Upload
samirjoshi73
View
217
Download
0
Embed Size (px)
Citation preview
7/31/2019 Annexure I A
http://slidepdf.com/reader/full/annexure-i-a 3/4
Annexure-I A
Sr.
No.
Activity Dept.
Responsible
Capacity Remarks IBM's Scope CMI FPE's Response
26 Procurement of Component Planning PO Delivery
date
SAP - -
27 QA Inspection (Source Inspection) - UD1 (inspection type
ZS / ZR)
Quality Man Hours - Part of purchase order external lead
time
28 Incoming QA - UD2 (inspection type 01) Quality Man Hours - To be added in GR processing time in
material master
29 Subcontracting Planning PO Delivery
date
APS Solution. Supply Web will be
integrated with SAP and these dates
will be brought in APS Solution
30 QA Inspection (Source Inspection) - UD1 Quality Man Hours - Should be a part of external lead
time in PO
31 Incoming QA - UD2 (inspection type 01) Quality Man Hours - To be added in GR processing time in
material master
32 Machining of components Mshop Machine Hours SAP Integration with APS Solution.
33 In process inspection (inspection type 03) Quality Man Hours - Should be a part of Routing in SAP
34 Quality inspection against Production Order (inspection
type 04)
Quality Man Hours Quality Check will be defined as a
Routing Operation and Work Center in
SAP and integrated with APS Solution.
Agreed
35 Assembling of components Assembly Man Hours APS solution Should be a part of Routing in SAP
36 In process inspection (inspection type 03) Quality Man Hours - Should be a part of Routing in SAP
37 Quality inspection against Production Order (inspection
type 04)
Quality Man Hours Quality Check will be defined as a
Routing Operation and Work Center in
SAP and integrated with APS Solution.
Agreed
38 Third Party inspection Quality Man Hours - Tracking outside SAP i.e. in APS
Solution.39 Despatch Clearance Projects NA - Tracking outside SAP i.e. in APS
Solution
40 Packing Despatch Man hours to be considered
as it is outsourced.
- Tracking outside SAP i.e. in APS
Solution.
41 Despatch Despatch NA - Despatch intimation to be triggered
by application and confirmed by E& C
on site team on actual receipt of
goods.
Outsourcing of equipment (Make - Buy Decision of Manufacturing Item based on Machine Shop Load - Planning Dept.)
Assembly by Assembly Dept.
7/31/2019 Annexure I A
http://slidepdf.com/reader/full/annexure-i-a 4/4
Annexure-I A
Sr.
No.
Activity Dept.
Responsible
Capacity Remarks IBM's Scope CMI FPE's Response
42 Transportation time Despatch NA This will differ from
customer to customer
(based on geographical
location).
- Despatch intimation to be triggered
by application and confirmed by E& C
on site team on actual receipt of
goods.
43 E & C - Foundation (if in our scope), arrangement of
equipments, alignment of equipments, piping,
instrumentation, final automation, cold run, PAT and
FAT.
E & C Man Hours Project Scheduling Package Confirmation (partial/complete as
applicable)against activities(%
completion based on elapsed time
/site status reports) in Project
strucutre will be carried out by
Project department.
Key stages of E & C activites are
1. E& C of Mechanical Equip
2. E&C of Hydraulic System.
3. E &C of Electrical sytem.
4. PAT
5. FAT
This date will be pushed into APS
application.
End Notes -
1 - Production Order will continue to be made in SAP and TECO etc. performed with no change in cost capture process in SAP.
2 - Engineering efforts for assemblies will be aggregated as 'activities' for each week and will have to be confirm in SAP. Hence if engineering takes say 3 months, there will be 12confirmation required.
3 - All Master data such as Material master, Bill of material, Routing (Including Multiple routing ) will continue to be created in SAP only.
4- All APS standard objects will have Project & WBS element field and selection criteria.