contact Paseo de la Reforma 483, 06500, Mexico City. T. +52 (55) 7316 2228 1200 Smith St, 77002, Houston, Texas. T. +1 (713) 353 3952 www.talanza.energy thalya berrones is in charge of providing advice to clients within the Midstream and Downstream sectors, in order to propose reliable and competitive solutions, through an in-depth analysis of the market conditions, the applicable regulation and the commercial potential for the business development. [email protected] david rosales provides solutions for business development, regulatory compliance and feasibility analysis for natural gas and liquids projects. He has experience designing strategies to identify supply, demand and funding for infrastructure projects, including a deep feasibility analysis due to a profound understanding of the regulatory environment and t regional energy balances involved on each case, both for natural gas and liquid fuels. [email protected] 1.- NEW INTEGRATION PROPOSAL The current General Director of CENAGAS, Lic. Elvira Daniel, declared in April 2019 that the Mexican Government is evaluating “to integrate more gas pipelines in the country" to convert said Center into a "national manager", consistent with the provisions of the Fourth Review of the Five-Year Expansion Plan of the SISTRANGAS, published in the last days of March by the Ministry of Energy, where the intention will be to expand the SISTRANGAS to include the following projects: 2.- FOLLOWING MOVES It is interesting to evaluate what should happen for CENAGAS to be able to integrate the referred projects into SISTRANGAS. It is worth reiterating that the incorporation is voluntary, so one of the first steps will be to find incentives for pipeline developers to seek integration, either in tariff, energy securi- ty or operational efficiency. Under this framework, the driver of integration requires an analysis of the different feasible options in each case, with the understanding that integration is acceptable for gas pipelines as long as there are economic incentives for the developer, and is acceptable for CENAGAS if it represents systemic benefits (security, continuity, reliability, redundancy, etc.) As Pemex once was the anchor shipper, now CFE integrates into the scheme being a feasible long-term counterpart for CENAGAS contracts, highlighting the need to evaluate the options and conduct studies, such as those that were made for the transfer of the contracts of Los Ramones Fase I of Pemex Gas and Petroquímica Básica to CENAGAS itself. The Centro Nacional de Control del Gas Natural (CENAGAS), is the operator of the Sistema de Transporte y Almacenamiento Nacional Integrado de Gas Natural (SISTRANGAS) and currently, the only shipper of the integrated systems, offering to the market integrated capacity and charging tariffs to the users. In order to achieve its purpose, CENAGAS proposes and the Comisión Reguladora de Energía (CRE) approves the transportation rates for each tariff zone, as well as the terms and conditions that govern the provision of services. With these tariffs charged for transportation services, the operator pays the different integrated systems for their respective revenue requirements, as well as their own management costs and, occasionally, the purchase of natural gas for the balancing of their systems. april 2019 CENAGAS, the operator of the SISTRANGAS seeks to expand Comprehensive energy regulatory consultancy given by former key officials that participated in the design and implementation of the new energy model. In TALANZA we support our clients preparing the strategy for requesting integration, in which we involve regulatory, technical and economical arguments as well as advocacy efforts, for building a strong case in the application for integration. NEXT STEPS CENAGAS must include the integration and its motivations in the Five-Year Expansion Plan of SISTRANGAS 2020 to 2024. 4 Together, they must inform CRE of their intention to integrate. 3 CRE must approve a new tariff package for the CENAGAS and resolve the integration. 5 Developers must obtain approval from their respective Boards of Directors, but more importantly from those entities that have financed part of their investments, such as banks or funds. 2 CENAGAS should approach the develop- ers to know their interest in joining the system. 1 The steps to continue with the integration plans would be the following: 3.- POSSIBLE INCENTIVES Recover the certainty of the return on investment. Solve a problem of public relations with the government. Extend the commercial life of the infrastructure. Reduce the administrative and regulatory burden when transferring commercial responsibilities to CENAGAS manager. 4.- CONSIDERATIONS Parties interested in integration, need to build a solid case that includes, among others, pre-feasi- bility technical analyzes, a tariff proposal that considers the needs of the environment, a legal sequence in accordance with the regulatory framework and the understanding of bilateral relations that derive from integration, as well as a full understanding of the benefits and / or risks of the process. ANALYSTS Current tariff zones at SISTRANGAS Tuxpan – Tula PROJECT La Laguna – Aguascalientes Tula – Villa de Reyes Villa de Reyes – Guadalajara Sur de Texas – Tuxpan El Encino – La Laguna San Isidro – Samalayuca DEVELOPER TransCanada Fermaca TransCanada Fermaca TransCanada - IEnova Fermaca IEnova

april CENAGAS, the operator of the SISTRANGAS seeks to …

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: april CENAGAS, the operator of the SISTRANGAS seeks to …

contact

Paseo de la Reforma 483,06500, Mexico City. T. +52 (55) 7316 2228

1200 Smith St, 77002,Houston, Texas.T. +1 (713) 353 3952

www.talanza.energy

thalya berrones is in charge of providing advice toclients within the Midstreamand Downstream sectors, in order to propose reliable and competitive solutions, through an in-depth analysis of the market conditions, the applicable regulation and the commercial potential for the business development.

[email protected]

david rosales provides solutions for business development, regulatory compliance and feasibility analysis for natural gas and liquids projects. He has experience designing strategies to identify supply, demand and funding for infrastructure projects, including a deep feasibility analysis due to a profound understanding of the regulatory environment and t regional energy balances involved on each case, both for natural gas and liquid fuels.

[email protected]

1.- NEW INTEGRATION PROPOSAL

The current General Director of CENAGAS, Lic. Elvira Daniel, declared in April 2019 that the Mexican Government is evaluating “to integrate more gas pipelines in the country" to convert said Center into a "national manager", consistent with the provisions of the Fourth Review of the Five-Year Expansion Plan of the SISTRANGAS, published in the last days of March by the Ministry of Energy, where the intention will be to expand the SISTRANGAS to include the following projects:

2.- FOLLOWING MOVES

It is interesting to evaluate what should happen for CENAGAS to be able to integrate the referred projects into SISTRANGAS. It is worth reiterating that the incorporation is voluntary, so one of the first steps will be to find incentives for pipeline developers to seek integration, either in tariff, energy securi-ty or operational efficiency. Under this framework, the driver of integration requires an analysis of the different feasible options in each case, with the understanding that integration is acceptable for gas pipelines as long as there are economic incentives for the developer, and is acceptable for CENAGAS if it represents systemic benefits (security, continuity, reliability, redundancy, etc.)

As Pemex once was the anchor shipper, now CFE integrates into the scheme being a feasible long-term counterpart for CENAGAS contracts, highlighting the need to evaluate the options and conduct studies, such as those that were made for the transfer of the contracts of Los Ramones Fase I of Pemex Gas and Petroquímica Básica to CENAGAS itself.

The Centro Nacional de Control del Gas Natural (CENAGAS), is the operator of the Sistema de Transporte y Almacenamiento Nacional Integrado de Gas Natural (SISTRANGAS) and currently, the only shipper of the integrated systems, offering to the market integrated capacity and charging tariffs to the users.

In order to achieve its purpose, CENAGAS proposes and the Comisión Reguladora de Energía (CRE) approves the transportation rates for each tariff zone, as well as the terms and conditions that govern the provision of services.

With these tariffs charged for transportation services, the operator pays the different integrated systems for their respective revenue requirements, as well as their own management costs and, occasionally, the purchase of natural gas for the balancing of their systems.

april 2019

CENAGAS, the operator of theSISTRANGAS seeks to expand

Comprehensive energy regulatory consultancy given by former key officials that participated in the design and implementation ofthe new energy model.

In TALANZA we support our clients preparing the strategy for requesting integration, in which we involve regulatory, technical and economical arguments as well as advocacy efforts, for building a strong casein the application for integration.

NEXT STEPS

CENAGAS must include the integration and its motivations in the Five-Year Expansion Plan of SISTRANGAS 2020to 2024.

4

Together, they must inform CRE of their intention to integrate.

3

CRE must approve a new tariff package for the CENAGAS and resolve the integration.

5

Developers must obtain approval from their respective Boards of Directors, but more importantly from those entities that have financed part of their investments, such as banks or funds.

2

CENAGAS should approach the develop-ers to know their interest in joining the system.

1

The steps to continue with the integration plans would be the following:

3.- POSSIBLE INCENTIVES

Recover the certainty of the return on investment.

Solve a problem of public relations with the government.

Extend the commercial life of the infrastructure.

Reduce the administrative and regulatory burden when transferring commercial responsibilities to CENAGAS manager.

4.- CONSIDERATIONS

Parties interested in integration, need to build a solid case that includes, among others, pre-feasi-bility technical analyzes, a tariff proposal that considers the needs of the environment, a legal sequence in accordance with the regulatory framework and the understanding of bilateral relations that derive from integration, as well as a full understanding of the benefits and / or risks of the process.

ANALYSTS

Current tariff zones at SISTRANGAS

Tuxpan – Tula

PROJECT

La Laguna – Aguascalientes

Tula – Villa de Reyes

Villa de Reyes – Guadalajara

Sur de Texas – Tuxpan

El Encino – La Laguna

San Isidro – Samalayuca

DEVELOPER

TransCanada

Fermaca

TransCanada

Fermaca

TransCanada - IEnova

Fermaca

IEnova