Barrow OWF Design & Build of UKs 1st OWF Substation
Citation preview
Barrow Offshore WindfarmDesign & Build of UKs First OWF Sub-
station
October 2005
Phillip CartwrightCommercial/Engineering Director
AREVA T&D Technology Centre
Rupert BerrymanEngineering Manager - Barrow Offshore Wind Farm
VKBR
2Agenda
1. Introduction to design & build team members
2. Overall Project Scope & Context
3. Lessons Learnt
4. Summary
31. Introduction to design & build team members
4The Team
XClientsCentrica - Major UK energy generation & supply
company
DONG - Major Danish Oil, Gas and energy generation & supply company
XPrime ContractorVestas - Major Danish wind turbine manufacturerKBR International engineering and programme
management company
5The Team
DONG CENTRICA
Barrow Offshore Wind Ltd
MPIOffshore
Installation
SIF/SMULDERSSubstructure fabrication
VESTAS
WTG
AREVAElectricalPackage
PIRELLI/NEXANSMarine Cable
Supply
VKBRConsortium
50% 50%
VKBRStructural
Design
62. Overall Project Scope and Context
7The Challenge
XConnect 30, 3MW Wind Turbines to the GridSystem via an offshore sub-station
XEnsure the connection meets the requirementsof the connection agreement
8The Key Connection Requirements
XThe steady state reactive power flow at the Heysham substation connection point shall be unity power factor +/- 5MVAr for active power flow in the range 0 and 90MW into the NGT system
XThe system shall remain stable and connected to the system without tripping for a solid three phase fault or any unbalanced short circuit for a total fault clearance time of up to 140ms
9The 90MW Barrow Offshore Wind Farm Project
10
The 90MW Barrow Offshore Wind Farm Project
VKBR copyright
11
Headline Project Scope1) Design
Conceptual and structural design VKBR System studies, detailed electrical design and equipment supply - AREVA
2) Connection at Heysham The wind farm connects into the Grid via an existing United Utilities circuit within
Heysham switchyard
3) Transmission Cable System 27km of offshore, single 3-core cable 132kV 2.8 km of single circuit, 3 off single-core cable 132kV system
4) Module supply and fitout - Module Builders, Aberdeen Cabins:- Protection and control, 33kV, 132kV, Capacitors, Diesel Generator, HVAC,
Mess/Refuge 132/32kV main and auxiliary transformers
5) Modules and other plant fitted onto Platform Fitted at Barrow, site and main deck supplied by VKBR. Module fixing and inter-
module cabling works performed by installation contractor, Test and Dry Commissioning by AREVA
6) Electrical System commissioning Includes commissioning work on offshore platform
12
Site Locations
Leatherhead VKBR Offices
Barrow, Platform kitout
Aberdeen, Modules
Heysham connection point
13
Connection at Heysham - Onshore
XHeysham Grid connection pointNew sub-station adjacent to Heysham switchyard
z All civil works
z 132kV open terminal bay (Extended creep)
z Solidly connected 24MVAr shunt reactor
z Incoming cable from beach cable vault
z Outgoing cable from new compound to existing Heysham switchyard circuit breaker
z Protection System, SCADA RTU,Batteries and LVAC auxiliaries
14
Offshore Sub-station
X OverviewLength - 23mWidth - 15mHeight - 10mWeight - 440 tonnes
15
Offshore Substation
XModularised quipment33kV Board 14 panel including protection33/132kV 120MVA Transformer with OLTC132kV GISRelay and control panel suite roomLVAC and DC plant room (incs UPS for navigation lights)225kVA standby diesel generatorRefuge, mess and workshop modules5MVAr shunt capacitor bank modulesHVAC systems INERGEN/water mist fire suppression system
16
Power Transformer
AuxiliaryTransform
er
Module BModule A Module C
Module E
Module D
Heli-Lift
AuxiliaryTransformer
Module B
Module A
Module C
Platform Deck
Cable Deck132kV Cable Transition
33kV Cable Transition
P+132+M+1-W-*
Offshore Substation
17
Module C
Module A Module B
StandbyDiesel
33kV
LV Room
Control
132kV
Fire
StoreAuxiliary
Transformer
Power Transformer
Offshore Substation
18
During Construction at end of June 05
19
Loading Out 12th August 05
20
Offshore Sub-station
21
Installed on Monopile 16th August 05
22
Project Programme
Order Placement 02/09/04 9
Modules ready for fitting to platform 10/05/05 9
Offshore Substation complete 02/08/05 9
Platform shipout (by VKBR) 16/08/05 9
Heysham available 24/08/05 9
Electrical System commissioned 01/11/05
Windfarm commissioned including10 day reliability run 10/05/06
23
3. Lessons Learnt
24
Lessons Learnt
X System Modelling Inter party confidentiality agreements need to be resolved pre-
contract commencement
XWay-leaves & Land LeasesAll way-leaves and land leases need to be finalised and secured
before construction contract is let
X Design Design Freezes are required after equipment interface reviews
z Hazop reviews
z Windfarm SCADA design that meets substation P&C design cycle
Clarity of Design & Supply responsibilitiesz Use of Division of Responsibility Matrix at contract development
stage - requires sufficient contract lead in time
25
4. Summary
26
Summary
XFirst high voltage offshore substation in the UKA modularised solution - rapid assembly time at load-
out point
Sub-structure (mono-piles) is common with wind turbines (mono-piles) - economy of design
Rapid design, build and install programme