Click here to load reader
Upload
erikapalinlintaguba
View
61
Download
4
Embed Size (px)
DESCRIPTION
ms
Citation preview
CHAPTER 8 STANDARD COSTING & VARIANCE ANALYIS
Exercise 1
1. Determine the material purchase price and quantity variances.
Material price variance:
100,000 P2.50 = P250,000
100,000 P2.60 = 260,000
P 10,000 F
Material quantity variance:
95,625 P2.60 = P248,625
89,250 P2.60 = 232,050
P 16,575 U
2. Determine the labor rate and efficiency variances.
Labor rate variance:
122,400 P8.35 = P1,022,040
122,400 P8.50 = 1,040,400
P 18,360 F
Labor efficiency variance:
122,400 P8.50 = P1,040,400
127,500 P8.50 = 1,083,750
P 43,350 F
Exercise 2
1. Two variance method
Actual (P6,400 + P17,500) P23,900
Budget Variance: P240 U
BFOH (8,900 P1.90) P16,910
VOH (1,800 5 P.75) 6,750 P23,660
Volume Variance: P190 F
Applied OH:
(1,800 5 P2.65) P23,850
2. Three variance method
Actual P23,900
Spending Variance: P315 U
Flexible Budget Based on Actual Input
BFOH P16,910
VOH (8,900 P.75) 6,675 P23,585
Efficiency Variance: P75 F Flexible Budget Based on Standard DLHs
BFOH P16,910
VOH (1,800 5 P.75) 6,750 P23,660
Volume Variance: P190 F
Applied OH:
(1,800 5 P2.65) P23,850
3. Four variance method
Actual VOH P6,400
Variable Spending Variance: P275 F
Flex. Bud. Based on Actual
Input Hours (8,900 P.75) P6,675
Variable Efficiency Variance: P75 F
Applied VOH
(1,800 5 P.75) P6,750
Actual FOH P17,500
FOH Spending Variance: P590 U BUDGETED FOH
P16,910
FOH Volume Variance: P190 F
Applied FOH
(1,800 5 P1.90) P17,100
Exercise 3
a. actual material cost P314,000
actual pieces at standard cost (80,000 P4) 320,000
material purchase price variance P 6,000 F
b. 3,900 units 20 pieces per unit = 78,000 standard quantity allowed
c. total standard cost of material (78,000 P4) P312,000
d. standard cost of actual material used
P312,000 + P6,400 U quantity variance P318,400
P318,400 P4 = 79,600 actual pieces used
e. actual labor cost P40,120
5,900 actual direct labor hours P6 35,400
labor rate variance P 4,720 U
f. 3,900 units 1.5 standard hours per unit 5,850 SHA
g. 5,850 Std Hours Allowed P6 P35,100
h. actual hours standard rate (from e) P35,400
standard cost of labor allowed (from g) 35,100
labor efficiency variance P 300 U
i. actual machine hours standard VOH rate (18,900 P2.50) P47,250
VOH spending variance 50 U
actual VOH P47,300
j. 3,900 units 4.8 standard hours per unit = 18,720 MH allowed
k. standard hours allowed (from j) standard VOH rate
(18,720 P2.50) P46,800
actual machine hours standard rate (from i)
(18,900 P2.50) 47,250
variable overhead efficiency variance P 450 U
l. 19,000 machine hours P3 P57,000
m. 3,900 units 4.8 hours per unit P3.00 P56,160
n. actual fixed overhead P60,000
budgeted fixed overhead (from l) 57,000
fixed overhead spending variance P 3,000 U
o. budgeted fixed overhead (from l) P57,000
applied fixed overhead (from m) 56,160
volume variance P 840 U
p. total actual overhead P107,300
[P60,000 + P47,300 (from i)]
total applied overhead (18,720 SHA P5.50) 102,960
Total overhead variance P 4,340 U
Exercise 4
a. Total direct material cost variance.
= Actual direct material cost Standard direct material cost = (1,900 lbs x P41) (8,000 x 0.25 x P40) ; = P77,900 - P80,000 ; = P2,100 favorable
b. Direct material price variance.
= (AP SP) x AQ ; = (P41 - P40) x 1,900 lbs = P1,900 unfavorable
c. Direct material quantity variance.
= (AQ SQ) x SP; = [1,900 lbs - (8,000 x 0.25)] x P40 = P4,000 favorable
d. Total direct labor cost variance.
= Actual direct labor cost Standard direct labor cost = (250 x P18.25) (8,000 x 0.03 x P18) ; = P4,562.50 - P4,320.00 = P242.50 unfavorable
e. Direct labor rate variance.
= (AR SR) x AH ; = (P18.25 - P18.00) x 250 = P62.50 unfavorable
f. Direct labor efficiency variance.
= (AH SH) x SR ; = [250 - (8,000 x 0.03)] x P18 = P180.00 unfavorable
Exercise 5
a. Master Flexible Actual
Budget Budget Results
Sales volume (in units) 30,000 25,000 25,000
Sales revenues P3,600,000 P3,000,000 P3,000,000
Flexible (variable) costs 2,160,000 P1,800,000 1,930,000
Contribution margin 1,440,000 P1,200,000 1,070,000
Capacity-related (fixed) costs 900,000 P 900,000 970,000
Operating profit P 540,000 P 300,000 P 100,000
b. Determine the flexible (variable) cost variance.
= Actual cost Flexible budget cost ; = P1,930,000 - P1,800,000 = P130,000 unfavorable
c. Determine the flexible (variable) planning variance.
= Flexible budget cost Master budget cost ; = P1,800,000 P2,160,000 = P360,000 less than planned
d. As these results suggest, the manager should not be congratulated for keeping costs under control.
Flexible (variable) costs were P130,000 over budget for actual output and capacity-related (fixed) costs
were also P70,000 over budget. These variances from the flexible budget highlight the amounts that are
different than planned. Since variances simply signal a deviation from what was planned, these differences
need to be investigated before corrective actions can be taken.
Exercise 6
MATERIAL QUANTITY VARIANCE
A (181,000 172,200) P0.06 = P 528 UNF
B (33,000 28,700) P0.12 = 516 UNF
C (6,000 4,100) P0.25 = 475 UNF
P1,519
Act Q x Act Mix x Std P Act Q x Std Mix x Std P Act Q x
Std Mix x Std P
A 181,000 P0.06 = P10,860 184,800 P0.06 = P11,076 172,200 P0.06 = P10,332
B 33,000 P0.12 = 3,960 30,800 P0.12 = 3,696 28,700 P0.12 = 3,444
C 6,000 P0.25 = 1,500 4,400 P0.25 = 1,100 4,100 P0.25 = 1,025
P16,320 P15,872 P14,801
MIX VARIANCE = P 436 UNF
YIELD VARIANCE = P1,083 UNF
Total P1,519 UNF
Exercise 7
(AH x AM X SR) x (AH x SM x SR ) x (SH x SM x SR )
MIX VARIANCE YIELD VARIANCE
A 5,400 P4 = P21,600 6,000 P4 = P24,000 5,880 P4 = P23,520
B 3,200 P6 = 19,200 3,000 P6 = 18,000 2,940 P6 = 17,640
C 1,300 P8 = 10,400 1,000 P8 = 8,000 980 P8 = 7,840
D 100 P10 = 1,000 P50,000 P49,000
P52,200
MIX VARIANCE = P2,200 UNF
YIELD VARIANCE = P1,000 UNF
RATE VARIANCE = P 800 UNF (P53,000 P52,200)
Exercise 8
TOTAL COST EQUATION = P80,000 FIXED + P20,000 / 10,000 = P2 variable per dlh
a. 120% = P80,000 + (12,000 P2) = P104,000
100% = P80,000 + (10,000 P2) = P100,000
80% = P80,000 + ( 8,000 P2) = P 96,000
60% = P80,000 + ( 6,000 P2) = P 92,000
APPLICATION RATE = P100,000 / 10,000 dlh = P10 per dlh
Volume variance = fixed oh rate x difference in normal or planned and actual units produced.
P80,000 / 10,000 = P8 per dlh
. 120% = (12,000 10,000 = 2,000 P8) = P16,000
100% = (10,000 10,000 = 0 P8) = P0
80% = ( 8,000 10,000 = -2,000 P8) = - P 16,000
60% =( 6,000 10,000 = - 4,000 P8) = - P 32,000
b. BUDGET VARIANCE = ACTUAL FOH BUDGETED FOH
P9,000 FAV = P87,000 P96,000
Exercise 9
1. Applied rate = P6/dlh
Total Overhead Cost = P50,000 + P1/dlh
Std Overhead (A) 5,000 2 = 10,000
(B) 5,000 4 = 20,000
Std Hrs. 5,000 2 = 10,000
2. a. 1. (P7.20 P7.00) 12,000 = P2,400 U
2. (P3.90 P4.00) 20,000 = 2,000 F
P 400 U
b. 1. (10,500 10,000) P7.00 = P3,500 U
2. (19,800 20,000) P4.00 = 800 F
P2,700 U
c. P79,380 (9,800 P8) = P980 U
d. (9,800 10,000) P8 = P1600 F
e. (10,000 10,000) P5 = 0
f. (9,800 10,000) P1 = P200 F
g. Fix Spd P48,100 P50,000 = P1,900 F
Var Spd P21,000 (9,800 P1) = P11,200 U
Exercise 10
STD Q A 120,000 3 = 360
1,000
B 120 6 = 720
C 120 9 = 1,080
ACT HRS ACT HRS STD HRS
ACT MIX STD MIX STD MIX
STD P STD P STD P
MIX VARIANCE YIELD VARIANCE
A 390 P4.50 = P1,755 390 P4.50 = P1,755 360 P4.50 = P1,620
B 980 P4.00 = P3,920 780 P4.00 = P3,120 720 P4.00 = P2,880
C 970 P3.00 = P2,910 1,170 P3.00 = P3,510 1,080 P3.00 = P3,240
P8,585 P8,385 P7,740
P200 UNF P645 UNF
Test I MULTIPLE CHOICE
1 D 13 C 25 C 37 A
2 B 14 A 26 B 38 B
3 D 15 B 27 A 39 A
4 A 16 B 28 C 40 A
5 D 17 C 29 B 41 B
6 C 18 C 30 A 42 D
7 B 19 A 31 D
8 A 20 B 32 A
9 C 21 A 33 C
10 C 22 D 34 A
11 B 23 B 35 B
12 A 24 C 36 A
Test II MULTIPLE CHOICE
1 A 13 D 25 B
2 D 14 B 26 D
3 C 15 C 27 D
4 D 16 D 28 B
5 D 17 D 29 D
6 D 18 C 30 D
7 A 19 B 31 C
8 B 20 C
9 A 21 B
10 C 22 D
11 C 23 C
12 D 24 A