Binamare Sub-Health Post Building
Construction Support Project
Binamare VDC- 4, Baglung, Nepal
Funding Organisation:
Rotary Stiftung – Rheine,
Germany
Implementing Organisation:
Social Welfare Association Of Nepal
(SWAN)
Introduction of Village and Health Service
� Binamare VDC is situated in the southern part, about 25 km far from district
headquarters of Baglung.
� There are 9 wards and population more than 3,500 in this VDC.
� The area is composed with various ethnic community inhabitants, such as,
Brahmins, Magars, Chettris, Sarkis, Damai, Newar, and other castes.
� This community life is based on farming and livestock.
� The sub-health post is the only health service institution for people in this area.
� The current sub health post is situated in a building which is a part of a
secondary school and is in a ruined and poor condition, which is not at all
suitable to carry out the task of providing health care facilities.
� In order to get out of this difficult situation to provide the health services to the
people, it was an urgent need to have a sub-health post building being
constructed in order to provide health services to the local community.
SHP Organogram
There are 4 staff in Binamare Sub-health post provided by the government
SHP
Management
Committee
Incharge -
Auxiliary Health
Worker(AHW)
Village Health
Worker (VHW)
Maternal & Child
Health Worker
(MCHW)
Office Helper
Program introductory workshop
A workshop on project work was conducted, and the SWAN representatives,
Village Development Committee members, all political party representatives,
representatives of various groups of the village and Binamare Sub-health Post
Management committee member and staff participated.
The Binamare Sub-health post construction site was observed by
SWAN President Mr. Krishna Karki, Project manager, Mr. Sakas G. C., together
with the Sub-health Post Management Committee and the site was finalized.
The following are the major activities that have been carried out during the
project period:
� Formation of a SHP construction committee
� Coordination with District Development Committee, District Health Office,
and Village Development Committee
� Constructed 6 rooms for SHP building
� Constructed a toilet
� Fences to be constructed
� Making furniture has been started
� Equipment to be supplied
� Drinking water supply to be constructed
Major activities
Formation of SHP construction committee
A Construction Management Committee was formed with 11 members and they
were briefed about the project by the SWAN project Manager. The following are
the members in the committee:
1. Mr. Krishna Bahadur Hamal President
2. Mr. Prabanna B. K. Vice-President
3. Mr. Tanka Bahadur K. C. Secretary, SHP In-charge
4. Mr. Prem Bahadur Thapa Treasurer
5. Mr. Khum Bahadur Roka Member
6. Ms. Manaka Roka Member
7. Mr. Krishna Paudel Member
8. Mr. Prem Bahadur Malla Member
9. Ms. Pabitra Paudel Member
10. Mr. Bhanu Bhakta Pandey Member
11. Mr. Lal Bahadur Thapa Member
Members and Chairperson, Mr Krishna Bahadur Hamal (Right) of the Building
Construction Committee commencing the construction work
SHP building construction committee chairperson, Mr. Krishna Bahadur
Hamal (left) and SHP incharge, Mr. Tanka Bahadur K. C., carrying out the
measurement work of the SHP construction site and planning other work
District Health Officer,
Mr. Arjun Adhikari (centre)
participated the
foundation
laying ceremony
First phase Activities“A Laying of foundation stone event”
A supervision work was carried out by SWAN President, Krishna Bahadur Karki,
Project Manager, Sakas G. C and staff
Estimated Budget
Amount
Requested
from Donors
To be funded
by District
Development
Committee
To be funded
by
District Health
Office
To be funded
by Village
Development
Committee
Community
contribution Total Budget
Rs.1,548,406 Rs.100,000 Rs.100,000 Rs.300,000 Rs.500,000 Rs. 2,548,406
Euro : 16,507 Euro:1,066 Euro:1,066 Euro: 3,198 Euro :5,330 Euro: 27,168
ROTARY STIFTUNG – RHEINE,
BINAMARE SUB HEALTH POST CONSTRUCTION PROJECT
(SWAN 2011/12)
1 Fund received from Rotary Stiftung - Rheine Feb 13, 2011 € 3.980,00
2 Fund received from Rotary Stiftung - Rheine June 27, 2011 € 3.980,00
3 Fund received from Rotary Stiftung – Rheine October 13, 2011 € 3.980,00
4 Fund received from Rotary Stiftung – Rheine February 02, 2012 € 4.567,00
Total fund received from Rotary Stiftung - Rheine, € 16.507,00
Community Contributions and VDC Support
PROJECT
BINAMARE SUB HEALTH POST CONSTRUCTION
SWAN 2011/12
1 Fund received from Binamare Village Development Committee Rs. 400,000
2 Community Contributions:
(a) Provided land for building construction
(b) Construction site leveling work
© Provided stone for wall
Rs. 300,000
Rs. 50,000
Rs. 200,000
Total Community Contributions and VDC support in Nepali Rupees
Total Community Contributions and VDC support in Euro
Rs. 950,000
€ 10,128
Expenditure Report
BINAMARE SUB HEALTH POST CONSTRUCTION
SWAN 2011/12
Descriptions
First Phase
Expenses
Second Phase
Expenses
Third Phase
Expenses
Fourth
Phase
Expenses
Total
1 Program Introductory
Cost 26,735 0 0 0 26,735
2 Wages 204,100 329,350 250,200 145,680 933,085
3 Construction Materials,
Transportation and other
costs
256,250 133,205 259,153 315,879 960,732
Total in Nepalese Rupees 487,085 462,555 509,353 461,559 1,920,552