Upload
doananh
View
220
Download
1
Embed Size (px)
Citation preview
Preparedness at PFBR Kalpakkam to meet
the challenges due to Natural events
Prabhat Kumar, Project Director, PFBR,
Director construction BHAVINI
BHARATIYA NABHIKIYA VIDYUT NIGAM LIMITED
(A Government of India Enterprise)
PFBR REACTOR ASSEMBLY Item
1 Main Vessel
2 Core Support Structure
3 Core Catcher
4 Grid Plate
5 Core
6 Inner vessel
7 Roof slab
8 Large Rotatable Plug
9 Small Rotatable Plug
10 Control Plug
11 Absorber Rod Drive Mechanism
12 Transfer Arm
13 Intermediate Heat Exchanger
14 Primary Sodium Pump
15 Safety Vessel
16 Reactor Vault
PFBR Details
• No. of fuel Assemblies
• No. of pins in one Sub Assembly
•Refueling interval
• Pu enrichment Zone I/II
• Rx Coolant inlet /outlet
• Steam Temp. / Pressure
: 181
: :217
: 185 EFPD
: 20.7 / 27.7 wt %
: 397 / 547 ºC
: 490 ºC / 167 Kg/Cm2
PFBR Flow Sheet
PFBR
• PFBR is being constructed near the coast of Bay
of Bengal.
Task Force has been constituted to review the issues
related to the:
• safety of reactor,
• spent fuel storage facility
• Multiunit site
• and other related issues arising due to natural
events.
Issues • Public perception is very low
– Equipment failure
– Human error
– Matural Event
Public is affected
• Livelyhood
• Fear of new issue:
– Design?
– QA?
– Materials?
– Manufacturing?
– Terrorism?
– Insider Threat?-Even operator must not be able to damage the core
Public is not concerned of source of
electricity-
Several decades of effort of nuclear
technology development is
at risk if we can not win public
confidence
Site
• Coastel- What if flooded due to cyclone
• Height of water during tsunami
• Effect of splash due to tsunami;
– Equipment
– Drainage
To be taken care
•Reactor Shutdown, maintaining core cooling and
containment integrity
• Gravity drop
•Cooling in every scenario:
• Operational Grade Decay Heat Removal
(OGDHR) • 4 loops are provided, each loop having capacity of 8
MWTh. (Total decay heat 20 MWTh)
Safety assessment of external events leading to BDBA
conditions to review and address the following parameters /
issues :
• Capability for reactor shut down, maintaining shut
down condition and core cooling
• Capability to maintain containment integrity under
credible BDBA conditions
Review of DBA and BDBA conditions to assess
the strengthening / upgradation of the systems
required to ensure the containment integrity.
Provision of reactor trip on seismic event
• Guard pipe is provided around primary sodium
piping
• Leak collection trays are provided for the
secondary sodium piping.
• All pipe lines are of welded construction-
No valves in primary main circuit
• Sodium fire fighting system is established
Support Systems • Alernate Battery bank
• Spares
• Obstruction clearence
• Communication
• Large scale public movement
• Shelters
Storage of large quantity of Sodium in the
Primary and Secondary systems
• Whether SGB could get flooded
– Can Sea water enter and affect the SS
– Whether fire fighting system is adequate
– Whether Cables have joints that can get affected
– Whether Adequate diesel supply can be ensured
– Water sources
– Can servive water, raw water and DM water get
affected due to sea water ingress?
Spent fuel Storage
Review of the spent fuel storage pool for seismic event
higher than the design value.
Review of possible cracks due to higher seismic, possible
pipe line failure and provisions to make up the water level.
Review of any possible fall of heavy object on storage pool
during the seismic event.
Spent fuel Storage
• Spent fuel is kept in the spent fuel storage location in
the reactor core for about two cycles.
• Hence decay heat of the spent fuel will be less
when it is removed for storage in spent fuel
storage pool.
• 45,000 Litres capacity demineralised water storage
tank installed in the Fuel Building can supply water
to spent fuel storage bay in case of failure of normal
source.
• Yet provision planned for additional cooning
facility
Effect on Spent Fuel and Fresh Fuel
assemblies storage facilities to remain
intact
• Analysis
• Water supply possibility
•Availability of Diesel Generator beyond design
basis scenario
•Possibility of hooking up back-up power supply
system in the event of plant Diesel Generator
unavailable
Availability of Emergency Diesel Generators
on wheel/ provision of backup power supply-
Levels and Roads
Accident management strategy
• Emergency preparedness – Emergency Crew
• Adequacy of the approaches to the plant site to
handle emergency scenarios
• Accident management
• (site & off site-NDMA, NDRF)
Preliminary review has indicated that we
donot have much concern- many concerns
were addressed after 2004 tsunami
• PFBR plant is designed to be safe in all
natural eventualities such as tsunami ,
earthquake, cyclone & flood.
• Kalpakkam comes in Seismic Category
Zone III as per the seismic classification.
• For PFBR, the Design Basis Flood Level is fixed
as 6.45 metres above Mean Sea Level (MSL)
based on 1000 years return period
• During the worst ever Tsunami that stuck
Kalpakkam in Dec. 2004, the maximum water
level rise was 4.71 metres above MSL.
• After the Tsunami at Kalpakkam in Dec. 2004,
shore protection and Tsunami bund made out of
engineered boulders stacked at a height of 5.4
Meters above MSL was erected for breaking
the intensity of sea waves during tsunami.
25
Tsunami bund
Shore protection
• The finished floor level of Safety related
Buildings are at 9.604 metres above Mean Sea
Level (MSL) :
• The finished floor levels of Safety related
Buildings are 3.15 metres above Design Basis
Flood Level (6.45M)and 4.9 metres above the
maximum water level rise observed during
Tsunami in Dec. 2004 (4.71 M))
• Hence operation of Emergency Diesel
Generators, reactor safe shut down & cooling
and spent fuel cooling will not be affected
during a design basis Tsunami event.
Hydrogen Issue
•In PFBR water is not used as the coolant for reactor.
This precludes any possibility of hydrogen
generation/explosion in RCB.
•Fuel clad material is not Zirconium (it is Alloy D-9 an
alloy of Cr , Ni, Mo, Ti & Si). Hence no metal – water
reaction & hydrogen generation in Spent fuel storage
facility in case loss of cooling.
•However Hydrogen due to BSC water and sodium
need to be studied
Emergency Diesel Power
•PFBR is provided with four diesel generators
•Two are sufficient to meet the station requirement
• All four DGs are in separate buildings
2 are in east . Remaining 2 are in the west side of Main
plant building , away from sea side.
• Located at 9.604 meters above MSL
• An in-depth study by the Task Force is in
progress to review & identify any weakness
Based on the review and recommendations of
Task Force, modifications will be carried out to
address these issues.
Erection of steam generator
• Mock up work completed as per the guide lines
of PDSC.
• Welding commenced
Sea water Intake
1. Sinking of caisson has reached
beyond soft rock region.
2. Concreting of caisson completed
for 12 m depth from cutting edge.
3. Inside caisson chiseling and
grabbing work is in progress.
4. On top of jetty pipe line pedestal
work is in progress.
Major TG equipment's at site
Around 4000 Tons of material
reached site in TG package
Thank you