2
Project update Ausgrid has finalised its plans to lay a new 132,000 volt underground cable between our substation in Campbell Street, Artarmon and our substation in Harbour Street, Mosman. Our contractors Taihan and Garde will soon start work. As outlined in our previous newsletters, Ausgrid’s Mosman substation is currently supplied by three 132,000 volt cables, one from the Willoughby substation in Artarmon and two from the Castle Cove substation in Chatswood. These cables are more than 45 years old and need to be replaced to maintain a safe and reliable power supply to customers. Pre-construction activities will start in early-mid November 2018. Trenching to install the new cables in roads will start in mid-January 2019 and work will continue for about 12 months. A map of the cable route is on the back page. There have been no changes in the route since our last newsletter. The project will also involve underbores of the Warringah Freeway, a section within the Cammeray golf course and under the cliff between Reynolds Street and Prospect Avenue, Cremorne. Information about what to expect during construction is over the page. Project assessment and approval Ausgrid is the approving authority for the work under the NSW Environmental Planning & Assessment Act. As part of the approval process, Ausgrid conducted an environmental assessment, known as a Review of Environmental Factors (REF), to investigate the potential environmental impacts associated with the project. The project is now approved for construction and the final REF is available on the project web page. Community feedback Ausgrid has taken feedback received from the community and key stakeholders into consideration in finalising the project. Thank you to everyone who provided feedback, including most recently on the REF, which was on public exhibition from 7 September to 28 September 2018. We received a total of ten submissions during the REF exhibition period. The main areas of community interest were route selection, electric and magnetic fields and construction impacts. All submissions were considered and addressed in the final REF. A report summarising all the feedback received from the community and key stakeholders during the REF exhibition period is now available on the project web page. Community Newsletter 3 – November 2018 Artarmon to Mosman cable project A similar cable project in progress Key dates Late 2017 – early 2018 Investigating route options and obtaining early feedback from key stakeholders. Mid 2018 Site investigations, REF prepared and displayed for public comment. Early – mid 2020 Target project completion. Mid Nov 2018 – mid Jan 2019 Further site investigations, start of construction. Late October 2018 Project approved for construction, contractor engaged and program prepared. Late 2019 – early 2020 Finish installing new cables in streets, start retiring existing cables. Early 2018 – Aug 2018 Obtaining feedback from community on the preferred cable route to inform project. Contacting us You are welcome to contact us with any enquiries: Call 1800 604 765 (free call from fixed phones) Email [email protected] Visit ausgrid.com.au/artarmontomosman Interpreter service 131 450 Environmental and health standards Ausgrid plans its infrastructure in line with relevant environmental and health standards for the protection of both the environment and the community. This includes designing and operating all new equipment to minimise electric and magnetic fields, minimising tree trimming and removal and managing issues such as dust, noise and vibration during construction, where reasonably practical to do so. The final REF has more details on how these impacts have been assessed. Working with you We are committed to working closely with the community to minimise disruption as much as possible. Your questions and comments about the project are welcome at any time to help us and our contractor manage the construction work effectively. Work will be done progressively along the route, which means it may be some time before we begin in your area. You will receive a letter approximately one week before work begins near you, including information about how you might be impacted. We apologise in advance for any inconvenience caused by this project and we thank you for your understanding and patience. Map of Artarmon to Mosman cable project W a rringa h Fre e w ay Warringah Freeway Mi li tary R d Military Rd Milita r y R d Miller St Cha n d o s S t C ha ndo s S t Alexander St O u rim ba h R d Christie St Willoughby Rd W illou ghby Rd West St Cowles Rd Cowles Rd Herbert St Herbert S t Campbell St Cl arendon St Cleg St Westbo u r ne St Atchison St A t c h i son St Oxley St Mitchell St Dev o n shir e S t Bells Ave Amherst St Camm er a y R d Par k Av e Sutherlan d St Ben Boyd Ln Young Ln Young St Cooper Ln Waters Ln B e n e l o n g R d Ger a rd Ln Ada St P r inc e S t Harbour St Wunda Rd A r t G alle ry Way Vista St Er i t h S t G l ov e r S t Macpherson St H u ntington St Alb a ny Ln A t ch is on L n Henry Ln Matthew St Falcon St Erne st St Warri nga Rd Bellvue St H o lte r mann St Frederi ck St Gerard St M e l r os e St B e l mon t R d Bardwell Rd Hale Rd Waters Rd Mor d e n S t Pacific Highway Ben Boyd Rd R o s a lin d S t St Leonards Crows Nest Cammeray Cremorne Cammeray Golf Course St Leonards Park Mosman Naremburn Artarmon Royal North Shore Hospital Grasmere Ln Grasmere Rd Prosp e ct Av Reynolds St St Leonards Station Wollstonecraft Station Legend Substation Cable route (trenching) Existing ducts beneath railway Underbore Mosman substation Willoughby substation

Artarmon to Mosman cable project - Ausgrid · Mosman. Our contractors Taihan and Garde will soon start work. As outlined in our previous newsletters, Ausgrid’s Mosman substation

  • Upload
    others

  • View
    12

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Artarmon to Mosman cable project - Ausgrid · Mosman. Our contractors Taihan and Garde will soon start work. As outlined in our previous newsletters, Ausgrid’s Mosman substation

Project updateAusgrid has finalised its plans to lay a new 132,000 volt underground cable between our substation in Campbell Street, Artarmon and our substation in Harbour Street, Mosman. Our contractors Taihan and Garde will soon start work.

As outlined in our previous newsletters, Ausgrid’s Mosman substation is currently supplied by three 132,000 volt cables, one from the Willoughby substation in Artarmon and two from the Castle Cove substation in Chatswood.

These cables are more than 45 years old and need to be replaced to maintain a safe and reliable power supply to customers.

Pre-construction activities will start in early-mid November 2018. Trenching to install the new cables in roads will start in mid-January 2019 and work will continue for about 12 months.

A map of the cable route is on the back page. There have been no changes in the route since our last newsletter.

The project will also involve underbores of the Warringah Freeway, a section within the Cammeray golf course and under the cliff between Reynolds Street and Prospect Avenue, Cremorne.

Information about what to expect during construction is over the page.

Project assessment and approvalAusgrid is the approving authority for the work under the NSW Environmental Planning & Assessment Act.

As part of the approval process, Ausgrid conducted an environmental assessment, known as a Review of Environmental Factors (REF), to investigate the potential environmental impacts associated with the project.

The project is now approved for construction and the final REF is available on the project web page.

Community feedbackAusgrid has taken feedback received from the community and key stakeholders into consideration in finalising the project.

Thank you to everyone who provided feedback, including most recently on the REF, which was on public exhibition from 7 September to 28 September 2018.

We received a total of ten submissions during the REF exhibition period. The main areas of community interest were route selection, electric and magnetic fields and construction impacts.

All submissions were considered and addressed in the final REF. A report summarising all the feedback received from the community and key stakeholders during the REF exhibition period is now available on the project web page.

Community Newsletter 3 – November 2018

Artarmon to Mosman cable project

A similar cable project in progress

Key dates

Late 2017 – early 2018

Investigating route options and obtaining early feedback from key stakeholders.

Mid 2018

Site investigations, REF prepared and displayed for public comment.

Early – mid 2020

Target project completion.

Mid Nov 2018 – mid Jan 2019

Further site investigations, start of construction.

Late October 2018

Project approved for construction, contractor engaged and program prepared.

Late 2019 – early 2020

Finish installing new cables in streets, start retiring existing cables.

Early 2018 – Aug 2018

Obtaining feedback from community on the preferred cable route to inform project.

Contacting usYou are welcome to contact us with any enquiries:

Call 1800 604 765 (free call from fixed phones) Email [email protected] ausgrid.com.au/artarmontomosman

Interpreter service 131 450

Environmental and health standards

Ausgrid plans its infrastructure in line with relevant environmental and health standards for the protection of both the environment and the community.

This includes designing and operating all new equipment to minimise electric and magnetic fields, minimising tree trimming and removal and managing issues such as dust, noise and vibration during construction, where reasonably practical to do so. The final REF has more details on how these impacts have been assessed.

Working with youWe are committed to working closely with the community to minimise disruption as much as possible.

Your questions and comments about the project are welcome at any time to help us and our contractor manage the construction work effectively.

Work will be done progressively along the route, which means it may be some time before we begin in your area. You will receive a letter approximately one week before work begins near you, including information about how you might be impacted.

We apologise in advance for any inconvenience caused by this project and we thank you for your understanding and patience.

Map of Artarmon to Mosman cable project

Warringah Freeway

Warringah Freeway

Military Rd M

ilitary Rd

Military Rd

Miller St

Chandos S

t Chandos St

Alexander St

Ourim

bah Rd

Christie St

Willoughby Rd Willoughby Rd

West St

Cowles Rd Cowles Rd

Herbert St

Herbert St

C

ampbell St

Clarendon St

Cleg

StWestbourne St

Atchison S

t Atchison St

Oxley St

Mitchell St

Devonshire St

Bells Ave

Am

herst StC

amm

eray Rd

Park Ave

Sutherland St

Ben Boyd Ln Young Ln

Young St Cooper Ln

Waters Ln Benelong R

d

Gerard Ln

Ada St

Prince St

Harbour StWunda Rd

Art G

allery Way

Vista St

Erith St

Glover S

t

Macpherson St

Huntington St

Albany Ln

Atchison Ln

Henry Ln

Matthew St

Falcon St

Ernest St

Warringa Rd

Bellvue St

Holterm

ann St

Frederick St

Gerard St

Melrose St

Belm

ont Rd

Bardwell Rd

Hale Rd

Waters Rd

Morden S

t

Pacific Highway

Ben Boyd Rd

Rosalind S

t

St Leonards

Crows Nest

Cammeray

Cremorne

CammerayGolf Course

St LeonardsPark

Mosman

Naremburn

Artarmon

Royal North Shore Hospital

Grasm

ere LnG

rasmere R

d

Prospect Av

Reynolds St

St LeonardsStation

WollstonecraftStation

Legend

Substation

Cable route (trenching)

Existing ducts beneath railway

Underbore

Mosman substation

Willoughby substation

Page 2: Artarmon to Mosman cable project - Ausgrid · Mosman. Our contractors Taihan and Garde will soon start work. As outlined in our previous newsletters, Ausgrid’s Mosman substation

What to expect during constructionBelow is a summary of the types of activities you can expect to see during construction.

Site investigations

Our contractors will undertake site investigations along the cable route before trenching starts to assess ground conditions and locate existing underground utility services. This will help confirm the final position of the new cables and conduits in the road and the location of associated pits.

Trenching and laying conduits (plastic pipes)

The most common activity will be digging 1.3 metre wide trenches in roads and laying conduits to house the new cables. There will be a number of crews doing this work progressively at multiple locations. This will start once site investigations have finished.

Typically, trenching and temporary restoration takes about a few days outside each property, depending on the ground and weather conditions.

Joint bays and other associated pits

Underground joint bays will be excavated approximately every 600 metres to 900 metres along the route. These will be used to pull through and join sections of cable together.

Each joint bay will be about 3 metres wide and 10 metres long and will be in place for 2-4 months.

There will also be smaller pits associated with controlling and monitoring the cables, and to assist with cable installation. Some of these pits would be located in the nature reserve next to the road.

The project team will discuss the location of the joint bays and pits with surrounding neighbours after the contractor has prepared their construction plans.

Installing cables

Once the joint bays and pits have been built, we will lay the new cables. This will involve transporting the cables to the joint bay and pit locations on large cable drums and pulling them into the conduits.

Underbore

As part of the project, we will need to underbore (using a horizontal directional drill) from Rosalind Street, Crows Nest to Morden Street, Cammeray, a section within Cammeray Golf Club and under a cliff between eastern Reynolds Street and western Prospect Avenue, Cremorne.

Access will be maintained at all times, unless we make arrangements with you in advance.

Work hours

Work hours are 7 am to 6 pm Mondays to Fridays, and 8 am to 1 pm on Saturdays.

To avoid traffic disruptions during the day, night works will be undertaken on Reserve Road and Herbert Street, Mosman; sections of Chandos Street and Oxley Street, St Leonards; Macpherson Street and Military Road, Mosman.

Nearby properties will be notified when work is planned outside normal hours and why different hours are required.

Restoring impacted areas

Typically, restoration is done in two stages:

• Excavated sections of road are filled and resurfaced straight away to allow normal use by traffic.

• Permanent resurfacing of the affected areas is done later once all cables are installed and tested.

Your power supply

Ausgrid does not plan to interrupt your power supply to complete the construction work. We will let you know in advance if this changes.

Managing impacts

As with any construction work, there will be some temporary impacts for residents and businesses on or near the cable route. This may include noise, traffic and parking disruptions. We will make every effort to keep these impacts to a minimum.

Our contractors will use traffic management crews to guide drivers, pedestrians and cyclists safely around the work areas.

Sections of the parking lane will need to be closed in streets where the crews are working, but these will be opened up again as they move along the street.

Access to properties, including driveways will generally be maintained, unless we make alternative arrangements with you in advance.

STOP

SLOW

SLOW

STOP

SLOW

SLOW

Jointbay

Jointbay

Trench

Road

Plasticconduits

3m wide

12m long

Typically 600 – 900 metres between joint bays

but only 30 metres are dug up at any one time

2.5mdeep

1.3m

Joint bays are600–900m apart

JOINT BAY

JOINT BAY DURINGCABLE INSTALLATION

COVEREDJOINT BAYDURING

JOINTING WORK

SEALEDJOINT BAY

TRENCH

RESURFACEDROAD

Not to scale

Construction stages

2–4 weeksTime it takes to complete work outside most properties.

Cable installation

• The 132,000 volt cables are pulled through the pipes and connected at the joint bays.

• At a later date, cable drums will be set up at joint bay locations.

• Underground joint bays will be constructed every 600–900m along the route.

• Between construction of the joint bay and connection of the cables, joint bays are either backfilled temporarily, barricaded or enclosed. Once cables are connected, the section of road is resurfaced.

• The joint bays are used to connect the cable sections.

2–4 monthsOverall time it takes to work at each joint bay location.

Underground joint bays• Trenching can occur on more than one site on a project simultaneously.

• The section of the road would then be permanently reinstated at the end of the project, in consultation with the Council.

• Plastic conduits (pipes) will then be placed in the trenches and then the area is backfilled with a special kind of concrete.

1–3 daysTime it takes to complete work outside most properties.

Trenching and conduit installation

The projectUNDERGROUNDJOINT BAY

The new cables will mainly be installed under thesurface of local roads along the route.

The proposed route aims to minimise impact on the community by avoiding major roads where possible and essential services such as existing underground electricity cables, water and sewerage pipes and gas mains.

Sealed trench through park.Work occurs quicker in parkland areas. Once construction is finished, the park is restored to its original state.

Trenches are backfilled and the a�ected section of roadway will be permanently resurfaced.

132,000 volt cables are drawn through conduits and connected at joint bays.

Truck removing spoil from excavation site.

Open trench showing plastic conduits.

Trench excavationOnce the plastic conduits are placed in the trench, the trenches are filled with a special kind of concrete with high thermal conductivity.

Road is resurfaced.

Tra�c controllers work to maintain tra�c flow and safety around the construction site.

Underground 132,000 volt cable installation

• Cable connection takes one to two weeks.

Underground 132,000 volt cable installation