Augusta County Public Schools Ten-Year Capital Facilities Plan 2015-2025

Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

Embed Size (px)

Citation preview

Page 1: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

A-1

Augusta County School Board

2015-2025

Augusta County Public Schools Ten-Year Capital Facilities Plan

2015-2025

Page 2: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

TEN-YEAR CAPITAL FACILITIES PLAN

2015 – 2025

Augusta County Public Schools School Board Members

Nicholas T. Collins Elizabeth P. Godfrey Dr. John L. Ocheltree

Timothy R. Quillen Dana M. Sensabaugh

David R. Shiflett Tim Z. Swortzel

Dr. Eric W. Bond, Superintendent

Capital Facilities Planning Team

Dr. Eric W. Bond, Superintendent Dr. Douglas W. Shifflett, Assistant Superintendent

George R. Earhart, Assistant Superintendent Ron Houser, Director of Operations & Maintenance

John Matherly, Director of Instruction Gary Bryant, Supervisor of Technology

Mark Lotts, Director of Business & Finance

Page 3: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

TEN – YEAR CAPITAL FACILITIES PLAN: 2015-2025

TABLE OF CONTENTS

SECTION 1: INTRODUCTION & BACKGROUND Augusta County Public Schools................................................................................. 1-1 Executive Summary ................................................................................................... 1-2 Background and Development ................................................................................... 1-4 System-Wide Facility Modernization Evaluation ...................................................... 1-5 Inventory of Educational Facilities ............................................................................ 1-6 School Support Facilities ........................................................................................... 1-7

SECTION 2: INFRASTRUCTURE Building Infrastructure ............................................................................................... 2-1 Technology Infrastructure .......................................................................................... 2-6

SECTION 3: CONSTRUCTION & RENOVATION OF FACILITIES Principles Behind the Plan ......................................................................................... 3-1 Guidelines for School Facilities and New School Sites............................................. 3-1 Priority of New Construction ..................................................................................... 3-3

SECTION 4: MOTHBALLING OF SCHOOLS Guidelines for Determining if a School is to be Mothballed ..................................... 4-1 Proposed Schedule of Schools to be Mothballed ....................................................... 4-2

SECTION 5: REDISTRICTING Attendance Area Adjustment Process ........................................................................ 5-1 Planning Principles for School Attendance Zones..................................................... 5-2 Direct Expenditures by School .................................................................................. 5-3 Procedural Guidelines ................................................................................................ 5-4 Enrollments ................................................................................................................ 5-4

SECTION 6: FACILITY MAINTENANCE NEEDS ................................................ 6-1

SECTION 7: FUNDING FOR CAPITAL PROJECTS Capital Improvement Program Funding .................................................................... 7-1 Construction Costs ..................................................................................................... 7-2 Analysis of Current School Debt Schedule & School CIP Fund Balance ................. 7-6 Impact of Proposed Projects on School CIP .............................................................. 7-8

SECTION 8: SUMMARY & TIMELINE OF IMPLEMENTATION Ten-Year Plan Summary............................................................................................ 8-1 Timeline for Implementation ..................................................................................... 8-2 History of Capital Projects: Phase I – VI .................................................................. 8-4 Funding the Depreciation Schedule ........................................................................... 8-5

SECTION 9: APPENDICIES Appendix A: Building Component Useful-Life Standards ...................................... A-1 Appendix B: Current Attendance Zones ...................................................................B-1 Appendix C: Year-End Operational Fund Balances .................................................C-1 Appendix D: Augusta County Profile ...................................................................... D-1

Page 4: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

1—1

Section 1 INTRODUCTION & BACKGROUND

Augusta County Public Schools

Augusta County Public Schools’ central administration offices are located in Verona, Virginia. The district serves 10,563 students and has 11 elementary, four middle, and five high schools. In addition, the district houses several regional programs including the Shenandoah Valley Governor’s School, Valley Vocational-Technical Center, and the Shenandoah Valley Consortium for Head Start.

Augusta County encompasses 971 square miles and includes the two independent cities of Staunton and Waynesboro. Each city operates their own school division independent of Augusta County Public Schools.

Government Organization

The District is governed by a seven-member board and operates under the Constitution and laws of the State. Each board member represents one of seven areas within the District and is elected by citizens of each respective district. Members of the Board are elected for four-year terms. The Board holds regular meetings once a month and special meetings as needed. All meetings are open to the public as provided by law and agenda items are prepared in advance.

The Board appoints a chief executive officer for the Division, designated as the Superintendent, who serves at the discretion of the Board. The Superintendent is responsible to the Board for the administration of all schools and departments of the District.

The District employs 1,630 employees, including 880 teachers, 81 administrators, and 669 classified staff.

The Community

A community profile for the County of Augusta is provided in Appendix C. The profile contains information on a broad range of factors including demographics of the population, economy, housing, employers and the labor force, and educational attainment of the citizens. Such data are useful for understanding growth trends, ethnicity, income, and mobility needs of a population. A profile provides basic information and understanding of the community as a whole.

Page 5: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

1—2

AUGUSTA COUNTY PUBLIC SCHOOLS CAPITAL IMPROVEMENT PLAN 2015-2025

Executive Summary The Augusta County Schools’ Capital Facilities Plan is a description of anticipated capital facility needs and anticipated expenditures for the next ten years. The Plan identifies the capital needs of the school system to include new facilities, additions, building infrastructure needs, facility maintenance needs, technology upgrades, and other projects and is presented to the School Board for their review and comment.

The Plan is intended to be reviewed and revised each year for the succeeding ten years.

The Plan is not intended to be the sole planning tool for determining capital facilities needs of the District and is not intended to serve as a budget document; however, the document provides a framework from which future budgets may be developed. The Plan assesses the ability of the District’s facilities to assist in the delivery of the educational program adopted by the District. The plan looks at the need for the District to modernize and/or replace existing. The plan is based on current conditions. The projects and associated costs in this plan are to be updated annually to adapt to changing facility needs, conditions, and demographic changes within the community. The funding source for capital needs will be from the School Board’s operational budget or the School Capital Improvement Program which currently has an authorized annual debt ceiling of $7,256,250. It is anticipated the revenue stream generated from the retirement of school construction debt will be utilized to assist in meeting major capital needs such as building renovations and/or new construction.

The Capital Improvement Plan is focused on maintaining existing facilities to ensure their proper operation, safety, and the ability to accommodate changing academic programs in order to meet our student’s needs. Major mechanical and maintenance projects as well as the modernization of our oldest facilities will continue to be an on-going need as our buildings age. Construction of new facilities will replace those schools that were constructed based upon a “pod” design which are inherently inefficient, possess an aged infrastructure, expose students to inclement weather, and pose safety concerns.

In this capital improvement plan, facility maintenance is addressed by either “Building Infrastructure” needs or “Facilities Maintenance” needs. Building Infrastructure projects are necessary when many building components are simultaneously nearing the end of their useful life due to age and the facility needs a more comprehensive approach. Infrastructure needs may include for example replacement of major building systems (roof, HVAC, etc.), and may also include the replacement of lighting, flooring, windows, water lines, and sewer replacement. Facilities Maintenance projects are the replacement of individual building components then they

Page 6: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

1—3

are no longer functioning or have reached an age when repairs are no longer possible due to cost or the lack of available replacement parts. Additionally, these aging components were not designed with current technologies that would conserve energy.

This plan identifies projects using the following criteria

• Major maintenance projects needed to maintain the structural and mechanical soundness of existing facilities.

• Renovation and modernization to existing facilities that are aging and in need of a major overhaul to renew materials and building systems at the end of their life cycle.

• Technology upgrades • Additional classroom spaces required to provide specialized instructional space and relief

to overcrowded schools. • New facilities needed to address overcrowding, or consolidation of multiple schools to

gain operational efficiencies, or to replace inefficient, aged, and unsafe facilities.

Page 7: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

1—4

Background and Development

The capital improvement plan is a management tool for planning the capital improvement projects that will be needed to house students adequately or to support the educational mission, including the maintenance of facilities. As such, it is useful for (1) estimating capital improvement expenditures over the future ten-year period, (2) identifying short- and long-range (ten-year) building and maintenance projects, and (3) establishing priorities for the orderly completion of projects. The purpose of this report is to present the School Board’s Proposed Capital Improvement Plan for the school system for the 2015-2025 planning period. The capital improvement plan includes the following types of projects:

• Building Infrastructure – the replacement of mechanical systems, roofs, and large maintenance projects.

• Facilities Maintenance Needs – the ongoing need for renovation or modernization of existing facilities.

• New or expanded permanent facilities. • Special initiatives related to prioritizing school infrastructure needs, implementing

school technology upgrades, or other campus improvements.

Page 8: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

1—5

System-Wide Facility Modernization Evaluation

Modernization Needs and Objectives

Research indicates buildings have a finite life of approximately 50-80 years provided the building is properly maintained throughout that time period. Additionally, as addressed in the Building Infrastructure section, major building systems such as roofs and HVAC have a shorter life span of about 15-20 years before replacement is required. With seventy five percent of Augusta County Public Schools, 15 of the 20 schools, being over 30 years of age, our facilities are aging and it is anticipated that many facilities require a major modernization in order to extend the useful life of the facility, bring the building up to current standards, and avoid potential system and/or structural failures. It is imperative that a system-wide approach is used to evaluate school facilities to determine facility priorities, the need for replacement or modernization, and a preliminary cost estimate. Timely facility modernizations protect Augusta County Public Schools’ facility investment, avoid costly and unexpected system failures, ensure a safe and secure learning environment, and provide a facility that supports the current educational program.

A modernization may include many of the major building systems (roof, HVAC, etc.), and may also include the replacement of lighting, flooring, windows, casework, etc. Additionally, modernizations may include the installation of the infrastructure necessary to support current technology tools as well as a more mobile computing environment.

Page 9: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

1—6

Inventory of Educational Facilities

Table 1

Elementary Schools

Year Built AgeSchool Site Size (acres)

Original Building Square Footage

Year(s)BuildingAdditions

Completed

SquareFootage

ofAdditions

Total Square Footage

# ofModular

Classrooms

Square Footage of

Modular Classrooms

Beverley Manor 1961 53 31.000 27,440 1974 36,100 63,540

Hugh Cassell 1973 41 40.680 46,796 1993 6,300 53,096 3 2,880

Churchville 2000 14 26.000 77,280 none none 77,280

Clymore 1995 19 22.000 90,960 none none 90,960

Craigsville 1931 83 7.980 13,700 1974, 1999 25,965 39,665

North River 1930 84 9.390 13,770 1970, 1999 39,950 53,720

Riverheads 1970 44 10.200 41,051 1974, 1993 14,000 55,051 3 2,880

Stuarts Draft 1995 19 20.000 90,960 none none 90,960

Guy Stump 1955 59 10.100 38,860 1968, 1979, 1999 20,090 58,950 1 960

Verona 1967 47 18.200 40,254 1976 4,000 44,254 3 2,880

Wilson 1958 56 14.060 17,913 1967, 1977, 1993, 2011 74,898 92,811

Middle Schools

Year Built Age

School Site Size

(acres)

Original Building Square Footage

Year(s)BuildingAdditions

Completed

SquareFootage

ofAdditions

Total Square Footage

# ofModular

Classrooms

Square Footage of

Modular Classrooms

Beverley Manor 1988 26 32.000 104,490 1993 3,400 107,890

S. Gordon Stewart 1980 34 19.637 104,490 none none 104,490

Stuarts Draft 1978 36 27.500 104,490 1993 9,750 114,240

Wilson Middle 2005 9 16.352 113,613 none none 113,613

High Schools

Year Built Age

School Site Size

(acres)

Original Building Square Footage

Year(s)BuildingAdditions

Completed

SquareFootage

ofAdditions

Total Square Footage

# ofModular

Classrooms

Square Footage of

Modular Classrooms

Buffalo Gap 1962 52 118.400 91,716 1969, 1997 37,810 129,526 2 1,920

Fort Defiance 1962 52 29.875 80,577 1969, 1975, 1996 82,518 163,095

Riverheads 1962 52 63.074 74,596 1976, 1997 48,905 123,501 2 1,920

Stuarts Draft 1970 44 32.300 110,942 2007 46,726 157,668

Wilson Memorial 1970 44 62.000 108,330 2007 43,337 151,667

Page 10: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

1—7

School Support Facilities

The School Board administrative and instructional support services offices are located at the Augusta County Government Center in Verona.

The Shenandoah Valley Head Start Consortium offices as well Maintenance Services and Transportation Services are currently located in surplus military (WWII) structures in Fishersville. The county’s Government Center Master Plan has planned for the eventual relocation of the facilities to Verona. The cost to relocate these facilities could range from $7 million to $10 million. No specific time frame has been associated with the relocation of these facilities (Augusta County Capital Improvement Plan, Version 1, July 1, 2014).

Page 11: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

2—1

Section 2 INFRASTRUCTURE

Building Infrastructure Needs

This section provides information about current facilities, existing facility needs, and expected future facility requirements for Augusta County Schools. Research based average life expectancy of HVAC equipment, piping, roofing, and other building components were utilized to compile the list of infrastructure needs (see Appendix A for Building Component Useful-Life Standards). In most cases, actual counts of equipment numbers and square footages were utilized in preparing cost estimates. Cost estimates were derived from prior Augusta County School Board infrastructure replacement projects and research of remodeling project cost estimates for building renovation projects. No allowances were made on estimated costs for inflation of manufactured goods and/or services.

The economic downturn of recent years coupled with state budget cuts to education have caused the school division to use available resources to address educational programs and employee salaries and benefits at a time where there have been increasing needs to maintain existing facilities. The following infrastructure lists are quite extensive and exceed available funding resources. However, a well-developed facilities plan must identify these items as they are considered essential needs in maintaining a safe and efficient learning environment.

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Fort Defiance High HVAC - replace chiller/cooling tower 525,000$ 21Fort Defiance High HVAC - replace oil-fired boilers 160,000$ 21Fort Defiance High HVAC - replace hot and chilled water circulating pumps 60,000$ 21Beverley Manor Elementary Roof replacement - partial 230,000$ 32Stuarts Draft Middle Lighting retrofit - entire school 235,000$ 38

TOTAL 1,210,000$

YEAR ONE 2015-16

Page 12: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

2—2

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Buffalo Gap High HVAC - replace chiller/cooling tower 525,000$ 21Buffalo Gap High HVAC - replace oil-fired boilers 160,000$ 21Buffalo Gap High HVAC - replace hot and chilled water circulating pumps 60,000$ 21Fort Defiance High Roof replacement - partial 274,000$ 32S.G. Stewart Middle Lighting retrofit - entire school 220,000$ 37

TOTAL 1,239,000$

YEAR TWO 2016-17

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Riverheads High HVAC - replace chiller/cooling tower 525,000$ 22Riverheads High HVAC - replace oil-fired boilers 160,000$ 22Riverheads High HVAC - replace hot and chilled water circulation pumps 60,000$ 22Beverley Manor Middle Lighting retrofit 230,000$ 30Riverheads High Roof replacement - partial 273,000$ 35

TOTAL 1,248,000$

YEAR THREE 2017-18

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Hugh Cassell Elementary HVAC - rooftop unit replacement 85,000$ 25Hugh Cassell Elementary Replace/rehab main school sewer and water lines 380,000$ 45Hugh Cassell Elementary Replace all school plumbing fixtures 60,000$ 45Hugh Cassell Elementary HVAC - replace all classroom heat pumps 336,000$ 20Hugh Cassell Elementary Lighting retrofit - entire school 107,000$ 45Stuarts Draft High HVAC - replace heat pump/air handlers - athletic fieldhouse 120,000$ 15Wilson Memorial High HVAC - replace heat pump/air handlers - athletic fieldhouse 120,000$ 14

TOTAL 1,208,000$

YEAR FOUR 2018-19

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Verona Elementary HVAC - rooftop unit replacement 389,000$ 53/27Verona Elementary HVAC - replace HVAC controls 112,000$ 53Verona Elementary Replace/rehab main school sewer and water lines 310,000$ 53Verona Elementary Replace all school plumbing fixtures 60,000$ 53Verona Elementary Electrical system upgrade(conductors, transformers, panels) 950,000$ 53Verona Elementary Lighting retrofit - entire school 90,000$ 53

TOTAL 1,911,000$

YEAR FIVE 2019-20

Page 13: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

2—3

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Guy Stump Elementary HVAC - replace chiller/cooling tower 425,000$ 23Guy Stump Elementary HVAC - replace classroom fan coil units 451,200$ 23Guy Stump Elementary HVAC - rooftop unit replacement 185,000$ 23Guy Stump Elementary HVAC - replace air handlers 75,000$ 23

TOTAL 1,136,200$

YEAR SIX 2020-21

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Clymore Elementary HVAC - replace oil fired boilers 160,000$ 28Clymore Elementary HVAC - replace cooling tower 55,000$ 28Clymore Elementary HVAC - replace classroom heat pumps 360,000$ 28Clymore Elementary HVAC - replace large heat pumps 120,000$ 28Clymore Elementary HVAC - replace small heat pumps 30,000$ 28Clymore Elementary HVAC - replace/rebuild hot water/cooling tower pumps 80,000$ 28Clymore Elementary Lighting retrofit - entire school 190,000$ 28

TOTAL 995,000$

YEAR SEVEN 2021-22

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Stuarts Draft Elementary HVAC - replace gas fired boilers 140,000$ 29Stuarts Draft Elementary HVAC - replace cooling tower 55,000$ 29Stuarts Draft Elementary HVAC - replace classroom heat pumps 360,000$ 29Stuarts Draft Elementary HVAC - replace large heat pumps 120,000$ 29Stuarts Draft Elementary HVAC - replace small heat pumps 30,000$ 29Stuarts Draft Elementary HVAC - replace/rebuild hot water/cooling tower pumps 80,000$ 29Stuarts Draft Elementary Lighting retrofit 190,000$ 29

TOTAL 975,000$

YEAR EIGHT 2022-23

Page 14: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

2—4

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Beverley Manor Elementary HVAC - replace chiller/condensing unit 325,000$ 25Beverley Manor Elementary HVAC - replace large air handlers 30,000$ 51Beverley Manor Elementary HVAC - rooftop unit replacement 185,000$ 51Beverley Manor Elementary HVAC - replace classroom unit ventilators 336,000$ 51Beverley Manor Elementary HVAC - replace hot/chilled water circulating pumps 60,000$ 51Beverley Manor Elementary HVAC - replace hot water boilers (new wing) 30,000$ 25Beverley Manor Elementary HVAC - convert 1961 wing from steam to hot water heat 548,800$ 63Beverley Manor Elementary Lighting retrofit - entire school 254,000$ 51/63

TOTAL 1,768,800$

YEAR NINE 2023-24

SCHOOL ITEM ESTIMATED

COST AGE AT PROPOSED

REPLACEMENT

Buffalo Gap High Roof replacement - partial 344,000$ 34Guy Stump Elementary Roof replacement - entire school 321,000$ 34/40Fort Defiance High Replace/rehab main school sewer line 235,000$ 63

TOTAL 900,000$

YEAR TEN 2024-25

The total projected cost of the 10-year Building Infrastructure needs is $12,591,000 (see Table 2). These costs assume that all current facilities remain in operation. The cost of the infrastructure needs exceed available funding resources. Historically, the school division’s annual operational budget has not been able to support the level of expenditures as outlined in the summary table below; however, savings realized in the operational budget have been used at year-end to address some capital needs (a history of year-end operational fund balances in provided in Appendix C) . The school division’s Capital Improvement Program account has mostly been utilized to meet the debt payment schedule of bond issuances. Planning dictates that the operational budget and the school CIP account will have to share in support of these costs in future years.

Page 15: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

2—5

Table 2

YEAR ESTIMATED COSTS2015-16 1,210,000$ 2016-17 1,239,000$ 2017-18 1,248,000$ 2018-19 1,208,000$ 2019-20 1,911,000$ 2020-21 1,136,200$ 2021-22 995,000$ 2022-23 975,000$ 2023-24 1,768,800$ 2024-25 900,000$

TOTAL 12,591,000$

CAPITAL FACILITIES PLANBUILDING INFRASTRUCTURE

Cost estimates were derived from prior Augusta County School Board infrastructure replacement projects and research of remodeling project cost estimates for building renovation projects. Estimated costs in future years do not include an allowance for inflation nor do they incorporate technology infrastructure upgrades.

Technology Infrastructure: Multi-Year Strategic Planning

Like roofs and HVAC systems, technology is another major component of a school building’s infrastructure, though technology has an even shorter life span than most other maintenance and infrastructure components. The strategic planning process for technology must remain cognizant of the fact that advances in software, hardware, and the means by which information is accessed and delivered continues to change and evolve at an ever-increasing pace. These changes coupled with increasing costs, limited resources, and expanding enterprise requirements, will force the division to continually focus on maximizing efficiency wherever possible.

The school division’s current standard is to design facilities with an electrical and mechanical infrastructure capable of supporting existing and future instructional technology. The goal is to establish an infrastructure that will support an increasingly mobile computing environment with the potential to support one-on-one computing in the future. Current technology tools include interactive white boards, document cameras, printers, copy machines, surveillance and access control systems for the building, paging and classroom audio systems, as well as the distribution of video. Along with all of these hardware components, technology includes the software and the data network required. The convergence of voice, video, and data onto the data network requires a robust technology infrastructure as well as adequate power and HVAC systems to support the additional equipment.

Page 16: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

2—6

Within the school division, several schools have been constructed and renovated within the last fifteen years and although a major modernization of these schools is not necessary at this time, a major technology upgrade is warranted. The multi-year strategic plan for ACPS technology contains components that are relevant to the long-range vision. This includes programs and projects that are vital to ACPS operations. The division develops strategies and plans to construct an environment that is flexible, scalable, maintainable, supportable, manageable, and secure. Multi-Year Needs Assessment

These costs are intended to provide an outline of future funding requirements but may not necessarily reflect costs used for budget planning especially for years that extend further into the future as these costs and needs will likely change over time. Computer Replacement

There are more than 3,500 computers used by students, faculty, and staff in the Augusta County School division. Equipment used by students and faculty is aging with 50% of the computers in the inventory over five years old. Presently, there is roughly 1 computer for every 4 children in the division. Funding for computer replacement is limited. Without adequate replacement funding, the age of the computer inventory will continue to increase causing difficulty running the software used by many of our students and staff. Sustained annual funding over $1.3 million is required to grow the number of devices to support 1 computer for every 2 children and to maintain a three-year replacement cycle of all ACPS school computers. This cost will be embedded in the school division’s annual operating budget. Presently, ACPS is using capital improvement funds to purchase mobile computers as part of the division’s Digital Transformation Initiative. These funds represent an advance on the future sale of the Ladd Elementary School property and will not be available after the 2016-17 school year. The $1.3 million needed to maintain a three-year replacement cycle for all devices will need to be supported from operational funds. It is important to recognize that as computers are replaced that an equal distribution of computers to schools contributes to, but does not guarantee, equity. True equity involves the ability of students, teachers, and staff members to use those computers effectively to enhance instruction and school operations. It involves equal access to supporting technology and resources. These resources include professional development, support, and the information that is needed to effectively use the technologies for the education of students.

Page 17: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

2—7

Network Equipment Replacement

These funds are to replace/upgrade network equipment as it comes to end of life and is no longer supported by the vendor. Such infrastructure consists of core switches, bandwidth capacity, local area switches, wireless access points, servers, and data storage units. Over the past several years there has been an explosive growth in each of these areas; Internet Bandwidth, ACPS Core Bandwidth, WAN Bandwidth to Schools, Local Area Network Switches and wireless access points. To keep up with the progression we will need to upgrade areas of our core infrastructure. For any ten-year period going forward, it is estimated that a capital cost of $6 million dollars is needed to replace the network infrastructure twice during that period – a five-year life-cycle for the equipment involved. For the ten-year period beginning the fall of 2014, Augusta County Schools anticipate capital needs of approximately $4 million to replace and upgrade network infrastructure (see Table 3).

Table 3

Year Fiscal Year ProjectedCost

Year 1 2014-2015 250,000$ Year 2 2015-2016 400,000$ Year 3 2016-2017 400,000$ Year 4 2017-2018 N/AYear 5 2018-2019 N/AYear 6 2019-2020 N/AYear 7 2020-2021 1,000,000$ Year 8 2021-2022 1,000,000$ Year 9 2022-2023 1,000,000$

Year 10 2023-2024 N/A

Technology Infrastructure Costs *

*These costs are related only to infrastructure needs and do not include the cost of computers, tablets, or other handheld computing devices.

ACPS has funding for the first replacement cycle that begins in the fall of 2014 by utilizing the funds available from the future sale of Ladd Elementary School. The lower cost in Year One is a result of using operating funds to pay for some infrastructure upgrades. The equipment being replaced and upgraded in this cycle includes PoE (power over Ethernet) distribution switches, wireless access points, wireless controllers, and associated cable.

Page 18: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

2—8

The next replacement is scheduled to begin in the seventh year, 2020-2021, and continue through the ninth year, 2022-2023. ACPS estimates a cost of $1million dollars for each of the three years. ACPS anticipates a more significant infrastructure upgrade to accommodate an increase in the number of mobile devices accessing the network and in increase in the bandwidth required between schools and the network operating center. Estimating costs for technology upgrades that are scheduled more than five years out is challenging to due changes in the technology. Routine replacement of other aging infrastructure equipment (e.g., core switches, firewalls) is funded through the annual operational budget. Student Home Computer and Internet Access

In order to address the digital-divide and ensure equitable access for all students to instruction 24 hours a day, 7 days a week, students without Internet and computing resources in their home must be provided support in obtaining these critical resources. ACPS IT and Instructional Departments see an opportunity to work jointly with the county to seek ways to address this significant challenge for our neediest students. Funding would be determined at a later time.

The planning and determination of technology needs is not a one-time event, it is an on-going cyclical process which requires continual planning, implementation, and checking outcomes in order to improve our processes.

Page 19: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

3—1

Section 3 CONSTRUCTION & RENOVATION OF FACILITIES

Principles Behind the Plan

Augusta County Public Schools’ facilities are an expression of the community’s commitment to educate and to invest in its children and its future. Based upon this principal, the 2015-2025 Capital Improvement Plan has incorporated the following academic and design features. Principles behind the plan include:

• Provide facilities that meet the curricular and extracurricular program needs of our students, that are logically designed and, to the extent possible, that are flexible enough to adapt to changing requirements.

• Provide facilities that support and enhance the use of current and future technology • Plan schools that have sufficient space to house current and projected students. • Evaluate potential consolidation of schools in order to increase operational

efficiencies and achieve higher utilization of instructional spaces. • Design and construct school facilities free of safety hazards. • Design and construct school facilities in harmony with the history and architecture of

the community. • Construct and maintain school facilities to be structurally sound, clean, efficient, safe

and attractive. • Provide facilities that meet the requirements of the centralized support services, such

as transportation and plant operation and maintenance.

Guidelines for School Facilities and New School Sites

When additional facility space is required, existing facility expansion is considered before the construction of new facilities unless the current facility is in such condition that renovation/expansion is not a cost effective option. If a new facility is required, it is planned to provide the basic instructional, administrative, and extracurricular programs of the school system. Design and construction of a new school’s central facilities, or core infrastructure (cafeteria, auditorium, media center, and administrative unit) should adequately address near-term and long-term projected enrollments. Design capacity may be a factor of current attendance, planned adjustments in attendance zones, or planned and/or projected population growth.

Several considerations are used when determining the location of a new school site. These considerations include:

• Adequate road frontage and ease of access • Proximity to compatible services, such as athletic fields, and utilities • Adjacent zoning

Page 20: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

3—2

• Adhere to, or exceed, the Virginia Department of Education guidelines when determining useable acreage required for a school site (see below) – to provide adequate site acreage to separate pedestrian, bus, and car traffic

• The configuration of the site, the curricular and extracurricular educational program (including physical education and playing fields), and local requirements (including parking and storm water management) will impact the guidelines and the size of the site.

• Additional considerations would be the shape of the site, topography, and soil conditions.

• Adequate perimeter road circulation for emergency response vehicles.

In order to accommodate appropriate sized facilities and grounds, the guidelines for school site size are as follows:

• Elementary Schools: 4 acres + 1 acre/100 pupils • Middle Schools: 10 acres + 1 acre/100 pupils • High Schools 10 acres + 1 acre/100 pupils

Page 21: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

3—3

Priority of New Construction

The Augusta County School Board’s priority list of school construction projects are identified in Table 4 – additional information is provided for each project.

Table 4

School Type Completed

1: Riverheads Elementary New Construction 2016

2: Wilson Middle Classroom Addition 2016

3: Hugh Cassell Elementary New Construction 2017

4: Riverheads & Buffalo Gap Middle New Construction 2023

Riverheads Elementary

The current school was built in 1970 and is situated on approximately 10 acres. The school is a “pod-type” design. The division operated four pod-type elementary schools up until the closure of Ladd in 2013. The other pod-type schools include Hugh Cassell Elementary and Verona Elementary. The pod-type design provided for an “open classroom,” an innovation that swept through the United States between the late 1960s and early 1970s. The idea being that about 100 students and their three or four teachers would mingle, learning together and sharing ideas and lesson plans. What happened instead was that many children were distracted by students in other classes and teachers going over unrelated work a few feet away. Teachers carved out their own rooms by building walls of bookcases, coat racks, blackboards and vertical files or open classrooms were subdivided with movable partitions.

Inherent disadvantages of the pod-type design include increased safety and security concerns, student exposure to temperature extremes and inclement weather and lost instructional time due to preparing for transitions or class changes. Riverheads’ electrical system is insufficient to support the needs of current technology and online testing. The plumbing system is failing and needs significant upgrades. In summary, most of the school’s infrastructure is inadequate to ensure safe, efficient, and an instructionally conducive learning environment. The pod-type design does not lend itself to infrastructure upgrades due to limited interior space and underground utilities are covered by buildings and/or sidewalks.

The new facility will be approximately 91,000 square feet and designed for 750 pre-Kindergarten through 5th grade students and will be situated on a site adjacent to Riverheads High School. The design calls for a three-story building which efficiently utilizes the site’s topography. The projected time-line for construction is 14-16 months. Construction is anticipated to begin in the

Page 22: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

3—4

fall of 2014 with completion scheduled for the summer of 2016. The estimated cost for the project is $18.6 million.

Wilson Middle

Wilson Middle School opened in 2005 with a program capacity of 520. Enrollment as of June 2014 was 571, or 109.8% of capacity. Projected enrollment for the 2018-2019 school year is 575, or 110.6% of capacity, based upon current attendance zones. Adjustments to the current attendance boundary lines would impact future enrollments. The design of the school allows for classrooms to be added onto one of the instructional wings. The projected cost of eight classrooms to accommodate 160 additional students is approximately $2.2 million. The core infrastructure of the building was designed to accommodate 750 students. The projected construction time would be one year. The design and construction of the additional classroom could be completed for the summer of 2016.

Hugh Cassell Elementary

The school was built in 1973 and sets on approximately 41 acres. As previous referenced, this school is of a pod-type design and possess the same disadvantages associated with this type of design as does Riverheads Elementary including students exposed to weather, aging infrastructure (except for electrical), safety and security, and loss instructional time due to transitioning. The kitchen was renovated following a fire in 2011. The electrical system was upgraded throughout the buildings at that time as well. The kitchen renovation and electrical upgrade cost approximately $1 million. It is anticipated that a new school design will incorporate the newly renovated kitchen and existing administrative building. Initial consideration for capacity is 750 students. The actual enrollment of June 2014 of 506 exceeded the program capacity of the school. Projected enrollment for the 2018-2019 school year is 480, or 96% of capacity. Enrollment projections assume no changes in current attendance zones.

Currently included in the proposed Ten-Year Capital Facilities Plan are $1.438 million in needed infrastructure improvement for the current facility. These include replacement of rooftop ventilation units, sewer and water lines, school-wide plumbing fixtures, heat pumps, and a lighting retrofit.

The estimated cost for the project is $17.6 million (assuming a significant portion of the project involves new construction). This cost is based upon the per pupil cost of the Riverheads Elementary School less the investment already made in the renovation to the kitchen and electrical upgrades and is subject to change based upon inflation, design specifics, site attributes, and general economic and construction market conditions. A feasibility study should be undertaken to identify the scope of work and the degree of renovation and/or new construction. The projected time-line for completion of this project is the summer of 2017.

Page 23: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

3—5

Riverheads and Buffalo Gap Middle School Wings

The addition of middle school classroom wings at Riverheads High School and Buffalo Gap High School would allow the middle schools students from these districts to remain vertically aligned with their respective elementary and high schools. The facilities would accommodate approximately 450 to 500 students and encompass approximately $72,900 square feet each. The configuration of a middle school wing would be efficient in that common spaces such as food service and physical education facilities could be shared with the high school. The design would provide for a separate, secure main entrance, grade level grouping, STEM flexible learning areas, faculty work rooms, and support and resource rooms.

The addition of these two middle school facilities would eliminate the transport of students from Riverheads and Buffalo Gap to Beverley Manor Middle School. The elimination of these bus routes would result in an average annual operational savings in labor and fuel in the amount of $39,000, exclusive of vehicle maintenance and depreciation costs. In addition instructional time for students would be increased. Students who presently attend BMMS would gain 24 minutes each day by attending a middle school at Buffalo Gap. Students attending middle school at Riverheads would gain 34 minutes each day. These numbers are based on the difference in instructional time from 2013-14 master schedules for BMMS, BGHS and RHS and will vary only slightly over the next several years.

BMMS students also benefit from a move to middle school wings by increasing the opportunity for advanced coursework. While our other middle schools already benefit from close proximity to a high school, BMMS has had to rely on virtual programs or hiring teachers specifically to provide advanced coursework in mathematics. Collaborative hiring and scheduling may provide new instructional opportunities to middle school students in the southern and western portions of our county.

The projected costs of the middle school additions at Riverheads and Buffalo Gap are $14.3 million and $14.6 respectively. The projected time-line for completion of this project is the summer of 2023 and is contingent upon the ability of the School Capital Improvement Program to fund the project.

Page 24: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

4—1

Section 4 Mothballing of Schools

The decision to mothball a school profoundly affects a variety of stakeholders. However, amidst circumstances of declining enrollment and economic necessity, at times such a decision cannot be avoided. Consideration needs to be given to how the potential mothballing of a school could affect or reinforce the division’s Capital Facilities Plan.

Guidelines for Determining if a School is to be Mothballed

The following tasks and criteria need to be considered in determining if a school should be mothballed.

• Evaluation of enrollment projections including historical school data trends and potential growth initiated by development and construction and their impact on space utilization.

• Inventory the capacity and conditions of existing facilities. The capacity of a school to accommodate additional students includes core facilities – library, multipurpose room, cafeteria, gymnasium, and toilets. While there may be room on a school site to add portable classrooms, there may be limited room to accommodate additional students in these core areas.

• Determine per-student operating cost at each facility. The operating cost of a school will include personnel, energy consumption and needed capital improvements.

• Consider uniqueness of the educational program at each site. Special program facilities, such as providing services for special education students, may require special facilities. Closing a school where a large capital investment in these special facilities exists may not be cost effective if those specialized facilities need to be rebuilt elsewhere.

• Identify specific new environmental/safety concerns for each site. Environmental factors surrounding a school may have changed since it was first opened. Zoning may have been changed to allow for commercial development, or there might be new environmental hazards (i. e., pipelines, high voltage power lines, fuel storage tanks, etc.) that now compromise the safety of the students at a school.

• Determine cost-savings projected for each school considered to be mothballed. The reduction in operational costs is crucial and needs to be an integral part of the decision-making process when evaluating the potential mothballing of a school.

• Identify transportation options for displaced students. Transportation is a factor in the decision to mothball a school. Not only from an operational cost perspective, but how routes and pick up and drop off times for students will be altered.

• Consider cost benefits of property disposition/use options. • Recommend transition strategies.

Page 25: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

4—2

Proposed Schedule of Schools to be Mothballed

Beverley Manor Elementary

Following the scheduled completion of the new Riverheads Elementary School in 2016, Beverley Manor Elementary School will be made inactive (mothballed). Students who would have attended Beverley Manor Elementary School will be attending either Riverheads Elementary School or Churchville Elementary School resulting in an improved vertical alignment as these students will eventually attend high schools that are in closer proximity to these elementary schools.

The capacity of the new Riverheads Elementary School will be 750. The June 2014 enrollment for Riverheads Elementary was 544. If enrollment remains relative stable, the new Riverheads Elementary School could absorb up to approximately 200 of the students who would have been attending Beverley Manor Elementary.

Churchville Elementary School’s capacity is 540. Current enrollment, as of June 2014, is 317; or an utilization factor of 58.7%. Churchville could potentially absorb approximately 233 students. The current enrollment of Beverley Manor Elementary is 365, with a utilization factor of 70.2%. The redistribution of these students to Riverheads and Churchville could easily be accomplished given the fact that there would be a combined 429 available seats, and thus allowing both Riverheads and Churchville to operate at a relative high degree of utilization of capacity.

The Beverley Manor facility could possibly be repurposed as a site for the Shenandoah Valley Governor’s School. Currently, the Governor’s School occupies space at Valley Vocational-Technical Center. With ongoing efforts to offer courses that are in response to employer needs and to provide quality training for the tomorrow’s work force, Valley Vocational-Technical Center could utilize the space for that would be available should the Governor’s School relocate for expanded course offerings. The facility would offer flexibility to accommodate the Governor’s School curriculum including providing a stage for the performing arts. Additionally, the facility could serve to house the Augusta County Department of Parks and Recreation or other community based services.

Verona Elementary

Verona Elementary, as previously referenced, was built based upon a pod-type design. This type of design inherently heightens concerns for safety and security. In addition, students are exposed to temperature extremes and inclement weather and lost instructional time due to preparing for transitions or class changes. The facility is need of more than $1.9 million in infrastructure repairs within the next five years to address HVAC replacements/controls, replacement of water and sewer lines and all plumbing fixtures, an electrical upgrade, and a lighting retrofit.

Page 26: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

4—3

Verona would be taken offline following the 2016-2017 school year and the renovation to Hugh Cassell Elementary. The division would have no remaining pod-type schools in operation. The June 2014 enrollment for Verona Elementary was 330. These students would be reassigned based upon revised attendance zones. The recommendations of the Boundary Line Committee will not be available until 2015. Based upon the projected 2018-2019 enrollments, Clymore, North River, and Churchville elementary schools could increase their enrollments without exceeding capacity.

Beverley Manor Middle

The addition of middle school classroom wings at Riverheads Highs School and Buffalo Gap High School would allow the middle schools students from these districts to remain vertically aligned with their respective elementary and high schools. There would no longer be a need to have Beverley Manor Middle School online. It was previously referenced that one of the potential uses for Beverley Manor Elementary School was to serve host to the Shenandoah Valley Governor’s School. Alternatively, Beverley Manor Middle could be utilized as the site for the Governor’s School. The disadvantage for using BMMS would be the period of time associated with the building of the middle school wings at Riverheads and Buffalo Gap – as these projects would not come online until the 2023-2024 school year.

Operational Cost Savings

With the addition of classroom wings at Riverheads and Buffalo Gap High Schools it is estimated that the elimination of shuttle bus runs to Beverley Manor Middle would generate a savings of $39,000 annually. No additional operational cost savings related to the mothballing of Beverley Manor Middle School are known at this time and will require future in-depth analysis. While the precise impact on transportation costs associated with potential boundary line adjustments throughout the division is unknown at this time, it is anticipated that the mothballing of these three schools would result in other significant operational cost savings. These savings could be used to address improvements in the salary scales and ongoing facility maintenance and infrastructure needs. The projected operational cost savings and the related infrastructure costs that would be eliminated by mothballing these schools are provided in Table 5.

Table 5

Site

AnnualOperational

CostSavings

Fiscal YearSavings are

Initially Realized

# Years of Operational

Savings(2015-2025)

10-YearOperational

SavingsRealized

(2015-2025)

Infrastructure Costs

Eliminated(2015-2025)

TotalProjected Savings

(Operational & Capital:

2015-2025)

Beverley Manor Elementary 550,000$ 2016-2017 9 4,950,000$ 1,998,800$ 6,948,800$

Verona Elementary 550,000$ 2017-2018 8 4,400,000$ 1,911,000$ 6,311,000$

Beverley Manor Middle 39,000$ 2023-2024 2 78,000$ 230,000$ 308,000$

Total 4,139,800$ 13,567,800$

Page 27: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

5—1

Section 5 Redistricting

Attendance Area Adjustment Process

The School Board may direct the Superintendent to recommend the establishment of a Boundary Line Committee to evaluate the potential need for attendance zone adjustments following the submission of the Ten-Year Capital Facilities Plan. It is anticipated that a division-wide study to review elementary, middle, and high school attendance zones in an effort to efficiently utilize program capacities will require approximately one year. One must recognize and realize that adjusting boundary lines for attendance is a process, not an exact science. Continued efforts to refine the process will be ongoing. Throughout this process, the School Board will continue to adhere to their philosophy and policies. First, the Board continues to endorse their Plan of Organization for instruction by maintaining the instructional configuration which is elementary school grades K-5; middle school grades 6-8; and high school grades 9-12. Secondly, efforts to maintain the concept that feeder school populations will continue to be affiliated with an existing middle school and/or high school attendance area in order to promote community tradition, allegiance, and pride. Thirdly, to provide all students the best physical learning environment possible by uniform and equitable utilization of facilities according to the needs of the educational program that will produce successful 21st Century Learners.

• The attendance areas adjustment process for Augusta County Schools begins with the appointment of the Boundary Line Committee by the School Board.

• The committee will be comprised of a Central Office administrator(s), a building administrator from the schools within the attendance zone being evaluated, teacher(s), and School Board members.

• The committee develops potential boundary change scenarios that follow regulations and prepares data to show the effects of potential changes on the number of current students at affected sites. Possible alternatives are reviewed with appropriate staff.

• The committee will review possible alternatives with the Superintendent and School Board members.

• The School Board schedules date for initial presentation of the proposed plan, public hearing date(s), and location(s), for community and public input.

• The school division prepares and disseminates a public notice.

• Information packets for affected schools and letters to parents and patrons in the affected area are mailed directly to families and sent home with students.

Page 28: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

5—2

• The proposed plan and supporting information are shared with the affected parent-teacher organizations, civic groups and other stakeholders as needed.

• The School Board conducts a public hearing(s) on the proposed plan that includes the Committee’s proposals and receives input on such adjustments.

• The School Board considers the public’s input and makes a final decision.

Planning Principles for School Attendance Zones

The following guidelines are to be used when evaluating school attendance zones and/or boundary line adjustments:

• Explore all viable options for accommodating students before constructing new schools and/or additions including: the review of existing school attendance zones, utilization of portable classrooms for temporary space until enrollment stabilizes, and possible relocation of instruction programs.

• Evaluate per pupil operational costs for each school. The per pupil expenditures by school for fiscal year 2012-2013 are provided in Table 6.

• Establish boundary lines for school zone changes according to minimum and maximum enrollment guidelines that will reduce overcrowding scenarios, near school capacity facilities, or efficiency for operational and cost savings.

• Plan to stabilize school attendance zone boundaries to the extent possible by considering current enrollment, utilizing projected student population growth through historical school data, and speculating potential growth initiated by the ever changing rezoning and construction of housing units.

• Reviewing the existing Comprehensive Plan for the County of Augusta. • Reevaluate the operational capacity of school buildings regularly based on the current

instructional program in each building. • Reevaluate and revise annually, all proposals (such as new construction projects,

renovations, and attendance zone adjustments) for inclusion in the School Board’s ten-year Proposed Capital Improvement Plan

Page 29: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

5—3

Table 6

Compensation Costs

of Contracted Employees

(excludes Bus Drivers & Food

Service)

Compensation Costs

of Contracted Employees

Bus Drivers & Food Service

TotalCompensation

Costsof Contracted

Employees

Instructional Allocation

ExpendituresUtilities(Total)

TotalDirect

Expenditures

EnrollmentMarch 31,

2013Direct CostPer Pupil

AverageDirect CostPer Pupil

VarianceFrom

AverageDirect Cost Per Pupil

PercentVariance

FromAverage

Direct CostPer Pupil

1 Beverley Manor Elementary 2,243,798$ 125,421$ 2,369,219$ 13,454$ 94,688$ 2,477,361$ 336.55 7,361$ 6,903$ 458$ 6.63%2 Hugh K. Cassell Elementary 2,905,367$ 215,408$ 3,120,775$ 18,865$ 92,432$ 3,232,072$ 460.29 7,022$ 6,903$ 119$ 1.72%3 Churchville Elementary 2,207,548$ 142,910$ 2,350,458$ 15,426$ 131,518$ 2,497,402$ 331.18 7,541$ 6,903$ 638$ 9.24%4 Edward G. Clymore Elementary 3,589,694$ 357,239$ 3,946,933$ 26,104$ 136,638$ 4,109,675$ 627.81 6,546$ 6,903$ (357)$ -5.17%5 Craigsville Elementary 1,421,784$ 94,311$ 1,516,095$ 7,984$ 78,485$ 1,602,564$ 151.06 10,609$ 6,903$ 3,706$ 53.68%6 North River Elementary 1,944,986$ 188,528$ 2,133,514$ 11,523$ 63,432$ 2,208,469$ 258.18 8,554$ 6,903$ 1,651$ 23.92%7 Riverheads Elementary 2,964,115$ 180,993$ 3,145,108$ 21,675$ 95,682$ 3,262,465$ 532.26 6,129$ 6,903$ (774)$ -11.21%8 Stuarts Draft Elementary 3,272,225$ 182,030$ 3,454,255$ 24,020$ 138,768$ 3,617,043$ 574.84 6,292$ 6,903$ (611)$ -8.85%9 Guy K. Stump Elementary 2,118,650$ 127,235$ 2,245,885$ 13,975$ 82,715$ 2,342,575$ 320.79 7,303$ 6,903$ 399$ 5.79%10 Verona Elementary 2,412,108$ 196,252$ 2,608,360$ 11,990$ 60,224$ 2,680,574$ 309.66 8,657$ 6,903$ 1,753$ 25.40%11 Wilson Elementary 2,438,733$ 142,570$ 2,581,303$ 17,382$ 103,382$ 2,702,067$ 438.83 6,157$ 6,903$ (746)$ -10.80%12 Beverley Manor Middle 3,875,966$ 312,518$ 4,188,484$ 64,805$ 100,439$ 4,353,728$ 741.03 5,875$ 6,903$ (1,028)$ -14.89%13 S. G. Stewart Middle 3,440,083$ 299,322$ 3,739,405$ 58,553$ 147,351$ 3,945,309$ 632.10 6,242$ 6,903$ (661)$ -9.58%14 Stuarts Draft Middle 3,559,176$ 258,295$ 3,817,471$ 49,744$ 125,045$ 3,992,260$ 543.04 7,352$ 6,903$ 449$ 6.50%15 Wilson Middle 3,142,726$ 311,270$ 3,453,996$ 52,871$ 147,218$ 3,654,085$ 564.22 6,476$ 6,903$ (427)$ -6.18%16 Buffalo Gap High 3,566,075$ 301,538$ 3,867,613$ 45,244$ 226,144$ 4,139,001$ 555.23 7,455$ 6,903$ 551$ 7.99%17 Fort Defiance High 5,416,971$ 298,423$ 5,715,394$ 56,533$ 280,344$ 6,052,271$ 793.32 7,629$ 6,903$ 726$ 10.52%18 Riverheads High 3,207,814$ 251,574$ 3,459,388$ 42,889$ 266,672$ 3,768,949$ 513.12 7,345$ 6,903$ 442$ 6.40%19 Stuarts Draft High 4,398,029$ 198,941$ 4,596,970$ 55,903$ 220,654$ 4,873,527$ 757.53 6,433$ 6,903$ (470)$ -6.80%20 Wilson Memorial High 4,309,618$ 169,357$ 4,478,975$ 53,800$ 219,757$ 4,752,532$ 737.58 6,443$ 6,903$ (460)$ -6.66%

Totals 62,435,466$ 4,354,135$ 66,789,601$ 662,740$ 2,811,588$ 70,263,929$ 10,178.62

Notesa:

b: Personnel costs do not include tuition reimbursement, travel & conference reimbursement.

c: Enrollment March 31, 2013 represents total enrollment - not enrollment for funding

d: Certain administrative/overhead costs are not directly allocated to specific cost centers; these include:Central Office Administrative Expenditures Equipment ServicesInstructional Support Services Contracted Outside ServicesTravel Reimbursement Fuel / Vehicle Parts & RepairsTuition Reimbursement AdvertisingConference Expenditures Legal, Auditing ServicesContracted Maintenance Services Postal & Delivery ServicesProfessional Services

School

2012-2013Direct Expenditures by School

Personnel salaries include administration, instructional, and support staff (principals, teachers, aides, guidance, nurses, media, clinic aides, clerical staff, computer aides & technicians, bus drivers and cafeteria staff; Head Start personnel are excluded). Not all bus drivers are assigned to a specific school. Substitutes and time-card employees are excluded.

Page 30: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

5—4

Procedural Guidelines

The following procedural guidelines are used when attendance zones are adjusted:

• Major roads and natural boundaries will be used whenever feasible to define attendance zones.

• Consider road intersections. • Avoid the transporting of students through another school’s attendance area. • All reasonable efforts should be made to ensure contiguous geographic zones which

minimize division of clearly identifiable community components (e.g. apartment units, residential subdivisions).

• Efforts will be made to ensure an efficient system of school bus transportation. • Provisions should be made to ensure the continuity of a child's K-12 progress.

A link to access the current attendance zones can be found in Appendix B.

Enrollments

There are several methods by which school enrollments can be measured. The most common two are Average Daily Attendance (ADA) and Average Daily Membership (ADM). The Average Daily Attendance (ADA) calculates the frequency at which students attend school. Attendance rates are used in calculating the federal measure of adequate yearly progress. The Average Daily Membership (ADM) is a count of students that is taken at different times of the year to satisfy local, state and federal data collection needs and also to ensure that school districts are adequately funded, according to student population. Average Daily Membership (ADM) is a specific count of enrollment at a particular site collected at various times throughout the school year. ADM drives school funding and local, state, and federal data collection. ADM is more consistent than Average Daily Attendance (ADA) as it does not rely solely on attendance, but instead on the overall number of students on the roll throughout the course of the year. A student can miss five straight days and negatively impact ADA but have no impact at all on ADM.

The Average Daily Membership information for Augusta County Schools as reported to the Virginia Department of Education does not include pre-school students, Shenandoah Valley Regional Program Students, or Consolidated Services Act students. A 20-year history of the Average Daily Membership as reported to VADOE is provided in Table 7.

Page 31: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

5—5

Historical Enrollment

Table 7

10,000.00

10,100.00

10,200.00

10,300.00

10,400.00

10,500.00

10,600.00

10,700.00

10,800.00

10,900.00

10,417

10,629

10,79110,824

10,86910,804

10,695 10,685

10,597 10,62410,690

10,769 10,798

10,716 10,688

10,51510,456

10,405 10,414

10,325

Average Daily Membership as Reported to DOE in March

Although pre-school students, Shenandoah Valley Regional Program Students, or Consolidated Services Act students are not included in the reporting of the Average Daily Membership, these students do receive instructionally related services and occupy classroom space. Thus, they must be included in evaluating total enrollments and in determining utilization of instructional space. School utilization planning is necessary to provide effective learning environments for all students. Well utilized schools have ample learning spaces for all students in attendance, as well as sufficient common spaces to support educational programs and enrollment. School utilization planning requires an understanding of space needs for the range of academic programs offered in a school, as well as classroom and common spaces available for student use and the number of students anticipated in the future.

School Year March ADM School Year March ADM1994-1995 10,417.00 2004-2005 10,690.46 1995-1996 10,629.00 2005-2006 10,769.07 1996-1997 10,791.00 2006-2007 10,797.83 1997-1998 10,824.00 2007-2008 10,716.18 1998-1999 10,869.00 2008-2009 10,688.28 1999-2000 10,803.50 2009-2010 10,514.72 2000-2001 10,695.00 2010-2011 10,456.22 2001-2002 10,685.00 2011-2012 10,405.37 2002-2003 10,597.00 2012-2013 10,414.45 2003-2004 10,624.00 2013-2014 10,324.73

Page 32: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

5—6

Table 8 provides enrollment information, instructional program capacity, and percent of utilization for each school as of June 6th, 2014.

Table 8

SchoolTotal

(6/6/2014)ProgramCapacity Difference

PercentUtilization

Buffalo Gap High 522 740 218 70.5%Fort Defiance High 779 960 181 81.1%Riverhead High 472 600 128 78.7%Stuarts Draft High 699 940 241 74.4%Wilson Memorial High 739 900 161 82.1%

Beverley Manor Middle 727 800 73 90.9%Steward Middle 591 720 129 82.1%Stuarts Draft Middle 538 960 422 56.0%Wilson Middle 571 520 -51 109.8%

Beverley Manor Elementary 365 520 155 70.2%Hugh Cassell Elementary 506 500 -6 101.2%Churchville Elementary 317 540 223 58.7%Clymore Elementary 665 750 85 88.7%Craigsville Elementary 156 360 204 43.3%North River Elementary 276 440 164 62.7%Riverheads Elementary 544 600 56 90.7%Stuarts Draft Elementary 680 750 70 90.7%Guy Stump Elementary 390 480 90 81.3%Verona Elementary 330 420 90 78.6%Wilson Elementary 696 750 54 92.8%

Total 10,563 13,250 2,687 79.7%

Page 33: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

5—7

Projected Enrollments

By moving students forward one grade level per year and taking the five-year average number of Kindergarten students the projected enrollments for 2018-2019 are presented in Table 9 (assuming no adjustments in current attendance zones).

Table 9

School

2018-2019Projected

EnrollmentProgramCapacity Difference

PercentUtilization

Buffalo Gap High 533 740 207 72.0%Fort Defiance High 761 960 199 79.3%Riverhead High 436 600 164 72.7%Stuarts Draft High 708 940 232 75.3%Wilson Memorial High 769 900 131 85.4%

Beverley Manor Middle 714 800 86 89.3%Steward Middle 529 720 191 73.5%Stuarts Draft Middle 519 960 441 54.1%Wilson Middle 575 520 -55 110.6%

Beverley Manor Elementary 327 520 193 62.9%Hugh Cassell Elementary 480 500 20 96.0%Churchville Elementary 293 540 247 54.3%Clymore Elementary 579 750 171 77.2%Craigsville Elementary 152 360 208 42.2%North River Elementary 243 440 197 55.2%Riverheads Elementary 509 600 91 84.8%Stuarts Draft Elementary 595 750 155 79.3%Guy Stump Elementary 301 480 179 62.7%Verona Elementary 321 420 99 76.4%Wilson Elementary 637 750 113 84.9%

Total 9,981 13,250 3,269 75.3%

Relative to elementary schools, Beverley Manor, Churchville, Craigsville, and North River have the lowest percentage of utilization in both 2013-2014 and projected 2018-2019.

In 2013-2014 and 2018-2019, Wilson Middle School’s enrollment exceeds capacity by 9.8% and 10.6% respectively.

Wilson Memorial High School has the highest degree of utilization for a high school in both 2013-2014 and 2018-2019 with rates of 82.1% and 85.4% respectively.

Page 34: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

6—1

Section 6 Facilities Maintenance Needs

While the planning, design, and construction of the school facility may take two to three years, the management of it will last the entire life cycle of the facility. At the beginning of this century, the average age of a school building in the United States was forty-two years, with 28 percent of school buildings built before 1950. Many of the building materials, furnishings, and equipment will not last half that long and will require constant upkeep, maintenance, and inevitable replacement to defer building obsolescence.

The costs of managing school facilities have historically received much less attention than facility planning. The percentage of the operating budget for the maintenance and management of school facilities has steadily decreased, creating a capital renewal crisis as a result of years of deferred maintenance at all levels of education.

Best practice requires that a comprehensive facility maintenance program be established and monitored by the school district. The maintenance program often includes several distinct programs, including deferred, preventive, repair/upkeep, and emergency maintenance. Responsibility for facility management is divided between the district office and the school site, with the principal being the primary administrator responsible for the day-to-day operation of the school, including custodial, food, and transportation services. Custodians are typically hired by the school district but managed by the principal. Custodial staff is generally responsible for cleaning the building; monitoring the mechanical, electrical, and plumbing systems; and providing general maintenance of both building and grounds. District staff is responsible for long-term maintenance programs and the procurement of outsourced services for specialized maintenance projects.

Several environmental quality issues have emerged over the past few decades, such as classroom acoustics, indoor air quality, water quality, energy conservation, and abatement of asbestos, radon, and other hazardous materials. Many of these issues require the services of facility consultants hired through the district. Other issues for the building-level administrator include safety and security, vandalism and threats, and acts of violence and terrorism. All of these functions must be conducted within a constantly changing set of government mandates, such as energy deregulation, accessibility guidelines, codes, and other regulations and guidelines at the state and federal levels.

A comprehensive maintenance plan is established to develop, maintain, and/or improve the maintenance program of the public school system to support the delivery of educational programs and services and to provide a safe and healthy environment as effectively and efficiently as possible.

Page 35: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

6—2

The following is an evolving list of renovation and modernization needs for Augusta County Schools that will need to be funded through the school division’s operational budget. Not all items can be funded in a fiscal year, thus budgeting to meet these needs will be on-going. The list does not take into account any potential mothballing of sites.

SCHOOL PRIORITY ITEM DESCRIPTION COST

ESTIMATE

RES 0Pending School Board Recommendation to Pursue Construction of New Facility

HKC 0Refer to "Infrastructure" Spreadsheet for Other Improvements Needed for This Facility

VES 0Refer to "Infrastructure" Spreadsheet for Other Improvements Needed for This Facility

SDHS 1 Extend Fence on Softball Field 9,000$ WMHS 1 Improve ADA Accessibility at Softball Field Restrooms 1,000$

BME 1 Install New Fire Alarm Panel and Devices 40,000$ BME 1 Install Security System (Does Not Have one) 25,000$ HKC 1 Install Security System (Does Not Have one) 30,000$ VES 1 Install Security System (Does Not Have one) 30,000$

FDHS 1 Install Window Blinds on All South Facing Windows 12,000$ SDHS 1 Refinish New Gymnasium Floor 26,000$ FDHS 1 Rekey All Exterior Doors 12,000$ RHS 1 Remove (2 Sides) and Replace (1 Side) Auxiliary Gym Bleachers 35,000$ SES 1 Remove All Trees Along Lower Border of Parking Lot 7,000$

BGHS 1 Repaint Parking Lot/ Add Crosswalks Across Entrance Road 4,500$ BMMS 1 Repave Tennis Courts 40,000$ BMMS 1 Repave Track 85,000$ BME 1 Replace 3 Sets of Exterior Doors 9,000$

SDMS 1 Replace All Exhaust/Ventilation Fans on Building 9,000$ HKC 1 Replace and Upgrade Telephone System 6,000$

SDMS 1 Replace Boys/Girls Locker Room Baskets and Lockers 15,000$ BGHS 1 Replace Cafeteria Tables 32,000$

SES 1 Replace Cafeteria Tables 32,000$ VES 1 Replace Classroom Vinyl Divider Partitions With Masonry Walls 16,000$ BME 1 Replace Existing Gym Bleachers 30,000$ SDHS 1 Replace Floor Mats at All Entrance Doors 2,000$ SDMS 1 Replace Folding Tables in forum 500$ BGHS 1 Replace Original Ceramic Tile Floor in Restrooms 8,500$ SDHS 1 Replace Parking Lot Curbing 16,000$ BGHS 1 Replace School Intercom System 65,000$ FDHS 1 Replace School Intercom System 75,000$ RHS 1 Replace School Intercom System 65,000$

Page 36: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

6—3

SCHOOL PRIORITY ITEM DESCRIPTION COST

ESTIMATE RHS 1 Replace Science Lab Tables and Chairs 19,500$

BGHS 1 Replace Sidewalk at New Gym Entrance 14,000$ SDHS 1 Replace Sidewalk at New Gym Entrance/Main Sidewalk 4,000$ BMMS 1 Replace Stage Curtains 8,500$ FDHS 1 Replace Student Tables and Chairs (Family/Consumer Sciences) 4,200$ SMS 1 Replace Tables - Math Classrooms 5,000$ FDHS 1 Replace Telephone System 12,000$ RHS 1 Replace Wall Matting in Gymnasium 5,000$ RHS 2 Add Baseball Field Lighting 110,000$

SDHS 2 Add Hallway Security Gates Near Auditorium 16,000$ WMHS 2 Add Hallway Security Gates Near Auditorium 16,000$ SDHS 2 Add Lighting to Soccer Field 120,000$ BGHS 2 Add Softball Field Lighting 140,000$ FDHS 2 Add Softball Field Lighting 140,000$ RHS 2 Add Softball Field Lighting 110,000$ BME 2 Clear-Cut Mature Pine Stand of Trees Beside School/Debris 10,000$

WMHS 2 Clear-Cut Pine Stands at Softball Field and Behind School 10,000$ RHS 2 Construct Athletic Practice Field (Beside RES) 30,000$

FDHS 2 Construct Athletic Practice Fields (Behind SMS) 60,000$ WMHS 2 Construct New Concession Stand on Football Field 220,000$ SDHS 2 Construct New Dugouts on Baseball Field 12,000$ SDHS 2 Construct New Storage Shed (Athletic, Ag, Custodial Storage) 18,000$

WMHS 2 Construct New Storage Shed (Athletic, Ag, Custodial Storage) 18,000$ RHS 2 Construct Pressbox on Softball Field 45,000$

BGHS 2 Construct Road/HC Parking Area at Softball Field 80,000$ SDHS 2 Construct Road/HC Parking Area at Softball Field 40,000$ RHS 2 Construct Ticket Booths(3) on Football Field 30,000$ HKC 2 Evaluate Exterior Condition of Well Water Storage and Pressure Tanks 10,000$ NRE 2 Evaluate Exterior Condition of Well Water Storage and Pressure Tanks 11,000$ CHES 2 Excavate and Construct Track for PE Class/Community Use 75,000$

CHES 2Excavate Bank at Bus Entrance and Plant Crown Vetch or Other Low Maintenance Plant 15,000$

WMHS 2 Fence Remainder of Football/Soccer/Track Area 11,600$ RHS 2 Football Field Bleacher Addition (Homeside) 180,000$ SMS 2 Improve Parking Lot and Site Lighting 75,000$ HKC 2 Improve Parking Lot and Site Lighting 75,000$ VES 2 Improve Parking Lot and Site Lighting 75,000$

BMMS 2 Improved Parking Lot and Site Lighting 75,000$ SDMS 2 Improved Parking Lot and Site Lighting 75,000$ CHES 2 Install Building Automation Controls/Alarms on WWTP 6,000$ CLES 2 Install Ceiling Fans in Outer office/Vestibule W/ A-Frame Ceilings 3,000$ SDES 2 Install Ceiling Fans in Outer office/Vestibule W/ A-Frame Ceilings 3,000$ SDHS 2 Install Door to Require Visitors to go Through Main office 6,000$

WMHS 2 Install Door to Require Visitors to go Through Main office 6,000$ SDHS 2 Install Fence Around Soccer Field 20,000$ RHS 2 Install Generator for Emergency Evac. Shelter Usage 85,000$ RHS 2 Install Irrigation System on Softball Field 16,000$ RHS 2 Install Lighting at Softball Field Parking Area, Athletic Areas 35,000$

Page 37: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

6—4

SCHOOL PRIORITY ITEM DESCRIPTION COST

ESTIMATE BGHS 2 Install Lights on Tennis Courts 40,000$ RHS 2 Install Lights on Tennis Courts 40,000$

WMHS 2 Install Lights on Tennis Courts 40,000$ CHES 2 Install PVC Borders Around Playground 8,000$ CLES 2 Install Ventilation/Exhaust System in Clinic 12,000$ SDES 2 Install Ventilation/Exhaust System in Clinic 12,000$ BME 2 Install Video Surveillance System 35,000$ HKC 2 Install Video Surveillance System 35,000$ CHES 2 Install Video Surveillance System 25,000$ CLES 2 Install Video Surveillance System 25,000$ CRES 2 Install Video Surveillance System 25,000$ NRE 2 Install Video Surveillance System 25,000$ SDES 2 Install Video Surveillance System 25,000$ SES 2 Install Video Surveillance System 25,000$ VES 2 Install Video Surveillance System 25,000$ WES 2 Install Video Surveillance System 32,000$ BGHS 2 Lighting Retrofit of Gymnasiums 15,000$ FDHS 2 Lighting Retrofit of Gymnasiums 15,000$ RHS 2 Lighting Retrofit of Gymnasiums 15,000$ RHS 2 New Storage Building 3,000$

WMS 2 Rebuild Hot Water /Chilled Water Circulating Pumps 25,000$ SMS 2 Refinish Stage Floor in Cafetorium 5,000$ BME 2 Refinish Stage Floor in Cafetorium 2,500$ SES 2 Refinish Stage Floor in Cafetorium 4,000$ BME 2 Reglaze and Paint All Classroom Windows on Old Wing 25,000$ SMS 2 Regrade and Surface Treat Road and Parking Lot (Athletic Field) 60,000$ NRE 2 Regrind Concrete Floors at Expansion Joints and Retile 3,500$ BME 2 Rekey interior Classroom Doors (K/Middle Wing) 1,000$ FDHS 2 Renovation/Addition - Football Field Pressbox 105,000$ CLES 2 Repaint Metal Roofing ( Subcontracted Service) 28,000$ SDES 2 Repaint Metal Roofing ( Subcontracted Service) 28,000$ RHS 2 Repaint Parking Lot/ Add Crosswalks Across Entrance Road 4,500$

SDHS 2 Repaint Parking Lot/ Add Crosswalks Across Entrance Road 4,500$ HKC 2 Repair and Extend Sidewalk at Pod 4 2,000$

BMMS 2 Repair/Repave Main Entrance Road to School 150,000$ SDES 2 Repave Playground 30,000$ SES 2 Replace "Storefront" Exterior Main Entrance Doors 5,000$

CLES 2 Replace Aluminum Storefront Exterior Entrance Doors 6,000$ CRES 2 Replace Aluminum Storefront Exterior Entrance Doors 6,000$ NRE 2 Replace Aluminum Storefront Exterior Entrance Doors 6,000$ SDES 2 Replace Aluminum Storefront Exterior Entrance Doors 6,000$ CLES 2 Replace and Upgrade Telephone System 7,000$ SDES 2 Replace and Upgrade Telephone System 7,000$ FDHS 2 Replace Baseball Field Lighting Poles and Fixtures 110,000$ BGHS 2 Replace Baseball Field Lighting Poles/Fixtures 110,000$

WMHS 2 Replace Baseball Field Lighting Poles/Fixtures 110,000$ WMHS 2 Replace Baseball Field Scoreboard 7,500$ FDHS 2 Replace Bathroom Stall Partitions 18,000$ RHS 2 Replace Bathroom Stall Partitions 18,000$

Page 38: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

6—5

SCHOOL PRIORITY ITEM DESCRIPTION COST

ESTIMATE BMMS 2 Replace Cafeteria Tables 32,000$ CLES 2 Replace Cafeteria Tables 32,000$ FDHS 2 Replace Carpet in Media Center 14,000$ CLES 2 Replace Carpet in Speech Room, Admin., Guidance, Media Center 15,000$ BME 2 Replace Condensate Pumps on Steam Boilers 6,000$ BGHS 2 Replace Domestic Water Booster Pumps and Control 15,000$ WMS 2 Replace Hallway Lockers 50,000$ BGHS 2 Replace incandescent Auditorium House Lighting With LED 6,500$ FDHS 2 Replace incandescent Auditorium House Lighting With LED 6,500$ RHS 2 Replace incandescent Auditorium House Lighting With LED 6,500$

SDHS 2 Replace incandescent Auditorium House Lighting With LED 6,500$ WMHS 2 Replace incandescent Auditorium House Lighting With LED 6,500$

SMS 2 Replace Intercom System and Assoc. Wiring for Two-Way Comm 65,000$ SDMS 2 Replace Intercom System and Assoc. Wiring for Two-Way Comm 65,000$ SDHS 2 Replace interior/Exterior Lighting Control Systems 10,000$

WMHS 2 Replace interior/Exterior Lighting Control Systems 10,000$ BGHS 2 Replace Library Tables 4,000$ SMS 2 Replace Light Fixtures in Tech Ed and Agriculture Shop 7,500$

SDMS 2 Replace Overhead Garage Doors (Tech Ed/Agric. Shops) 4,500$ CLES 2 Replace Recessed Entrance Mats at All Exterior Doors 6,000$ SDES 2 Replace Recessed Entrance Mats at All Exterior Doors 6,000$ CLES 2 Replace Security Alarm System 20,000$ NRE 2 Replace Security Alarm System 20,000$ SDES 2 Replace Security Alarm System 20,000$ CLES 2 Replace Sink Faucets in All "Gang" Bathrooms 8,000$ SDES 2 Replace Sink Faucets in All "Gang" Bathrooms 8,000$

WMHS 2 Replace Soccer Field Lighting Poles/Fixtures 140,000$ RHS 2 Replace Sound System in New Gym 3,000$ SMS 2 Replace Stage Curtains 8,500$

SDMS 2 Replace Stage Curtains 8,500$ RHS 2 Replace Stage Curtains in Auditorium 15,000$ SES 2 Replace Stage Curtains in Cafetorium 10,000$

BGHS 2 Replace Telephone System 12,000$ RHS 2 Replace Telephone System 12,000$ SMS 2 Replace Telephone System 8,000$ CHES 2 Replace Timers and Controls at Wastewater Treatment Plant 3,000$ CLES 2 Replace Two Existing Wooden Playground Structures 170,000$ SMS 2 Replace Water Fountains Throughout Building (ADA) 9,000$

SDMS 2 Replace Water Fountains Throughout Building (ADA) 9,000$ BME 2 Replace Window Shades 10,000$ NRE 2 Replace Window Shades 12,000$

SDMS 2 Replace Wooden Chairs and Tables in Media Center 8,600$ RHS 2 Replace Wooden Chairs in Media Center 4,000$ SES 2 Replace Wooden Playground Structure 80,000$

SDMS 2 Replace/Upgrade Phone System 8,000$ SMS 2 Repoint Masonry on Exterior Walls of Building 25,000$

SDMS 2 Repoint Masonry on Exterior Walls of Building 25,000$ CRES 2 Repoint Masonry on Exterior Walls of Building 25,000$ HKC 2 Repoint Masonry on Exterior Walls of School 25,000$ VES 2 Repoint Masonry on Exterior Walls of School 25,000$

Page 39: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

6—6

SCHOOL PRIORITY ITEM DESCRIPTION COST

ESTIMATE HKC 2 Rework Brick Exterior Over Windows Which Turn Water Inward 40,000$

SDMS 2 Structural Repair of Boiler Room and Shop Walls 90,000$ BME 2 Upgrade Telephone System 6,000$ BGHS 2 Upgrade Video Surveillance System in School 40,000$ FDHS 2 Upgrade Video Surveillance System in School 40,000$ RHS 2 Upgrade Video Surveillance System in School 40,000$

SDHS 2 Upgrade Video Surveillance System in School 40,000$ WMHS 2 Upgrade Video Surveillance System in School 40,000$ BMMS 2 Upgrade Video Surveillance System in School 40,000$ SMS 2 Upgrade Video Surveillance System in School 40,000$

SDMS 2 Upgrade Video Surveillance System in School 40,000$ WMS 2 Upgrade Video Surveillance System in School 40,000$ BMMS 2 Upsize and Replace School Generator (Emerg. Evac. Shelter) 50,000$ SDES 3 Install PVC Borders Around Playgrounds 16,000$ FDHS 3 Refinish Auxiliary Gym Floor 11,000$ RHS 3 Refinish Auxiliary Gym Floor 14,000$

SDHS 3 Refinish Auxiliary Gym Floor 14,000$ WMHS 3 Refinish Auxiliary Gym Floor 14,000$ BMMS 3 Refinish Gym Floor 17,000$ SMS 3 Refinish Gym Floor 17,000$

SDMS 3 Refinish Gym Floor 17,000$ WMS 3 Refinish Gym Floor 19,000$ BME 3 Refinish Gym Floor 15,000$ CHES 3 Refinish Gym Floor 14,000$ CRES 3 Refinish Gym Floor 14,000$ NRE 3 Refinish Gym Floor 15,000$ RHS 3 Refinish New Gym Floor 24,000$

WMHS 3 Refinish New Gymnasium Floor 26,000$ BMMS 3 Refinish Stage Floor in Cafetorium 5,000$ SDMS 3 Refinish Stage Floor in Cafetorium 5,000$ WMS 3 Refinish Stage Floor in Cafetorium and forum 12,000$ WMS 3 Repaint Parking Lot 4,000$ FDHS 3 Repaint Parking Lot Lines 3,500$

WMHS 3 Repaint Parking Lot/ Add Crosswalks Across Entrance Road 4,500$ BGHS 3 Repave Parking Lot (Partial) 60,000$ FDHS 3 Repave Parking Lot (Partial) 60,000$ RHS 3 Repave Parking Lot (Partial) 60,000$

BMMS 3 Repave Parking Lot (Partial) 60,000$ SMS 3 Repave Parking Lot (Partial) 60,000$ BME 3 Repave Parking Lot (Partial) 50,000$ HKC 3 Repave Parking Lot (Partial) 60,000$ CLES 3 Repave Parking Lot (Partial) 60,000$ CRES 3 Repave Parking Lot (Partial) 40,000$ SDES 3 Repave Parking Lot (Partial) 60,000$ SES 3 Repave Parking Lot (Partial) 60,000$ VES 3 Repave Parking Lot (Partial) 60,000$

SDMS 3 Repave Parking Lot(Partial) 60,000$ BME 3 Repave Playground 25,000$ BME 3 Replace All Classroom Area Carpets Used for Instructional Purposes 4,200$ HKC 3 Replace All Classroom Area Carpets Used for Instructional Purposes 4,500$

Page 40: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

6—7

SCHOOL PRIORITY ITEM DESCRIPTION COST

ESTIMATE CHES 3 Replace All Classroom Area Carpets Used for Instructional Purposes 4,500$ CLES 3 Replace All Classroom Area Carpets Used for Instructional Purposes 5,200$ CRES 3 Replace All Classroom Area Carpets Used for Instructional Purposes 4,000$ NRE 3 Replace All Classroom Area Carpets Used for Instructional Purposes 5,000$ SDES 3 Replace All Classroom Area Carpets Used for Instructional Purposes 5,200$ SES 3 Replace All Classroom Area Carpets Used for Instructional Purposes 4,200$ VES 3 Replace All Classroom Area Carpets Used for Instructional Purposes 4,200$ WES 3 Replace All Classroom Area Carpets Used for Instructional Purposes 5,200$ BME 3 Replace All Exhaust/Ventilation Fans on Building 10,000$ HKC 3 Replace All Exhaust/Ventilation Fans on Building 10,000$ CHES 3 Replace All Exhaust/Ventilation Fans on Building 10,000$ CLES 3 Replace All Exhaust/Ventilation Fans on Building 10,000$ CRES 3 Replace All Exhaust/Ventilation Fans on Building 10,000$ NRE 3 Replace All Exhaust/Ventilation Fans on Building 10,000$ SDES 3 Replace All Exhaust/Ventilation Fans on Building 10,000$ SES 3 Replace All Exhaust/Ventilation Fans on Building 10,000$ VES 3 Replace All Exhaust/Ventilation Fans on Building 10,000$

SDES 3 Replace Cafeteria Tables 32,000$ SDMS 3 Replace Carpet in Administration Offices 6,000$ CHES 3 Replace Carpet in Administration, Guidance, and Media Center 22,000$ CRES 3 Replace Carpet in Administration, Guidance, Media Center 17,000$ NRE 3 Replace Carpet in Administration, Guidance, Media Center 20,000$

FDHS 3 Replace Carpet in Administration/Guidance Offices 4,000$ SDHS 3 Replace Carpet in Administration/Guidance Offices 4,500$

WMHS 3 Replace Carpet in Administration/Guidance Offices 7,000$ WMS 3 Replace Carpet in Library 10,000$ WMS 3 Replace Carpet in Main Office 8,000$ SES 3 Replace Carpet in Media Center and Guidance 13,000$

SDES 3 Replace Carpet in Speech Room, Admin., Guidance, Media Center 15,000$ CHES 3 Replace Circulator Pumps in Boiler Room 25,000$ FDHS 3 Replace Domestic Water Softener 6,000$ BGHS 3 Replace Exhaust/Ventilation Fans on Entire Building 12,000$ FDHS 3 Replace Exhaust/Ventilation Fans on Entire Building 12,000$ RHS 3 Replace Exhaust/Ventilation Fans on Entire Building 12,000$ CRES 3 Replace Floor Tile in Old Wing 25,000$ CLES 3 Replace Heat Exchanger 15,000$ SDES 3 Replace Heat Exchanger 15,000$ CRES 3 Replace Hot Water Circulating Pumps 18,000$ BGHS 3 Replace Hot Water Heater 10,000$ FDHS 3 Replace Hot Water Heater 10,000$ RHS 3 Replace Hot Water Heater 10,000$

SDHS 3 Replace Hot Water Heater 10,000$ WMHS 3 Replace Hot Water Heater 10,000$

SMS 3 Replace Hot Water Heater 10,000$ SDMS 3 Replace Hot Water Heater 10,000$ WMS 3 Replace Hot Water Heater 10,000$ BME 3 Replace Hot Water Heater 10,000$ HKC 3 Replace Hot Water Heater 10,000$ CHES 3 Replace Hot Water Heater 10,000$ CLES 3 Replace Hot Water Heater 10,000$

Page 41: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

6—8

SCHOOL PRIORITY ITEM DESCRIPTION COST

ESTIMATE CRES 3 Replace Hot Water Heater 10,000$ NRE 3 Replace Hot Water Heater 10,000$ SDES 3 Replace Hot Water Heater 10,000$ SES 3 Replace Hot Water Heater 10,000$ VES 3 Replace Hot Water Heater 10,000$ WES 3 Replace Hot Water Heater 10,000$ CLES 3 Replace Hot Water/Chilled Water Circulating Pumps 32,000$ SDHS 3 Replace Library Carpet 9,500$

WMHS 3 Replace Library Carpet 9,500$ HKC 3 Replace Sewer Pumps at WWTP 12,000$ CHES 3 Replace Stage Curtains in Cafetorium 10,000$ HKC 3 Replace Well Pump 8,000$ NRE 3 Replace Well Pump 8,000$ SMS 3 Replace Zero-Turn Mower/Riding Mower 12,000$ BME 3 Replace Zero-Turn Mower/Riding Mower 12,000$ BME 3 Replace Zero-Turn Mower/Riding Mower 12,000$ HKC 3 Replace Zero-Turn Mower/Riding Mower 12,000$ CHES 3 Replace Zero-Turn Mower/Riding Mower 12,000$ BGHS 3 Replace/Rebead Domestic Water Softener 4,000$ FDHS 3 Replace/Rebead Domestic Water Softener 4,500$ SMS 3 Replace/Rebead Domestic Water Softener 4,000$ BME 3 Replace/Rebead Domestic Water Softener 4,000$ CHES 3 Replace/Rebead Domestic Water Softener 4,000$ CLES 3 Replace/Rebead Domestic Water Softener 4,000$ NRE 3 Replace/Rebead Domestic Water Softener 4,000$ RHS 3 Replacement Zero-Turn Mower 7,500$

WMHS 3 Replacement Zero-Turn Mower 7,500$ BGHS 3 Replacement Zero-Turn Mower/Riding Mower 7,500$ SDHS 3 Replacement Zero-Turn Mower/Riding Mower 12,000$ CLES 3 Replacement Zero-Turn Mower/Riding Mower 12,000$ NRE 3 Replacement Zero-Turn Mower/Riding Mower 12,000$ SDES 3 Replacement Zero-Turn Mower/Riding Mower 12,000$ SES 3 Replacement Zero-Turn Mower/Riding Mower 12,500$ VES 3 Replacement Zero-Turn Mower/Riding Mower 12,000$ WES 3 Replacement Zero-Turn Mower/Riding Mower 12,000$ FDHS 3 Replacement Zero-Turn Mower/Riding Mower 12,000$ BGHS 3 Sand and Refinish New Gym Floor 24,000$

TOTAL 7,907,100$

Page 42: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—1

Section 7 Funding for Capital Projects

Capital Improvement Program Funding

Traditionally, Augusta County has used two sources for funding school capital projects: loans from the state Literary Fund, or by participating in a general obligation bond sale through the Virginia Public Schools Authority. The General Assembly created the VPSA in 1962 as a political subdivision and an agency of the Commonwealth. The statutory purpose of the VPSA is to provide bond financing to localities to fund capital projects for school purposes. The VPSA sells its bonds to obtain funds to purchase school bonds of localities in Virginia. Under the Virginia Constitution and state statutory law, localities may sell their school bonds to the VPSA without holding a referendum on the question of contracting debt. VPSA financings provide low cost financing and market access to localities which may not otherwise have ready access. Additionally, localities can plan the funding of their construction projects according to the predictable semi-annual schedule of sales to the VPSA, while shifting a significant portion of the administrative costs generally associated with issuing bonds to the VPSA. The following basic schedule provides an outline of the public process necessary for the issuance of general obligation school bonds:

• School Board resolution to request the governing body to take necessary steps to issue a bond to the VPSA.

• Resolution of the governing body to (i) consent to the School Board’s application to the VPSA to participate in the bond sale, and (ii) call a public hearing on the proposed bond issuance.

• Submit the VPSA application form to the Treasury • Publish notice of public hearing on the proposed bond issuance. • Hold public hearing. • Resolution of the governing body to authorize the bond issuance. • File Authorizing Resolution with the Circuit Court • School Board Resolution to consent to the issuance.

The VPSA sets the closing date and provides an estimated financing schedule to coordinate the bond sales of the participating localities. Generally, it requires 6-8 weeks to accomplish the necessary governmental process. Beginning in 1999, additional funding was made available at the state level through lottery proceeds and funds specifically identified for school construction. Due to the economic downturn the state is no longer providing this limited funding for capital projects. Additionally,

Page 43: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—2

no money is available from the state Literary Fund. At this time, it is unclear whether the state will reinstate the funding for school capital projects in the future. Construction Costs

The cost figures utilized to estimate the cost of new and renovated school facilities in the school division are updated annually. When determining these estimates the following are considered:

• Virginia Averages for Construction Costs of School Buildings published annually by the Virginia Department of Education

• Projects currently under design for which detailed cost estimates have been prepared • Recently bid projects • Consultation with architects, contractors, and neighboring school systems • Other construction costs data such as the yearly update of the Building Construction

Cost Data published by R.S. Means Company, Inc. Many factors impact construction costs. Some of the most important are (1) the number of other large construction projects either online or soon to be online, (2) the availability and cost of manpower, (3) the availability and cost of materials, (4) fluctuations in the rate of inflation, (5) location, (6) physical site conditions, (7) resource availability, and (8) the effect of the global economy. Beginning in December 2003, the price of all types of construction materials and labor experienced sharp increases. Prices continued to increase beginning in late 2003 and into 2004, as increasing costs of steel and steel products were being experienced across the United States and in the global market. By the end of 2008, the economy began to significantly slow and the number of construction projects declined. Because of this, costs submitted by the successful bidders generally decreased due to market competition for the minimal work available. As can be seen in Table 10 and Chart 1, the cost of school construction in Virginia has increased at a modest pace from 1993 through 2003. School construction costs then accelerated significantly beginning in 2004 through 2007. This acceleration generally mirrored the overall construction boom (residential, commercial, etc.) during that period. As the economy began to slow, elementary and middle school construction costs also began to decrease in 2008 and 2009. No new high school construction costs were available for 2009. Most recently, state-wide average school construction costs experienced a modest increase in 2010 and 2011, however no middle school costs were available. In 2012, construction costs were available for all school levels and indicated a slight decline at the elementary and high school levels. Middle school constructions costs increased since the last reported data in 2009. This recent data suggests that school construction costs are relatively favorable. In identifying cost estimates to prepare proposed construction budgets, the school system is guided first by the yearly update of the Virginia Averages for Construction Costs of School

Page 44: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—3

Buildings. The information contained in this data is compared to data collected from the other sources listed previously. In addition, other school divisions whose cost data is contained in the Virginia average cost tabulation are consulted to compare information about how those projects compare to projects in the Shenandoah Valley.

Table 10

Year Elementary Middle High1992-1993 67.29$ 69.92$ 76.63$ 1993-1994 74.91$ 74.46$ 67.75$ 1994-1995 88.41$ 84.80$ 89.77$ 1995-1996 86.33$ 86.03$ 91.94$ 1996-1997 97.45$ 102.90$ 106.97$ 1997-1998 93.82$ 102.17$ 98.81$ 1998-1999 102.66$ 86.02$ 114.66$ 1999-2000 107.51$ 104.95$ 118.12$ 2000-2001 110.96$ 111.52$ 130.36$ 2001-2002 105.12$ 112.22$ 120.83$ 2002-2003 116.73$ 113.50$ 131.62$ 2003-2004 124.48$ 125.66$ 131.91$ 2004-2005 153.16$ 175.78$ 157.60$ 2005-2006 171.17$ 168.60$ 183.94$ 2006-2007 180.30$ 169.52$ 205.68$ 2007-2008 179.41$ 195.35$ 176.81$ 2008-2009 170.90$ 180.08$ 209.05$ 2009-2010 160.66$ 142.17$ -$ 2010-2011 164.51$ -$ 210.39$ 2011-2012 176.18$ -$ 210.64$ 2012-2013 179.84$ 182.49$ 218.69$

1 Includes construction, site development, water system, sewage disposal, built-in equipment and demolition. A&E fees, value engineering, construction management fees, cost of site, loose equipment, and furniture are excluded.

Construction Costs Analysis

Virginia Department of Education Construction Cost DataStatewide Average Total Cost/Sq. Ft. 1

Page 45: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—4

Chart 1

Page 46: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—5

The county’s annual school debt ceiling is $7,256,250. Currently, total annual school debt payments exceed this ceiling. However, there are sufficient funds available in the School CIP account to meet current obligations. Years in which the actual debt payments are less than the debt ceiling results in a funds being carried forward for future years. In addition, year-end fund balances from school operations are returned to the appropriating body and requested to be re-appropriated to the school CIP account. Thus, in years where actual debt payments exceed the authorized debt level, there are sufficient funds to meet obligations. Table 11 shows the current projected Analysis of School Debt Schedule and School CIP Fund Balance from fiscal year 2015 through fiscal year 2025. It is important to note that a significant amount of school construction debt (bond series: 1995A, 1995B, 1998A, 1999B, and 1999A) will be retired within the next five years as shown in the Schedule of School Debt (see Table 12).

Page 47: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—6

Table 11

ANALYSIS OF CURRENT SCHOOL DEBT SCHEDULE & SCHOOL CIP FUND BALANCE

Line # 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023 2023-2024 2024-2025

1 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$

2 (7,767,847)$ (7,574,652)$ (6,475,888)$ (6,256,611)$ (6,106,929)$ (5,223,449)$ (4,629,012)$ (4,520,708)$ (4,414,390)$ (4,305,235)$ (4,195,570)$

3 (511,597)$ (318,402)$ 780,362$ 999,639$ 1,149,321$ 2,032,801$ 2,627,238$ 2,735,542$ 2,841,860$ 2,951,015$ 3,060,680$

Line # 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023 2023-2024 2024-2025

4 Beginning CIP Balance (previous year's ending balance) 2,572,085$ 2,530,746$ 2,525,544$ 3,619,106$ 4,931,945$ 6,394,466$ 8,740,467$ 11,680,905$ 14,729,646$ 17,884,707$ 21,148,922$

SOURCES / USES OF FUNDS

5 $ (511,597) $ (318,402) $ 780,362 $ 999,639 $ 1,149,321 $ 2,032,801 $ 2,627,238 $ 2,735,542 $ 2,841,860 $ 2,951,015 $ 3,060,680

6 $ 157,058 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -

7 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200

NET CHANGE IN FINANCIAL POSITION $ (41,339) $ (5,202) $ 1,093,562 $ 1,312,839 $ 1,462,521 $ 2,346,001 $ 2,940,438 $ 3,048,742 $ 3,155,060 $ 3,264,215 $ 3,373,880

PROJECTED SCHOOL CIP ENDING BALANCE (June 30) 2,530,746$ 2,525,544$ $ 3,619,106 $ 4,931,945 $ 6,394,466 8,740,467$ 11,680,905$ 14,729,646$ 17,884,707$ 21,148,922$ 24,522,802$

SCHOOL DEBT SCHEDULE

Authorized Annual Debt

Sum of Current Debt Payments(from Schedule of School Debt - 1992A Series Through 2012A Series)Difference Between Authorized Debt Ceiling and Actual Debt( + / - cash flow)

Description

Description

Difference Between Authorized Annual Debt & Actual Debt Payments(Line 3)

Add: Reimbursement of Interest from 2011 QSCB Loan

Add: Year-End Operational Fund Balance Appropriated to CIP From Previous Fiscal Year

CASH FLOW ANALYSIS OF SCHOOL CIP ACCOUNT

Page 48: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—7

Table 12

Bond Series 1992 A 1993 A 1993 B 1994 A 1995 A 1995 B 1998 A 1999 B 1999 A 2004 A 2004 B 2006 B 2007 A 2011 QSCB 2012 A TOTALAmount

(in millions) $2.33 $3.00 $3.00 $12.00 $6.00 $10.48/($12.5) $13.04/($15.0) $6.02/($7.5) $2.02 $5.875($6.3) $6.454($7.5) $26.610/($27.401)

$12.729 ($13.416) $7.50 $6.6 ($7.567) $121.328

($130.704)Rate 5.85% 5.30% 4.72% 6.17% 5.24% 5.23%(3.0%) 4.77%(3.0%) 5.69%(3.0%) 5.77% 4.20% 3.97%(3.0%) 4.26% 3.00% reimbursable 4.45%

F/Y ------- ------- ------- ------- ------- ------- ------- ------- ------- ------- ------- ------- ------- ------- ------- ------- ------- -------

1993 71,467 - - - - - - - - - - - - - - 71,467 - (71,467)

1994 307,655 327,911 79,998 - - - - - - - - - - - - 715,564 2,435,000 1,719,436

1995 274,695 314,585 398,198 1,011,160 - - - - - - - - - - - 1,998,638 2,435,000 436,362

1996 252,950 320,533 332,570 1,229,205 - - - - - - - - - - - 2,135,258 2,435,000 299,742

1997 232,340 325,715 332,949 1,220,503 628,350 1,033,450 - - - - - - - - - 3,773,307 2,435,000 (1,338,307)

1998 180,232 383,730 342,656 1,219,970 592,050 971,875 - - - - - - - - - 3,690,513 3,690,000 (513)

1999 171,025 253,020 322,111 1,183,370 576,750 953,125 - - - - - - - - - 3,459,401 4,832,250 1,372,849

2000 220,543 240,497 301,876 1,146,770 561,450 934,375 1,274,500 - - - - - - - - 4,680,011 4,832,250 152,239

2001 208,655 228,230 281,986 1,115,018 546,150 915,625 1,166,250 643,705 227,039 - - - - - - 5,332,658 4,832,250 (500,408)

2002 196,835 216,218 257,671 1,078,112 530,850 896,875 1,143,750 583,125 204,225 - - - - - - 5,107,661 4,832,250 (275,411)

2003 204,540 214,205 238,839 1,041,208 515,550 878,125 1,121,250 571,875 199,125 - - - - - - 4,984,717 4,832,250 (152,467)

2004 186,980 207,065 215,496 1,004,302 498,750 859,375 1,098,750 560,625 194,025 - - - - - - 4,825,368 4,832,250 6,882

2005 174,778 199,855 192,859 977,093 480,450 840,625 1,076,250 549,375 188,925 201,415 - - - - - 4,881,625 4,832,250 (49,375)

2006 162,705 197,372 175,773 939,577 462,150 821,875 1,053,750 538,125 183,700 587,102 642,600 - - - - 5,764,729 7,256,250 1,491,521

2007 150,831 189,615 154,176 902,063 445,350 803,125 1,031,250 526,875 178,475 572,057 583,125 - - - - 5,536,942 7,256,250 1,719,308

2008 139,250 181,713 138,114 864,548 430,050 784,375 1,008,750 515,625 173,375 557,013 571,875 2,803,391 - - - 8,168,079 7,256,250 (911,829)

2009 123,108 168,875 117,592 831,493 414,750 765,625 986,250 504,375 167,900 541,967 560,625 2,502,535 1,289,715 - - 8,974,810 7,256,250 (1,718,560)

2010 112,404 151,450 87,990 788,053 399,450 746,875 963,750 493,125 162,050 526,923 549,375 2,429,578 1,166,250 - - 8,577,273 7,256,250 (1,321,023)

2011 101,992 134,575 59,625 749,769 384,150 728,125 941,250 481,875 156,450 511,877 538,125 2,361,747 1,143,750 - - 8,293,310 7,256,250 (1,037,060)

2012 96,728 118,250 37,375 711,485 368,850 709,375 918,750 470,625 150,975 496,833 526,875 2,293,918 1,121,250 780,938 - 8,802,227 7,256,250 (1,545,977)

2013 72,047 97,612 16,125 673,202 353,550 690,625 896,250 459,375 145,312 378,464 515,625 2,226,087 1,098,750 806,250 200,356 8,629,630 7,256,250 (1,373,380)

2014 - - 15,375 639,530 338,250 671,875 873,750 448,125 139,462 466,743 504,375 2,158,258 1,076,250 806,250 501,723 8,639,966 7,256,250 (1,383,716)

2015 - - - - 322,950 653,125 851,250 436,875 133,488 451,697 493,125 2,064,571 1,053,750 806,250 500,766 7,767,847 7,256,250 (511,597)

2016 - - - - 307,650 634,375 828,750 425,625 127,450 436,653 481,875 1,996,741 1,031,250 806,250 498,033 7,574,652 7,256,250 (318,402)

2017 - - - - - - 806,250 414,375 121,350 421,607 470,625 1,928,911 1,008,750 806,250 497,770 6,475,888 7,256,250 780,362

2018 - - - - - - 783,750 403,125 115,250 406,563 459,375 1,795,272 986,250 806,250 500,776 6,256,611 7,256,250 999,639

2019 - - - - - - 761,250 391,875 109,150 391,517 448,125 1,736,861 963,750 806,250 498,151 6,106,929 7,256,250 1,149,321

2020 - - - - - - - 380,625 103,050 376,473 436,875 1,679,031 941,250 806,250 499,895 5,223,449 7,256,250 2,032,801

2021 - - - - - - - - - 356,555 425,625 1,620,951 918,750 806,250 500,881 4,629,012 7,256,250 2,627,238

2022 - - - - - - - - - 341,765 414,375 1,560,958 896,250 806,250 501,110 4,520,708 7,256,250 2,735,542

2023 - - - - - - - - - 326,975 403,125 1,503,708 873,750 806,250 500,581 4,414,390 7,256,250 2,841,860

2024 - - - - - - - - - 312,185 391,875 1,444,380 851,250 806,250 499,295 4,305,235 7,256,250 2,951,015

2025 - - - - - - - - - 297,395 380,624 1,385,300 828,750 806,250 497,251 4,195,570 7,256,250 3,060,680

2026 - - - - - - - - - - - 1,325,138 806,250 806,250 499,324 3,436,962 7,256,250 3,819,288

2027 - - - - - - - - - - - 1,263,208 783,750 806,250 499,313 3,352,521 7,256,250 3,903,729

2028 - - - - - - - - - - - - 761,250 - 500,519 1,261,769 7,256,250 5,994,481

2029 - - - - - - - - - - - - - - 497,168 497,168 7,256,250 6,759,083

2030 - - - - - - - - - - - - - - 500,258 500,258 7,256,250 6,755,993

2031 - - - - - - - - - - - - - - 498,576 498,576 7,256,250 6,757,674

2032 - - - - - - - - - - - - - - 497,874 497,874 7,256,250 6,758,376

2033 501,148 501,148 7,256,250 6,755,103

TOTAL 3,641,760 4,471,026 4,099,354 19,326,431 9,157,500 16,292,825 19,585,750 9,799,330 3,180,776 8,959,779 9,798,224 38,080,545 19,600,965 12,874,688 10,190,766 189,059,719 250,430,750 61,371,031

Bond Series Bond Series1994A Refunding of 1987B Beverley Manor and 1988B School Capital Projects 1999A Churchville Elem1992A Wilson Elem, Hugh Cassell Elem, Riverheads Elem, Stuarts Draft Middle, Beverley Manor Middle 1999B Churchville Elem1993A North River Elem, Stuarts Draft Elem 2004A Wilson Middle (new)1993B North River Elem 2004B Wilson Middle (new)1994A Stuarts Draft Elem (new), Fort Defiance High School, Clymore Elem. 2006B Stuarts Draft High, Wilson Memorial High1995A Riverheads High, Buffalo Gap High, Fort Defiance High 2007A Stuarts Draft High, Wilson Memorial High1995B Riverheads High, Buffalo Gap High, Fort Defiance High 2011 QSCB Wilson Elementary1998A North River Elem, Craigsville Elem, old Stuarts Draft Elem (Stump Elem) 2012A Wilson Elementary

Project Project

CURRENT SCHEDULE OF SCHOOL DEBT

AUTHORIZEDBY

COUNTY

(OVER)/UNDER

Page 49: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—8

Impact of Proposed Projects on School CIP

The School Capital Improvement Fund and projected cash flow analysis will be impacted by the proposed capital projects found in Table 13.

Table 13

In addition, the projected Analysis of School Debt Schedule & School CIP Fund Balance (Table 14) assumes an annual operational savings of $500,000 each from the mothballing of Beverley Manor Elementary beginning in fiscal year 2016-2017 and Verona Elementary in fiscal year 2017-2018 (line 8 of the Cash Flow Analysis schedule). The projected operational savings resulting from the closing of Beverley Manor Middle beginning in fiscal year 2023-2024 is $39,000 which represents the elimination of middle school bus routes from Riverheads and Buffalo Gap to the middle school. Additional savings may be realized, however, an in-depth analysis must be conducted to determine the impact on staffing and other operational costs associated with the closing of Beverley Manor Middle and the opening of two classrooms wings at Riverheads and Buffalo Gap. Beginning in fiscal year 2015-2016, $500,000 annually will be directed toward capital depreciation and infrastructure needs. Any additional operational savings from the mothballing of schools can be directed toward a bus replacement schedule, facilities maintenance needs, or the capital depreciation schedule.

The projected School CIP account ending balance remains positive each year until fiscal years 2024 and 2025. While the Cash Flow Analysis assumes no annual year-end funds from operations, in reality there will be year-end funds which would positively impact School CIP ending balances in future years.

School Type ProjectedCost

FY First DebtPayment

1: Riverheads Elementary New Construction $18.6 million 2016-2017

2: Wilson Middle Classroom Addition $2.2 million 2016-2017

3: Hugh Cassell Elementary New Construction $17.6 million 2017-2018

4: Riverheads & Buffalo Gap Middle New Construction $28.9 million 2023-2024

Page 50: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

7—9

Table 14

ANALYSIS OF PROJECTED SCHOOL DEBT SCHEDULE & SCHOOL CIP FUND BALANCE

Line # 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023 2023-2024 2024-2025

1 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$ 7,256,250$

2 (7,767,847)$ (7,574,652)$ (6,475,888)$ (6,256,611)$ (6,106,929)$ (5,223,449)$ (4,629,012)$ (4,520,708)$ (4,414,390)$ (4,305,235)$ (4,195,570)$

3 (511,597)$ (318,402)$ 780,362$ 999,639$ 1,149,321$ 2,032,801$ 2,627,238$ 2,735,542$ 2,841,860$ 2,951,015$ 3,060,680$

Line # 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 2020-2021 2021-2022 2022-2023 2023-2024 2024-2025

4 Beginning CIP Balance (previous year's ending balance) 2,568,858$ 2,526,581$ 2,021,380$ 1,704,504$ 921,149$ 287,477$ 537,285$ 381,530$ 334,078$ 392,946$ (429,199)$

SOURCES / USES OF FUNDS

5 $ (511,597) $ (318,402) $ 780,362 $ 999,639 $ 1,149,321 $ 2,032,801 $ 2,627,238 $ 2,735,542 $ 2,841,860 $ 2,951,015 $ 3,060,680

6 $ 156,120 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ -

7 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200 $ 313,200

8 $ - $ - $ 550,000 $ 1,100,000 $ 1,100,000 $ 1,100,000 $ 1,100,000 $ 1,100,000 $ 1,100,000 $ 1,139,000 $ 1,139,000

9 $ - $ (500,000) $ (500,000) $ (500,000) $ (500,000) $ (500,000) $ (500,000) $ (500,000) $ (500,000) $ (500,000) $ (500,000)

10 $ - $ - $ - $ - $ - $ - $ (1,000,000) $ (1,000,000) $ (1,000,000) $ - $ -

11 $ - $ - $ (1,305,969) $ (1,305,969) $ (1,305,969) $ (1,305,969) $ (1,305,969) $ (1,305,969) $ (1,305,969) $ (1,305,969) $ (1,305,969)

12 $ - $ - $ (154,469) $ (154,469) $ (154,469) $ (154,469) $ (154,469) $ (154,469) $ (154,469) $ (154,469) $ (154,469)

13 $ - $ - $ - $ (1,235,755) $ (1,235,755) $ (1,235,755) $ (1,235,755) $ (1,235,755) $ (1,235,755) $ (1,235,755) $ (1,235,755)

14 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ (2,029,167) $ (2,029,167)

NET CHANGE IN FINANCIAL POSITION $ (42,277) $ (505,202) $ (316,876) $ (783,354) $ (633,672) $ 249,808 $ (155,755) $ (47,451) $ 58,867 $ (822,145) $ (712,480)

PROJECTED SCHOOL CIP ENDING BALANCE (June 30) 2,526,581$ 2,021,380$ $ 1,704,504 $ 921,149 $ 287,477 537,285$ 381,530$ 334,078$ 392,946$ (429,199)$ (1,141,679)$

Annual debt payments for Riverheads and Cassell elementary, Wilson Middle, and Riverheads/Buffalo Gap middle schools based upon straight-line amortization.

Difference Between Authorized Debt Ceiling and Actual Debt( + / - cash flow)

Description

Authorized Annual Debt

Sum of Current Debt Payments(from Schedule of School Debt - 1992A Series Through 2012A Series)

SCHOOL DEBT SCHEDULE

CASH FLOW ANALYSIS OF SCHOOL CIP ACCOUNT

Less: Technology Infrastructure

Description

Difference Between Authorized Annual Debt & Current Actual Debt Payments (Line 3)Add: Year-End Operational Fund Balance Appropriated to CIP From Previous Fiscal Year

Add: Reimbursement of Interest from 2011 QSCB Loan

Less: Additional Debt - Wilson Middle ($2.2 million)

Less: Capital Depreciation / Infrastructure

Add: Capital Charge from Operations[Projected Savings from Mothballing Schools ($550,000 each)]

Less: Additional Debt - Riverheads Elementary ($18.6 million)

Less: Additional Debt - Riverheads & Buffalo Gap Middle Schools ($28.9 million)

Years shaded in purple represent the opening of a new facility.

Less: Additional Debt - Hugh Cassell Elementary ($17.6 million)

Page 51: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

8—1

Section 8 Summary & Timeline of Implementation

Ten-Year Plan Summary

The division’s ten-year plan addresses the need for new and renovated facilities, the potential for operational efficiency gains, increased utilization of student capacities, and directs funds toward facility maintenance and infrastructure needs. Specific initiatives addressed in this plan are:

• Proceed with the design phase of a new 750-student capacity Riverheads Elementary School in the fall of 2014 with construction to be completed for the opening of the 2016-2017 school year.

• Initiate a division-wide boundary line study in the fall of 2014 to review elementary, middle, and high school attendance zones with an effort being made to increase utilization of capacity.

• Allocate $500,000 per year to capital deprecation / infrastructure needs beginning in fiscal year 2015-2016.

• Mothballing of Beverley Manor Elementary School in 2016 following the opening of the new Riverheads Elementary School – with consideration given to alternative uses such as a site for the Shenandoah Valley Governor’s School or to house the Augusta County Department of Parks and Recreation or other community based services.

• Addition of eight classrooms to Wilson Middle School for the opening of the 2016-2017 school year.

• Renovation/new construction of Hugh Cassell Elementary with a capacity of 750 students with completion in the summer of 2017.

• Mothballing Verona Elementary School in 2017 following the renovation/construction of Hugh Cassell Elementary.

• Allocate $1,000,000 per year for three years Technology Infrastructure upgrades beginning in fiscal year 2020-2021.

• Construction of middle school wings at Riverheads and Buffalo Gap High Schools to open for the 2023-2024 school year followed by the mothballing of Beverley Manor Middle School.

A timeline for implementing the ten-year facilities plan in provided in Chart 2.

Page 52: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

8—2

Chart 2

Page 53: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

8—3

The Ten-Year Capital Facilities Plan is to be used as a management tool. It allows for the review of factors that influence the formulation of Capital Budgets and the Capital Improvement Program. It identifies a time-line for future facilities planning and provides information that the community and the School Board need as they work toward addressing facilities-related issues and setting school system priorities.

Specifically, the plan addresses the following:

• The Need to Replace Facilities • Elimination of “Pod-Type” Facilities • The Need to Initiate Attendance Zone Review • Current Overcrowding • Flexibility for Future Increases in Enrollments • Vertical Alignment • Operational Efficiencies and Cost Savings • Increased Instructional Time • Reduction in Bus Travel / Deadhead Miles • Increased Utilization of School Capacities • Funding for Facility Infrastructure • Funding for Technology Infrastructure • Facility Maintenance Needs • Requires NO Increase in Annual Funding of Debt • Assumes NO Year-End Fund Balances from Operations

Page 54: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

8—4

The implementation of this facilities plan in association with previous construction phases will allow Augusta County Schools to have addressed renovation and construction needs throughout the division. The initial three middle schools were built in 1978 and in the 1980s followed by capital project phases I through VI from 1992 through 2013 (see Table 15).

Table 15

Phase I: 1992-1994: $2,433,991 CostsCassell Elementary School - Four additional classrooms 387,511$ Riverheads Elementary School - Two additional classrooms 209,058$ Wilson Elementary School - Additional library, two classrooms, HVAC/window replacement 939,522$ Beverley Manor Middle School - Four additional classrooms 210,680$ Stuarts Draft Middle School - Construction of eight classrooms 687,220$

Phase II: 1993-1996: $14,670,307 CostsClymore Elementary School - New school 7,501,573$ Stuarts Draft Elementary School - New school 7,168,734$

Phase III: 1994-1997: $25,239,380 CostsBuffalo Gap High School - New gym, HVAC replacement 8,413,480$ Fort Defiance High School - Ten additional classrooms, gym, library, major renovation, HVAC/window replacement 8,813,550$ Riverheads High School - New gym, HVAC/window replacement 8,012,350$

Phase IV: 1998-2000: $24,321,529 CostsCraigsville Elementary School - New gym, four additional classrooms, HVCA replacement, major renovation 3,927,435$ North River Elementary School - New gym, library, resource rooms, additional classrooms, major renovation 5,340,984$ Stump Elementary School - Major renovation, added library computer room, and resource rooms 5,690,071$ Churchville Elementary School - New school 9,363,038$

Phase V: 2000-2009: $58,012,712 CostsWilson Middle School - New school 12,712,641$ Stuarts Draft High School Field House 908,670$ Wilson Memorial High School Field House 961,660$ Buffalo Gap High School Field House 607,526$ Riverheads High School Field House 388,948$ Stuarts Draft High School - Eight additional classrooms, new gym, major renovation 21,386,863$ Wilson Memorial High School - Six additional classrooms, new gym, major renovation 21,046,404$

Phase VI: 2012-2013 CostsCassell Elementary School - Kitchen renovation and electrical power upgrade (fire) 861,905$ Wilson Elementary School - Major renovation, added gym, library, music & art rooms, additional classrooms 14,953,180$ Cassell renovation is the net of total construction costs ($1,188,582) minus the insurance reimbursement ($326,677)

Augusta County School BoardCapital Projects

Page 55: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

8—5

Funding the Depreciation Schedule

In the past the School Board has not had the opportunity to fund its depreciation schedule (infrastructure needs). This ten-year facilities plan is the initial step in addressing the need to fund depreciated assets and invest in infrastructure needs. While allowances have been made in this plan to address the ongoing need to invest in infrastructure, the needed improvements are greater than available resources. There is no doubt that facilities maintenance and infrastructure needs will continually be evolving and the associated costs of these needs is unclear the further projections are made into the future. Ongoing efforts must be maintained to direct additional monies to fund the division’s deprecation schedule. Sources of these funds may be any savings from the refinancing of debt obligations, year-end operational savings, or additional funding from the governing body. As older debt obligations are retired in years that extend beyond the scope of this plan, funding opportunities will exist to channel increased funding toward infrastructure needs. One option that could be implemented in the near-term would be to develop a “capital charge” budgeting concept to develop a reliable source of capital renewal funding. An annual amount would be incorporated into the operating budget and defined as a charge to create a reserve for funding capital renewal and debt reduction. Operational savings realized from the mothballing of facilities could allow funds to be earmarked for this purpose. This funding mechanism is incorporated into the Cash Flow Analysis of School CIP Account on page 7−9.

Page 56: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

Appendices

Page 57: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

A—1

Appendix A Useful Life

(Yrs)A SUBSTRUCTURE

Foundations 100+Excavation, waterproofing, insulation (vertical) 30-40

B SHELLExterior sealant 10-15Exterior metal panels 30+Expansion joint covers 40+

ENCLOSURE - WINDOWSMetal frame 20Aluminum CW or storefront See breakdown

Aluminum CW or storefront -- frame (60%) 50Aluminum CW or storefront -- IGU (40%) 20

Operable or fixed steel window See breakdownSteel frame -- frame (70%) 80

ENCLOSURE - EXTERIOR DOORSFrame (25%)

Aluminum Storefront 50Painted Steel Frame 45

Door (35%) See breakdownWood Door 30Aluminum Storefront Door 50Painted Steel Door 45Card Access - Card Reader 8-10Card Access - Server/Software 3-5Automatic ADA Door operator 15Mechanical (Non-CA) - Knob Set or Cylinder lock

Academic Buildings 30-50Butt Hinges 20+Overhead Closer 10-15Panic Bar 15-20

ROOF COVERINGSMetal roof (Copper or pnt mtl, flat or standing seam) 40-50Flat roof See breakdown

Built up - (Tremco) 30+Rubber - EPDM 15Elastomeric 10Modified Bituminous 10-15Thermoplastic 25-30

ROOF OPENINGSSkylights 20-40

BUILDING COMPONENT USEFUL-LIFE STANDARDS

Page 58: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

A—2

C INTERIORSINTERIOR CONSTRUCTION - PARTITIONS

Drywall or plaster on stud partitions 75Plaster or paint finish masonry partitions 80+Toilet partitions 40

INTERIOR CONSTRUCTION - INTERIOR DOORSFrame (25%)

Academic Buildings 30-50Door (35%)

Academic Buildings 30-50Hardware (40%)

Academic Buildings 30-50INTERIOR FINISHES - WALLS

Brick and stone 80Ceramic tile 40Plaster on masonry 60-80Plaster on studs 60Paint - paint only

Dorms 2Academic/Administrative Buildings 3-6

Plywood Paneling 40Wainscot 80

INTERIOR FINISHES - FLOORSCarpet - Dorms & Food Service Areas 6 (+/-)Carpet - Academic, Administrative and Athletics 15VCT 20Epoxy Flooring 20Seamless floors 15Access floors 25Wood floors - new and refinishing 80Resinous athletic flooring 10Terrazzo and stone 80

INTERIOR FINISHES - CEILINGSPlaster 80Drywall 60Acoustic tile 20Metal pan sanitary ceiling 20

Page 59: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

A—3

D SERVICESCONVEYING

ElevatorsElevator cab 40Controls 20Piston 30Pumps 30

Wheelchair lift 15PLUMBING

General See breakdownFixtures 30

Tankless WC, urinal or lav 35Lav faucet 10Shower head 10Stainless steel sink 40Photo sinks 20Drinking fountain 20

Equipment (pumps) 20Circulation pump 20Sump pump 20

Water Heater 15Distribution Systems

Horizontal piping and insulations (40% of piping) 30Vertical piping and insulation (60% of piping) 60Elbows and fittings 15Domestic Water Distribution

Drinking Water System 50Piping - copper 50Piping - plastic 30Piping - steel (galvanized) 30Emergency shower or eye wash 15Compressed air system compressor 25Compressed air piping 75Gas piping - steel 30Pipe insulation 15Valves 10

Sanitary WastePiping - CI waste 35piping/valve repairs and often not replaced.Piping - concrete N/APiping - vitrified tile 30

Rainwater DrainageRoof Drain 40Gutters, drain pipe 20

Page 60: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

A—4

HVACHVAC: GENERAL

Equipment See breakdownLow Pressure Distribution - ducts, insulation, balancing, 25

pipes, terminal units incl radiators, VAVMedium Pressure Distribution -- ducts, insulation, 40

balancing, pipes, valves, dampersHVAC: DISTRIBUTION SYSTEMS

Ventilating Systems, fan & exhaust See breakdownDiffusers, grilles, registers 40Induction and fan coil units 20VAV and double-duct boxes 20Ductwork 40Dampers 20

Pipes, valves, fittings See plumbing reference to this item

Fans, centrifugal 25Fans, axial 20Fans, propeller 15Fans, ventilating roof-mounted - Mushroom type 10Exhaust fan - Bathroom Interior 10

Central AC, including ductwork & piping 15Central Air Handing Unit 25

Heat exchanger, shell and tube 24Heat exchanger, reciprocating compressors 20Molded insulation 20Blanket insulation 20Pumps: base-mounted 15Pumps: pipe-mounted 10Pumps: sump and well 10Pumps: condensate (10 yrs for hp up to 5; use 18 yrs for > 5 hp) 10/18Circulator Pumps 10Electric Motors 18Motor Starters 20

Page 61: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

A—5

HVAC: TERMINAL & PACKAGE UNITSWindow AC units 5Water-cooled package - Fan Coils 20Radiators, convectors, piping 25

Radiant heaters, hot water 25Baseboard radiation / finned radiator 20Unit heaters, gas 13Unit heaters, electric 13Unit heaters, hot water 15Unit heaters, steam 15

Heat pump, commercial air-to-air 15Heat pump, commercial water-to-air 15Rooftop AC: single or multi zone 15Air conditioner, DX package 15Package chillers, reciprocating 15Package chillers, centrifugal N/APackage chillers, absorption N/A

HVAC: CONTROLS & INSTRUMENTATION ControlsControls

Pneumatic receiver controls 10Electronic controls - DDC 15ValvesValve actuators, hydraulic 8Valve actuators, pneumatic 20Valve actuators, self-contained 15

ELECTRICALSwitchgear, panels, feeders 30Branch distribution and devices 30

General Feeder wiring 30Bus duct 30Capacitor 20Power feed wiring mains 30Switchboards and switch units 30Wet type transformers 30Dry type transformers 30Electric transformers 30Circuit breakers 30Reciprocating engines 20Inverters 10

Page 62: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

A—6

Lighting See breakdownLighting conduit and wire 50Branch wiring, EMT and boxes 50Wireway 20Receptacles 20Fixtures 20Lightening protection 25Light dimming panel 15

Fire alarm 20Telephone, Data 25Security 25

FIRE PROTECTIONSprinklers and standpipes 40

Sprinkler heads 20E EQUIPMENT AND FURNISHINGS

EQUIPMENTGlass washing / Cage washing 15-20Fume hoods 15-20Lab casework 60Misc lab equipmentLoading dock 40Food service 15Miscellaneous specialties 15

FURNISHINGSWindow Treatments

Window shades 2Blinds 5Curtains 15

Auditorium seating 20Signage 10Lockers 50Athletic Equipment 10Acoustic motorized partitions 15Furniture - Tables and Chairs 20

F SPECIAL CONSTRUCTION AND DEMOLITIONSelective Demolition N/AHazardous components abatement N/A

Page 63: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

A—7

G SITEWORKStairs See breakdown

Pressure treated lumber 15Concrete stairs 50Concrete with metal stair treads 60

Handrails See breakdownPipe - galvanized 20Pipe - galvanized - painted 30

FencingWood fencing See breakdownMetal fencing See breakdownMetal - chain link 30Metal - painted tubular aluminum 50

Site Furnishings See breakdownBollards 20Steel benches 25Wooden playgrounds 15Metal coated playgrounds 40

SITE UTILITIESCulverts, concrete 75Piping, CI waste 50Storm and sanitary 50Steam, Chilled Water 75Electrical, Tel/Data 50Condensate 25

Page 64: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

B—1

Appendix B - Current Attendance Zones (2014)

Current attendance zones for all schools can be found on line at http://www.augusta.k12.va.us/Page/16075

Page 65: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

C—1

Appendix C - History of Year-End Operational Fund Balances

Fiscal Year Fund Balance

1998-1999 244,324

1999-2000 229,661

2000-2001 190,110

2001-2002 852,303

2002-2003 415,524

2003-2004 371,188

2004-2005 1,097,752

2005-2006 892,770

2006-2007 1,594,153

2007-2008 1,236,765

2008-2009 1,018,996

2009-2010 281,543

2010-2011 304,299

2011-2012 176,224

2012-2013 380,118

2014-2015 156,120

Page 66: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

D—1

Appendix D - Augusta County Profile

THE COMMUNITY

With 73,750 people, Augusta County is the 15th most populated county in the state of Virginia out of 93 counties. The largest Augusta County racial/ethnic groups are White (93.9%) followed by Black (4.0%) and Hispanic (2.2%). In 2012, the median household income of Augusta County residents was $50,971. Augusta County The median age for Augusta County residents is 44.7 years.

Economy Augusta County has a diverse economy. While manufacturing accounts for approximately 30% of the jobs in the County, the governmental, services, and trade sectors are also very strong. In fact, the Augusta Correctional Center and Target are two of the County's largest employers. Please see our Links page for the area's other major employers. Agriculture Agriculture has traditionally been an important part of the County's economy. As of January 1, 2000, Augusta County had 29,000 beef cows and 8,800 sheep and lambs, ranking first in both categories in Virginia. According to the latest Census of Agriculture, there are 1,691 farms in Augusta County covering more than 306,048 acres. The average farm in the County is 188 acres. The market value of agricultural products sold was over $143,914 million in 2006. Tourism Another significant component of the area's economy is tourism. Attracted by the scenic beauty of the area and the easy accessibility via the interstate system, thousands of tourists visit the area each year. The economic benefit of the tourism industry is significant. In 1999, visitors spent more than $60 million in the County and generated over $2.5 million in local meals and lodging taxes. Income In 1998, the adjusted gross income for married couples in the County was $43,190. The per capita personal income for the Augusta-Staunton-Waynesboro area in 1999 was $23, 612. While total income is important, a better indicator of the wealth in a community is the effective buying income of households. In 1999, the effective buying income of Augusta County households was $32,834. Twenty-four percent of households in the County had a buying income of $50,000 or more. Housing According to the last 2000 Census data, there are 18,903 families and 24,818 households in the County. There are more that 26,700 housing units in the County, of which 24,818 are currently occupied. Over 80% of the housing units (20,628) are owner occupied. The average household size in the County is 2.57.

Page 67: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

D—2

Retail Sales In 2000, taxable sales in Augusta County exceeded $316 million, up 2.6% from 1999. Not surprisingly, the highest amount of sales comes in the food group sector which includes grocery stores and restaurants. Other leading sectors include general merchandise and machinery, equipment, and supplies. Labor Force Augusta County has a labor force of nearly 32,000 workers. Combined with the Cities of Staunton and Waynesboro, the area labor force is over 52,000 strong. The County's unemployment rate is traditionally lower than both the state and federal unemployment figures. Employers / Employment

0 to 4 employees 928 5 to 9 employees 284 10 to 19 employees 193 20 to 49 employees 129 50 to 99 employees 46 100 to 249 employees 18 250 to 499 employees 10 500 to 999 employees ***1,000 and over employees ***

0 to 4 employees 1,575 5 to 9 employees 1,893 10 to 19 employees 2,703 20 to 49 employees 3,824 50 to 99 employees 3,129 100 to 249 employees 2,573 250 to 499 employees 3,704 500 to 999 employees ***1,000 and over employees ***

Note: Asterisks (***) indicate non-disclosable data.

Employers by Size of Establishment

Employment by Size of Establishment

Source: Virginia Employment Commission, Quarterly Census of Employment and wages (QCEW), 4TH Quarter (October, November, December) 2013.

Page 68: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

D—3

1. Augusta County School Board 26. Middle River Regional Jail2. Augusta Medical Center 27. Cerro Fabricated Products Inc.3. Hershey Chocolate of Virginia 28. Schick Manufacturing Inc.4. McKee Foods Corporation 29. Staunton-Augusta Dept. of Social Services5. Target Corp 30. Wilson Trucking Corporation6. AAF McQuay, Inc. 31. Blue Ridge Lumber Company7. Hollister, Inc. 32. Cracker Barrel Old Country Store8. Blue Ridge Community College 33. Carded Graphics, LLC9. County of Augusta 34. Augusta County Service Authority

10. J. B. Hunt Transport 35. The Bradford Cothetalley Group11. Woodrow Wilson Rehabiliation Center 36. Packaging Services, Inc.12. Variform Inc. 37. Virginia Department of Corrections13. Augusta Correctional Center 38. Neuman Aluminium Impact14. NIBCO of Virginia 39. Autumn Corporation15. Valley Community Services 40. Augusta Nursing & Rehab Center16. U.P.S. 41. Shenandoah Landscape Services, Inc.17. Innovative Refrig. Systems Inc. 42. Valley Vocational-Technical Center18. Augusta Medical Group 43. Rexnord Industries19. McKee Foods Transportation 44. UVA Health Services Foundation20. Staffing Concepts National 45. Virginia Eagle Dis. Co., LLC21. System One Holding 46. Adams & Garth Staffing22. Food Lion 47. C. Obaugh Buick GMC23. Houff Transfer, Inc. 48. Neuman USA24. Pactiv Corporation 49. Postal Service25. McDonald's 50. B & S Contracting

50 Largest Employers

Source: Virginia Employment Commission, Quarterly Census of Employment and wages (QCEW), 4TH Quarter (October, November, December) 2013.

Page 69: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

D—4

Page 70: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

D—5

- 1,000 2,000 3,000 4,000 5,000 6,000 7,000

Under 5 years5 to 9 years

10 to 14 years15 to 19 years20 to 24 years25 to 29 years30 to 34 years35 to 39 years40 to 44 years45 to 49 years50 to 54 years55 to 59 years60 to 64 years65 to 69 years70 to 74 years75 to 79 years80 to 84 years

85 years and over

Population by Age

Augusta County: Population by Age

Under 5 years 3,839 5 to 9 years 4,323 10 to 14 years 4,655 15 to 19 years 4,769 20 to 24 years 3,654 25 to 29 years 3,905 30 to 34 years 3,995 35 to 39 years 4,679 40 to 44 years 5,239 45 to 49 years 6,201 50 to 54 years 6,049 55 to 59 years 5,563 60 to 64 years 5,040 65 to 69 years 4,002 70 to 74 years 2,890 75 to 79 years 2,133 80 to 84 years 1,558 85 years and ove 1,256 Total 73,750

Source: 2010 Census

Page 71: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

D—6

Page 72: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

D—7

2020 2030 % ChgUnder 5 years 3,878 4,198 8.25%5 to 9 years 4,327 4,733 9.38%10 to 14 years 4,913 5,049 2.77%15 to 19 years 4,726 4,813 1.84%20 to 24 years 3,640 3,908 7.36%25 to 29 years 4,445 4,482 0.83%30 to 34 years 4,772 4,836 1.34%35 to 39 years 4,986 5,775 15.82%40 to 44 years 4,675 5,683 21.56%45 to 49 years 5,177 5,613 8.42%50 to 54 years 5,614 5,097 -9.21%55 to 59 years 6,533 5,549 -15.06%60 to 64 years 6,315 5,963 -5.57%65 to 69 years 5,357 6,400 19.47%70 to 74 years 4,504 5,743 27.51%75 to 79 years 3,174 4,322 36.17%80 to 84 years 1,877 2,976 58.55%85 years and over 1,745 2,440 39.83%

Total 80,658 87,580 8.58%

School Age: 5 to 19 years 13,966 14,595 4.50%

Source: Virginia Employment Commission

Population Projections by Age

Page 73: Augusta County Public SchoolsTen-Year Capital Facilities Plan · Ten-Year Capital Facilities Plan . 2015-2025. ... technology upgrades, ... The School Board administrative and instructional

D—8