Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
Application of AC – DC in the connection of wind farms
G.J.Gerdes
Deutsche WindGuard GmbH
www.windguard.de
EU Round table
16th of May 2018
www.windguard.dewww.windguard.de
Outline
• AC/DC/AC Inverter in wind turbines
• HVDC and AC in German wind farm feeders
www.windguard.de
DC in Wind Turbines
2
www.windguard.dewww.windguard.de
Direct ConnectionDirect Connection
Grid coupling of wind turbines
Disadvantage:
• fluctuations in wind are directly transformed into power fluctuations
• this having an impact on mechanical loads (torque) and electrical power quality
• Low controllability
3
Gen
generatorGear box
rotor
grid
Grid frequency
inverter system
coupled
=Decoupled
≠
Advantage:
• lower mechanical stress high controllability
• Improved electrical power quality
• Higher aerodynamic efficiency
Generating frequency
www.windguard.dewww.windguard.de
Downtime due to inverter failures in wind turbines
4Source: Elforsk
From research study “Investigation of converter failure in wind turbines”, Elforsk
www.windguard.de
• Technical availability calculated for 5 wind farms
– Covers: standstills due to technical failures of the wind turbines and repair
– Excludes: regular maintenance, external faults (grid, meteorology, owner stops)
5
Example of annual availability of selected wind farms
Year11 WTG Full
inverter5 WTG Full
inverter4 WTG
double fed IG5 WTG
double fed IG5WTG direct
coupling
2017 97.7% 99.6% 99.1% 97.7% 98.3%
2016 98.2% 96.7% 98.9% 99.1% 96.1%
2015 99.9% 99.3% 99.0% 97.2% 98.3%
2014 99.1% 96.0% 98.9% 97.7% 95.5%
Average 98.7% 97.9% 99.0% 97.9% 97.1%
Standstill 1.3% 2.1% 1.0% 2.1% 3.0%
www.windguard.de
Development of Offshore wind farm connection in Germany
6
www.windguard.dewww.windguard.de
Planning of offshore connections started in 2002: Total capacity planned from 2010 on
6,3 GW
6,8 GW
2,4 GW
9,5 GW
3
3
4
Total capacity: 25 GW
1
www.windguard.de
•
8
Ecological concerns
• Extension of areas:
– National park: along most of the coast line
– Shipping routes: the remaining coast line
• Compromise:
– Very few drillings underneath the national park area
– Limited number through shipping lines
Resulting in cables with high transport capacity
www.windguard.de
Target:
• to minimize the number of connecting cables
• To maximize the transport capacity of each cable
• To minimize the ecological impact (electromagnetic fields, heating of see ground, etc.)
First plans for connecting offshore wind farms
www.windguard.dewww.windguard.de
Available technology in 2004 for maximumtransport capacity of each cable
• 3-phase AC current:
– Three-conductor cable : 170kV, 200MW to 245kV, 250MW
– Single conductor cables: 420kV, 400MW
– Largest distance offhsore 120km
• DC current:
– Conventional HVDC (Thyristor): 800MW to 1 GW, 800kV (±400kV)
– Bipolar Transmission (Monopolar cable) ±600kV, 2500MW
– HVDC-IGBT up to 145kV, 250 - 300MW
• GIL:
– At that time realisation of 400kV at 2000MVA
– Higher capacities are theoretically possible
www.windguard.dewww.windguard.de
Technology and transmission distance
11
0 60 120 180 240
Co
st
Length of Line[km]
HVAC
HVDC
www.windguard.dewww.windguard.de
Offshore wind farm connections in operation or construction – North Sea
15
ConnectionCommissioning
date
Cabel
length
Offshore
Cabel
length
Onshore
Cabel
length
total
Technology CapacityVoltage
Level
DC
platform
Supplier
Alpha Ventus 2009 60 km 6 km 66 km HVAC 62 MW 110 kV AC
Riffgat 2014 50 km 30 km 80 km HVAC 113 MW 155 kV AC
Nordergründe 2017 28 km 4 km 32 km HVAC 111 MW 155 kV AC
BorWin1 2012 125 km 75 km 200 km HVDC 400 MW ±150 kV ABB
BorWin2 2015 125 km 75 km 200 km HVDC 800 MW ±300 kV Siemens
BorWin3 u. constr. 2019 130 km 30 km 160 km HVDC 900 MW ±320 kV Siemens
DolWin1 2015 75 km 90 km 165 km HVDC 800 MW ±320 kV ABB
DolWin2 2017 45 km 90 km 135 km HVDC 916 MW ±320 kV ABB
DolWin3 u. constr. 2018 80 km 80 km 160 km HVDC 900 MW ±320 kV Alstom
HelWin1 2015 85 km 45 km 130 km HVDC 576 MW ±250 kV Siemens
HelWin2 2015 85 km 45 km 130 km HVDC 690 MW ±320 kV Siemens
SylWin1 2015 160 km 45 km 205 km HVDC 864 MW ±320 kV Siemens
HelWin2 2015 85 km 45 km 130 km HVDC 690 MW ±320 kV Siemens
Total 1 133 km 660 km 1 793 km 7 822 MW only DC 7 536 MW
www.windguard.dewww.windguard.de 16
Source: TenneT
HVDC offshore wind farm connections in the North Sea
www.windguard.dewww.windguard.de
Offshore development in Germany until 2025
17
5.4 GW
0.8 GW
1.5 GW
0.02 GW
1.5 GW
1.6 GW
OWT (feeding in)
Installed OWT (no feed-in)
Construction in Progress
Final Investment Decision
Grid Connection Capacityassigned
Acceptance of Bid
Available in Tender 2018
Expected Development
by 2020 (7.7 GW)
Expected Development
by 2025 (10.8 GW)
Until 2030: 15GW, tender starting 2021
www.windguard.dewww.windguard.de
Development of offshore transmission and wind farm capacities
• Transmission capacity:
– 2020 7.8 GW
– 2021 to 2030 15.0 GW
• Offshore wind farm capacities:
– Today 5.4 GW
– 2020 7.8 GW
– 2025 10.8 GW
– From 2021 on 700-900 MW/year
– 2030 15.0 GW
18
www.windguard.dewww.windguard.de
Grid connection and offshore wind farm capacities
19Source: Stiftung Offshore Windenergie
www.windguard.de
Towards an offshore meshed grid
20
www.windguard.dewww.windguard.de
Development of a meshed offshore grid (MOG) in the North Sea
• Several studies have been conducted by the EU, showing the overall benefit for the participating countries
• Purpose of a MOG is
– the transport of offshore wind power to land
– the connection of markets and thus
– more electricity trading and levelling of electricity market prices in the EU
• A project to accelerate the development of a MOG is currently running: PROMOTION
21
www.windguard.dewww.windguard.de
Example of a meshed offshore grid
22Source: PROMOTION
www.windguard.dewww.windguard.de
Example of meshing offshore grid connections
23
Kriegers Flak combined grid solution
Source:Energienet, Tennet
Thank you
Gerhard Gerdes
04451 9515 110
www.windguard.dewww.windguard.de
www.windguard.de 26
Personal DC Experience, long time ago
• Stand alone system, 1983
• consumption approx. 10000kwh/a
• Electricity supply: wind turbine, photovoltaics, Back-up CHP-unit
• Storage: Lead acid Batteries and later Hydrogen
• Battery Storage: 170kWh
• System tension: DC, 208 VDC
Experience:
Huge switches
Huge auxiliary drives (pumps etc.)
Even ohmic loads were difficult
Sine wave (and even trapeze) inverters were very expensive