for 1 pan 3,381.45

    17.1

    17.1.1

    Code Description Unit Quantity Rate AmountDetails of cost for one pan

    MATERIALS

    1,954

    White Vitreous china Orrisa pattern W.C.

    pan each 1.00 700.00 700.00

    7,358

    10 litre low level P.V.C. flushing cistern

    with each 1.00 570.00 570.00

    fitting accessories and flush pipe 0.00

    Providing and fixing white vitreous china pedestal type water closet (European

    Providing and fixing water closet squatting pan (Indian type W.C. pan with

    White Vitreous china Orissa pattern W.C. pan of size 580x440mm with integral

  • 8/13/2019 Analysis for Building

    47/51

    1,896

    100 mm Sand C.I. P orS trap with vent

    horn each 1.00 260.00 260.00

    9,999 Cement, sand and grit etc. L.S. 26.91 1.26 33.91

    9,999 Carriage of materials L.S. 26.91 1.26 33.91

    LABOUR 0.00

    0116 Fitter 1st class Day 1.25 150.00 187.50

    0123 Mason 1st class Day 0.50 200.00 100.00

    0114 Beldar Day 1.00 135 135.00TOTAL 2,020.31

    Add 1 % for water charges 20.20TOTAL 2040.52

    Add 15% for contractors profit and

    overheads 306.08Cost for 1 pan 2346.59

    17.7

    17.7.1

    Code Description Unit Quantity Rate Amount

    Details of cost for one no.

    MATERIALS

    1947

    630x450 mm flat back wash basin of white

    vitreous china each 1.00 585.00 585.00

    1885 15 mm C.P. brass piller taps each 2.00 103.00 206.00

    1951

    32 mm diameter C.P. brass waste of

    standardpattern each 1.00 48.00 48.00

    1309 C.I./M.S. brackets pair 1.00 48.00 48.00

    9999 Red lead, white lead and gasket L.S. 16.12 1.26 20.31

    9999 Cement, sand and grit etc. L.S. 13.39 1.26 16.87

    9999 Painting of brackets, fittings etc. L.S. 26.91 1.26 33.91

    9999 Carriage of materials L.S. 13.52 1.26 17.04

    LABOUR 0.00

    0116 Fitter 1st class Day 0.33 150.00 49.500123 Mason 1st class Day 0.33 200.00 66.00

    0114 Beldar Day 0.67 135.0 90.45

    TOTAL 1,181.07

    Add 1% for water charges 11.81

    TOTAL 1,192.89

    Add 15% for contractors profit and

    overheads 178.9328

    Cost for one no 1,371.82

    17.10 Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as per IS 13983

    with C.I. brackets and stainless steel plug 40 mm including painting of fittings

    and brackets, cutting and making good the walls wherever required:17.10.1 Kitchen sink with drain board

    17.10.1.4 510x1040 mm bowl depth 178mm.

    Code Description Unit Quantity Rate Amount

    Details of cost for one no

    MATERIALS

    7,098 Stainless steel kitchen sink - with drain boa each 1.00 2,600.00 2,600.00

    510xl040mm bowl depth 178 mm 0.00

    1,309 C.I. Brackets pair 2.00 48.00 96.00

    White Vitreous China Wash basin size 630x450 mm with a pair of 15 mm C.P. brass

    Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32 mm

  • 8/13/2019 Analysis for Building

    48/51

    9,999 Cement, sand and grit etc. L.S. 27.04 1.26 34.07

    9,999 Painting brackets L.S. 26.91 1.26 33.91

    9,999 Carriage of materials L.S. 13.52 1.26 17.04

    LABOUR 0.00

    0116 Fitter 1st class Day 0.22 150.00 33.00

    0123 Mason 1st class Day 0.60 200.00 120.00

    0114 Beldar Day 0.82 135.00 110.70

    TOTAL 3,044.71Add 1% for water charges 30.45

    TOTAL 3,075.16

    Add 15% for contractors profit and overheads 461.2739

    Cost for one no 3,536.43

    18.51 Providing and fixing C.P. brass long body bib cock of approved quality conforming

    to IS standards and weighing not less than 690 gms.

    18.51.1 15mm nominal bore.

    Code Description Unit Quantity Rate Amount

    Details of cost for one no.

    Materials:

    725915mm diameter C.P. brass long body bibcock each 1.00 258.00 258.00

    9999 Carriage of material and fixing changes LS 13.91 1.26 17.53

    TOTAL 275.53

    Add for water charges @ 1 % 2.76

    TOTAL 278.28

    Add for contractors profit and over head

    @ 15% 41.74

    Cost for 1 No. 320.02

    18.64 Providing and fixing PTMT swivelling shower, 15 mm nominal bore, weighing not

    less than 40gms.Code Description Unit Quantity Rate Amount

    Details of cost for one no

    Materials :

    7501 Swiveling shower 15 mm each 81.00 1.00 81.00

    9999 Carriage of materials and fixing charges L.S. 6.76 1.26 8.52

    TOTAL 89.52

    Add 1% for water charges 0.90

    TOTAL 90.41

    Add 15% for contractors profit and overheads 13.56

    Cost of one no 103.97

    18.53 Providing and fixing C.P. brass angle valve for basin mixer and geyser points ofapproved quality conforming to IS:8931

    18.53.1 15 mm nominal bore

    Code Description Unit Quantity Rate Amount

    Details of cost for one no.

    Materials:

    7261 C.P. brass angle valve each 1.00 288.00 288.00

    9999 Carriage and fixing changes L.S. 11.31 1.26 14.25

    TOTAL 302.25

  • 8/13/2019 Analysis for Building

    49/51

    Add for water charges @ 1% 3.02

    TOTAL 305.27

    Add for contractors profit and over head@ 15% 45.79

    Cost for 1 No. 351.06

    18.16 Providing and fixing brass stop cock of approved quality :

    18.16.2 20 mm nominal bore

    Code Description Unit Quantity Rate AmountDetails of cost for one no.

    Materials :-

    1343 20mm dia. brass bib cock, each 1.0 193.00 193.00

    9999 Carriage of materials and fixing charges L.S. 10.79 1.26 13.60

    TOTAL 206.60

    Add 1% for water charges 2.07

    TOTAL 208.66

    Add 15% for contractors profit and overheads 31.30

    Cost of one no. 239.96

  • 8/13/2019 Analysis for Building

    50/51

    3

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Detail for 100 m.

    3.1 90 mm dia O.D.(Finolex ring fit )

    Material

    PVC pipe 90 mm dia (O D ) Rmt. 100.00 178.90 17890.00

    PVC Specials @ 5% 894.5

    18784.50

    Labour

    Fitter Each 0.625 150.00 93.75

    Beldar Each 5 135.00 675.00

    Testing & Sundries Job 96.60

    19649.85

    2947.48

    22597.33Rate per meter 225.97

    Providing and laying and jointing & testing of PVC pipe (Finolex make - ring fit) of

    following dia 6 Kg / cm2 including all specials & fittings etc. as required for proper

    complition of work.( The contractor has to arrange the source of water and require

    head for testing ).

    Add 15% C.P

  • 8/13/2019 Analysis for Building

    51/51

    DESCRIPTION UNIT QTY. RATE AMOUNT

    3.2 Detail for 100 m.

    110 mm dia O.D.(Finolex ring fit )

    Material

    PVC pipe 110 mm dia (O D ) Rmt. 100.00 213.65 21365.00

    PVC Specials @ 5% 1068.25

    22433.25

    Labour

    Fitter Each 0.75 150.00 112.50

    Beldar Each 5.25 135.00 708.75

    Testing & Sundries Job 104.3

    23358.80

    3503.82

    26862.62

    Rate per meter 268.63

    3

    DESCRIPTION UNIT QTY. RATE AMOUNT

    Detail for 100 m.3.1 75 mm dia O.D.(Finolex ring fit )

    Material

    PVC pipe 75 mm dia (O D ) Rmt. 100.00 145.53 14553.00

    PVC Specials @ 5% 727.65

    15280.65

    Labour

    Fitter Each 0.625 150.00 93.75

    Beldar Each 5 135.00 675.00

    Testing & Sundries Job 96.60

    16146.00

    2421.90

    18567.90

    Rate per meter 185.68

    Providing and laying and jointing & testing of PVC pipe (Finolex make - ring fit) of

    following dia 6 Kg / cm2 including all specials & fittings etc. as required for proper

    complition of work.( The contractor has to arrange the source of water and require

    head for testing ).

    Add 15% C.P

    Providing and laying and jointing & testing of PVC pipe (Finolex make - ring fit) of

    following dia 6 Kg / cm2 including all specials & fittings etc. as required for proper

    complition of work.( The contractor has to arrange the source of water and require

    head for testing ).

    Add 15% C.P