33
AFRICAN DEVELOPMENT BANK COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL REPORT Emergency Community Development Programme Support Project (PA PUDC) RDGW September 2018 Translated Document Public Disclosure Authorized Public Disclosure Authorized

b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

AFRICAN DEVELOPMENT BANK

COUNTRY : REPUBLIC OF SENEGAL

PROJECT APPRAISAL REPORT

Emergency Community Development Programme Support Project (PA – PUDC)

RDGW

September 2018

Translated Document

Pu

blic D

isclosu

re Au

tho

rized

P

ub

lic Disclo

sure A

uth

orized

Page 2: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

TABLE OF CONTENTS

Project Summary ............................................................................................................................ v

I. Strategic Orientation and Rationale ..................................................................................... 1

1.1 Project Linkages with Country Strategy and Objectives ............................................ 1

1.2 Rationale for Bank Intervention .................................................................................... 1

1.3 Aid Coordination ............................................................................................................. 2

II. Project Description ................................................................................................................. 3

2.1. Description of the first operation of the Emergency Community Development

Programme Phase 2 ................................................................................................................... 3

2.2. Objectives of the first operation of the Emergency Community Development

Programme Phase 2 ................................................................................................................... 4

2.3. Description of the Bank’s Intervention ......................................................................... 4

2.4. Technical Solutions Adopted and Alternatives Considered ........................................ 5

2.5. Project Type ..................................................................................................................... 6

2.6. Project Cost and Financing Arrangements ................................................................... 6

2.7. Project Area and Beneficiaries ....................................................................................... 8

2.8. Participatory Approach to Project Identification, Design and Implementation,

including the private sector and civil society ........................................................................... 8

2.9. Bank Group Experience and lessons learned from Project Design ............................ 8

2.10. Key Performance Indicators ....................................................................................... 9

III. Project Feasibility ................................................................................................................... 9

3.1. Economic and Financial Performance............................................................................ 9

3.2. Environmental Impact .................................................................................................. 10

IV. IMPLEMENTATION .......................................................................................................... 13

4.1. Implementation Arrangements ........................................................................................ 13

4.2. Project Monitoring ........................................................................................................ 15

4.3. Governance..................................................................................................................... 16

4.4. Sustainability .................................................................................................................. 16

4.5. Risk Management .......................................................................................................... 17

4.6. Knowledge Building ...................................................................................................... 17

5. LEGAL FRAMEWORK ..................................................................................................... 17

5.1. Legal Instrument ........................................................................................................... 17

5.2. Conditions for Bank Intervention ................................................................................ 18

5.3. Compliance with Bank Policies .................................................................................... 18

6. RECOMMENDATION ....................................................................................................... 18

Annex 1: Comparative Socio-economic Indicators of Senegal ....................................................... I

Annex 2: Table of Bank Portfolio in Senegal as at 30 June 2018 ................................................... II

Annex 3: Map of Project Area ...................................................................................................... IV

Page 3: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

CURRENCY EQUIVALENTS

(July 2018)

UA 1 = XOF 791.41

UA 1 = EUR 1.20

UA 1 = USD 1.41

FISCAL YEAR

1 January – 31 December

WEIGHTS AND MEASURES

1 kilometer (km) = 1 000 m

1 km² = 1 000 000 m²

1 hectare (ha) = 10 000 m²

1 tonne = 1 000 kg

1 kilojoule (kJ) = 1 000 Joule (J)

1 kilovolt (kV) = 1 000 Volt (V)

1 kilovolt-ampere (kVA) = 1 000 Volt – Ampere (VA)

1 kilowatt (kW) = 1 000 Watt

1 Megawatt (MW) = 1 000 000 W = 1 000 kW

1 Gigawatt (GW) = 1 000 000 kW = 1 000 MW

1 kilowatt hour (kWh) = 1 000 Watt hour = 3 600 000 Joules (J)

1 Megawatt hour (MWh) = 1 000 000 Wh = 1 000 kWh

1 Gigawatt hour (GWh) = 1 000 000 kWh = 1 000 MWh

1 tonne of oil equivalent (Toe) = 41 868 Joules = 11 630 kWh

1 million tonnes of oil equivalent (MToe) = 1 000 000 Toe

Page 4: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

ii

ACRONYMS AND ABBREVIATIONS

ADF : African Development Fund

AfDB : African Development Bank

AGEROUTE : Road Management Agency

ANCAR : National Rural Agricultural Council Agency

ANRAC : Agence Nationale pour la relance des activités en Casamance

ARD : Regional Development Agency

AVC : Agricultural Value Chain

BD : Bidding Document

CIF : Collective Interest Fund

CSP : Country Strategy Paper

DCFE : Department of Cooperation and External Financing

DEEC : Department of Environment and Classified Institutions

DTS : Deconcentrated Technical Services

FDL : Local Development Fund

FERA : Autonomous Road Maintenance Fund

GIS : Geographic Information System

GVT : Government

IFAD : International Fund for Agricultural Development

IsDB : Islamic Development Bank

ITA : Institute of Food Technology

LA : Local Authority

MAER : Ministry of Agriculture and Rural Equipment

MEFP : Ministry of the Economy, Finance and Planning

MFFG : Ministry of Women’s Affairs, the Family and Gender

MHA : Ministry of Water Management and Sanitation

MSA : Ministry of Health and Social Action

NGO : Non-Governmental Organization

PCGES : Environmental and Social Management Framework Plan

PNDL : Local National Development Programme

PPC : Community Roads Project

PPDC : Casamance Development Pole Project

PRACAS : Senegalese Agriculture Acceleration Programme

PSE : Emerging Senegal Plan

PUDC : Emergency Community Development Programme

PUMA : Emergency Border Highways and Territory Modernization Programme

SF : Saudi Fund

TFP : Technical and Financial Partner

UA : Unit of Account

WFP : World Food Programme

Page 5: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

iii

PROJECT INFORMATION SHEET

COUNTRY : Republic of Senegal

BORROWER : Republic of Senegal

EXECUTING AGENCY : National Directorate of the Emergency Community Development

Programme (PUDC)

PROJECT NAME : Emergency Community Development Programme Support

Project (PA – PUDC)

PROJECT AREA : Ziguinchor, Kolda, Sédhiou, Kaolack, Louga, Thiès, Diourbel,

Fatick, Kaffrine, Tambacounda, Kédougou and Matam regions

1. Financing Plan

Source Amount (EUR Million) Instrument

AfDB 60.00 AfDB loan to the Republic of Senegal

IsDB 55.5 Loan to the Republic of Senegal

Saudi Fund 37.5 Loan to the Republic of Senegal

Government 9.03 Counterpart Contributions

TOTAL COST 162.03

2. Key AfDB Financial Information

Loan currency Euros (EUR)

Loan type Fully flexible loan

Maturity 20 years

Grace period 5 years

Weighted average maturity**: 12.75 years

Repayments Semi-annual payments at the end of the grace period

Interest rate Base rate + Financing cost margin +Loan margin + Maturity premium. This interest

rate must be greater than or equal to zero.

Base rate Floating (EURIBOR 6 Months revised every 1 February and 1 August or any other

acceptable rate). A free option is available to set the base rate

Financing cost margin Bank's funding cost margin revised every 1 January and 1 July and applied every 1

February and 1 August with the base rate

Loan margin 80 base points (0.8%)

Maturity premium - 0.00% for a weighted average maturity of 12.75 years

Opening fee 0.25% of the loan amount payable no later than the date of signature of the loan

agreement

Commitment fee 0.25% per year of the undisbursed amount. It begins 60 days after the date of signature

of the loan agreement and is payable on the interest payment dates.

Base rate conversion option * In addition to the free option of determining the base rate, the Borrower is offered the

option of returning to the floating rate or adjusting all or part of the disbursed amount

of its loan. Transaction fees are payable.

Ceiling or rate tunnel option * The Borrower is offered the possibility of putting a ceiling or tunnel on the base rate

for all or part of the disbursed amount of its loan. Transaction fees are payable.

Loan currency conversion option * The Borrower is offered the possibility of changing the currency of all or part of its

loan, disbursed or not, into another lending currency of the Bank.

Transaction fees are payable.

Page 6: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

iv

3. Timeframe – Main Milestones (projected)

Economic Analysis EIRR : 27%; NPV @10%: EUR 49.18 million

Financial Analysis FIRR: 11% ; NPV @ 2 % : EUR 86.77 million

Stages Periods

Concept Note Approval June 2018

Project Approval September 2018

Effectiveness December 2018

Completion September 2022

Last Disbursement December 2022

Last repayment December 2048

Page 7: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

v

Project Summary

1. Overview: Drawing lessons from the implementation of two generations of Poverty

Reduction Strategy Papers (PRSPs, PNEDS and SNEDS), the Government of Senegal in 2014

developed a new development model known as Emerging Senegal Plan (PSE). In this new strategy,

emphasis is laid on improving people's living conditions and combating social inequalities.

Furthermore, in order to achieve the PSE objectives, the Government in 2015 developed the

Emergency Community Development Programme (PUDC), which seeks to help improve access to

basic social services for the rural population by building socio-economic infrastructure and

promoting the involvement of local actors in the economic and social development of their areas.

Phase 1 of the programme, to which the Bank contributed with a budget support operation, was

finalized at end December 2017 (the outcomes of Phase 1 are given in Annex A.2.1 of the Technical

Annexes). This project is the Bank's support for the first operation of PUDC Phase 2, which will

be financed along with other donors. It will improve people's living conditions with substantial

support for the development of agricultural value chains and easier access to basic socio-economic

road and energy infrastructure. The project has been coherently designed, drawing lessons from

achievements of Phase 1 of the programme and taking into account interventions planned by other

donors (details of consistency of the operation are given in Annex A.2.1 of the Technical Annexes).

2. The first Phase 2 operation will be implemented over a period of four (4) years. Its total

cost is estimated at EUR 162.03 million. The Bank's contribution, as parallel financing, is estimated

at EUR 60 million, excluding taxes and customs duties. The operation is co-financed with the

Islamic Development Bank (IsDB), the Saudi Fund (SF), and the Government of Senegal.

3. The main expected outcomes of the first operation of Phase 2 include: (i) support for the

establishment of 109 Rural Agricultural Societies (SAR) and 109 farming areas, including

irrigation equipment (5-10 hectares); (ii) the construction of 105 boreholes and drinking water

supply infrastructure ; (iii) the procurement of 799 processing machines for women and young

people; (v) the construction of 710 km of rural roads and 76 solar power stations; (vi) the

installation of 1,023 km of Medium and Low Voltage networks and 190 H61 sub-stations; (vii) the

construction of 70 equipped health posts. The AfDB will finance part of the proposed activities. Its

approach is based on : (i) sustained support for agricultural value chains (tomato, pepper, sweet

potato, onion, etc.) to improve the development of commercial agriculture and help increase

incomes in rural areas; and (ii) the construction of transport and energy infrastructure (rural roads

and rural electrification) and basic socio-economic infrastructure and facilities (water, sanitation

and health) to improve the people's living conditions. The intervention will also lay emphasis on

strengthening community development mechanisms by targeting the involvement of all

stakeholders in the project implementation.

4. The project area will cover several localities in Ziguinchor, Kolda and Sédhiou, Kaolack,

Diourbel, Fatick, Thiès and Kaffrine Tambacounda, Kédougou and Matam regions, and will affect

3 million people. The direct beneficiaries of the project are estimated at 1.5 million people who

live in the project area, as well as people polarized by the localities. The project will help: (i)

increase incomes in rural areas; and (ii) improve people's access to basic social services. As regards

impacts, the development of agricultural activities will help reduce the poverty rate from 67% to

54%, the child mortality rate from 51 to 25%, and the chronic malnutrition rate from 21% to 8%.

Page 8: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

vi

5. Needs Assessment: In Senegal, rural areas have the majority of the population (57%),

who are mainly engaged in agro-pastoral activities. The current trend is for young people to leave

the rural areas and go to the cities in search of jobs, and sometimes even go on illegal emigration.

The country's cereal deficit is huge, and many rural households are vulnerable, with recurrent

rainfall deficits and acute malnutrition rates exceeding the emergency threshold (10%). In addition,

the rural population has poor access to infrastructure (water, health, electrification, transport,

economic services) with large regional disparities. The 187 most isolated rural municipalities are

scattered in 11 of the country's 14 regions. Consequently, access to markets is still limited, and

input and transport costs for agricultural products are still high, with significant post-harvest losses.

In these localities, there are strong regional disparities.

6. Value Added for the Bank: The project design took into account the project document

prepared by the Government for Phase 2, various similar operations of the Bank and other partners in the

country, as well as those provided in the Bank's 2018 lending programme. Given that the PUDC is basically

a multi-sector and cross-cutting programme, the added value for the Bank lies mainly in its intervention

approach based mainly on substantial support for the implementation of value chain activities and provision

of basic infrastructure, equipment and socio-economic services. This operation will therefore complement

those already implemented, ongoing or scheduled under other projects financed by the Bank in areas as

diverse as water and sanitation, rural electrification, rural roads, health and nutrition. In addition, the Bank

will finance technical studies in different sectors, an IEC programme for behaviour change, and capacity

building programmes for stakeholders. Finally, the Bank will be involved in the operation of the Project

Management Unit (PMU), which is in charge of carrying out and monitoring activities.

7. Knowledge Management: The project monitoring and evaluation system will be

common to the other donors involved in the programme, and will generate relevant information on

its impact. It will also be used in monitoring and evaluating the various sectors covered by the

programme. Information from this operation will be discussed and used to fine tune and better plan

the country's development policies and strategies.

Page 9: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

vii

RESULTS-BASED LOGICAL FRAMEWORK

REPUBLIC OF SENEGAL: Emergency Community Development Programme Support Project (PA-PUDC)

Project Goal: Help to develop activities in rural areas and improve people’s access to socio-economic infrastructure

RESULTS CHAIN

PERFORMANCE INDICATORS

MEANS OF VERIFICATION

RISKS/

MITIGATION MEASURES Indicator

Baseline Situation

(2017)

Target

IMP

AC

T Sustainably improve the socio-economic and health conditions

of people in rural areas

1. Poverty rate in rural areas

2. Infant and child mortality rate

3. Chronic malnutrition rate

67%

51‰

21%

(2030)

54 %

25‰

8%

ANSD Reports

PUDC final evaluation reports/

EDS Report

CLM Reports

EF

FE

CT

S

Effect 1: Improved access to basic socio-economic

infrastructure for people in rural areas and in the programme

area.

1.1. Number of additional people, including

vulnerable groups, with access to health

infrastructure as a result of the project

1.2. Number of additional people, including

vulnerable groups, with access to safe drinking

water and sanitation infrastructure as a result of

the project

0

0

(In 2025)

300 000 with 51% women

800 000 with 51% women

Sources:

Reports of the Ministry of

Health, Reports of the Ministry

of Water Resources

PEPAM Annual Reports,

Reports of the Ministry of

Energy

ASER Annual Reports

AGEROUTE Annual Reports

ANDS Reports.

Sources: Reports of the Ministry

of Energy and Ministry of

Transport. ASER, AGEROURE

Reports, ANSD Annual Reports

Risks

- Failure to assign health staff to new health

posts.

Mitigation Measures

- The Senegalese Government has

undertaken to assign the required staff and

include the salaries in the annual budgets

concerned.

Risks

- Delays in procurement

- Poor performance of local businesses

Mitigation

- During Phase 1 of the programme, the

PUDC Management Unit prepared a list of

successful businesses, and will take this into

account during the procurement process.

Effect 2 : Improved access to road and energy infrastructure

for people in the programme area

2.1. Number of additional people with access to

electricity as a result of the project;

2.2. Number of villages opened up by the project

0

0

(In 2025)

300 000 with 51% women

800

Effect 3: Improved access to markets and increased incomes

for producers in the programme area.

3.1.

3.2. % of the population with access to markets

within one hour

3.3. Annual household incomes in rural areas

3.4. Number of jobs created or consolidated by the

programme

27.6

CFAF 684 008

0

(In 2025)

50

CFAF 730 000

6 000 indirect/ 30 000 direct

jobs, with 30% for women

Page 10: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

viii

OU

TP

UT

S

Output 1 : Road and energy infrastructure

A1. Rural roads

A2. Rural electrification

Output 2 : Water supply, health and education facilities

B.1. Health stations equipped

B.2. Boreholes with water towers

B.3. Drinking water supply systems

1. Km of roads

2. Number of solar plants

3. Km of MV/LV lines

1. Number of health posts built

2. Number of new boreholes constructed and

equipped

3. Km of water systems provided

0

0

0

0

0

0

(In 2025)

300

30

300/300

20

40

500

Sources: Quarterly project

progress reports and Bank

supervision reports

Sources: Annual reports of the

Ministry in charge of PUDC

monitoring.

Reports of sector Ministries

concerned with the programme

Sources: ANSD reports

Mitigation

The PUDC Management Unit team acquired

solid experience in procurement during Phase

1. It will also receive training in AfDB

procurement rules and procedures at project

start-up.

Output 3. Market Gardening Areas and Agricultural

Equipment

C.1. Farming areas developed

C.2. Rural agricultural societies (SAR)

C.3. Procurement of harvesting machines / SAR

C.4. Procurement of post-harvest machines

Output 4 : Studies and capacity building

D.1. Development of IEC/CCC

D.2. Preparation of business plans for promoters

D.3. Training of Sector Ministry staff

D.4 Training of Women/Young People’s Groups

D.5 Training of local authorities’ workers

D.6. Capacity building for mutual health insurance companies

D.7 Nutritional surveillance (NS)

D.8 Treatment of cases at community level

1. Number of farming areas developed

2. Number of SARs created and supported

3. Number of machines procured

4. Number of post-harvest machines procured

1. Number of people sensitized

2. Number of business plans prepared

3. Number of Ministry staff trained

4. Number of women and young people trained

5. Number of workers trained

6. Number of mutual health insurance companies

supported

7. Number of children under NS

8. Number of malnourished children under treatment

0

0

0

0

0

0

0

0

0

0

0

0

40

40

100

500

1 500 000 with 50% women

100

50 with 30% women

CFAF 250/day

2 000 with 30% women

100

3 000

At least 80%

Sources: Project activity and

Bank supervision reports

Sources: ANSD Reports

Sources: Project activity and

Bank supervision reports

Risks

- Delays in procurement and poor performance

of businesses

- Failure by beneficiaries to assume ownership

Mitigation

- The PUDC Management Unit team will

receive training in AfDB procurement

procedures at project start-up. In addition, the

project will use AAA option for certain

procurements.

- The various local administrations working in

community development (sub-prefectures,

ARD, NGOs, etc.) will be involved in the

process to ensure proper ownership of the

programme by the population.

COMPONENTS OF AFDB’S INTEREVENTION RESOURCES OF THE FIRST OPERATION OF PUDC, PHASE 2

KE

Y A

CT

IVIT

IES

Components Amounts – EUR Million

A. Value Chains and Infrastructure Development 64.50

B. IEC, Studies and Capacity Building 2.31

C. Project Management 2.22

Total 69.03

Donors Amounts – EUR Million

AfDB 60.00

IsDB 55.50

Saudi Fund 37.5

Government of Senegal 9.03

Total 162.03

Page 11: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

ix

Project Implementation Schedule

Years 2018 2019 2020 2021 2022

Activities / Months

7 8 9 10 11 12 1 2 3 4 5 6 7 8 9

1

0

1

1

1

2 1 2 3 4 5 6 7 8 9

1

0

1

1

1

2 1 2 3 4 5 6 7 8 9

1

0

1

1

1

2

1 2 3 4 5 6 7 8 9

1

0

1

1

1

2 I. Initial Activities

Board Presentation/Approval

Signature and Effectiveness

Fulfilment of conditions precedent to

first disbursement

II. Value Chains and Infrastructure

Development

Procurement (Anticipated

Procurement Action)

A.1-Value chain activities

A2. Rural road works and rural

electrification

A3.1 Water infrastructure works

A.3.2. Other DWS activities

A.3.3 Health post works

A.4. Works control and supervision –

Environmental monitoring

B - IEC, Studies and Capacity

Building

Procurement (anticipated procurement action)

B.1. IEC, Sensitization, Behaviour

Change

B.2. Training of actors

B.3. Studies

C. Project Management

C.1. Rental/ office costs

C.2 PMU salaries

C.2. Office operating costs

C.4 Assistance for ESMP

implementation

C.5 Project audit

Completion Report

Page 12: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

1

BANK GROUP MANAGEMENT REPORT AND RECOMMENDATION TO THE BOARD OF

DIRECTORS ON AN AfDB LOAN FOR THE COMMUNITY DEVELOPMENT PROGRAMME

SUPPORT PROJECT (PA - PUDC)

The Management hereby submits this report and recommendation on a proposal to grant EUR 60 million

AfDB loan to the Republic of Senegal to finance the Emergency Community Development Programme

Support Project (PA-PUDC).

I. STRATEGIC ORIENTATION AND RATIONALE

1.1 Project Linkages with Country Strategy and Objectives

1.1.1 Over the past few decades, Senegal has been marked by major profound changes due to

slowdown in economic growth. Furthermore, the various strategy papers prepared so far have not always

produced convincing results, and most of them have been based on imported paradigms. The country has

also recorded strong demands from the population, especially the rural population, for concrete actions

to improve their living conditions. Consequently, to accelerate progress towards emergence, the

Senegalese Government in 2014 adopted a new development strategy known as the Emerging Senegal

Plan (PSE) for the year 2035. This new medium and long-term economic and social policy reference

framework comprises three pillars: (i) Structural economic transformation and growth; (ii) Human

capital, social protection and sustainable development; and (iii) Governance, institutions, peace and

security. This project, known as the "Emergency Community Development Programme Support Project

(PA - PUDC)" and intended to support agricultural production and processing activities, as well as

improve the living conditions of the population by opening up production areas and strengthening local

governance, is fully consistent with the Emerging Senegal Plan (PSE), particularly pillars (i) and (ii).

1.1.2 The project is also consistent with the CSP (2016-2020) currently being implemented. In view

of its multi-sector nature, the project is based on the two CSP pillars, namely : (i) "Support for agricultural

transformation"; and (ii) "Infrastructure development (Energy, Health and Transport)". The project is

also in line with the Bank's Ten-Year strategy (2013-2022), which focuses on infrastructure development

to promote green and inclusive growth. Finally, it complies with: (i) the Bank's rural development policy;

and (ii) three (3) of the Bank’s five (5) priorities (High 5s), namely: (a) Light up and power Africa, (b)

Feed Africa, (d) Improve the living conditions of the people of Africa. The project is on the list of projects

provided in the CSP. Finally, the project is aligned with the Bank's gender and youth employment

strategies. The project is also complementary to the Electricity Access Improvement Project in semi-

urban and rural areas, as well as the Entrepreneurship and Youth Employment Project, currently being

approved by the Bank.

1.2 Rationale for Bank Intervention

1.2.1 In Senegal, the rural population, which accounts for 57% of the total population, has poor access

to infrastructure (water and sanitation, electricity, health, transport, and economic services), with wide

regional disparities. The 187 most isolated rural municipalities are scattered in 11 of the country's 14

regions. Thus, access to markets is still limited, and input and transport costs for agricultural production

are high, with significant post-harvest losses. The Bank is a major partner for Senegal in financing rural

projects, and has already financed several operations whose implementation has significantly improved

Page 13: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

2

the living conditions of the rural population. Furthermore, the employability of young people and women

is a crucial issue in rural areas.

1.2.2 This has helped to enhance the productive capital, increase food security, and promote the

emergence of production centres. This operation, which has the particularity of being linked to a multi-

sector programme intended mainly for the most vulnerable populations, and which has a cross-cutting

dimension in relation to sector projects already implemented or ongoing, will significantly confirm the

Bank's commitment in Senegal. The Bank's intervention in this Phase 2 of the Programme will therefore

help to further reduce social inequalities, not only by reinforcing the achievements of Phase 1, but also

by extending it to other areas that have not yet been covered. In addition, the Bank's intervention could

help to attract other partners to financing the programme.

1.2.3 The Bank's intervention, whose main objective is to improve the living conditions of the rural

population, will also help to increase their incomes and improve access to infrastructure and socio-

economic facilities. It is based on strong synergy between the various sectors covered, as well as on

pooling successful approaches and capacity building for community development actors.

1.2.4 That is why, in the project area, the various proposed activities will complement and reinforce

the actions already initiated with financing from the Bank and other donors, in particular : (i) the Food

Security Support Project (PASA Lou-Ma-Kaf); (ii) the Multinational Programme for Strengthening

Resilience to Food and Nutritional Insecurity in the Sahel (P2RS); (iii) the PPC/PNDL Project; and (iv)

the Water and Sanitation Sector Project. The list of projects financed by the Bank in the sectors covered

by the PUDC is given in the annex to this report.

1.3 Aid Coordination

1.3.1 Development aid is coordinated by the Government of Senegal, through the Department of

Cooperation and External Financing (DCFE) of the Ministry of the Economy, Finance and Planning.

Coordination is ensured by the Technical and Financial Partners Consultative Committee (CCPTF)

through three levels of consultation: the G50, the G12 and 20 thematic groups. The various sectors

(agriculture, water/sanitation, rural roads, energy, and health/nutrition) covered by the project have sector

groups with designated TFP Leads, and meet regularly.

1.3.2 The main ongoing projects supported by other TFPs and covering sectors similar to the PUDC

are as follows: (i) the Emergency Border Highways and Territory Modernization Programme (PUMA),

the National Rural Roads Programme (PNRR 2014-2018); (ii) the Agricultural Sectors Support Project

- Extension (PAFA E) ; (iii) the Agricultural Development and Rural Entrepreneurship Support

Programme (PADAER) ; and (iv) the Project for Developing Resilience to recurrent Food Insecurity in

Senegal (DRIARS). The list of projects financed by the other TFPs and that relate to the sectors covered

by the PUDC is given in paragraph A.2.3 of the Technical Annexes.

1.3.3 As regards the PUDC specifically, the African Development Bank, the IsDB and the Saudi

Fund are the three donors already committed to financing Phase 2 of the programme with parallel co-

financing interventions. However, to ensure better collaboration between the partners, promote the

pooling of resources, and make management and monitoring of activities more efficient, the Programme

Management Unit will be the same for the various operations.

Page 14: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

3

II. PROJECT DESCRIPTION

2.1. Description of the first operation of the Emergency Community Development

Programme Phase 2

2.1.1 The first operation has been coherently designed and is based on PUDC Phase 2 consistency,

for multi-donor funding. It will be jointly financed (concurrently) by the IsDB, the Saudi Fund, the AfDB

and the Government of Senegal. AfDB's intervention will focus on sustained support for agricultural

value chains and infrastructure development. The main expected outcomes of this first operation include :

(i) support for the establishment of 109 Rural Agricultural Societies (SAR) and 109 farming areas,

including irrigation equipment (5-10 hectares); (ii) the construction of 105 boreholes and drinking water

supply infrastructure ; (iii) the procurement of 799 processing machines for women and young people;

(v) the construction of 710 km of rural roads and 76 solar power plants; (vi) the installation of 1,023 km

of Medium and Low Voltage networks and 190 H61 sub-stations; and (vii) the construction of 70

equipped health posts.

2.1.2 The activities to be financed by the various donors are given in the table below:

Table 2.1: Donor-Financed Activities in the Programme

2.1.3 The first operation of the programme Phase 2, in continuity with Phase 1 and in order to expand

to other sectors, is designed mainly around the following pillars: (i) support for structural transformation

of the agricultural sector; (ii) infrastructure reinforcement; and (iii) improvement of access to basic social

services. The activities under these various pillars were identified following harmonization of PUDC

projections with the programmes of the various technical Ministries concerned, as well as consultations

with stakeholders and beneficiaries.

2.1.4 The operation is designed in a logical and coherent manner, and incorporates full

complementarity with the interventions of the three donors already committed, namely the IsDB, whose

financing was already approved in February 2018, the Saudi Fund, whose financing is expected to be

approved in October 2018, and the AfDB. The total cost of this first operation, including the

Government's contribution, is estimated at CFAF 106.33 billion (EUR 162.03 million). The operation

will be implemented over a four-year period from 2018 to 2022. The interventions of the various donors

will be complementary, and will take place concurrently. The AfDB loan of EUR 60 million will account

for 37.03% of the total cost of the operation, excluding taxes. The contributions by the various donors

already committed to the programme, as well as the amounts and % of financing are given in the table

below:

Donors

Project Activities

Value

Chains

Rural

Electrificatio

n

Water

Supply

Health Rural

Roads

Capacity

Building

Project

Management

Education

AfDB X X X X X X X

IsDB X X X X X X X X

SF X X X X X

Page 15: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

4

Table 2.2: Donor Contributions to Financing the Operation

Sources Amounts

(EUR Million)

Amounts

(UA Million)

Amounts

(CFAF Billion) %

AfDB 60 49.7 39.4 37.0

IsDB 55.5 46 .0 36.4 34.2

SF 37.5 31.08 24.6 23.1

GVT 9.03 7.52 5.95 5.60

Total Cost 162.03 134.3 106.35

2.2. Objectives of the first operation of the Emergency Community Development

Programme Phase 2

2.2.1. The objectives of this first phase 2 operation are in line with the efforts made by the Senegalese

Authorities to improve the living conditions of the population, namely: (i) foster the development of

economic activities in rural areas; (ii) improve the people’s access to basic socio-economic infrastructure

and facilities; and (iii) promote the involvement and mobilization of all stakeholders in community

development.

2.3. Description of the Bank’s Intervention

2.3.1. The Emergency Community Development Programme Support Project (PA - PUDC) is the

Bank's intervention in the first operation of PUDC Phase 2, described above. It is designed in a manner

consistent with the announced interventions of the IsDB and Saudi Fund. The AfDB's intervention will

finance part of the operation’s activities. Its approach is based on : (i) sustained support for agricultural

value chains (tomato, pepper, sweet potato, onion, etc.) to improve the development of commercial

agriculture and increase incomes in rural areas; and (ii) the construction of transport and energy

infrastructure (rural roads and rural electrification) and basic socio-economic infrastructure and facilities

(water, sanitation and health) to improve the people's living conditions. The intervention will lay

emphasis on strengthening community development mechanisms by targeting strong involvement of all

stakeholders in the project implementation.

2.3.2. Given the multisector dimension of the intervention, the project was designed in such a way as

to develop full synergy between the various sectors covered and promote the involvement of several

Government structures in the project implementation. This aspect is developed in paragraph A.2.2 of the

Technical Annexes.

2.3.3. The implementation procedures of the various activities, as well as conditions for handing over

works and infrastructure to Government structures and local authorities which will be responsible for

them, have been discussed between the PUDC, the various technical Ministries, and the Bank. This

information is provided in paragraph B1 of the Technical Annexes.

2.3.4. The project is structured around the following components, as shown in the table below: (A).

Value Chains and Infrastructure Development; (B). IEC, Studies and Capacity Building; and (C). Project

Management.

Page 16: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

5

Table 2.3: Project Components and Activities

2.4. Technical Solutions Adopted and Alternatives Considered

2.4.1. The technical solutions adopted for the project stem from the various studies conducted, the

project document prepared in Phase 2 of the Programme, and the lessons learned from the implementation

of Phase 1. As regards the water supply component, the solution consists in drilling and equipping

boreholes for the supply of drinking water to the population, livestock, and irrigation of horticultural

areas, with surplus flow.

2.4.2. As for horticultural areas, the solution consists in creating areas in line with the existence of

Rural Agricultural Societies (SAR) which operate as private companies with members who are jointly

and severally responsible for the smooth running of the companies and are beneficiaries of the outcomes.

This will ensure better management of the areas, as well as greater profitability of the activities. As

regards rural electrification, the solution consists in mixing, depending on the localities concerned, the

construction of photovoltaic (PV) solar power plants, connection to existing SENELEC electricity

networks, and the installation of solar kits in the few inaccessible localities. The other alternative

technical solutions, their brief description, and reasons for their rejection are given in the table below:

Name of Component Cost in EUR

Million

% Content of Components

A. Agricultural

Value Chains

and

Infrastructure

Development

64.50

93.44

Agricultural Value Chains Sub-Component: (i) Support for the establishment of 40 Rural Agricultural Societies (SAR); (ii) Creation of 40 horticultural areas (5-10 hectares) for agriculture, including

irrigation equipment, (iii) Support for development of 40 farming areas; (iv) Support for the marketing

of SAR products (targeting and updating) ; (v) Support for project promoters, Fund for project financing; (vi) Procurement of start-up kits to support young people and women ; (vii) Construction of 30

warehouses for agricultural products ; (viii) Construction of 5 stores for packaging agricultural products;

(ix) Conduct of a technical and economic feasibility study for the establishment of agricultural platforms; (x) Establishment of 25 agricultural platforms; (xi) Procurement of equipment lots for the 25 agricultural

platforms; (xii) Procurement of 500 processing machines for women and young people; (xiii) Training

of members of the management committee for agricultural platforms and processing equipment; (xiv)

Training of operators of agricultural platform machinery; and (xv) Training for managers of mini dairies.

Road and Energy Infrastructure Sub-Component : (i) 300 km of rural roads; (ii) Support for road

maintenance groups and committees; (iii) Installation of 30 photovoltaic (PV) solar power plants; (iv)

Installation of 300 km of medium-voltage (MV) networks; (v) Installation of 300 km of low-voltage

(LV) networks; (vi) Procurement of 150 H61 sub-stations; (vii) Installation of indoor electricity

networks for 3,000 vulnerable households.

Improvement of Basic Social Services Sub-Component: (i) Conduct of geophysical studies to confirm borehole sites ; (ii) Construction and equipment of 40 new boreholes (ii) Construction and equipment

of 40 water towers (iii) Installation of 800 km of drinking water supply and distribution networks; (iv)

Construction of 80 water troughs; (vi) Establishment of 40 cart sockets; (vii) Establishment of 40 school connections; (viii) Construction of 40 school kiosks; and (ix) Installation of 600 standpipes; (x)

Construction of 20 health posts, with the minimum package of health/nutrition activities.

B. IEC, Support

Studies and

Capacity

Building 2.31 3.34

Project IEC, Sensitization, Behaviour Change: (i) Support for the training of 100 decentralized service

workers; (ii) Capacity-building for 50 local authorities; (iii) Training of trainers for 250 women's groups; (iv) Study on the cost of hunger; (v) Training of 150 CSOs in the project area; (vi) Monitoring and

promotion of growth-revival-disease management; (vii) Institutional support for sector services; (viii)

Support for school canteens in 2 regions; (ix) Support for updating the RNU (Survey); (x) Impact assessments on poverty and social protection; (xi) Capacity-building for mutual health insurance

companies ; and (xii) Institutional support for ANRAC.

C. Project

Management 2.22 3.22

(i) Salaries for PMU members ; (ii) Computer and office consumables ; (iii) Procurement of vehicles; (iv) Fuel, Maintenance and Repair of vehicles ; (v) Project launching, Communication, Advertising,

Survey; (vi) Support to decentralized services for project monitoring and supervision ; (vii)

Miscellaneous (mission expenses, others.); (viii) Project monitoring and evaluation activities ; (ix)

Assistance for ESMP implementation ; and (ix) Project audit.

Page 17: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

6

Table 2.4: Technical solutions adopted and reasons for rejection

Alternative Brief Description Reasons for Rejection

For the water supply

component: use of surface water

Instead of boreholes, use existing surface

water, with treatment of part of the water intended for the population

This solution was rejected for two reasons: (i) Surface water is not available

in all the localities concerned; (ii) Treatment and the required installations would be very costly.

For the farming areas:

community support approach

It consists in providing infrastructure and

various forms of support without

necessarily first having a formal structure for management.

This solution was rejected because it does not allow for proper farming areas

management. Creation of the farming areas depends on the existence of Rural

Agricultural Societies that operate as private companies whose members, who joined voluntarily, are jointly and severally liable.

For rural electrification/ Use of only solar kits

It was possible to think of installing only

solar kits in households, instead of mixing with solar power plants and MV/LV lines.

This solution was rejected, given that this approach is not yet widespread in

Senegal. In addition, sustainability of the kits is not guaranteed because their maintenance often poses problems.

2.5. Project Type

2.5.1. The project is an autonomous, multi-sector investment operation that forms part of the

programme co-financed by donors and the Government of Senegal. The proposed financing instrument

is an AfDB loan, which will be granted to the Government of Senegal.

2.6. Project Cost and Financing Arrangements

2.6.1. The financing of the Community Development Programme Support Project (PA-PUDC), which

is the Bank's intervention, will be provided by the Bank and the Government of Senegal. The total project

cost, exclusive of taxes and duties, is EUR 69.37 million (CFAF 45.28 billion), comprising EUR 49.08

million in foreign currency (71%) and EUR 19.95 million in local currency (29%). It was calculated on

the basis of unit prices of recent completed projects, and includes provision for physical contingencies

(4%) and price escalation (3%). The detailed costs of project activities are given in paragraph B.2 of the

Technical Annexes.

Table 2.5 : Project Cost by Component

Components Cost in CFAF Million Cost in EUR Million Cost in UA Million

% F.E. F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total

A. Value Chains and Infrastructure

Development

A.1Value chains 3 745 3 745 7 489 5.708 5.71 11.42 4.73 4.73 9.46 50

A2. Rural roads and rural electrification 18 108 2 012 20 120 27.61 3.07 30.67 22.88 2.54 25.42 90

A3 Water supply, Sanitation, Health and Social

Protection 7 448 3 192 10 640 11.35 4.87 16.22 9.41 4.03 13.44 70

A.4. Works Control and Supervision –

Environmental Monitoring 387.3 903.7 1 291 0.59 1.38 1.97 0.49 1.14 1.63 30

Total Component A 29 688 9 852 39 540 45.26 15.02 60.28 37.51 12.45 49.96 75

B - IEC, Studies and Capacity Building

B.1. IEC Sensitization, Behaviour Change 120 280 400 0.18 0.43 0.61 0.15 0.35 0.51 30

B.2. Training of actors 33 297 330 0.05 0.45 0.50 0.04 0.38 0.42 10

B.3. Studies 84 196 280 0.13 0.30 0.43 0.11 0.25 0.35 30

B.4. Institutional support operations 82 327 409 0.12 0.50 0.62 0.10 0.41 0.52 20

Total Component B 319 1 100 1 419 0.49 1.68 2.16 0.40 1.39 1.79 22.00

C. Project Management

C.1. Office rental and expenses 0 192 192 0.00 0.29 0.29 0.00 0.24 0.24 0

C.2 Salaries of PMU members 0 360 360 0.00 0.55 0.55 0.00 0.45 0.45 0

C.2. Operating costs of office and other costs 71 635 706 0.11 0.97 1.08 0.09 0.80 0.89 10

Page 18: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

7

Table 2.6 : Project Cost by Source of Financing

Sources of Financing CFAF Million EUR Million UA Million

% in F.E. F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total

AfDB 27 552 11 808 39 360 42.00 18.00 60.00 34.81 14.92 49.73 70%

Government 592 5 331 5 923 0.90 8.13 9.03 0.75 6.74 7.48 10%

Total 28 144 17 139 45 283 42.91 26.13 69.03 35.56 21.66 57.22

2.6.2. The project will be financed by an AfDB loan of EUR 60 million, representing 86.84% of the

total cost of project activities, and a contribution from the Government of Senegal. The Government's

contribution amounts to EUR 9.08 million or 13.16% of the total cost, and will be used to finance part

of the operating costs, particularly the project premises and related costs, the project vehicles and part of

the rural roads and rural electrification costs.

Table 2.7 : Project Cost by Expenditure Category

Table 2.8 : Expenditure Schedule by Project Component (in EUR Million)

Table 2.9 : Expenditure Schedule by Component of the AfDB Loan (in EUR Million)

C.4 Assistance for ESMP implementation 0 50 50 0.00 0.08 0.08 0.00 0.06 0.06 0

C.5 Project audit 10 40 50 0.02 0.06 0.08 0.01 0.05 0.06 20

Total Component C 81 1 277 1 358 0.12 1.95 2.07 0.10 1.61 1.72 6.00

TOTAL BASE COST 30 087 12 230 42 317 45.87 18.64 64.51 38.02 15.45 53.47 71

Physical contingencies (4%) 1 203 489 1 693 1.83 0.75 2.58 1.52 0.62 2.14

Financial contingencies (3%) 903 367 1 270 1.38 0.56 1.94 1.14 0.46 1.60

TOTAL COST 32 193 13 086 45 279 49.08 19.95 69.03 40.68 16.53 57.21 71

Categories CFAF Million EUR Million UA Million

% in F.E. F.E. L.C. Total F.E. L.C. Total F.E. L.C. Total

GOODS 2 137.8 916.2 3 054.0 3.26 1.40 4.66 2.70 1.16 3.86 70%

WORKS 26 504 6 626.1 33 130.3 40.41 10.10 50.51 33.49 8.37 41.86 80%

SERVICES 1 148 2 677.7 3 825.3 1.75 4.08 5.83 1.45 3.38 4.83 30%

OPERATING COSTS 231 2 077.0 2 307.8 0.35 3.17 3.52 0.29 2.62 2.92 10%

TOTAL COST excl. contingencies 30 020 12 297 42 317 45.77 18.75 64.51 37.93 15.54 53.47 71%

TOTAL COST incl. contingencies 32 122 13 158 45 280 48.97 20.06 69.03 40.59 16.63 57.21 71%

Components 2018 2019 2020 2021 2022

A. Value Chains and Infrastructure Development 0 12 18 21 9

B - IEC, Studies and Capacity Building 0 0.6 0.8 0.4 0.2

C. Project Management 0.07 0.7 0.5 0.5 0.3

Total 0.07 13.3 19.3 21.9 9.5

Components 2018 2019 2020 2021 2022

A. Value Chains and Infrastructure Development 0 10 17.3 20 9

B - IEC, Studies and Capacity Building 0 0.6 0.8 0.4 0.2

C. Project Management 0 0.5 0.6 0.4 0.2

Total 0 11.1 18.7 20.8 9.4

Page 19: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

8

2.7. Project Area and Beneficiaries

2.7.1. The project area will cover the southern regions, namely Ziguinchor, Kolda and Sédhiou, as

well as Kaolack, Diourbel, Fatick, Thiès and Kaffrine regions in the central zone, and Tambacounda,

Kédougou and Matam regions, with a population of 3 million inhabitants. The choice of the project area

was guided by three main objectives, namely: (i) the need to build on the achievements of Phase 1; (ii)

complementarity with interventions by other PUDC donors and other projects; and (iii) targeted and

urgent intervention in locations without infrastructure. Complete service packages including the covered

sectors will be implemented for the localities covered by the project in the various regions. The direct

project beneficiaries are estimated at 1.5 million people, 51% of whom are women living in the project

area and in villages polarized by the localities. The project will take into account the needs of women,

men, and young people of all age groups and social categories. The vulnerable population in the project

area will be given priority, particularly with regard to access to drinking water, rural electrification and

health infrastructure.

2.8. Participatory Approach to Project Identification, Design and Implementation,

including the private sector and civil society

2.8.1. The project has been designed to supplement funding from the Government of Senegal and

other donors on the basis of a participatory and inclusive approach so as to take into account the concerns

of the communities that are the final beneficiaries. This approach, which began during discussions with

the National Directorate, the Ministries concerned, civil society and beneficiaries, continued during the

appraisal mission. It will be consolidated during implementation of the various activities under Phase 2.

2.8.2. The mission’s various field visits and meetings with institutional stakeholders and beneficiaries

allowed for better understanding of the population’s expectations, as well as the implementation

constraints that were taken into account in the project design. To ensure consistency and proper

coordination in implementation, discussions were held with the technical and financial partners involved

in financing the project, and public consultations were also held in the project area. Furthermore, it should

be noted that the various project activities were identified thanks to close collaboration between the

PUDC, the various Ministries and support structures concerned with the various components. Thus, for

sectors such as nutrition and social protection, the project will be based mainly on the complementarity

of actions carried out with the Malnutrition Control Unit (CLM) and the Delegation for Social Protection

and National Solidarity (DPSSN).

2.9. Bank Group Experience and lessons learned from Project Design

2.9.1. The performance of the Bank's national public portfolio in Senegal was deemed satisfactory

following the portfolio review in December 2017, with a rating of 3 out of 4. The Bank is Senegal’s

privileged partner in the various sectors covered by the project (Agriculture, Water and Sanitation,

Transport, Rural Electrification and Health). Over the past ten years, the Bank has financed several

operations in rural areas for an amount of about EUR 100 million (CFAF 65.9 billion). It also makes

valuable contribution to sector dialogue and annual sector reviews. The experience gained from the

implementation of projects financed by the Bank in the various sectors mentioned above (PSEA,

PREFELAG, PASA Lou-Ma-Kaf, PPC/PNDL, PROMOVILLES, P2RS and PARDC) has been taken

into account in the project design.

Page 20: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

9

2.9.2. The portfolio has become much younger over the past few years, with the average age of

operations falling from 5.5 years in 2011 to 2.7 years in 2017. Furthermore, there are no problematic

(PP) or potentially problematic (PPP) projects in the portfolio. The sector breakdown of national projects

is as follows: Infrastructure (66.4%), Water and Sanitation (12.6%), Rural Sector (11%), Governance

(6.2%), and Social Sector (3.8%). The portfolio composition is aligned with the pillars of the CSP (2016

- 2020). All Bank-financed projects in the sector are being implemented, they all satisfied to first

disbursement conditions.

2.9.3. The key lessons learned from project implementation in the AfDB's intervention areas are: (i)

the need to improve quality of projects at entry; (ii) compliance with timeframes for procurement, project

implementation and audits; and (iii) poor impact monitoring-evaluation and follow-up after project

completion. The design of this operation has taken these lessons into account through: (i) more accurate

technical studies and cost estimates; (ii) closer monitoring of procurement documents in the project

management unit by reinforcing the PUDC procurement team; and (iii) reinforcement of the project

financial and accounting management team. In addition, the recommendations of the IDEV report on

the evaluation of the Bank Group's strategies and programmes 2004-2013 in Senegal have also been

taken into account in this operation.

2.10. Key Performance Indicators

The existing PUDC monitoring and evaluation system, which was effective during Phase 1, will be

reinforced. Given the multisector dimension of the project and the various interventions (AfDB, IsDB

and SF), the system will be more adapted to the new context with strong synergy between the various

Ministries concerned and the project donors. The selected output indicators are: (i) the number of new

boreholes constructed; (ii) the number of water towers built; (iii) the length of drinking water supply

mains laid; (iv) the number of horticultural areas created; (v) the number of rural agricultural societies

(RAS) established; (vi) the number of solar power plants established; (viii) the number of health posts

built; (ix) the number of people sensitized on behavioural change; (ix) the number of permanent jobs

created; and (xi) the number of studies validated under the various sector support operations.

III. PROJECT FEASIBILITY

3.1. Economic and Financial Performance

Table 3.1: Key Economic Data

Financial Analysis FIRR 11 % FNPV @ 2%: EUR 86.77 million

Economic Analysis EIRR: 27%; ENPV @10%: EUR 49.1 million

Financial Analysis

3.1.1. The project will help improve the people’s living conditions by developing economic activities

around horticultural areas and providing production and processing equipment for agricultural products,

as well as post-harvest equipment. The project will also help improve people's access to transport and

energy infrastructure and basic socio-economic infrastructure. This will also increase the people's

incomes.

Page 21: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

10

3.1.2. At the financial level, the FIRR is estimated at 11%, which is higher than the discount rate of

2%, and the FNPV is EUR 86.77 million (CFAF 56.92 billion), which is positive. The project is therefore

financially viable.

Economic Analysis

3.1.3. The costs used to calculate economic rate of return are those for investment costs, exclusive of

taxes and duties, provisions for price escalation, maintenance costs and other operating expenses. The

main economic benefits are: (i) benefits from socio-economic investments ; (ii) net benefits for the other

actors (Government, suppliers, and enterprises) ; (iii) benefits arising from reduced health expenses. In

addition to the benefits indicated in paragraph 3.1.1 above, the project will contribute to reducing health-

related expenses by improving access to drinking water, sanitation and, especially, health infrastructure.

The project will also help to develop commercial activities by constructing rural roads, electric power

plants, and solar power plants.

3.1.4. Based on the adopted assumptions, the project's economic rate of return (ERR) is estimated at

27%. The NPV of benefits and costs calculated at the rate of 10% is estimated at EUR 49.1 million

(CFAF 32.26 billion), which is positive. The project is therefore economically viable. Details of the

financial and economic analysis are also provided in Annex B.7 of the Technical Annexes.

Sensitivity Analysis

3.1.5. The sensitivity of the project's economic and financial performance was analyzed by simulating

as follows: (i) 10% increase in the project cost due to increase in investment costs; (ii) 10% decrease in

the additional benefits of the project; and (iii) the combination of the two scenarios mentioned above.

The results of the sensitivity analysis show that rates of return and net present values are at acceptable

levels. The FIRR varied from 9% to 7%, and remained above the discount rate of 2%. The EIRR varied

from 23% to 19%, and remained above the opportunity cost of 10%. Both FNPV and ENPV remained

positive. The results of the sensitivity tests are given in paragraph B.7 of the Technical Annexes.

3.2. Environmental Impact

Environment

3.2.1. The programme has been classified under category 2 of the Bank's environmental and social

safeguards system, which corresponds to the category selected by the country's environmental services.

It has undergone a strategic environmental assessment, whose report has been validated by the country.

The negative environmental and social impacts of the programme are considered minor and very

ephemeral. They will mainly be observed during the works, since most of the infrastructure will provide

a solution that substantially improves the living conditions of the rural population (opening up of villages,

access to water and electricity, health facilities, income and better nutritional status). Summaries of the

strategic environmental assessment are posted on the Bank's website as of 24 August 2018.

Page 22: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

11

Climate Change

3.2.2. The project complies with the Bank's climate safeguard policies by identifying the climate risks.

The programme’s sensitivity to climate has been analyzed in accordance with the Adaptation Review

and Evaluation Procedures (AREP) and the Climate Safeguard System (CSS).

3.2.3. Based on the preliminary analysis of project activities, some of the activities will be more

sensitive than others. Rural roads and water supply structures will be more sensitive to climate than other

infrastructure. The roads to be constructed will incorporate civil engineering structures into their design

to ensure normal flow of waterways that cross them. In addition, the longitudinal profiles of the runways

will be oriented to facilitate drainage of water falling or running on the surface course. The construction

materials will allow for a good level of compaction capable of reinforcing adhesion of various primary

particles so as to reduce crumbling with threshing of waters from exceptional rainfall. Water supply

structures should target sufficiently productive slicks to avoid early depletion. Other socio-economic

infrastructures will be built taking into account their probable exposure to hazards (high winds,

temperature rise, exceptional rainfall, etc.). In addition, the project will promote the use of solar energy

for lighting socio-economic infrastructures and operating the equipment provided under the programme.

This alternative will make the project's actions cleaner and greener.

Gender

3.2.4. The project will take into account the needs of women, men, and young people of all age groups

and social categories. Specifically, the project will promote the empowerment of women and young

people by establishing production, processing, packaging and storage units for agricultural and dairy

products, depending on the areas. The capacities of women and young people will be strengthened in the

processing of groundnut into oil, as well as its processing into other derived products, packaging, bottling

and labelling.

3.2.5. Women will be highly involved in activities related to value chains, also more than 55% of the

resources of promising projects will also be used for women. Women's commitment to empowerment

initiatives will be reinforced by the time gained due to the construction of improved village water supply

structures, access to energy, and access to socio-economic infrastructure and innovative production

technologies. Through the rehabilitation of rural roads, the project will facilitate access to remote areas

and transportation of local products. Through IEC (information, education and communication),

sensitization campaigns will be organized for the community at large, targeting 51% of women, on

gender, reproductive health and family planning, nutrition, hygiene and sanitation, fight against early

marriage, and other topics to be selected in line with the needs of each community. Training in

entrepreneurship and the development of bankable project proposals will be organized for women and

young people with support for project promoters and access to financing for the creation and development

of local businesses, and this will reduce rural exodus to large cities.

3.2.6. Support for women project promoters will also include support for access to land. The updating

of the RNU database and domestic installation in the rural electricity component, which will be

subsidized for 3,000 vulnerable households, will reach the most vulnerable population and be rationally

selective in the provision of assistance services to the most needy. The gender activities will be

implemented in collaboration with the Ministry in charge of gender. The project is categorized 2 in the

“gender marker system” The detailed gender analysis for each intervention sector and the action plan for

Page 23: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

12

activities implementation are presented in Annex B.8.2 of the Technical Annexes. The budget allocated

for gender promotion and women's empowerment activities is estimated at EUR 15,5 million and is

included in the costs of the activities indicated above.

Socio-economic Impact

3.2.7. In order to improve the people’s living conditions, the project will help: (i) increase incomes in

rural areas; (ii) broaden people's access to basic social services; and (iii) strengthen community

development mechanisms. As regards impacts, with improved basic socio-economic services, the project

will help to reduce the poverty rate in rural areas from 67% to 54%. The project will also reduce child

mortality from 51‰ to 25‰, and chronic malnutrition from 21% to 8% by 2030. Finally, the project will

also help to increase access to drinking water in rural areas from 82% to 95%, as well as increase the

rural electrification rate from 33 to 55%.

3.2.8. Furthermore, as regards impacts, thanks to the construction of road and energy infrastructure,

more than 300,000 people, 51% of whom are women, will have access to electricity, and more than 800

villages will be opened up. In the health component, more than 300,000 additional people, 51% of whom

are women, will have access to quality health infrastructure and services, and more than 800,000 people,

51% of whom are women, will have access to drinking water. Women's access to health services will

also contribute to reducing maternal mortality. Above all, the project will, through the construction of

rural roads, the creation of farming and horticultural areas and support for rural agricultural societies, the

increase and diversification of horticultural production, provide better access to markets and

consequently increase the incomes of the rural population.

Employment

3.2.9. In 2016, the Bank adopted the Youth Employment Strategy in Africa 2016-2020 which, under

its first pillar, incorporates employment in all its sector operations. The project will provide support in

line with national employment promotion strategies. The project will support this initiative by: (i)

including incentives for the use of local labour in the bidding documents for works, particularly labour-

intensive works for rural roads; and (ii) involving the maximum number of women and young people in

the development of agricultural activities. Furthermore, as regards maintenance of rural roads and

equipment for the production and processing of agricultural products, support and employability training

for young people will be provided for the establishment of maintenance committees to be managed by

young people from the localities in the project area. The project will also encourage certain service

providers (design and supervision firms and works companies) to recruit engineers and trainee

technicians for them to gain experience in worksite works. Accordingly, more than 150 engineers and

technicians in water supply, transport, electricity, civil engineering and horticulture will be able to

undergo internships throughout the duration of the project. At project completion, the trained engineers

and technicians can either join the administration, or be recruited in large companies or design firms, or

employ themselves. In any case, the experience acquired will help them to integrate into the professional

environment.

3.2.10. The support fund for promising projects that will be set up will also help to create more than

500 jobs for young people and women in the medium term. The project will create 6,000 jobs inherent

in the works, and develop over 30,000 jobs in the agricultural and related sectors. The project's various

socio-economic impacts will thus help to curb rural exodus and illegal emigration.

Page 24: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

13

Fragility

3.2.11. The main challenge in Casamance is to strengthen institutional, economic and social resilience,

while reducing gender disparities, as well as to accelerate decentralization by constructing key

infrastructure for lasting peace. Indeed, the region suffers from enormous infrastructure deficit, which

constitutes a major obstacle to sustained and inclusive growth of the Casamance economy and regional

integration. Rural exodus to Ziguinchor, which concentrates 81% of the urban population, and whose

population doubled between 1976 and 2014, was not accompanied by appropriate investments, with no

connection to infrastructure, nor access to basic services, thereby limiting any development initiative in

both urban and rural areas, and hampering the provision of government goods and services in the region.

Emigration, which mainly concerns young people, aggravates unemployment and urban poverty, which

in turn constitute an additional risk of social tension.

3.2.12. The infrastructure to be provided under the project, particularly rural roads, boreholes and water

towers, as well as health posts, will help to bridge the infrastructure gap in the region and will have a

major impact on improving the living conditions of the rural population. In addition, the establishment

of farming areas and rural agricultural societies, as well as processing facilities will help rural populations

to develop economic activities, which will in turn reduce rural exodus and emigration. Finally, support

will be provided to the National Casamance Reconstruction Agency (ANRAC) whose mission is mainly

to facilitate the return of the population to their land.

IV. IMPLEMENTATION

4.1. Implementation Arrangements

4.1.1. Institutional Arrangements: Established by Decree No. 2015-403 of 30 March 2015 and located in

the Prime Minister’s Office, the PUDC was organized by Prime Minister's Order No. 10386 of 19 May 2015 with

the following bodies : (i) The Steering Committee, chaired by the Prime Minister and responsible for strategic

orientation of the programme; (ii) the National Director serves as the interface between the PUDC and the technical

services of the Ministries involved in the PUDC implementation; (iii) the Technical Committee, which assists the

Steering Committee in monitoring the technical implementation of the programme under the chairmanship of the

National Director, and (iv) the Programme Management Unit (PMU), responsible for the day-to-day management

of the Programme under the supervision of a Coordinator, Secretary of the Technical Committee and responsible

for preparing technical and financial implementation reports to be submitted to the National Director. In the first

phase of the programme, the PMU was placed under the supervision of UNDP, which was responsible for

programme implementation using its own procurement and financial management rules and procedures. Given

that, the PUDC Support Project, financed by the Bank, will be implemented through national expertise, the PMU

led by a Coordinator will be placed under the supervision of the National Director of the PUDC. The National

Director will report to the Premier Minister Delegate in charge PUDC monitoring. Details on the various organs

of the institutional arrangements are given in Paragraph B of the Technical Annexes. The PMU Management Unit,

will be mainly composed of a Coordinator, experts in Rural Engineering - Value Chains, Civil Engineering, Water

Supply, Energy, Transport, Health, Procurement, Accounting, Administrative and Financial Management,

Environment, Social and Community Development, Monitoring and Evaluation, and any other human resource

required for the proper implementation of the programme. The PMU experts will be recruited or reappointed, for

those who worked in the first phase of the PUDC, on the basis of favourable assessment of their CVs by the Bank.

Page 25: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

14

4.1.2. Procurement Procedures

Procurement: All procurements for this project will be made in accordance with the Procurement

Framework for Bank Group-financed operations of October 2015 and the provisions of the Financing

Agreement. An assessment of Senegal's public procurement system (SPMS) deemed the procurement

risk to be moderate. This generic country risk was reassessed during implementation of all activities

under the Emergency Community Development Programme Support Project (EP-CDP) to be taken into

account in determining the overall procurement risk of the project. The overall project contracting risk

level at project appraisal was deemed to be moderate. Furthermore, the SPMS will be used for the

procurement of works, goods and services of consultants for which the fiduciary risk is considered

relatively low. The Bank's Procurement Methods and Procedures (BPM) will be used for larger and more

complex works, goods, and consultancy contracts, where the country fiduciary risk is deemed substantial.

The Project Management Unit will be responsible for the procurement of all works, goods and

consultancy services under the project, and will be supported by the Procurement Unit of the Prime

Minister's Office. The PMU will have qualified procurement staff with solid experience in the

procurement of works, goods and consultancy services in accordance with the Bank's procurement

methods and procedures, and with the national public procurement system in Senegal. Given the volume

and scope of the project activities, the procurement staff will include at least one Procurement Specialist

and one Procurement Assistant to be recruited on a competitive basis or reappointed, for those who

worked in the first phase of the PUDC, on the basis of a favourable assessment of their CVs by the Bank.

Assessment of Procurement Risks and Capacities: Risk assessments at country, sector and project levels,

as well as the procurement capacities of the executing agency (EA) have been conducted and the results

were used to guide the decision on the selection of BPMs activities and the SNPM for activities where

fiduciary risk is deemed low. Appropriate risk mitigation measures have been included in the PERCA

action plan referred to in paragraph B5 of the Technical Annexes. A procurement audit will be conducted

on an annual basis by an independent firm.

Financial Management: The PMU managed by a Coordinator, which is responsible for financial

management under the supervision of the National Director of the PUDC, will have qualified financial

management staff whose capacities will be strengthened in the Bank's financial management rules and

procedures. The staff will, in addition to the Coordinator, include an Administrative and Financial Officer

and an Accountant to be recruited on a competitive basis or reappointed, for those who worked in the

first phase of the PUDC, on the basis of a favourable assessment of their CVs by the Bank. The Unit will

also need an appropriate administrative, financial and accounting procedures manual. The manual will

form the basis of the Unit’s internal control system and will cover all the project management cycles:

expenditure management cycle (procedures for the procurement of goods and services), asset

management cycle (fixed assets, inventories, etc.), treasury management cycle (authorization,

disbursement, monitoring and control of cash flows, etc.), resource mobilization cycle (calls for funds,

direct payments, etc.), accounting, financial and budgetary information cycle, personnel management

cycle, internal control and audit cycle, etc. The PMU will ensure that an integrated multi-project and

multi-post management system is put in place for proper keeping of the project's budgetary, cost and

general accounts. The general accounts must be private commitment accounts, applying SYSCOHADA

standards and taking into account the specific features of development projects.

Page 26: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

15

Disbursements: Mobilization of the Bank's funds will follow the Bank's disbursement rules and

procedures, through the three direct payment methods for the payment of procurement contracts for

works, goods and services, the special account mainly for operating expenses, and reimbursement, where

appropriate and subject to prior authorization by the Bank. The use of the special account method will

require the opening of: (i) a special account at BCEAO in the name of the PUDC Support Project, which

will be used to mobilize the Bank's funds and under the signature of a signatory designated by the

Minister of the Economy, Finance and Planning ; and (ii) a sub-account in a commercial bank for

execution of the current expenses of the PA-PUDC under the signature of the Coordinator and the

Administrative and Financial Officer of the PMU.

Financial and Accounting Audit: Finally, the PMU will set up external audit mechanisms for the

project's financial statements and internal control system. Audits of the annual financial statements will

be conducted by independent external auditors, recruited on a competitive basis and in accordance with

terms of reference agreed with the Bank, as well as in accordance with the Bank's requirement to submit

audit reports by 30 June of the year following the year audited.

4.2. Project Monitoring

4.2.1. The project implementation will be monitored by the PMU under the supervision of the Director

of the PUDC, which will prepare quarterly progress reports on the physical and financial implementation

of the project, in accordance with the Bank's procedures. During Phase 1, the PUDC procured a high-

performance geographic information system (GIS) that will be enhanced under the project. The project's

achievements will be monitored through the logical framework indicators. The monitoring and evaluation

expert in the PMU, based on the mechanism already put in place, will monitor all the activities. The

various regional technical services of the Ministries involved in the PUDC and the Steering Committee

will regularly monitor the project's achievements in the field. In addition, within the framework of the

IEC, documents (reports, photos, documentary films, etc.) will be prepared regularly during the various

phases of the project to ensure good visibility of the actions. The information collected during project

monitoring could, if necessary, be recorded in the sector monitoring and evaluation system of the various

Ministries involved.

4.2.2. At the Bank, project monitoring will be conducted through: (i) semi-annual supervision

missions, in collaboration with the Government; (ii) quarterly activity reports submitted by the Borrower;

and (iii) annual audit reports to be submitted by the Borrower within six months following the end of

each fiscal year. The milestones in the project implementation are given below:

Date Milestones Monitoring Activities

09/2018 Loan approval AfDB Board of Directors

10/2018 Signing of the loan agreement AfDB/ Government

11/2018 Effectiveness

Fulfilment of conditions precedent to

effectiveness

02/2019 Fulfilment of conditions precedent to first disbursement AfDB No Objection Opinion

03/2019 IEC start-up AfDB No Objection Opinion

04/2019 Studies start-up AfDB No Objection Opinion

05/2019 Start-up of value chain activities AfDB No Objection Opinion

06/2019 Start-up of rural road works and rural electrification AfDB No Objection Opinion

06/2019 Start-up of health post works AfDB No Objection Opinion

07/2019 Start-up of DWS infrastructure works AfDB No Objection Opinion

06/2019 End of works AfDB No Objection Opinion

Page 27: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

16

4.3. Governance

4.3.1. Economic and financial governance risks at national and local levels are well under control.

The location of the project within the Prime Minister's Office and the participation of all the Ministries

concerned, representatives of elected representatives, and civil society in the Steering Committee will

ensure good governance of the project. Furthermore, the commitment of the various Ministries, the

involvement of the Government's technical support structures in developing the activities of the various

components, as well as the experience gained by the project team during Phase 1 give the hope that

leadership and management will be well ensured by the various actors involved in the implementation of

Phase 2. In addition, technical partnership agreements will be concluded between the PUDC and the

various technical structures that support the project in carrying out certain activities (ANCAR, ITA,

CDH/ISRA, CLM, DGS, SENELEC, ASER, etc.). The involvement of these structures in the project

will further enhance project governance. Furthermore, Act III of decentralization, which took place in

2013, will ensure better readability of territorial governance scales by clarifying the relations between

actors and articulating the powers to be transferred to technical, financial and human resources, and

improving the mechanisms for financing territorial development and budgetary governance. Finally, the

reforms initiated with the Bank's support under the Community Development Reform Support Project

(PARDC) will contribute to better community management.

4.3.2. The national procurement system and procedures are largely in line with international

standards. There are control institutions (Court of Auditors, General State Inspectorate, National Anti-

Corruption Authority - OFNAC), and they play their roles in the various stages of the procurement of

works, goods and services. In addition, the Bank's methods and procedures will be used for procurements

that pose substantial risks if the Senegalese procurement system is used. A mechanism of accelered

processing for procurements documents will be set up, wihin the project, the concerned national

department and the Bank to allow an efficient implementation of the activities.

4.4. Sustainability

4.4.1. Project sustainability depends to a large extent on the quality of the works, adequate operating

and maintenance conditions of the infrastructure, and the degree of ownership of the works carried out

by the actors and beneficiaries. It also depends to a large extent on the willingness and commitment of

the Government, decentralized structures and local authorities to provide sustainable support for the

management of the various infrastructures and facilities that will be constructed by the project. In this

project, such willingness and commitment from the Government and other institutional actors is obvious,

as indicated in the national policy and strategy documents developed over the past few years concerning

the various sectors targeted by the project. Furthermore, the significant resources regularly allocated by

the Government through the FERA and by the municipalities for maintenance and monitoring of

infrastructure financed with their own funds demonstrate their commitment. The support provided under

the project to the local maintenance committees to be set up will ensure real ownership and sustainability

of the works, infrastructure and equipment.

4.4.2. Furthermore, part of this funding will be used for establishing maintenance mechanisms for the

structures, as well as for building the capacities of the actors and communities that will be responsible

for the maintenance component. These actions will thus further reinforce the resources already mobilized

and regularly allocated for the viability and sustainability of investments made at community level.

Page 28: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

17

4.5. Risk Management

4.5.1. The main identified risks are: (i) delays in procurement; (ii) lack of project ownership by local

actors and beneficiaries; and (iii) poor performance of local businesses. However, these risks will be

mitigated by: (i) the fact that PMU members, particularly the procurement experts, will receive training

in AfDB procedures at project start-up; (ii) the lessons learned from Phase 1 by the PUDC and the steps

already taken by the various local administrations and organizations involved in community development

(Regional Governments, Sub-Prefectures, ARD, NGOs, etc.) to facilitate ownership of the programme.

These measures will be reinforced under the project to ensure stronger ownership of the programme by

the population.

4.6. Knowledge Building

4.6.1. The studies to be conducted under this project will help to adjust the policies and strategies of

the sectors concerned. Thus, the results of the study on the cost of hunger will provide information on

the economic cost of hunger in Senegal, and will serve as advocacy tools for the food and nutritional

security sector. Assessing the poverty impact and updating the database of the most vulnerable people

will strengthen mechanisms for taking into account the most vulnerable groups and adopting more

sustained poverty reduction strategies. In addition, the operational and participatory monitoring and

evaluation system to be established will generate a database on the status of the sectors concerned in the

project areas. In addition, the integrated approach under the PA-PUDC will provide a reference model in

the implementation of a minimum package of services at community level. Indeed, this integrated

approach incorporates the development of agricultural value chains (including nutritional security), the

population’s access to energy (including clean energy), access to basic social services (health-water-

sanitation), and rural roads. The approach also incorporates the participation of the most vulnerable

people through social protection mechanisms to identify them.

4.6.2. The establishment of key impact indicators before project start-up and the assessment of

outcomes at project completion will produce useful information on the project's effects and impacts. The

various experiences to be gained from the project implementation will serve as references for the

Government of Senegal and the Bank. As regards the Borrower, the project will enable PUDC experts

and other structures involved in the project to acquire knowledge in the Bank's procedures with the

assistance of the Bank's Dakar Office (COSN).

V. LEGAL FRAMEWORK

5.1. Legal Instrument

A loan agreement will be signed between the Republic of Senegal ("the Borrower") on the one hand, and

the African Development Bank (AfDB) (the "Bank"), on the other.

Page 29: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

18

5.2. Conditions for Bank Intervention

5.2.1 Conditions precedent to effectiveness of the AfDB Loan Agreement: Effectiveness of the loan

agreement shall be subject to the Borrower’s fulfilment of the conditions specified in Article 12.01 of

the General Conditions Applicable to Loan Agreements and Guarantee Agreements of the African

Development Bank (Sovereign Entities).

5.2.2 Conditions precedent to the first disbursement of AfDB loan resources: In addition to

effectiveness of the Loan Agreement, the first disbursement of the loan resources shall be subject to the

Borrower’s fulfilment, to the Bank's satisfaction, of the following conditions:

(i) Provide the Bank with satisfactory evidence of the establishment of the Project

Management Unit and the appointment of its staff as specified in paragraph 4.1.1

(institutional arrangements) above. The CVs of the staff shall be submitted to the Bank

for prior approval.

(ii) Provide evidence that the procedures manual has been adapted to the new project

implementation arrangements;

(iii) Provide evidence of the inclusion of the counterpart contribution in the project, in the

amount of 8 280 000 euros, in the Borrower's Finance Law for 2018.

5.2.3 Other conditions: The Borrower shall, to the satisfaction of the Bank:

5.3. Compliance with Bank Policies

The project complies with all the Bank’s applicable policies.

VI. RECOMMENDATION

Management recommends that the Board of Directors should approve the proposal to grant a EUR

60 million AfDB loan to the Republic of Senegal to finance the Emergency Community Development

Programme Support Project (PA - PUDC) under the conditions specified in this report.

Page 30: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

I

Annex 1: Comparative Socio-economic Indicators of Senegal

Year Senegal Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2017 197 30,067 80,386 53,939Total Population (millions) 2017 16.1 1,184.5 5,945.0 1,401.5Urban Population (% of Total) 2017 43.8 39.7 47.0 80.7Population Density (per Km²) 2017 83.4 40.3 78.5 25.4GNI per Capita (US $) 2016 950 2 045 4 226 38 317Labor Force Participation *- Total (%) 2017 57.5 66.3 67.7 72.0Labor Force Participation **- Female (%) 2017 45.3 56.5 53.0 64.5Sex Ratio (per 100 female) 2017 96.7 0.801 0.506 0.792Human Dev elop. Index (Rank among 187 countries) 2015 162 ... ... ...Popul. Liv ing Below $ 1.90 a Day (% of Population) 2011 38.0 39.6 17.0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2017 3.0 2.6 1.3 0.6Population Grow th Rate - Urban (%) 2017 3.6 3.6 2.6 0.8Population < 15 y ears (%) 2017 43.7 41.0 28.3 17.3Population 15-24 y ears (%) 2017 19.4 3.5 6.2 16.0Population >= 65 y ears (%) 2017 2.9 80.1 54.6 50.5Dependency Ratio (%) 2017 87.2 100.1 102.8 97.4Female Population 15-49 y ears (% of total population) 2017 24.1 24.0 25.8 23.0Life Ex pectancy at Birth - Total (y ears) 2017 67.7 61.2 68.9 79.1Life Ex pectancy at Birth - Female (y ears) 2017 69.5 62.6 70.8 82.1Crude Birth Rate (per 1,000) 2017 36.2 34.8 21.0 11.6Crude Death Rate (per 1,000) 2017 5.6 9.3 7.7 8.8Infant Mortality Rate (per 1,000) 2016 33.6 52.2 35.2 5.8Child Mortality Rate (per 1,000) 2016 47.1 75.5 47.3 6.8Total Fertility Rate (per w oman) 2017 4.9 4.6 2.6 1.7Maternal Mortality Rate (per 100,000) 2015 315.0 411.3 230.0 22.0Women Using Contraception (%) 2017 22.5 35.3 62.1 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2016 6.8 46.9 118.1 308.0Nurses and midw iv es (per 100,000 people) 2016 30.9 133.4 202.9 857.4Births attended by Trained Health Personnel (%) 2015 53.2 50.6 67.7 ...Access to Safe Water (% of Population) 2015 78.5 71.6 89.1 99.0Access to Sanitation (% of Population) 2015 47.6 51.3 57 69Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2016 0.4 39.4 60.8 96.3Incidence of Tuberculosis (per 100,000) 2016 140.0 3.8 1.2 ...Child Immunization Against Tuberculosis (%) 2016 97.0 245.9 149.0 22.0Child Immunization Against Measles (%) 2016 93.0 84.1 90.0 ...Underw eight Children (% of children under 5 y ears) 2014 12.8 76.0 82.7 93.9Prev alence of stunding 2014 19.4 20.8 17.0 0.9Prev alence of undernourishment (% of pop.) 2015 11.3 2 621 2 335 3 416Public Ex penditure on Health (as % of GDP) 2014 2.4 2.7 3.1 7.3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2016 83.1 106.4 109.4 101.3 Primary School - Female 2016 87.9 102.6 107.6 101.1 Secondary School - Total 2016 48.1 54.6 69.0 100.2 Secondary School - Female 2016 48.4 51.4 67.7 99.9Primary School Female Teaching Staff (% of Total) 2016 32.9 45.1 58.1 81.6Adult literacy Rate - Total (%) 2013 42.8 61.8 80.4 99.2Adult literacy Rate - Male (%) 2013 52.8 70.7 85.9 99.3Adult literacy Rate - Female (%) 2013 33.6 53.4 75.2 99.0Percentage of GDP Spent on Education 2015 7.1 5.3 4.3 5.5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2015 16.6 8.6 11.9 9.4Agricultural Land (as % of land area) 2015 46.1 43.2 43.4 30.0Forest (As % of Land Area) 2015 43.0 23.3 28.0 34.5Per Capita CO2 Emissions (metric tons) 2014 0.6 1.1 3.0 11.6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available. * Labor force participation rate, total (% of total population ages 15+)

** Labor force participation rate, female (% of female population ages 15+)

SenegalCOMPARATIVE SOCIO-ECONOMIC INDICATORS

May 2018

0

10

20

30

40

50

60

70

80

90

100

2000

2005

2010

2011

2012

2013

2014

2015

2016

Infant Mortality Rate( Per 1000 )

Senegal A frica

0

500

1000

1500

2000

2500

2000

2005

2010

2011

2012

2013

2014

2015

2016

GNI Per Capita US $

Senegal A frica

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

2000

2005

2010

2012

2013

2014

2015

2016

2017

Population Growth Rate (%)

Senegal A frica

01020304050607080

2000

2005

2010

2012

2013

2014

2015

2016

2017

Life Expectancy at Birth (years)

Senegal A frica

Page 31: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

II

Annex 2: Table of Bank Portfolio in Senegal as at 30 June 2018

3.1. Active National Projects as at 30 June 2018

Sector / Operation

Approval

Date

Approved

Amount

(UA Million)

Disb. Amount

(UA Million)

Disb.

Rate

(%)

Disb. Deadline

RURAL

1

Community roads project in support of the PNDL

(PPC/PNDL) - ADF

- OPEC

17-July-13

11-Dec.-13

15.00

7.11

13.39

3.77

89.3

53.0

31-Dec.-18

30-June-19

2

Project for restoring the ecological and economic

functions of Lac de Guiers (PREFELAG)- ADF

- GEF

4-Sept.-13

4-Sept.-13

15.00

0.93

12.07

0.50

80.5

54,2

31-Dec.-18

31-Dec.-18

3

Food Security Support Project in Louga, Matam and

Kaffrine regions - ADF

- GAFSP

26-April-13

26-April-13

2.00

28.44

1.26

19.07

63.0

67.1

31-Dec.-18

31-Dec.-18

4

Project for opening up production areas in support of the

National Local Development Programme (PDZP/PNDL) 22-June-18 20.00 0 0 31-Dec.-23

5

PPF Rice Value Chain Development Project in Senegal

River Valley (PDCV Riz) 18-May-16 0.55 0.02 4.46 30-June-18

6

PPF Youth Entrepreneurship Development Project for

agriculture and agri-food in Senegal (PDEJAS) 01-June-16 0.81 0.78 95.5 31-Dec.-18

7

Climate Information Quality Improvement Project for

Building Community Resilience in Senegal (FSCD) 17-March-17 0.82 0.01 1.6 31-Dec.-19

Sub-Total 90.66 50.87 56.1

INFRASTRUCTURE

8

Dinguiraye-Nioro-Keur-Ayib Road Rehabilitation Project

(DNK) - FAD

28-May-14

23.77

15.81

66.5

31-Dec.-19

9 Project for rehabilitating National Road 2 and opening up

the island of Morphil - AfDB

16-Dec.-15

100.20

16.92

16.9

31-Dec.-19

10

Towns Modernization Programme (PROMOVILLES) –

AfDB

29-March-17

94.84

7.49

7.9

31-Dec.-21

11 Regional Express Train Project (TER) - AfDB 21-June-17 151.74 17.42 11.5 31-Dec.-21

12 Digital Technologies Pool Project - AfDB 21-Oct.-15 50.56 1.54 3.0 31-Dec.-20

Sub-Total 421.11 59.18 14

WATER AND SANITATION

13

Multiple use water supply strengthening project on the

Louga - Thiès – Dakar highway from Keur Momar station

SARR - AfDB

18-Nov.-16 53.91 3.12 5.8 30-June-21

14

Sewage Sludge Management and Recycling Improvement

Project in Ziguinchor 23-April-13 1.04 1.04 100 31-Dec.-18

15

Water and Sanitation Sector Project (PSEA) - ADF

- RWSSI

23-April-14

23-April-14

20.00

4.97

8.07

2.10

40.4

42.3

31-Dec-18

31-Dec-18

Sub-Total 79.92 14.33 17.9

SOCIAL

16

Youth and Women's Employment Promotion Support

(PAPEJF) - ADF 23-Oct.-13 21.19 3,56 16.8 30-June-19

17

Support Project for the Virtual University of Senegal

(PAUVS) - ADF 18-Dec.-13 3.38 1.30 38.4 30-June-19

Page 32: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

III

Sub-Total 24.57 4.86 19.8

GOVERNANCE

18

Private Sector Promotion Support Project (PAPSP) - ADF 10-Sept.-12 4.04 2.98 73.9 30-Dec.-18

19 Legal assistance in the mining sector (ALSF) 30-Sept.-16 0.71 0 0 31-Dec.-18

Sub-Total 4.75 2.98 62.7

TOTAL 621.01 132.22 21.3%

* Source : SAP-PS June 2018

Sector Breakdown: Infrastructure (70%); Water and Sanitation (13.3%); Rural Sector (11.8%); Social (4.1%) and Governance (0.8%)

3.1. Active private sector window projects as at 30 June 2018

Sector / Operation

Approval Date

Approved

Amount

(UA Million)

Disb.

Amount

(UA Million)

Disb.

Rate

(%)

Closing Date

1 Blaise Diagne International Airport (AIBD) 17-Dec.-10 58.06 58.06 100 5-March-29

2

Dakar Toll Motorway Project

- Preferred loan

19-July-10

7.85

7.85

100

31-Dec.-25

3

Sendou Power Plant Project

- Preferred loan

25-Nov.-09

45.62

45.62

100

31-Dec.-24

- Supplementary loan 30-Oct.-15 4.15 4.15 100

4

Saint Louis Agricultural Company Rice Project of

Senegal (CASL) 22-June-16 13.02 8.34 64.1 23-March-22

TOTAL

128.70 124.02 96.3%

* Source: SAP-PS June 2018

3.2. Active Multinational Projects as at 30 June 2018

Sector / Operation

Approval

Date

Approved

Amount

(UA Million)

Disb.

Amount

(UA Million)

Disb.

Rate

(%)

Disb. Deadline

RURAL

1

Resilience Strengthening Programme in the Sahel (P2RS)

16-March-15 22.25 7.68 34.5 30-June-20

INFRASTRUCTURE

2

Trans-Gambian Bridge Construction and Cross-Border

Crossing Improvement Project

(Senegal loan)

16-Dec.-11

3.18

0.02

0.7

31-Dec.-19

3

Rosso Bridge Construction Project

(Senegal loan)

09-Dec.-16

7.50

0.06

0.8

31-Dec.-20

4 OMVG Energy Project 30-Sept.-15 42.50 8.80 20.7 31-Dec.-20

Sub-Total

53.18 8.88 16.7

TOTAL 75.43 16.56 22% * Source: SAP-PS June 2018 - Sector Breakdown: Infrastructure (70.5%) et Rural Sector (29.5%).

Page 33: b ized COUNTRY : REPUBLIC OF SENEGAL PROJECT APPRAISAL

IV

Annex 3: Map of Project Area