34
1 . Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ Roger Berna, GM Construction Services Report as of May 31, 2015

Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

1

.

Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement

Phoenix, AZ

Roger Berna, GM Construction Services

Report as of May 31, 2015

Page 2: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

2

ADVS Arizona Veterans’ Memorial ADVS Arizona Veterans’ Memorial

Cemetery, Marana, AZ Cemetery, Marana, AZ

Summary Report ADOA Project # Project Description by Agency Project Manager Page No

New Projects:

8430 Corporation Commission-Attorney General, William Anderson 11 1200-1275 W. Washington, Phoenix, AZ Central Plant Repair/Replacement

8720C ADOA, 2910 N. 44th Street, Phoenix, AZ John Webster 15 Elevator Modernization 4045TI.1 ADJC AMS New Access Controls and Locks, Phoenix, AZ Armando Milheiro 19 4046TI.1 ADJC AMS Fire Suppression System Replacement, Phoenix, AZ 20 4046TI.2 ADJC AMS Fan Coil Unit Replacement, Phoenix, AZ 21 8954TI.5A ASDB Tucson, New Fire Alarm Replacement, Maricopa Dorm, Janet Collegio 31 Tucson, AZ 8954TI.6B ASDB Tucson, New Fire Alarm Replacement, Palo Verde Dorm, 32 Tucson, AZ

ADOT Building Renewal Projects - FY2015-2016 Globe Equipment Storage, Globe, AZ – Repaint the building exterior. Alvin Spencer 25 Grey Peak Modular Residence, Greenlee County, AZ – Replace existing windows with energy efficient windows. Safford District Office, Safford, AZ – Repaint the exterior of all site buildings. Payson Equipment Shop, Payson, AZ – Replace failed building siding with new panels.

Completed Projects:

ADOT Building Renewal Projects - FY2015 9651 N 99 Ave. West Valley Construction Office Bldg. 1631, Peoria, AZ, Alvin Spencer 24 Roof and parapet wall repairs Facilities Maintenance & Support, Bldg 1762, Phoenix, AZ – Repair existing roof with application of insulation board and single ply roof system. 7130 W Fairfield, Bldg 1521, Chandler, AZ – Repair and recoat existing roof with white elastomeric coating Globe Maintenance Office, Globe, AZ – Replace existing HVAC Units and roofing

Page 3: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

3

Arizona State Hospital (ASH) Arizona State Hospital (ASH)

Chiller Replacement Chiller Replacement Phoenix, AZ Phoenix, AZ

Table of Contents

Page No. Summary Report 2

Table of Contents 3-5 Legend 6 Frequently Used Acronyms 7-8

ADOA Project # Project Description by Agency Project Manager

ARIZONA DEPARTMENT OF ADMINISTRATION (ADOA)

8410 ADOA Security System Replacement Assessment and Design Capitol Mall, Phoenix, AZ John Webster 9-10 8430 Corporation Commission-Attorney General, 1200-1275 W. Washington, Phoenix, AZ - Central Plant Repair-Replacement William Anderson 11 8633TI.19 Replace Electrical Service Entrance (SES) @ Executive Tower, Phx, AZ William Anderson 12 8709TI.9C Capitol Mall ADC HR Bldg, 1831 W. Jefferson, Phx, AZ Janet Collegio Fire Alarm Replacement 13 8720B ADOA Managed Building, 1300 W. Washington, Phx, AZ

Elevator Modernization John Webster 14 8720C ADOA Managed Building (Sunstate), 2910 N. 44th Street, Phx, AZ Elevator Modernization 15

ARIZONA DEPARTMENT OF CORRECTIONS (ADC)

5507 ASPC Lewis Complex – Drill New Potable Well #6, Buckeye, AZ John Webster 16

ARIZONA DEPARTMENT OF HEALTH SERVICES (ADHS)

8336 Arizona State Hospital (ASH) Chiller Replacements, Phx, AZ Roger Berna 17

*Note: ASPC - acronym for Arizona State Prison Complex

Page 4: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

4

ADJC Adobe Mountain School ADJC Adobe Mountain School Firefighting Water Distribution Sys. Firefighting Water Distribution Sys.

Phoenix, AZ Phoenix, AZ

ADOA Project # Project Description by Agency Project Manager Page No

ARIZONA DEPARTMENT OF JUVENILE CORRECTIONS (ADJC)

4045 ADJC Adobe Mountain Schools-Fire Fighting Water Distribution System Armando Milheiro 18 Phx, Arizona

4045TI.1 ADJC Adobe Mountain Schools, New Access Controls and Locks, 19 Phx, Arizona 4046 ADJC Adobe Mountain Schools, Plumbing Chase Pipe Replacement 20

Phx, Arizona 4046TI.1 ADJC Adobe Mountain Schools, Fire Suppression System Replacement, 21 Phx, Arizona 4046TI.2 ADJC Adobe Mountain Schools, Fan Coil Unit Replacement 22 Phx, Arizona

ARIZONA DEPARTMENT OF PUBLIC SAFETY (DPS)

9505 DPS Tucson, CI Bldg., 6401 S. Tucson, Blvd., Tucson, AZ Bill Anderson 23

Fire Alarm System Replacement ARIZONA DEPARTMENT OF TRANSPORTATION (ADOT) ADOT Building Renewal Projects - FY2014-2015 Facilities Equipment Shop 2080, Globe, AZ – Replace HVAC system. Alvin Spencer 24-25 Port of Entry W/B I-8 2017, Yuma, AZ – Replace failing a/c unit. 9651 N 99 Ave. West Valley Construction Office Bldg. 1631, Peoria, AZ – Roof and parapet wall repairs. 200 N ADOT Ln Winslow MVD, Winslow, AZ – Replace windows. Facilities Maintenance & Support, Bldg 1762, Phoenix, AZ – Repair existing roof with application of insulation board and single ply roof system. 7130 W Fairfield, Bldg 1521, Chandler, AZ – Repair and recoat existing roof with white elastomeric coating.. Various Sites, Central District, Maricopa County, AZ – Review existing roofs and assist ADOT to establish a priority list for repair and maintenance. Grey Peak Residence 2144, Greenlee County, AZ – Replace windows Globe Maintenance Office, Globe, AZ – Replace existing HVAC Units and roofing Tucson Regional MVD, Tucson, AZ – Repaint building exterior. Tucson East MVD, Tucson, AZ – Repaint building interior and exterior. Grey Peak Maintenance Yard, Greenlee County, AZ – Repaint the exterior of all buildings.

Page 5: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

5

ADVS Arizona Veterans’ Memorial ADVS Arizona Veterans’ Memorial Cemetery @ Camp Navajo Cemetery @ Camp Navajo Bellemont, AZ Bellemont, AZ

ADOA Project # Project Description by Agency Project Manager Page No

ARIZONA DEPARTMENT OF TRANSPORTATION (ADOT) ADOT Building Renewal Projects - FY2014-2015 Globe Equipment Storage, Globe, AZ – Repaint the building exterior. Alvin Spencer 25 Grey Peak Modular Residence, Greenlee County, AZ – Replace existing windows with energy efficient windows. Safford District Office, Safford, AZ – Repaint the exterior of all site buildings. Payson Equipment Shop, Payson, AZ – Replace failed building siding with new panels.

ARIZONA DEPARTMENT OF VETERANS’ SERVICES (ADVS)

9009 Arizona Veterans’ Memorial Cemetery @ Camp Navajo, Bellemont, AZ Jeff Pugh 26-27 9011 Arizona Veterans’ Memorial Cemetery @ Marana, AZ Jeff Pugh 28-29

ARIZONA HISTORICAL SOCIETY MUSEUM - TEMPE MUSEUM

8647TI.2 AHS Tempe Museum, 1300 N. College Ave., Tempe, AZ FA Replacement System Janet Collegio 30-31

ARIZONA SCHOOL FOR THE DEAF and BLIND/Tucson Campus

8954TI.5A ASDB Tucson, Fire Alarm Replacement System, Maricopa Dorm, Janet Collegio 32 Tucson, AZ

8954TI.5B ASDB Tucson, Fire Alarm Replacement System, Palo Verde Dorm, 33 Tucson, AZ

ARIZONA STATE TUCSON OFFICE COMPLEX

8630TI.15 Arizona State Tucson Office Complex - EMS Upgrades 400, 402, 416 W. Congress, Tucson, AZ Bill Anderson 34

Page 6: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

6

Arizona Dept. Public Safety Capitol Mall Records Retention 6401 S. Tucson Blvd., Tucson, AZ 1919 W. Jefferson, Phx, AZ Fire Alarm Replacement Fire Alarm Replacement

Legend: Date Funded: *Date funding assigned to the project

Project Manager: Individual assigned to carry out and be responsible for construction of all portions of the project Senior Project Manager: Oversees the Project Manager Budget: The sum established as available for the entire project including but not limited to

professional fees, contingency allowance and construction of the project Budget Source: *Where the money is appropriated from - Capital Appropriation, Building Renewal, Operations, Client Funded etc. Architect/Engineer (A/E): Licensed Consultant hired to perform architectural/engineering services including

analyzing project requirements, creating and developing project designs, preparing drawings and specifications, bidding and general construction administration of the construction contract

Contractor: Company hired to provide all materials, labor, equipment and supervision to perform all

necessary work to complete the project Statewide Statutory Plans and Specifications reviewed by State Engineer for code compliance are Review Project Number: given a specific project number by State Engineer’s office Completion Dates Construction Documents: *Anticipated date when Construction Documents/Drawings and Specifications

(description of materials and workmanship required) are completed by the A/E for bidding for pricing purposes

Bid Date: Date for the receipt of bids (cost proposals) from the Contractors Notice to Proceed (NTP): Written notice to Contractor indicating the date established to proceed with the

project Substantial Completion: Date certified by Architect when the project or designated portion of the project is sufficiently complete for the use for which it is intended Target Completion: *Date identified by ADOA Construction Services and Client when Client can expect the

project to be finally compete *ADOT projects excluded. All ADOT projects are considered Client Funded as ADOA receives no information regarding Budget Source, Funding Year, etc. when projects are assigned to ADOA by ADOT.

Page 7: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

7

1700 W. Washington, SES Replacement 1700 W. Washington, SES Replacement

Phoenix, AZ Phoenix, AZ

FrequentLy used ACrOnyMs

ACM: Asbestos Containing Material CA: Construction Administration – additional services performed by A/E (not under basic services) to administer

the construction contract (facilitate project communications, maintain project records, review and certify pay applications, review shop submittals/drawings, attend progress meetings, perform site visits, ensure that construction is per plans, specifications and codes).

CD: Construction Documents - prepared drawings and specifications from the approved design development

documents comprising the working drawings (drawings intended for use by a contractor, subcontractor, or fabricator) which form part of the contract documents for a building project.

CCD: Construction Change Directive - a directive for changes in the Work for use where the Owner and

Contractor have not reached an agreement on proposed changes in the Contract, the contract sum or contract time.

CO: Change Order - a written order to the Contractor (signed by the Owner and the Architect), issued after the

execution of the Contract, authorizing a change in the Work or an adjustment in the contract sum or the contract time, as originally defined by the contract documents.

COP: Certificates of Participation - a type of financing where an investor purchases a share of the lease revenues of a program rather than the bond being secured by those revenues. The authority usually uses the proceeds to construct a facility that is leased to the municipality.

CM@R: Construction Manager @ Risk - is a delivery method which entails a commitment by the Construction Manager to

deliver the project within a Guaranteed Maximum Price (GMP), acting in the owner's interest. The Construction Manager must manage and control construction costs to not exceed the GMP.

CRAC: Computer Room Air Conditioner DCN: Design Change Notice - a written order to the Architect/Engineer issued after the execution of their contract

to direct the A/E of an addition or change in scope of work to the construction project. DD: Design Development Documents – documents prepared by the Architect and other documents, to fix and

describe the size and character of the entire project, as to structural, mechanical and electrical systems, materials and such other essentials as may be appropriate (and also when a further statement of probable construction cost may be submitted) for the owner’s approval and review.

EIFS: Exterior Insulation and Finish System - a synthetic stucco weatherproofing and insulation system that is

lightweight, inexpensive and very flexible. EIFS consists of an extruded (XPS) or expanded polystyrene (EPS) or a polyisocyanurate foam glass fiberboard for insulation and an acrylic stucco finish for weatherproofing.

ESCO: Energy Service Company - a professional business providing a broad range of comprehensive energy solutions

including designs and implementation of energy savings projects.

Page 8: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

8

continued…

ESPC: Energy Savings Performance Contract - an agreement with a private energy service company (ESCO). The ESCO will identify and evaluate energy-saving and water saving opportunities and then recommend a package of improvements to be paid for through savings. The ESCO will guarantee that savings meet or exceed annual payments to cover all project costs, usually over a contract term of seven to ten years or longer. If the guaranteed savings aren’t realized, the ESCO pays the difference between the actual and projected cost. To ensure savings, the ESCO offers staff training and long-term maintenance services.

FOAM: Division of ADOA – Facilities Operations and Maintenance - provides service in the areas of maintenance,

custodial, grounds and landscaping, and HVAC operations. GMP: Guaranteed Maximum Price - (also known as Not-To-Exceed Price, NTE, or NTX) contract is a cost-type

contract (also known as an open-book contract) where the contractor is compensated for actual costs incurred plus a fixed fee subject to a ceiling price. The contractor is responsible for cost overruns, unless the GMP has been increased via formal Change Order (only as a result of additional scope from the client, not price overruns, errors, or omissions). Savings resulting from cost under runs are returned to the Owner, or shared with the Contractor as an incentive.

HVAC: The abbreviation for heating, ventilation and air conditioning systems, used in building design and construction. IGA: Investment Grade Audit – is a technical and economic analysis of potential energy saving projects in a facility. JCCR: Joint Committee on Capital Review – committee that ascertains facts and makes recommendations to the

Legislature regarding State expenditures for land, buildings and improvements. JOC: Job Order Contract - is a way for organizations to get numerous, commonly encountered construction projects

done quickly and easily through multi-year contracts. JOC reduces unnecessary levels of engineering, design, and contract procurement time along with construction project procurement costs by awarding long-term contracts for a wide variety of renovation, repair and construction projects. Projects are priced from the Owner’s unit cost book rather than bid.

MPE: The abbreviation for mechanical, plumbing and electrical systems. NTP: Notice to Proceed. PEA: Preliminary Energy Audit – an early audit of the energy and water systems of a building to identify

opportunities for an ESPC. PDU: Power Distribution Unit - a device used in datacenters to distribute AC power to multiple servers and other

equipment. RFP: Request for Proposal - document sent by a potential buyer to potential vendors soliciting price quotes. RFQ: Request for Quote - document sent to potential vendors soliciting price quotes OR Request for Qualifications - used to indicate that the Owner is seeking qualifications from a design firm

(usually an architect or engineer). SPO: State Procurement Office - serves as the central authority on procurement statutes and rules for all

governmental bodies of the State. TBD: To be determined. UPS: Uninterruptible Power Supply - a device that provides battery backup when the electrical power fails or drops

to an unacceptable voltage level. VCT: Vinyl Composition Tile - A resilient floor covering which is composed of a binder (one or more resins, such as

vinyl chloride, compounded with suitable plasticizer and stabilizers) with fillers, and pigment.

Page 9: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

9

Arizona Department of Administration ADOA Security System Replacement

Assessment, Design and Construction Capitol Mall, Phoenix, AZ

Date Funded: 11/03/14 Senior Project Manager: Janet Collegio Project Manager: John Webster General Manager: Roger Berna Budget: $3,850,000.00 Budget Source: BR #615019-00 Index No: 21460 ($1,850,000) Capital Appropriation: Index No: 21950 ($2,000,000) Laws 2013, Chapter 8, 51st Leg. 1st Special Session Architect/Engineer: Arrington Watkins Architects, LLC Contractor: Sun Eagle Corporation Statewide Statutory Review Project #: CG-13-09

Completion Dates Construction Documents: 09/14 100 Percent Complete Notice to Proceed: 12/22/14 Substantial Completion: 10/18/15 30 Percent Complete Target Completion: 11/02/15 Project Description: A.R.S. 41-791 directs ADOA’s responsibility for security of its 73 buildings. ADOA’s current electronic command and control security system, which controls facility badge access and monitors alarms of a variety of types, is over 25-years old, obsolete, in chronic repair-mode, unsupported by current technology, and does not meet ADOA’s current needs. ADOA has procured the services of Construction-Manager-at-Risk (CMAR) that will serve as the general contractor throughout construction, and assume the risk of delivering the project through a fixed lump sum or Guaranteed Maximum Price (GMP) contract. This $3.85 million project will replace the existing access control system (“brain”); select and issue new access control cards; and integrate the new system with HRIS. The fundamental framework of the new card access system will facilitate future expansion of the system and integration of additional building components as funding becomes available.

Page 10: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

10

continued…. Project Status: Building walks with the Facilitator have been completed.

Meetings are being held weekly to coordinate the present data base into the new Lenel

data base.

Photographs of all active employees in the ADOA managed buildings have been taken in preparation for issuing new cards as the buildings are converted to the new access system.

The software and servers have been received and installed with construction of the new

data base underway.

The preliminary development phase is nearly finished and hard construction is expected to start June 22, 2015.

JCW 8410

Page 11: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

11

Corporation Commission / Attorney General 1200 / 1275 West Washington Phoenix, AZ

Central Plant Repair / Replacement Date Funded: 04/28/15 Project Manager: William Anderson Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $200,000 (Design)

Budget Source: BR615007-02 Index 21465 Architect/Engineer: LSW Engineers Arizona, Inc. Contractor: TBD Statewide Statutory Review Project # CG-15-11

Completion Dates Construction Documents: 10/16/15 0 Percent Complete Bid Date: 11/20/15 Notice to Proceed: 12/04/15 Substantial Completion: 03/25/16 0 Percent Complete Target Completion: 04/22/16 Project Description Provide Construction Administration and Project Management for the repair / replacement of the Central Plant and related equipment for the Corporation Commission and Attorney General buildings to allow for the reliable and efficient operation of the facilities. Project Status A proposal has been received from LSW Engineers and is under review. WFA 8430

Page 12: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

12

Arizona Department of Administration Executive Tower Service Entrance Section (SES) Replacement

1700 W. Washington, Phoenix, AZ Date Funded: 07/01/11 Project Manager: William Anderson Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $1,133,000 BR2013-22 Index 21440 $ 930,000 BR614009-00 Index 21450 Total funding: $2,063,000 Architect/Engineer: LSW Engineers Arizona, Inc. Contractor: Data Specialties Inc. Statewide Statutory Review Project # CG-12-11

Completion Dates Construction Documents: 01/15/13 100 Percent Complete Bid Date: 03/20/14 Notice to Proceed: 05/22/14 Substantial Completion: 12/16/14 99 Percent Complete Target Completion: 06/30/15 Project Description Replace the antiquated Electrical Service Entrance at the Executive Tower at 1700 W. Washington, Phoenix, AZ and install the new SES in a new above ground location that is less vulnerable to flooding. Project Status

The remaining Closeout Documents, the G706 and G706A are enroute. The SES monitoring equipment is being re-programmed to expand its reporting of the data

being monitored.

WFA 8633TI.19

Page 13: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

13

Arizona Department of Corrections HR Building New Fire Alarm Replacement System 1831 W. Jefferson, Phoenix, Arizona

Date Funded: 06/16/14 Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $75,000.00 Budget Source: BR 614001-05 Index No. 21465 Architect/Engineer: LSW Engineers Arizona, Inc. Contractor: JOC – The SJ Anderson Company (in conjunction with Firetrol Protection Systems) Statewide Statutory Review Project # CG-09-03(TI.9)

Completion Dates Construction Documents: 12/31/14 100 Percent Complete Bid Date: N/A Notice to Proceed: 03/19/15 Substantial Completion: 06/30/15 45 Percent Complete Target Completion: 06/30/15

Project Description Engineer is to design a new fire alarm replacement system and provide construction administration services for 1101 W. Washington; 1919 W. Jefferson and 1831 W. Jefferson. General Contractor (JOC) in conjunction with Firetrol Protection Systems, fire alarm contractor is to furnish and install a new fire alarm system in this building starting with 1101 W. Washington then 1919 W. Jefferson then 1831 W. Jefferson. Project Status

Wire has been pulled on the first floor and half way through the second floor.

The new remote annunciator has been installed on the west-side Lobby.

JC8709TI9.C

Page 14: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

14

Arizona Department of Administration 1300 W. Washington, Phoenix, AZ

Elevator Modernization Date Funded: 11/21/13 Project Manager: John Webster Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $500,000 Budget Source: BR 614008-02 Index 21450 Architect/Engineer: Sun Engineering/Vertical Transportation Excellence (VTX)

Contractor: Builders Guild, Inc. Statewide Statutory Review Project #: CG-13-29

Completion Dates Construction Documents: 05/19/14 100 Percent Complete Bid Date: 08/12/14 Notice to Proceed: 01/07/15 Substantial Completion: 10/26/15 20 Percent Complete Target Completion: 11/10/15 Project Description: Sun Engineering and their design team (VTX & CH Architects) provided an elevator modernization assessment that identified the components on the elevator system that needed to be upgraded or replaced. The assessment also provided a construction cost estimate for the project. The Sun Engineering team is responsible for re-designing the elevator with modern components so that the elevator will operate more efficiently and be more reliable. Sun Engineering and the design team are also responsible for providing bidding support and construction administration during the construction phase of the project. Project Status

Builders Guild started the preliminary construction process on January 7, 2015.

Shop drawings have been reviewed.

Hard construction is expected to start end of June.

JCW 8720B

Page 15: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

15

Arizona Department of Administration 2910 N. 44th Street, Phoenix, AZ

Elevator Modernization Date Funded: 03/18/15 Project Manager: John Webster Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $500,000 Budget Source: BR 615014-01 Index 21460 Architect/Engineer: Sun Engineering/Vertical Transportation Excellence (VTX)

Contractor: TBD Statewide Statutory Review Project #: CG-13-29

Completion Dates Construction Documents: 05/21/15 100 Percent Complete Bid Date: NA Notice to Proceed: TBD Substantial Completion: 01/31/16 0 Percent Complete Target Completion: 02/15/16 Project Description: Sun Engineering and their design team (VTX & CH Architects) provided an elevator modernization assessment that identified the components on the elevator system that needed to be upgraded or replaced. The assessment also provided a construction cost estimate for the project. The Sun Engineering team is responsible for re-designing the elevator with modern components so that the elevator will operate more efficiently and be more reliable. Sun Engineering and the design team are also responsible for providing construction administration during the construction phase of the project. Project Status The plans are 100% complete and are being quoted by the JOC contractor, SJ Anderson.

The quote is anticipated by June 5, 2015.

JCW 8720C

Page 16: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

16

Arizona Department of Corrections (ADC) ASPC Lewis – Potable Well #6

Buckeye, AZ Date Funded: 08/07/14 Project Manager: John Webster Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $2,000,000.00 Budget Source: Client Funded Index 20702 Architect/Engineer: Southwest Ground-water Consultants, Inc.

Contractor: TBD Statewide Statutory Review Project #: CG 14-23

Completion Dates Construction Documents: 02/13/15 100 Percent Complete Phase 1: Bid Date: 05/27/15 Notice to Proceed: TBD Substantial Completion: 10/15/15 0 Percent Complete Target Completion: 10/30/15 Phase 2: Project Description: The project is to drill a new potable well for the Lewis Prison Complex. It will be the main well for the prison. Well 3 and Well 4 will be backup wells when Well 6 requires maintenance. Project Status

Bid documents were advertised on 04/16/15, pre-bid site tour was 05/07/15 and bid date

was 05/27/15. Two bids were received and are presently being reviewed for award.

The project will start with a pilot hole down to 1200 feet that will be extensively tested for water quality. When approved for development, the pilot hole will be drilled out larger for installation of the well casing.

The second phase will start after completion of the well casing which will be the installation of well gear and electrical equipment.

The two phases will be bid separately. JCW 5507

Page 17: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

17

Arizona Department of Health Services (ADHS) Arizona State Hospital – Chiller Replacements

2500 East Van Buren Street, Phoenix AZ Date Funded: 09/11/14 Project Manager: Roger Berna General Manager: Roger Berna Budget: $114,107 (Design)1

$1,000,000 (Construction)2

Budget Source: BR 615012-02 Index No. 214601

BR 615018-00 Index No. 214602 Architect/Engineer: Bridgers and Paxton Consulting Engineers, Inc. Contractor: JOC - Johnson Controls Statewide Statutory Review Project # CG 14-17 Completion Dates Construction Documents: 01/31/15 100 Percent Complete Bid Date: N/A Notice to Proceed: 04/06/15 Substantial Completion: 06/30/15 80 Percent Complete Target Completion: 06/30/15 Project Description Scope has been revised for the replacement of one 700 ton chiller, chilled water pumps and all associated piping, valves and accessories, including upgrades to the energy management system (EMS) and controls. Project Status

Johnson Controls (JCI) has installed the condenser water pipe supports. The chilled water

piping is on-going and the new primary pump is set. The new chiller was installed on May 28th.

JCI is providing two 400 ton air cooled rental chillers to provide uninterrupted cooling for the

campus during construction of the condenser water piping. The rental chillers will be installed the week of June 1st and remain in place for the month.

Controls work by JCI is on-going. Software for the new EMS system will be installed on a

server provided by DHS.

The Engineer is preparing plans for the installation of an additional exit door for code required exit separation.

All work is on schedule and within budget. RB 8336

Page 18: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

18

Arizona Department of Juvenile Corrections (ADJC) Adobe Mountain Schools, Phoenix, AZ

ADJC Fire Fighting Water Distribution System Date Funded: 08/09/13 Senior Project Manager: Armando Milheiro General Manager: Roger Berna Budget: $1,387,765.48 Budget Source: BR 614003-00 Index 21450 $1,198,189.68 BR 615003-00 Index 21465 $ 189,575.80 Architect/Engineer: David Evans & Associates (DEA)

Contractor: Redpoint Contracting Statewide Statutory Review Project #: CG-13-16 Completion Dates Construction Documents: 05/15/14 100 Percent Complete Bid Date: 08/20/14 Notice to Proceed: 09/15/14 Substantial Completion: 09/30/15 90 Percent Complete Target Completion: 10/30/15 Project Description: Design, replace and relocate existing fire hydrants as well as upgrade firefighting waterlines to meet code. In addition, design and construct fire lanes campus wide. Project Status

Redpoint began construction on the expansion of fire lines and hydrants in the areas

designated section #5 located in the heart of the Adobe Mountain facility.

Redpoint is still encountering a great number of unknown subsurface utilities. There have been a few damages, but were unavoidable as there were no accurate as-builts and the locator did not find many of the utilities on site.

Redpoint has begun work on the fire lane around the entire Adobe Mt. Campus. AJM 4045

Page 19: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

19

Arizona Department of Juvenile Corrections (ADJC) Adobe Mountain Schools, Phoenix, AZ ADJC New Access Controls and Locks

Date Funded: 08/09/13 Senior Project Manager: Armando Milheiro General Manager: Roger Berna Budget: $ 219,389.04 Budget Source: BR 615003-00 Index 21465 Architect/Engineer: David Evans & Associates (DEA)

Contractor: TBD Statewide Statutory Review Project #: CG-13-16 Completion Dates Construction Documents: 07/10/15 70 Percent Complete Bid Date: 07/31/15 Notice to Proceed: 08/14/15 Substantial Completion: 10/23/15 0 Percent Complete Target Completion: 11/23/15 Project Description: Design new control panels that will interface correctly with replacement locks for the existing cells. Purchase of the replacement locks will be under this project, and ADJC will install the locks. Project Status

Working with David Evans & Associates to finalize design this month.

AJM 4045TI.1

Page 20: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

20

Arizona Department of Juvenile Corrections (ADJC) Adobe Mountain Schools, Phoenix, AZ ADJC Replace Plumbing Chase Piping

Date Funded: 10/24/13 Senior Project Manager: Armando Milheiro General Manager: Roger Berna Budget: $424,468.15 Budget Source: BR 614010-00 Index 21450 Architect/Engineer: Energy Systems Design (ESD)

Contractor: JOC – The SJ Anderson Company Statewide Statutory Review Project #: CG-13-20 Completion Dates Construction Documents: 07/09/14 100 Percent Complete Bid Date: 04/09/15 Notice to Proceed: 04/08/15 Substantial Completion: 04/31/16 10 Percent Complete Target Completion: 05/31/16 Project Description: Design, remove and replace existing plumbing chase in six (6) buildings. This project will consist of working on one (1) building at a time to minimize disturbance on the ADJC campus. Project Status

S. J. Anderson Company started work on the Vision Building 05/25/15 with the demolition

of the existing piping in the Vision Building.

Work activity is contained within the building and secured.

Piping contractor on site starting 06/01/15 to begin their scope and should be complete by 06/08/15.

AJM 4046

Page 21: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

21

Arizona Department of Juvenile Corrections (ADJC) Adobe Mountain Schools, Phoenix, AZ

ADJC Fire Suppression System Date Funded: 07/17/14 Senior Project Manager: Armando Milheiro General Manager: Roger Berna Budget: $ 413,812.42 Budget Source: BR 615003-00 Index 21465 Architect/Engineer: Energy Systems Design (ESD)

Contractor: JOC – The SJ Anderson Company Statewide Statutory Review Project #: CG-13-20 Completion Dates Construction Documents: 07/09/14 100 Percent Complete Bid Date: 04/09/15 Notice to Proceed: 04/29/15 Substantial Completion: 04/31/16 10 Percent Complete Target Completion: 05/31/16 Project Description: Design and install new fire sprinkler system in six (6) buildings on the ADJC campus. This project will be completed in tandem with the Chilled Water Piping system project. Project Status

S. J. Anderson Company started work on the Vision building 05/25/15 with the demolition

of the existing piping in the Vision Building.

Work activity is contained within the building and secured.

Piping contractor on site starting 06/01/15 to begin their scope.

Sprinkler Contractor scope, this phase, should be complete by 06/12/15. AJM 4046TI.1

Page 22: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

22

Arizona Department of Juvenile Corrections (ADJC) Adobe Mountain Schools, Phoenix, AZ

ADJC Fan Coil Unit Replacement Date Funded: 07/17/14 Senior Project Manager: Armando Milheiro General Manager: Roger Berna Budget: $67,897.05 Budget Source: Transfer from ADJC Index 20706 Architect/Engineer: Energy Systems Design (ESD)

Contractor: JOC – The SJ Anderson Company Statewide Statutory Review Project #: CG-13-20 Completion Dates Construction Documents: 07/09/14 100 Percent Complete Bid Date: 04/09/15 Notice to Proceed: 04/28/15 Substantial Completion: 04/31/16 75 Percent Complete Target Completion: 05/31/16 Project Description: Design and specification of four (4) fan coils to be placed in the Vision Building at Adobe Mountain Campus. Project Status

All (4) fan coils have been received and installed.

Inspection of fan coils will be week of June 15, 2015.

AJM 4046TI.2

Page 23: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

23

Arizona Department of Public Safety Southern Region Office, 6401 S. Tucson, Blvd., Tucson, AZ

Fire Alarm System Replacement Date Funded: 11/18/14 Project Manager: William Anderson Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $30,000 Design only Budget Source: BR614014-02 Index: 21450 Budget: $195,000 Construction Index: 21460 Budget Source: BR614015-00 Architect/Engineer: LSW Arizona Engineers, Inc. Contractor: JOC – Centennial CE, Inc. Statewide Statutory Review Project # CG 14-09

Completion Dates Construction Documents: 09/15/14 100 Percent Complete Bid Date: N/A Notice to Proceed: 01/05/15 Substantial Completion: 03/30/15 99 Percent Complete Target Completion: 06/30/15 Project Description Provide Construction Administration and Project Management to Replace the Fire Alarm System. Project Status Installation of the new Fire Alarm is complete. Assembling Closeout Documents WFA 9505

Page 24: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

24

Arizona Department of Transportation (ADOT) 2015 – 2016 Building Renewal Projects

Date Assigned: Throughout Project Manager: Alvin Spencer Senior Project Manager: Mike Rank General Manager: Roger Berna Budget Source: Purchasing and Payments by ADOT Statewide Statutory Review Project #: See Individual ADOT Projects

Completion Dates Notice to Proceed: Various Dates Substantial Completion: Various Dates Target Completion: Various Dates Project Description ADOT provides Architectural/Engineering (A/E) services; ADOA provides Construction Administration (CA) and Project Management (PM) services for the ADOT projects listed below. Projects

Facilities Equipment Shop 2080, Globe, AZ – Replace HVAC system.

Status: This project will commence spring 2015.

Port of Entry W/B I-8 2017, Yuma, AZ – Replace failing a/c unit. Status: This project will commence spring 2015.

9651 N 99 Ave. West Valley Construction Office Bldg. 1631, Peoria, AZ – Roof and parapet

wall repairs. Status: This project is complete.

200 N ADOT Ln Winslow MVD, Winslow, AZ – Replace windows.

Status: The window installation is scheduled to start 06/10/2015. Facilities Maintenance & Support, Bldg 1762, Phoenix, AZ – Repair existing roof with

application of insulation board and single ply roof system. Status: This project is complete.

7130 W Fairfield, Bldg 1521, Chandler, AZ – Repair and recoat existing roof with white

elastomeric coating. Status: This project is complete.

Various Sites, Central District, Maricopa County, AZ – Review existing roofs and assist

ADOT to establish a priority list for repair and maintenance. Status: The site review and evaluation is complete.

Page 25: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

25

continued…. Grey Peak Residence 2144, Greenlee County, AZ – Replace windows.

Status: A purchase order for this work is will be issued.

Globe Maintenance Office, Globe, AZ – Replace existing HVAC Units and roofing. Status: This project is complete.

Tucson Regional MVD, Tucson, AZ – Repaint building exterior. Status: A contract has been awarded.

Tucson East MVD, Tucson, AZ – Repaint building interior and exterior. Status: A contract has been awarded.

Grey Peak Maintenance Yard, Greenlee County, AZ – Repaint the exterior of all buildings.

Status: A contract has been awarded.

Globe Equipment Storage, Globe, AZ – Repaint the building exterior. Status: A contract has been awarded.

Grey Peak Modular Residence, Greenlee County, AZ – Replace existing windows with energy

efficient windows. Status: Window design is under review.

Safford District Office, Safford, AZ – Repaint the exterior of all site buildings.

Status: A contract has been awarded. Payson Equipment Shop, Payson, AZ – Replace failed building siding with new panels.

Status: The replacement panels have been ordered.

AS-ADOT

Page 26: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

26

Arizona Department of Veterans’ Services Arizona Veterans’ Memorial Cemetery at Camp Navajo

14317 Veterans Way, Bellemont, AZ 86015 Date Funded: 03/14 Project Manager: Jeff Pugh Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $7,450,000 Budget Source: U S Department of Veterans Affairs Cemetery Grants

Administration Architect/Engineer: David Evans & Associates and Orcutt Winslow

Contractor: SDB Contractors, Inc. Statewide Statutory Review Project #: VS-12-01 Completion Dates Construction Documents: 100 Percent Complete Bid Date: 06/27/14 Notice to Proceed: 07/14/14 Substantial Completion: 12/20/15 65 Percent Complete Target Completion: 12/20/15 Project Description: Design and construction of Northern Arizona Veterans Memorial Cemetery roadways, family assembly area and committal shelter, 1994 square foot maintenance facility, 1270 gross square foot visitor and administration center. The project provides a variety of burial options for the local veterans including in-ground casket burials, columbaria walls, in-ground cremain burials, and a scatter garden with memorial walls. The site is planned to maximize interment for as many years as possible with each phase supporting approximately 10 years of service. The first phase of development includes the following interment types and quantities: 274 In-Ground Double Depth Pre-Placed Crypts; 222 in-ground cremain; 220 Columbaria Niches and Memorial Wall Markers. Project Status

SDB Contractors, Inc. work was limited during the month of May due to inclement weather.

Masonry block work on the Maintenance Building, Committal Shelter and Visitors’ Center

is complete.

All structural steel has been erected.

Page 27: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

27

continued….

Roof decking has been completed on Maintenance and Storage Center (MSC), Committal

Shelter (CS) and Visitor/Administrative Center (VAC). All roads are cut in and aggregate base has been installed and prepared for asphalt.

However, due to inclement weather, the aggregate base will need to be reworked, compacted and tested prior to asphalt installation.

Concrete slab at CS facility is complete.

Concrete masonry entry wall is complete.

Site underground electrical is complete.

Maintenance and Storage Center waterproofing has been completed.

Visitor Center light gauge framing installation is ongoing and HVAC and electrical

installation is about 45% complete.

Plumbing at MCS and VAC buildings rough-in is ongoing.

Columbaria footing installation has begun and ongoing. Landscaping and irrigation waterline installation is a work in progress

Light gauge roof framing on VAC and CS complete.

.

JP 9009

Page 28: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

28

Arizona Department of Veterans’ Services Arizona Veterans’ Memorial Cemetery @ Marana

Marana, AZ Date Funded: 10/2013 Project Manager: Jeff Pugh Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $7,800,000 Budget Source: U S Department of Veterans Affairs Cemetery Grants

Administration Architect/Engineer: David Evans & Associates

Contractor: SDB Contractors, Inc. Statewide Statutory Review Project #: VS-14-01 Completion Dates Construction Documents: 100 Percent Complete Bid Date: 07/25/14 Notice to Proceed: 09/22/14 Substantial Completion: 09/09/15 68 Percent Complete Target Completion: 09/09/15 Project Description: Design and construction of Arizona Veterans’ Memorial Cemetery at Marana roadways, 1016 square foot family assembly area and committal shelter, 2,282 square foot maintenance facility, 1,788 gross square foot visitor and administration center. The project provides a variety of burial options for the local veterans including in-ground casket burials, columbaria walls, in-ground cremain burials, and a scatter garden with memorial walls. The site is planned to maximize interment for as many years as possible with each phase supporting approximately 10 years of service. The first phase of development includes the following interment types and quantities: 1,802 3’x 8’ In-Ground Double Depth Pre-Placed Crypts; 1,638 3’x4’ in-ground cremain; 1,920 Columbaria Niches and Memorial Wall Markers. Project Status The water well is drilled and capped. The Contractor is waiting on delivery of well pump.

Underground electrical and plumbing at the Committal Shelter, Visitor Center and

Maintenance Buildings are complete.

Page 29: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

29

continued….

Maintenance Building (MCS) and the Committal Shelter (CS) have complete steel packages installed and are currently being roofed with light gauge steel. Steel package on the Visitors/Administrative Center (VAC) is ongoing.

The MCS has its roll up doors installed, interior framing complete, mezzanine is complete.

HVAC and electrical installation is 50% complete on the interior of the MSC. At the VAC, 40% of the light gauge framing complete and HVAC and electrical installation is 30%complete.

Masonry construction for the Committal Shelter, Maintenance Building and the Visitors’

Center Buildings are complete.

1800 pre-cast crypts have been delivered, installed, tested and backfilled. This area is currently barricaded off to keep all traffic off.

1920 columbarium’s have been installed, leveled and fastened in their final location. The

Memorial Wall has been erected and the assembly area wall has been completed. Stairs at the assembly area have been installed and complete.

Roadway and parking area curb and gutter are currently being installed. Curbing at the

MSC has been installed in preparation for concrete parking lot pours. Curbing at entrance and all roadways are currently being installed. Irrigation sleeves have been placed under roadways.

ADVS, Tucson Electric Power (TEP), adjacent private land Owners and the Cantero Water

District have reached an agreement on the routing of the electrical utilities to the cemetery site. Trenching for electrical lines has been delayed until July.

JP 9011

Page 30: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

30

Arizona Historical Society Museum - Tempe Museum Fire Alarm Replacement System and a Pre-action System

Phoenix, Arizona

Date Funded: 05/28/14 Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $462,240.00 Budget Source: BR 614014-04 Index No. 21450 $ 30,000.00 BR 615001-01 Index No. 21465 $432,240.00 Architect/Engineer: LSW Engineers Arizona, Inc. Contractor: JOC – The SJ Anderson Company (in conjunction with Firetrol Protection Systems) Statewide Statutory Review Project # CG-14-21

Completion Dates Construction Documents: 11/05/14 100 Percent Complete Bid Date: N/A New Fire Alarm 04/30/15 Notice to Proceed: 01/07/15 Substantial Completion: 08/07/15 90 Percent Complete New Pre-action System Notice to Proceed: 04/30/15 Substantial Completion: 08/07/15 90 Percent Complete Target Completion: 06/30/16

Project Description Engineer is to design a new fire alarm replacement system and provide construction administration services for a new fire alarm replacement system and a new pre-action system for the Arizona Historical Society Tempe Museum Building Project Status

New Fire Alarm System

Building is currently under fire watch due to existing fire alarm failure and will remain that way until the new fire alarm replacement system is activated and inspected by the State Fire Marshal.

The Fire Alarm control Panel-1 is installed behind the Reception Desk.

Electrical work is still progressing above the new Main Fire Alarm Control Panel in Security Room 144.

All devices have been installed and all drywall patches have been completed in various locations.

Page 31: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

31

continued…. Pre-Action System

The repairs to the existing pre-action are nearing completion.

Once the new alarm system is activated, it will monitor the repaired pre-action system.

JC8647TI.2

Page 32: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

32

Arizona State Schools for the Deaf and Blind New Fire Alarm Replacement System

Maricopa Dormitory Tucson, Arizona

Date Funded: 02/09/15 Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $500,000 Budget Source: BR 615002-00 Index No. 21465 $13,375.85 BR 614002-00 Index No. 21450 $49,853.86 Architect/Engineer: LSW Engineers Arizona, Inc. Contractor: Firetrol Protection Systems Statewide Statutory Review Project # CG-11-03(TI.5)

Completion Dates Construction Documents: 02/11/14 100 Percent Complete Bid Date: N/A Notice to Proceed: 03/19/15 Substantial Completion: 10/10/15 0 Percent Complete Target Completion: 06/30/16

Project Description Engineer is to design a new fire alarm replacement system, underground wire and cable and construction administration services Project Status

Maricopa Dormitory is scheduled for a new fire alarm replacement system to be installed

after the Palo Verde Dorm has been completed. JC8954TI.5A

Page 33: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

33

Arizona State Schools for the Deaf and Blind New Fire Alarm Replacement System

Palo Verde Dormitory Tucson, Arizona

Date Funded: 02/09/15 Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $500,000 Budget Source: BR 615002-00 Index No. 21465 $143,801.84 Architect/Engineer: LSW Engineers Arizona, Inc. Contractor: Firetrol Protection Systems Statewide Statutory Review Project # CG-11-03(TI.5)

Completion Dates Construction Documents: 02/11/14 100 Percent Complete Bid Date: N/A Underground Cable / Wire Notice to Proceed: 03/19/15 Substantial Completion: 10/10/15 50 Percent Complete Palo Verde Dormitory Notice to Proceed: 03/19/15 Substantial Completion: 10/10/15 02 Percent Complete Target Completion: 06/30/16

Project Description Engineer is to design a new fire alarm replacement system, underground wire and cable and construction administration services Project Status

Palo Verde Dormitory

Building is currently under fire watch because the fire alarm control panel caught fire and rendered the fire panel inoperable.

Underground Cable / Wire

Firetrol has hired a boring company to do the underground wiring and cable raceways that will connect the buildings to the network Head End located in the Food Service Building.

The boring company is 50% complete

JC8954TI.5B

Page 34: Arizona Department of Health Services (ADHS) Arizona State ... 2015... · Arizona Department of Health Services (ADHS) Arizona State Hospital (ASH) Chiller Replacement Phoenix, AZ

34

Arizona State Tucson Office Complex 400, 402, 416 W. Congress, Tucson, AZ

EMS Upgrades Date Funded: 6/24/13 Project Manager: William Anderson Senior Project Manager: Janet Collegio General Manager: Roger Berna Budget: $703,395.911

$385,640.002

Budget Source: BR1300101 Index 21440 BR614013-062 Index 21450 Architect/Engineer: NA Contractor: Climatec Statewide Statutory Review Project # CG-14-03

Completion Dates Construction Documents: NA 100 Percent Complete Bid Date: NA Notice to Proceed: 04/15/14 Substantial Completion: 04/30/15 99 Percent Complete Target Completion: 06/30/15 Project Description Provide Construction Administration and Project Management for the upgrade of the Energy Management System (EMS) for the Tucson Complex Buildings to allow the mechanical infrastructure to be monitored and operated from the FOAM (Facilities Operations and Maintenance) HVAC Command Center in Phoenix. Project Status Climatec has completed the Punch List. The Submittals need to be updated to match the actual installation. The Close Out documents are being prepared

WFA 8630TI.15