Upload
fay-dawson
View
259
Download
7
Embed Size (px)
Citation preview
Basic Information
O/C E/F Relay & Time Coordination 1
O/C E/F Relay & Time Coordination
Basic Information
O/C E/F Relay & Time Coordination 2
General Circuit Diagram200/1 Amp
R Ph O/C (51R)
E/F (51N)
B Ph O/C (51B)
150 Amp
150 Amp
150 Amp
0.75 Amp
0.75 Amp
0.75 Amp
0.0 Amp
C11
C31
C51
C71
S1
S1
S1
S2
P1 P2
O/C E/F Relay & Time Coordination 3
1S1R
1S2R
1S3R
1S1Y
1S2Y
1S3Y
1S1B
1S2B
1S3B
2S1R
2S2R
2S3R
2S1Y
2S2Y
2S3Y
2S1B
2S2B
2S3B
3S1R
3S2R
3S3R
3S1Y
3S2Y
3S3Y
3S1B
3S2B
3S3B
R Ph CT
Y Ph CT
B Ph CT
Core-1Core-2Core-3
Core-1Core-2Core-3
Core-1Core-2Core-3
A11
A31
A51
A71
C11
C31
C51
C71
D71
D11
D31
D51
Yard MB Wiring
O/C E/F Relay & Time Coordination 4
1S1R
1S2R
1S3R
1S1Y
1S2Y
1S3Y
1S1B
1S2B
1S3B
2S1R
2S2R
2S3R
2S1Y
2S2Y
2S3Y
2S1B
2S2B
2S3B
3S1R
3S2R
3S3R
3S1Y
3S2Y
3S3Y
3S1B
3S2B
3S3B
R Ph CT
Y Ph CT
B Ph CT
Core-1Core-2Core-3
Core-1Core-2Core-3
Core-1Core-2Core-3
A11
A31
A51
A71
C11
C31
C51
C71
D71
D11
D31
D51
Yard MB Wiring
Terminal Diagram of MiComP141
O/C E/F Relay & Time Coordination 5
O/C E/F Relay & Time Coordination 6
Single Line to Ground Fault200/1 Amp
R Ph O/C (51R)
E/F (51N)
B Ph O/C (51B)
1500 Amp
7.5 Amp
7.5 Amp
C11
C31
C51
C71
S1
S1
S1
S2
P1 P2
O/C E/F Relay & Time Coordination 7
Electromagnetic Induction relays
50%75%
100%125%150%
200%
Φ 1 Φ 2
Relay Operation Time - 1
O/C E/F Relay & Time Coordination 8
E/F PSM 30% i.e. 0.3 AmpE/F Relay Current 7.5 AmpE/F Relay Current is 7.5/0.3 = 25 Times its operating currentFrom Graph for 25 Times relay operating current for TMS = 0.15 relay time of operation would be @ 0.35 Sec
O/C PSM 100%O/C Relay Current 7.5 AmpIt is 7.5 times relay operating currentFrom graph for 7.5 Times relay operating current and for TMS = 0.1 time of operation for the relay would be 0.35 Sec
( Zoom out Graph)
Relay Operation Time - 2
O/C E/F Relay & Time Coordination 9
Actually our problem is to decide relay settings and not relay time of operations as shown previously
Hence Unknowns are Relay PSMRelay TMS
Whereas known facts areRelay placement and purpose of useRelay current during fault ( i.e. CT secondary current during fault. )Relay desired time of operation.
General Steps1) Decide PSM2) Find out fault current3) Find out multiple of relay set current as per decided PSM in step-14) Find out time of operation for above multiple of current and TMS=1 using
relay characteristic curve5) Decide relay time of operation as per protection needs6) Find out TMS = Required Time of operation /Time of operation with TMS =1
Basic Information – Selection of PSM
O/C E/F Relay & Time Coordination 10
E/F PSM generally selected as 30% ( Other than 30% settings may also be selected but about this discussed somewhere else in the presentation)
For O/C PSM is selection depends upon place and purpose of use for example –1.Transformer O/C protection
a) Transformer HV or LV side O/C relay PSM settings should be in commensuration with transformer full load current and respective CT ratio such that PSM = T/F Full load current / CT ratio ( Generally expressed in %)
b) For example for a 25 MVA transformer HV side full load current is 109 A if HV CT ratio is 200/1 Amp then PSM =109/200 ≈ 55% ( exact value 54.5%)
c) For old type numerical relay it was not possible to go as near as possible to value calculated from above formula due to large steps available
d) Under such condition it is decision as per local condition to select higher or lower nearest PSM e) In above example it is customary to select 50%, however due to this selection there is apparent
loss of about 10% capacity of the T/Ff) It is also possible to select 75% but load on transformer is to be monitored carefully ( and manually
)2.For 220-132 kV feederHere generally it is customary to select relay PSM as per-
a) Line conductor allowable loading limitb) CT primary normal currentc) Substations capacity/normal load feed by the lined) Considering above facts it is very common to select 100% PSM for 132kV lines with CT ratio 400/1
Ampe) For 220kV lines with CT ratio 800/1 amp and conductor 0.4 ACSR or 0.525 AAAC it is 100%
a)For 33-11kV feedera) As per local feeder condition, load pattern and needs ranging between 50% to 100%
Relay Operation Time - 3
Desired time of operation will depend upon
a) Equipment being protected
b) Time discrimination from down stream protection (150 ms – 250 ms)
c) Time of operation of main protection etc.
• For transformer LV side protection it is common to adopt 250 ms as operating time.
• This is so as to have 150 ms time discrimination from 100 ms relay time of operation for lower (feeder) protection.
• When relays are used as backup protection of 132kV lines it’s time of operation shall be equal to Z-2 time of operation (300 – 350 ms).
• Once these two things decided there remains only mathematical part
O/C E/F Relay & Time Coordination 11
Worked out Example
O/C E/F Relay & Time Coordination 12
400/1 A
132 kV 33 kV400/1 A
25 MVA
33kV Bus fault level 1Ph 170 MVA , 3Ph 210 MVARelay current during fault 1Ph 7.43 Amp, 3 Ph 9.18 AmpRelay PSM E/F 30%, O/C 100 %Multiple of relay currentE/F 25, O/C 9.Time of operation with TMS = 1 E/F 2.2 s, O/C 3.0 SecDesired time of operation E/F 250 ms, O/C 250 msTMS E/F 0.114, O/C 0.083Roundup to E/F 0.125, O/C 0.1
More Information
O/C E/F Relay & Time Coordination 13
O/C E/F Relay & Time Coordination
More Information
Introduction
• Fuse wire is simplest protection• Fusing ampere of copper wire of diameter ‘d’
expressed in ‘Cm’ is given by the formula A = 2530*d3/2
• Time taken by fuse to blow off depends up on fusing amperes
O/C E/F Relay & Time Coordination 14
Introduction
• For a wire of length L carrying current I and diameter d heat produced is
• H = I2R • H = I2σ (L/A)• H = I2σ ( L/(πd2/4))• Heat dissipated = K’ (πd)L ( i.e.
proportional to surface area where K’ is constant of proportionality)
• Temperature will be steady state if heat generated is equal heat dissipated or
• I2σ ( L/(πd2/4)) = K’ (πd)L• I2σ ( 1/(d2/4)) = K’ d• I2 = K’’ d3
• I = K d 3/2
• And by experiments for normal ambient temperature value of K for copper is determined as 2530 for d expressed in Cm.
O/C E/F Relay & Time Coordination 15
SWG D in mm D in Inch Amp Fusing Amp
Fusing Amp by Formula
40 0.122 0.0048 1.5 3 3.41
39 0.132 0.0052 2.5 4 3.84
38 0.152 0.006 3 5 4.74
37 0.173 0.0681 3.5 6 5.76
36 0.193 0.0076 4.5 7 6.78
35 0.213 0.0084 5 8 7.86
34 0.234 0.00921 5.5 9 9.06
33 0.254 0.01 6 10 10.24
32 0.274 0.0108 7 11 11.47
31 0.29464 0.0116 8 12 12.80
30 0.315 0.0124 8.5 13 14.14
29 0.345 0.0136 10 16 16.21
28 0.376 0.0148 12 18 18.45
27 0.416 0.0164 13 23 21.47
26 0.457 0.018 14 27 24.72
25 0.508 0.02 15 30 28.97
24 0.559 0.022 17 33 33.44
23 0.61 0.024 20 38 38.12 MoreMore
Protection of transformer by a fuse
O/C E/F Relay & Time Coordination 16
For T/F with normal load of 100 AmpFuse Transformer
CurrentFusing Time
Current
Safe Operation Time as per IEEE
Safe Operation Time With FOS 2.5
200 10000 200 1800 720430 5 300 300 120
1200 0.4 475 60 241800 0.2 630 30 122800 0.1 1130 10 4
2500 2 0.8
Simplest Protection – Fuse
• These characteristic graphs are generally double log graph
• This is due to including from very small to very large values on both axis
O/C E/F Relay & Time Coordination 17
Simplest Protection - Fuse
• Log scale graph are use full tool where range of values varies very widely
• This variation in range is generally 10,000 times
• It does not affect overall accuracy of selecting proper value manually
O/C E/F Relay & Time Coordination 18
• General mathematical formula for time characteristic of the relay as per IEC Standards
KTime Of Operation = ---------------------
( ( Is/Ib) α - 1 )
O/C E/F Relay & Time Coordination 19
• General mathematical formula for time characteristic of the relay shown on previous slide, with parameter values for different curves are shown here
O/C E/F Relay & Time Coordination 20
Characteristic α K
Normal Inverse 0.02 0.14
Very Inverse 1 13.5
Extremely Inverse 2 80
Long Time Inverse 1 120
Use of log scale-1
O/C E/F Relay & Time Coordination 21
Use of Log Scale-2
O/C E/F Relay & Time Coordination 22
Use of Log Scale-3
O/C E/F Relay & Time Coordination 23
Use of Log Scale-4
O/C E/F Relay & Time Coordination 24
Transformer – Protection – Damage Curve
• Damages to the equipment due to fault current flowing through it are mainly due to heating effect of the current ( I2Rt)
• Hence fuse time characteristic initially suited very well to the equipments in the power system
• This figure shows protection of transformer with the help of relay and breaker
• This also indicates how inverse characteristic of O/C Relay is suitable to protection of power system equipments
• ( More about Transformer Damage Curves)• ( More about this figure )
O/C E/F Relay & Time Coordination 25
Transformer – Protection – Damage Curve
• Transformer damage curve as per IEEE 57.109 for class – III transformers ( 5 MVA to 30 MVA )
O/C E/F Relay & Time Coordination 26
Protection of Transformer by O/C Relay
O/C E/F Relay & Time Coordination 27
Trafo Damage Curve
Long Time Inverse
Extremely Inverse
Normal Inverse
End of More Information
O/C E/F Relay & Time Coordination 28
After understanding basics of relay characteristic curves and its selection according to protection needs we will turn to allied information about O/C E//F relayingThis allied information will prove helpful in overall understanding about development of protective relays and its use in power system
Basic Information
O/C E/F Relay & Time Coordination 29
O/C E/F Relay & Time Coordination
Allied Information
Disadvantages of fuses
• Though simple less accurate ( If Rewirable)– Because of previous heating effect– Ambient Temperature– In consistencies in material– Limitations for breaking capacities hence suitable for LV and to
some extent MV
• HRC Fuses– More accurate– Higher rupturing capacities– Requires time for replacement– Suitable for LV and to some extent MV
O/C E/F Relay & Time Coordination 30
Early Development of Protective Schemes
• This simple device (Fuse) played a very vital role during early development of power systems
• As the complexity of power system increased other technique get introduced like breaker, relay DC battery etc. (How?)
O/C E/F Relay & Time Coordination 31
Early development of power system
• History of power system protection dates back nearly to the start of development of power system it self
• In real sense power system started growing due to invention of incandescent lamp by Edison during 1880
• Edison was promoter of DC power system ( Why ? )
• General Electric founded by him was main supplier of electricity in Newyork.
• Washington first introduced AC system with the advancement in transformer during 1887
• During 1890 charls introduced symmetrical component analysis which helped in analyzing 3 ph. Power system and there by possible to design larger machines and power systems.
• Modern day power system came into existence from 1890
• One of the patent of fuse is in the name of Edison
• Development of relays breakers and instrument transformers took place during 1890 to 1920 and modern day protection system came into existence.
• And during last century development of power system continuous to be there however main principles of power system protection are 3S and 1R remained same.
• Development of relays breakers and instrument transformers took place during 1890 to 1920 and modern day protection system came into existence.
• And during last century development of power system continuous to be there however main principles of power system protection are 3S and 1R remained same.
O/C E/F Relay & Time Coordination 32
General Requirements of Protective Scheme
• For any protective device following Functional Characteristic are important.– Sensitive– Selectivity– Speed– Reliability
• ( Note:- 3 S & 1 R )• As a improvement over simple fuses (in above
areas) other protective devices get developed with the advancement of power system
O/C E/F Relay & Time Coordination 33
3S & 1R
• Sensitivity is that property of protection system which enables it to distinguish between fault and no fault condition very correctly.
• As if we say that some animals are more sensitive than humans to natural disasters like earthquake.
• Where as selectivity is that property of the power system which enables it to isolate only the faulty part from healthy part.
• In this sense differential protection is most selective protection• Once the fault detected by SENSITIVE system and area to be
disconnected detected by SELECTIVE system then there comes the SPEED.
• This faulty section should be get cleared as early as possible.• For EHV system Faults are once in blue moon. Hence this all above
said things should happen RELIABELY even after 5-10 years from design and commissioning of the protection system.
O/C E/F Relay & Time Coordination 34
O/C E/F Relay & Time Coordination 35
Changing Trend In Protective Relaying• Protection relay is a tool for
protection engineer• During last 30 years relay
operating principles changed very drastically– Electromagnetic Relays– Static Relays– Digital Relays– Numerical Relays
• Though it is not required to design a relay or repair a relay at site it is customary to have some working knowledge of these relays for better understanding and use of it
O/C E/F Relay & Time Coordination 36
Electromagnetic Induction relays
O/C E/F Relay & Time Coordination 37
Static Relays
O/C E/F Relay & Time Coordination 38
Digital Relay
O/C E/F Relay & Time Coordination 39
Numerical Relay
Fu
nct
ion
s A
vaila
ble
in N
um
eric
al O
/C R
ela
y
Introduction
O/C E/F Relay & Time Coordination 40
R3 R2 R1
A B C
110 ms350 ms500 ms
1) Consider a representative part of a power system as shown above.
2) It is being protected by over current relay
3) Typical expected time of operation for over current relays are as shown
4) In next couple of hour we will see a) What is mean by relay characteristics curveb) How relay characteristic curve suites our protection needsc) How it helps us in deciding relay time of operation
d) Workout relay settings so that they shall operate at expected time
e) Methodology being adopted for selective tripping by over current relay including directional relay
Introduction
O/C E/F Relay & Time Coordination 41
R3 R2 R1
A B C
10 sec.25 sec.40 sec.
R3 R2 R1
A B C
200 ms220 ms180 ms
R3 R2 R1
110 ms350 ms500 ms
S
S
S
Study of Time Co-ordination and its role in design of protection scheme.
• Over Current and Earth Fault Protection is used for– Protecting a equipment– Selective tripping of faulty section of the
power system– Backing up the main protection
O/C E/F Relay & Time Coordination 42
Role of Over Current Relay in Protecting the Equipment
• It is obvious that over current protective system should act and interrupt the fault current before to damage of equipment due to fault current through it.
• Power system equipments include Line, Isolator, CT, Breaker, Transformer
• Obviously Transformer is most costliest and delicate (for fault currents) equipment first we will consider its damage curve and decide parameters of protection system so that it should act fast enough to protect the transformer
• This can be ascertained with the help of Damage Curve of the transformer and time-current curve of the protective system
O/C E/F Relay & Time Coordination 43
Role of Over Current Protection in Selective Tripping
• It is obvious that only that part of the power system should get disconnected where the fault exists
• Hence proper time co-ordination should be there so as to let the down stream protection should act fast enough and up-stream protection should give sufficient time for down stream protection to act
• Otherwise un-necessary larger area get affected
O/C E/F Relay & Time Coordination 44
O/C E/F Relay & Time Coordination 45
Backup Protection
• When ever main protection fails to separate the faulty section backup protection take up this role
• As such there is inherent time delay in operation of backup protection
• This backup protection can be employed in main protection itself as additional function, but invariably it is employed as a separate relay to ensure it’s operation even if failure of quantities/links which are common to both functions such as-– DC Source– PT supply– Relay hardware– Main CTs
O/C E/F Relay & Time Coordination 46
Back up protection
• EHV line faults are of sever nature from power system security and stability point of view. Hence must be cleared instantaneously
• For this purpose distance relays which operates instantaneously (Z1) are employed for protection of EHV lines
• For protection of EHV transformers differential and REF relays are employed which are also instantaneous
O/C E/F Relay & Time Coordination 47
Backup Relay Time Coordination
A C
E
F
X Y
Z
M