Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1 | P a g e
BOARD OF INQUIRY
BASIN BRIDGE PROPOSAL
UNDER the Resource Management Act 1991.
IN THE MATTER of a Board of Inquiry appointed under s149J
of the Resource Management Act 1991 to
consider applications for a notice of
requirement and resource consents made by
the New Zealand Transport Agency in
relation to the Basin Bridge.
SUPPLEMENTARY EVIDENCE OF LAWRENCE MURRAY PARKER
ON BEHALF OF SAVE THE BASIN CAMPAIGN INCORPORATED
3 MARCH 2014
Barristers and Solicitors
PO Box 25 433 Featherston Street Wellington Tel: 64-4-4735755
Counsel acting: TH Bennion
Contact: Tom Bennion
DDI: +64 4 473 05755
Email: [email protected]
2 | P a g e
Contents 1.0 Introduction .................................................................................................................. 3
2.0 Purpose ........................................................................................................................ 3
Part A: Summary of Statement of Evidence .............................................................................. 3
Part B: Supplementary Evidence ............................................................................................... 6
4.0 Introduction – Supplementary Evidence ........................................................................ 6
5.0 NZTA BCRs: Strategic Fit vs. Economic Efficiency ........................................................... 6
6.0 TR17 BCR (of 1.2): NOT A BCR FOR THE PROJECT ........................................................... 7
7.0 THE BUCKLE STREET THIRD LANE .................................................................................. 7
8.0 PROJECT COST .............................................................................................................. 8
9.0 WIDER STRATEGIC FIT OF THE PROJECT......................................................................... 9
10.0 CAPACITY AVAILABLE IN THE EXISITNG BASIN RESERVE ROUNDABOUT ....................... 12
11.0 NZTA REBUTTAL OF MY STATEMENT OF EVIDENCE ..................................................... 13
APPENDIX A (1): OVERVIEW OF THE BCR METHODOLOGY ...................................................... 14
APPENDIX B: Application Documents BCR (TR 17) Overstated ................................................. 18
APPENDIX C: Revised BCR (2.0) Overstated ............................................................................. 19
APPENDIX D: NZTA Economic Evaluation Manual – Definition of “Do Minimum” .................... 20
APPENDIX E: Email Correspondence - Susan Rawles of NZTA ................................................. 21
APPENDIX F: Response to NZTA Rebuttal Evidence ................................................................. 23
3 | P a g e
1.0 Introduction
1.1 My name is Lawrence Murray Parker.
1.2 I have previously provided a Statement of Evidence (economic assessment) and
of Rebuttal Evidence for the Basin Bridge Proposal. My qualifications and
credentials are noted in section 1 of my Statement of Evidence. I attested to
the Code of Conduct requirement in section 2 of that Statement and confirm
that I continue to abide by that requirement. I again confirm that I agree to
comply with the “Expert Witness Code of Conduct”. I also again acknowledge
that I am a member of the organising committee for the Save the Basin
Campaign Incorporated and that in accordance with the Expert Witness Code
of Conduct I am not herein advocating for the Save the Basin Campaign.
1.3 I participated in the expert conferencing (economics) for the Proposal and
signed the Joint Witness Statement from that conference.
2.0 Purpose
2.1 This statement addresses the NZTA economic assessment of the Project, and in
particular the BCR. Part A provides a summary of my earlier Statement of
Evidence (SoE) of 13 December 2013. Part B provides supplementary evidence
based on further findings since that Statement was submitted, including a
response to the Rebuttal Evidence of Mr Copeland and Mr Blackmore, both of
whom appear for the NZTA.
Part A: Summary of Statement of Evidence
3.1 Appendix A provides a framework for considering the various BCRs presented
by NZTA in support of the Project. It is provided in this document because
there seems uncertainty about how to properly consider the BCR. Appendix A
also provides an explanation of the relevance of the 2021 and 2031 transport
models used by NZTA to support their analysis of the Project. This is provided
to explain how the benefits of the Duplicated tunnel projects ripple across the
entire benefits analysis provided by NZTA. It further clarifies that while the
4 | P a g e
2031 Models measure benefits inclusive of the Duplicated Tunnel projects,
those projects are actually assumed commissioned in an unspecified time well
before 2031.
3.2 The BCRs provided by NZTA overstate the BCR of the Project itself, and do not
provide a proper assessment of the Economic Efficiency of the Project. The
original BCR presented in application documents (TR 17) was overstated
because it included contingent benefits. Eliminating contingent benefits
reduces the BCR to between 0.2 and 0.3. This is illustrated in Appendix B.
3.3 In EIC, NZTA revised the BCR to 2.2. In rebuttal evidence and as explained in Mr
Dunlop’s Summary of Evidence (section 2), this was reduced to 2.0 following
the correction of errors. I will refer to this lower number even though my SoE
addressed the earlier number of 2.2. The revised BCR was similarly overstated
because it included contingent benefits. It also included a number of other
changes which inflated the BCR. These have since been more fully identified by
Mr Dunlop as being due to the 3rd lane at Buckle St (and associated
improvements to the Taranaki Street intersection) and the various Vivian Street
works1. These should be excluded from the Project BCR (included in the Do
Minimum) because they are either part of the existing baseline (Buckle St) or
fall within an existing designation (Vivian St works). On the basis of available
evidence, the BCR excluding contingent benefits and the Buckle St and Vivian St
works would be well short of parity. These issues with the revised BCR are
illustrated in Appendix C.
3.4 The project cost estimate of $90M has not been updated since it was
completed for the March 2012 SAR2 even though considerable works have
been added since then. These added works include the Northern Gateway
Building, the Building under the Bridge, the Green Screen and the further
1 In his rebuttal evidence (Annexure B table 12), Mr Dunlop identifies these projects as adding $50M of
the total benefits included in the BCR of 2.0. In his Supplementary Information Statement Mr Dunlop estimated a BCR of 1.4 excluding these projects. That BCR will still include the contingent benefits associated with the Bridge part of the Bridge Project. 2 Refer Appendix B of Appendix E, Basin Reserve SAR (March 2012)
5 | P a g e
mitigations agreed between NZTA and WCC). The project cost should therefore
have been updated.
3.5 The BCR assessment was based on a comparison of the Project against a “worst
case” scenario. This further inflated the BCR: it assumed a “Do Maximum” (the
Duplicate Tunnels) which created increased traffic demands on the Basin
Reserve zone; at the same time it assumed a “Do Nothing” for the Basin
Reserve itself. Overlaying the Project over this “worst case” Do Minimum
provided “relief” to the artificially stressed environment and delivered an
inflated assessment of benefits.
3.6 Apart from the flawed BCRs, NZTA has provided no other measurement based
evidence in support of the Project. The opinion based evidence that was
provided has not been assessed against the cost of the Project, and is difficult
to weigh against other effects of the project. My view therefore remains that
NZTA has not established proper economic justification for the Project.
6 | P a g e
Part B: Supplementary Evidence
4.0 Introduction – Supplementary Evidence
In this Supplementary Evidence, I address:
The NZTA use of “Strategic Fit” rather than “Economic Efficiency” BCRs
in its economic assessment (section 5)
The BCR in TR17 was not a BCR for the Project for which consent is
sought (Section 6)
The Buckle St Third Lane (Section 7)
The Project Cost (Section 8)
The wider Strategic Fit of the Project (Section 9)
The “Do Nothing” assumption for the Basin Reserve (Section 10)
Response to NZTA Rebuttal Evidence (Mr Blackmore and Mr Copeland)
(Section 11)
5.0 NZTA BCRs: Strategic Fit vs. Economic Efficiency
5.1 The BCRs presented in the NZTA Economic Assessment (TR17), EIC and rebuttal
evidence provide an assessment of the Project’s “strategic fit” to the wider
NZTA Northern Corridor RONS strategy. The BCRs are based on benefits that
the Project could deliver if that entire RONS programme is completed
(including current unconsented and unfunded projects). These BCRs have been
calculated to meet the needs of NZTA decision making processes rather than
for the RMA consenting process. They are useful for NZTA (and are useful
background for the BOI) as they show how the Project “fits” with the wider
NZTA strategy. NZTA would also seek to maximise the “strategic fit” BCR when
selecting between alternatives.
5.2 In my opinion however, these BCRs provided by NZTA do not measure the
economic efficiency of a Project for consenting purposes. An “economic
efficiency” BCR should only include the costs and benefits estimated to occur if
the Project itself is approved. Further benefits that might be crystallised from
other future projects would then be counted in the economic efficiency BCR of
7 | P a g e
those future projects. This is the same as for any infrastructure (including this
Bridge Project) built into an existing network.
6.0 TR17 BCR (of 1.2): Not a BCR For the Project
6.1 The BCR provided in the Economic Assessment of the Project (TR17) was not in
fact a BCR for the Project described in application documents, but was based
on an earlier version of the Project. It seems to have been prepared for NZTA
internal decision making purposes. Having served that purpose, NZTA decided
it was not necessary to revise that BCR, even though the Project as submitted
for consent was materially different to that earlier version of the Project.
Subsequent BCRs have been more correctly based on the Project as presented
for Consent but remain substantially overstated. NZTA should have provided
proper BCRs for the Board to consider, and could have provided proper BCRs
had they complied with their Economic Evaluation Manual, especially in terms
of setting the Do Minimum.
7.0 The Buckle St Third Lane
7.1 It is acknowledged that whether the Buckle St third lane is part of the Project
or of the Do Minimum remains contentious. In his presentation of evidence at
the Hearing, Mr Blackmore indicated the Buckle St third lane can only safely be
used if approached from the proposed Bridge. Mr Blackmore still then
considers the third lane and associated benefits should rightly be included in
the Project. I am not aware that this safety issue has been raised previously in
evidence. It was not raised in Mr Blackmore’s Opening Statement and appears
to remain undocumented apart from verbal evidence provided by Mr
Blackmore. There seems to be disagreement amongst NZTA experts on this
matter. Furthermore, at the time the Project application was submitted to the
EPA, NZTA held a different view to that now presented by Mr Blackmore. In
June 2013 I requested clarification from NZTA on this issue. In her email of 2
July 2013 (Appendix D) Susan Rawles of NZTA advised me that in the event the
Basin Bridge did not proceed:
8 | P a g e
“a decision will need to be made in respect of when the third lane within the
Underpass might be usefully opened and the improvements if any that are
required to other parts of the network as part of the opening of that
additional lane” [highlights not in original].
7.2 At the time this seemed a sensible response. More so now it is clear that the
benefits of relieving the Taranaki St bottleneck are substantial; more
substantial indeed (by a factor of 4) than the time saving now attributed to the
Bridge in the AM peak3. It is not clear why the newly raised safety issue could
not be remediated in the Do Minimum. Unless there is clear evidence to the
contrary, in my opinion the entire Buckle St project is part of the Do Minimum
and the benefits of the third lane should be excluded from the Project BCR.
8.0 Project Cost
8.1 Further to paragraph 3.4 above, there are further differences between the
March 2012 SAR Project Cost estimate and the Project in the consent
application. These include the Vivian Street works, and differences between
Buckle Street works in the SAR and in the final Project.
8.2 Turning again to the Northern Gateway Building, this was initially proposed by
the Basin Reserve Trust. It was considered but rejected in the March 2012 SAR
which concluded “it is not proposed to construct a Grandstand as part of the
Project”. Amongst other things, the SAR cited adverse visual and heritage
effects of the building4.
8.3 As documented in an MOU, and in a subsequent Agreement between NZTA,
Wellington City Council and the Basin Reserve Trust,5 the NZTA subsequently
reversed its position on the Grandstand/Northern Gateway Building. In the
MOU, the parties agreed they would work together to ensure the 65 Metre
option for the Northern Gateway Building (the subject of the Specific
3 Of the total 7.5 minutes time saving for the East/West journey in the AM peak, 80% is attributed to
relieving the Taranaki St bottleneck while just 20% is attributed to the Bridge itself. 4 Refer page 129 Section 8.7 for the March 2012 SAR assessment of the building proposal. Note that at the time, the building was referred to as a “grandstand”. 5 Both the MOU and subsequent Agreement are appended to Mr Blackmore’s rebuttal evidence.
9 | P a g e
Agreements in clause 3 of the MOU) can mitigate the adverse effects of the
Bridge “in such a manner as not to prevent the New Zealand Transport Agency
from obtaining consent for the bridge” (clause 2.1.1 of the MOU). In clause 3.6
the parties further agreed to support the 65 metre building [as mitigation]
separately from any expert evidence. This reversal of the NZTA position on the
matter can be considered against the fact that at the time of the March 2012
SAR, the Basin Reserve Trust was identified as the highest source of outturn
cost risk for the project6, and that the Basin Reserve Trust stuck to its original
position regarding its proposal for a “Grandstand”. This suggests that the
decision by NZTA to reverse its previous position and to proceed with the
Northern Gateway Building came at some cost and this could be expected to
be reflected in an updated Project Cost.
8.4 This further evidence adds more weight to my opinion that the Project Cost
should have been reviewed and updated since the March 2012 SAR.
9.0 Wider Strategic Fit of the Project
9.1 While it is important to properly assess the economic efficiency of the Project
itself, an economic assessment should also include an assessment of the
strategic fit of the Project. The proposed Basin Reserve improvements occur at
an important “intersection” of two key strategies: the Northern Corridor RONS
and the Ngauranga to Airport Corridor Plan (including the Public Transport
Spine Study). The Basin Reserve and the route for the Mt Victoria Duplication
project are key routes for both of these strategies – see Figure 1 below.
Figure 1: The Basin Reserve Improvements – an intersection of strategies
6 SAR March 2012, Appendix E page 11, Table 4
10 | P a g e
9.2 NZTA expert evidence relies significantly on the Ngauranga to Airport Corridor
Plan (NtoAC) and the outcomes of the Public Transport Spine Study (PTSS).
Much has been said about the Bridge enabling a “step change” for the PTSS
plans. A strategic fit assessment of the Bridge Project to the NtoAC and the
PTSS has however not been carried out. NZTA has instead clearly focussed its
strategic fit assessment on the RONS strategy. This is evidenced by:
Mr Blackmore’s assertion that the only relevant BCR for the Project is
the BCR for the Northern Corridor RONS7
The inclusion of the unconsented RONS projects in the Do Minimum,
while no attempt being made to reflect the PTSS projects
The insignificant Public Transport and Active mode benefits actually
assessed and included in the Project BCR analysis
9.3 In my opinion, an assessment of the strategic fit of the Project to the PTSS is
also required. This cannot be performed properly until the PTSS confirms its
choice of strategies and key design decisions are made. It is acknowledged that
7 Paragraph 7.3 of Mr Blackmore’s rebuttal evidence: “the Transport Agency is advancing the Project as part of the Wellington Northern Corridor RONS programme ... Accordingly the only relevant BCR for the Transport Agency is the [RONS] Programme BCR.
11 | P a g e
the NtoAC anticipates separation of vehicle flows at the Basin Reserve and this
is consistent with the Project. However, separation was not an objective of the
NtoAC Plan. It was a means to an end, and a detailed economic assessment of
whether it is the “right” means to that end can best be made only when the
“end” is determined, and at some level of detail.
9.4 A wider “strategic fit” assessment also seems to have been overlooked. This
concerns the interdependencies, and possible tensions and conflict between
the objectives of the RONS and the objectives of the PTSS. For example, the
preferred Bus Rapid Transport option of the PTSS seeks dedicated corridors
(dedicated bus lanes). In the case of the East/West spine this potentially
includes dedicated bus lanes in the duplicated Mt Victoria Tunnels8. This would
require a balancing of vehicle and Public Transport priorities along the
East/West corridor and through the Mt Victoria Tunnels. The outcome of that
balancing of priorities could have a substantial impact for both the assessment
of transport outcomes of the Bridge proposal, as well as the design of the Basin
Reserve and of the Bridge itself (e.g. the off ramp from Patterson to Dufferin St,
which in the Project is designed as one lane). The need to integrate the PTSS
and RONS strategies seems clear. This would ensure that possibly conflicting
priorities are assessed strategically, targets are set, and funds are properly
allocated to meet the confirmed priorities and targets.
9.5 The Urban RONS and the PTSS strategies anticipate very substantial
expenditures. A proper strategic fit assessment would consider the
interdependencies between these strategies and establish overarching
transport priorities and objectives for the affected Central Wellington zones.
Assessment of this wider strategic fit is an important issue that should be
addressed in an economic assessment of the Bridge Project. This cannot be
addressed by considering either the RONS or the PTSS plans in isolation.
8 On page 14 of its report to the Wellington City and Regional Councils, the Public Transport Spine Options Hearing Subcommittee noted “as a first step we agreed that it would be desirable for NZTA to plan for a designation over this corridor to include a provision for dedicated bus lanes”.
12 | P a g e
10.0 Capacity Available in the Existing Basin Reserve Roundabout
10.1 NZTA has indicated some urgency is needed to progress with the Project, and
that delays could undermine the timetable for the Mt Victoria Tunnel
Duplication project. This urgency seems to be based on the assumption that
the Basin Reserve is currently operating at capacity and would not be able to
handle the increased demand that might arise from the Duplication project.
The “Do Nothing” assumption for the Basin Reserve that was included in the
Project Do Minimum reflects this same assumption. Mr Dunlop’s rebuttal of
the BRREO9 indirectly confirms the “Do Nothing” assumption is flawed. In
Annexure B of his rebuttal evidence, Mr Dunlop provides an assessment of the
BRREO. He concludes that the BRREO (basically an optimisation of the existing
roundabout) delivers over 60% of the benefits attributed by NZTA to the Bridge
proposal. This is achieved with the relatively minor upgrades anticipated in the
BRREO. This suggests the urgency that NZTA has attributed to the Proposal is
misplaced.
10.2 Including Basin Reserve Optimisation in the Do Minimum would provide
further insight into the “Strategic Fit” of the Project – it helps answer the
question: is the Project necessary? This further “Strategic Fit” BCR is illustrated
in Figure 4 of Appendix C. An assessment of further optimisation for the
current Basin Reserve layout could have more properly shaped an assessment
of the need for the Project, the urgency for the Project, and the benefits
available to the Project. For example, according to Mr Dunlop’s analysis, the
Bridge itself delivers $96M of tangible benefits, of which $39M is available
from optimising the existing Basin Reserve layout. Thus for an incremental cost
of, say $77M ($80M10 less cost of BRREO, say $3M), the Project delivers
benefits of just $58M, or a “strategic Fit” BCR of 0.8. The contingent benefits
associated with the Duplicated Tunnels would need to be deducted from this
9 Dunlop Rebuttal Evidence, Annexure B Tables 12 and 13 10
The NZTA estimated cost of the Project is $90M. For purposes of the BCR, this future expenditure is discounted to $80M in the same way that future Project benefits are discounted.
13 | P a g e
BCR to determine an economic efficiency BCR; that could be expected to be
considerably lower than 0.8.
11.0 NZTA Rebuttal of my Statement of Evidence
Mr Copeland and Mr Blackmore provided rebuttal for NZTA for my Statement
of Evidence. I have responded to their rebuttal in Appendix F.
Lawrence M Parker
5 March 2014
14 | P a g e
APPENDIX A (1): OVERVIEW OF THE BCR METHODOLOGY
PART 1: Measurement of Benefits: Project vs. Do Minimum
1 NZTA has represented a variety of BCRs in evidence statements. This includes a
BCR for the Northern Corridor RONS, a BCR for the “Tunnel to Tunnel” suite of
projects, and BCRs which are represented as being for the Project itself. The
BCR is a simple discounted cost benefit analysis concept. All BCRs can provide
insight and can be relevant for specific purposes. The important point is to
ensure the BCR being used is “fit for purpose”. A key part of that requires that
only benefits and costs relevant to the purpose are included in the BCR.
2 Figures 1 to 3 below provide a schematic framework for considering the BCR. In
Figure 1 the “Do Minimum” is the transport infrastructure we currently have or
assume to have in the future. The “Project” represents the changes to the
transport infrastructure we are considering. Figure 2 shows that the outcomes
of the Project (inclusive of the Do minimum) are compared to the outcomes of
the Do Minimum infrastructure. The difference between the two (change
(delta) in costs and benefits) determines the BCR for the Project (Figure 3).
15 | P a g e
PART 2: Relevance of the 2021 and 2031 Models for the Basin Bridge Project Analysis
Frequent reference is made in NZTA evidence to the 2021 and 2031 transport models.
These have been used to assess the delta of benefits attributed to the Project. It is
important to note that while the 2031 model includes the unconsented RONS projects
(Duplication of the Tunnels, Ruahine St and Wellington Rd works), that is not the same
as assuming those works are completed in 2031. These unconsented projects are
assumed to be commissioned at an undefined earlier date. The benefits attributed to
the Project from the unconsented works in fact ripples through the entire period of
benefits from 2017 to 2053. This is illustrated in Figures 1 to 3 below. Figure 1 shows
the two modelled years. Figure 2 shows that the benefits in the intervening years are
assumed equivalent to a straight line interpolation between the years. Figure 3 shows
that the rate of change in benefits between 2021 and 2031 is assumed to persist
beyond 2031. The same rate of change is inferred into the benefits for 2017 to 2020.
There is no valid basis for either these latter assumptions.
16 | P a g e
Figure 1: Benefits modelled in 2021 and 2031 (relative values for illustration only)
Figure 2: Benefits between 2021 and 2031 estimated by “straight line” interpolation (relative values for illustration only)
2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Basin Bridge Project: Benefits (before discounting)
17 | P a g e
Figure 3: Benefits extrapolated forward to 2053 and “backward” 2017 (relative values for illustration only)
The benefits attributed to the Project are the sum of the “bars” shown in Figure 3
(after those values are discounted). The chart demonstrates the relationship between
the 2021 and 2031 model values and the overall 40 year benefits analysis. The benefits
stretching beyond 2031 simply assume the same rate in growth of benefits as
interpolated between 2021 and 2031. This has not been validated. It would be more
appropriate to assume no change in benefits after 2031 (i.e. which would result in a
“flat line” in the Figure 7 chart from 2031). The assumption that the rate of change in
benefits prior to 2021 would be the same as the interpolated rate of change has no
basis.
Benefits are extrapolated forward and backwards by assuming the same rate of change as for the interpolated years 2021 to 2031.
20
17
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
31
20
32
20
33
20
34
20
35
20
36
20
37
20
38
20
39
20
40
20
41
20
42
20
43
20
44
20
45
20
46
20
47
20
48
20
49
20
50
20
51
20
52
20
53
Basin Bridge Project: Benefits (before discounting)
18 | P a g e
APPENDIX B: Application Documents BCR (TR 17) Overstated
Figure 1 : Application | Figure 2 : Remove Unconsented
Documents - BCR = 1.2 | works - BCR = 0.2 to 0.3 (2)
[A "Strategic Fit" BCR] | [An "Economic Efficiency BCR]|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
| (2) L M Parker, Satement of Evidence.
DO MINIMUM
PROJECT
Tunnel
Duplications
ICB 3 lane -
2031
Basin Bridge
3 Lane
Buckle St (1)
(1) At grade; Taranaki St
bottleneck not remediated
DO MINIMUM
PROJECT
Tunnel
Duplications
ICB 3 lane -
2031
Basin Bridge
3 Lane
Buckle St (1)
(1) At grade; Taranaki St
bottleneck not remediated
19 | P a g e
APPENDIX C: Revised BCR (2.0) Overstated
20 | P a g e
APPENDIX D: NZTA Economic Evaluation Manual – Definition of “Do Minimum”
21 | P a g e
APPENDIX E: Email Correspondence - Susan Rawles of NZTA
From: Susan Rawles [mailto:[email protected]]
Sent: Tuesday, 2 July 2013 12:18 p.m.
To: 'Murray Parker'
Cc: Greg Lee
Subject: RE: Basin Reserve Flyover - Guide to Lodgement Document
Hi Murray,
Technical reports 4 and 5 have different definitions and terms. They are two distinct technical
fields and each report provides their own definitions based on best practice, and for noise
allowing for the relevant New Zealand Standard (NZS 6806).
Page 1 of the Technical Report 5 provides an explanation of the ‘do-nothing’ and ‘do-
minimum’, as follows:
the noise environment that would receive the Project, being the road layout without the Project as it would exist in 2021 operating with 2021 traffic for that road layout, termed the do-nothing receiving situation;
the noise environment with the Project in the road layout as it would exist in 2021 operating with 2021 traffic for that road layout including the Project, termed the do-minimum Project situation.
‘Do nothing’ as a term is not used in transport assessments as it might be taken to imply that
no improvements are undertaken to transport infrastructure/ network. Instead ‘do minimum’
is used which is ‘the minimum investment to maintain the network operation’ and accordingly
it includes planned improvements to the network but excluding the Project. See page 13
section 3.3.4 of Technical Report 4 for detail.
The ‘do minimum’ transport scenario includes two operational lanes of the Buckle street
underpass. The third lane will become operational as part of the Basin Bridge project opening.
If the Basin Bridge Project is not consented or does not proceed then a decision will need to be
made in respect of when the third lane within the Underpass might be usefully opened and
the improvements if any that are required to other parts of the network as part of the opening
of that additional lane.
I trust that the above is helpful and clear. If you want to discuss any aspect of the above then
please do not hesitate to contact me.
Kind regards,
Susan Rawles
From: Murray Parker [mailto:[email protected]]
Sent: Sunday, 30 June 2013 2:17 p.m.
To: Susan Rawles
Cc: Greg Lee
Subject: RE: Basin Reserve Flyover - Guide to Lodgement Document
22 | P a g e
Thank you Susan
My apologies for not looking more closely at Technical Report 5. I was put off by the reference
of that report to “noise effects” as I was hunting for a definition of “Do-min”. I have now found
a summary of the Do Minimum” in Table 4.1 of Technical Report 4.
It seems that the Do-Minimum definition of the “Noise Effects” report differs from this “Do-
Minimum” definition in Technical Report 4. Also, the Noise Effects report brings in a new
scenario “Do nothing” which is not included in Technical Report 4. Can you please clarify.
Can you also please also specifically confirm if the “Do-Minimum” summary definition noted in
Technical Report 4 includes “Buckle Street Three Laning”. I ask this because elsewhere in the
documents the three laning of Buckle St is described as dependent on the Flyover being built:
“A third lane ...[through the Buckle St underpass] ... will become operational once the bridge is
in place.” This implies that if the Flyover does not proceed, the third lane (which is presumably
being constructed as part of the Buckle St project currently underway) will be redundant if the
Flyover is not built – on the face of it this does not make sense. Can you please clarify this
apparent ambiguity.
Murray Parker
Home: +64 4 972 0565
Mobile: +64 27 633 0565
Email: [email protected]
Postal Address: 137 Clyde St, Island Bay, Wellington 6023, New Zealand.
23 | P a g e
APPENDIX F: Response to NZTA Rebuttal Evidence
Mr Copeland and Mr Blackmore provided rebuttal evidence to my Statement of
Evidence. I respond to that rebuttal evidence below.
1.0 Mr Copeland’s Rebuttal
1.1 In paragraph 9.4, referring to my assessment of the contingent benefits added
to the BCR from Duplication projects, Mr Copeland suggests they are in fact not
contingent (Mr Copeland refers to the “so called contingent benefits”). It is
difficult to understand Mr Copeland’s position. Benefits that are dependent on
a future decision or event are undoubtedly “contingent” on that decision or
event. Mr Copeland also considers that the contingent benefits remain relevant
to a consideration of the Project. Mr Copeland should have made a clear
distinction between the Strategic Fit assessment of the Project (for which the
contingent benefits can provide a useful context) and the economic efficiency
of the Project (for which the contingent benefits are not relevant since the
Project itself cannot deliver those contingent benefits).
1.2 In paragraph 9.5 Mr Copeland points out the uncertainty associated with road
improvement benefits as a reason for the Transport Agency reducing its
reliance on BCRs. This is in contrast to his rebuttal in paragraph 9.2 where he
defends the lack of quantified measurement in his economic assessment and
places reliance on the fact that he has included BCRs in his evidence (these
being the only measured benefits he includes in his assessment).
1.3 In paragraph 9.6 and 9.7 Mr Copeland defends the “Do Nothing” assumption at
the Basin Reserve on the grounds that no effective improvement options have
been identified. It would seem that Mr Copeland did not read the rebuttal
evidence of Mr Dunlop, which concluded at least in the case of one option for
enhancing the current Basin Reserve layout, benefits of $39M had been
identified.
1.4 In paragraph 9.8 Mr Copeland claims that benefits from the third lane at Buckle
St should be attributed to the Project because the third lane was only included
24 | P a g e
in the Buckle St project on the assumption that the Bridge project was going to
proceed. Mr Blackmore uses the same unusual justification in paragraph 7.8 (a)
of his rebuttal evidence. It would seem that neither Mr Copeland nor Mr
Blackmore have considered the concept of sunk costs. The decision to include
the third lane at Buckle St was made some time ago and the costs are now
“sunk”. Any benefits associated with that sunk cost are only relevant to a
future project - in this case the Bridge project – to the extent that the Bridge
Project might be necessary to crystallise benefits from that sunk cost. Neither
raised this point in written evidence or rebuttal although Mr Blackmore now
states the Bridge is in fact necessary to realise the benefits of the third lane.
1.5 In paragraph 9.10 Mr Copeland seems to confirm the cost of the Northern
Gateway Building (NGB) is not fully covered in the Project cost estimate. He
claims however that this will be at least partially offset by (presumably
intangible) benefits from the NGB to users of the Basin Reserve. This is not
consistent with the purpose of mitigation. The cost of mitigation offsets and is
a proxy for the costs of the unmitigated adverse effects of the Project. It would
seem Mr Copeland might be referring to benefits of the NGB in excess of that
needed for mitigation – in other words compensation. However I had
understood that the NGB was proposed for mitigation purposes. The Project
documents do not raise nor provide justification for compensation.
1.6 In paragraph 9.11 Mr Copeland clarifies that NZTA intend to sell or rent the
proposed “Building under the Bridge”, thus justifying its exclusion from the
Project cost. While this commercial proposition for the building is relevant, the
cost of the building still needs to be included in the Project cost and a proper
assessment made of the commercial value of the building. It is not sufficient to
simply say one will offset the other.
2.0 Mr Blackmore’s Rebuttal Evidence
2.1 In paragraph 7.1, Mr Blackmore “assumes” my assessment of the BCR relies on
the evidence of Mr Foster. It would appear Mr Blackmore has not read my
Statement of Evidence. It is clear from my evidence that it is based solely on
25 | P a g e
data provided by NZTA. This analysis was completed independent of and
without reference to Mr Foster’s evidence. It is though informative that Mr
Foster and I came to similar conclusions.
2.2 In paragraph 7.2 Mr Blackmore reiterates his view that the BCR has been
developed for a different purpose other than for considering economic
efficiency relevant to the RMA. It is unclear then why NZTA nevertheless
presented those same BCRs in support of the proposal in this RMA consent
hearing. Further, understanding that economic efficiency is “a relevant
consideration under the RMA”, it is unclear why Mr Blackmore did not ensure
that analysis appropriate to the RMA consideration of the proposal was in fact
presented. As I have demonstrated, it is certainly possible to provide that
proper BCR analysis. The result would have been considerably lower than the
BCRs actually put to the Board, which is more reason why correct BCRs should
have been presented in the first place.
2.3 In Paragraph 7.3 Mr Blackmore suggests that I have not understood that “the
only relevant BCR for the Transport Agency is the “Programme BCR” [the
Northern Corridor RONS programme] and not individual “sub-section” BCRs”
[for example, the Bridge BCR]. While the relevance of a BCR to the Transport
Agency might be interesting, this hearing is not made in front of the Transport
Agency. It is held under the RMA in front of a Board of Inquiry. Relevance is
determined by that context, not the context of the NZTA deliberations.
2.4 In paragraph 7.6 and as previously noted in his EIC, Mr Blackmore claims
support for his view that the only relevant BCR for this Inquiry is the BCR for
the entire Northern Corridor RONS. He refers to various comments from
previous reports of Northern Corridor RONS Boards of Inquiry in support of his
view. It is not entirely clear what those previous Boards intended. The
interpretation that Mr Blackmore draws from it however seems unusual. Mr
Blackmore is suggesting the BCR for the actual project in front of a consent
hearing should be put aside in favour of the BCR for a group of Projects which
have been considered through an administrative process (the Transport
26 | P a g e
Agency) but which otherwise stand outside the RMA consent hearing
procedures. Further, Mr Blackmore claims support for this view from other
Boards of Inquiry. In my view this is a misinterpretation of what those Boards
intended, and reflects a confusion between an assessment of the “strategic fit”
of the Project with its “economic efficiency”.
2.5 In paragraph 7.8 Mr Blackmore suggests my analysis should be subject to peer
review. Mr Blackmore has not understood that in fact my analysis is a peer
review. I have simply assessed the way that NZTA has made its assessment, and
found that the assessment does not properly measure the economic efficiency
of the Project for which consent is sought. It is perhaps notable that the NZTA
has not challenged the actual analysis which I performed.