    Erectionof

    2 X 500MWSteam Generator

    ((Vindhyachal, Stage-III)

  • 7/31/2019 Boiler Erection 1

    2/30

    Introduction

    Vindhyachalstage-III, comprises ofcoal based 2X 500 MWunit. It has been planned tosynchronise the unit within36 monthsfromNotification Of Award.

    Commissioning of a 500 MW unit within such ashort period requires meticulousplanning andintegrationof various site activities viz.

    Supply of materials,

    Agency mobilisation,

    Special T&Ps etc.

  • 7/31/2019 Boiler Erection 1

    3/30

    Major Packages Awarded

    Main Plant Package (SG, TG,PCP)

    Ash Handling System

    Station Piping

    Ventilation System

    AC System

    CHP

    CW System

    Fire Detection and Protection

    BHEL

    M/s DCPS Ltd.

    BHEL

    ABB

    ABB

    L&T.

    WPIL (Equipment Supply)

    Wormald

  • 7/31/2019 Boiler Erection 1

    4/30

    Major Packages Awarded

    Power Transformer

    Generator Bus Duct

    HT Switchgears

    400 KV Switchyard

    Electrical EquipmentSupply & Erection

    Main Plant Civil works

    Chimney

    BHEL

    Techno

    ABB

    Areva

    L&T

    SPML

    NBCC

  • 7/31/2019 Boiler Erection 1

    5/30

    Contracts

    First Contract - SUPPLY Ex.Works basis, including

    Mandatory Spares & Type

    Test Charges

    Payment Terms IA - 15%

    PPD - 55%PPR - 20%

    Stage Payment - 5%FP - 5%

    Second Contract - ERECTION Unloading, receipt, storage,

    Complete Installation &

    Commissioning, PG tests,Transportation & Insurance

    Payment TermsEA - 10%

    PPE - 80%

    Stage Payment - 5%FP - 5%

  • 7/31/2019 Boiler Erection 1

    6/30

    Technical Specifications

    Type of Boiler: Controlled circulation with rifledtubing (CC+), Dry bottom, Top supported,Tangentially fired, Balanced Draught Furnace

    with Fusion welded Water Walls.

    19177 301 - 51

    Designation of boiler : --------- ----------CC+

    15797 230 51

  • 7/31/2019 Boiler Erection 1

    7/30

    Technical Specifications

    Design Wt. of unit (Boiler + ESP) :31000 MT Approx.

    No. of actual HP joints : 27000 approx.

    No. of equivalent HP joints : 30000 approx. No of ceiling girders : 6 No

    Type of Main columns : Star section

    Type of Auxiliary columns

    (Except S4L&R) : Box section Elevation of T.O.S. of main columns : 84.945 m

    No of Coal elevations : 10

    No of Oil elevations : 5

  • 7/31/2019 Boiler Erection 1

    8/30

    Boiler Foundation Plan

  • 7/31/2019 Boiler Erection 1

    9/30

    Milestones

  • 7/31/2019 Boiler Erection 1

    10/30

    DRUM

  • 7/31/2019 Boiler Erection 1

    11/30

  • 7/31/2019 Boiler Erection 1

    12/30

  • 7/31/2019 Boiler Erection 1

    13/30

    TG OIL FLUSHING - (33 RD MONTH)

    BARRING GEAR - (34 TH MONTH)

    STEAM BLOWING - (34 TH MONTH)

    SAFETY VALVE FLOATING - (35 TH MONTH)

    STEAM TO TG SET - (35 TH MONTH)

    SYNCHRONIZATION WITH OIL - (36 TH MONTH)

    TRIAL RUN COMPLETION - (40 TH MONTH)

    COMPLETION OF ALL FACILITIES (TG) - (40 TH

    MONTH)

  • 7/31/2019 Boiler Erection 1

    14/30

    SG Scope of Work

    Structures (9000 MT approx.)

    Pressure parts(Water Circuit with 3 bank economiser,Steam Circuit including radiant roof,backpass walls,2 no.banks LTSH, divisional SH and platen SH, 2 stageReheaters)

    Rotary partsPAPH 2 nos.

    SAPH - 2 nos.

    PA Fans - 2 nos.

    FD Fans - 2 nos.

    ID Fans - 2 nos.

    Mills 10 nos.

    Ducting 4000 MT

    Insulation 2000 MT

    M h i E i S h d l

  • 7/31/2019 Boiler Erection 1

    15/30

    Month wise Erection Schedule

    Monthly Erection Details of Boiler

    0.0

    200.0400.0

    600.0

    800.0

    1000.0

    1200.0

    1400.0

    1600.0

    Aug'2

    006

    Jan'2

    007

    Feb'2

    007

    Mar'20

    07

    Apr'2

    007

    May'20

    07

    Jun'2

    007

    Jul'2

    007

    Aug'2

    007

    Sep'2

    007

    Oct'2

    007

    Nov'2

    007

    Dec'2

    007

    Jan'2

    008

    Feb'2

    008

    Mar'20

    08

    Apr'2

    008

    May'20

    08

    Jun'2

    008

    Jul'2

    008

    Aug'2

    008

    Sep'2

    008

    Oct'2

    008

    Nov'2

    008

    Dec'2

    008

    Jan'2

    009

    Feb'2

    009

    Mar'20

    09

    Apr'2

    009

    May'20

    09

    Nov'2

    009

    Dec'2

    009

    Jan'2

    010

    Feb'2

    010

    Month

    MonthlyTonnage(MT)

    0.0

    5000.0

    10000.0

    15000.0

    20000.0

    25000.0

    Cumul

    ativeTonnage(MT)

    Monthly Tonnage (MT)

    Cumulative Tonnage (MT)

    Drum LiftingHydro Test

    BLU

  • 7/31/2019 Boiler Erection 1

    16/30

    Infrastructure Development

    Open store yard

    Covered Stores 2 nos. (size 60 X 22 M)

    Preassembly yard of approx. 5,000 sq.m. at erection site

    One welders testing booth near preassembly yard.

    Contractors colony is being developed near material gate.

  • 7/31/2019 Boiler Erection 1

    17/30

    Construction Power Supply

    One ring main fitter @ main plant area

    Radial fitter - BHEL store yard, agency offices, fabrication yard.

    4 nos. substations for Boiler+TG # 9&10.

    Each substation of capacity 667 Amps.

    Infrastructure DevelopmentContinued

  • 7/31/2019 Boiler Erection 1

    18/30

    Preservation of Materials

    Open yard - Structural materials.

    Closed sheds - Items like bearings, valves, actuators, insulation etc

    Huge tarpaulins - Prevent the items from dust and rust.

    Grease coating - Items like girder pin assembly etc...

    One closed cabin - Regularly used loose items like HSFG Bolts and

    emitting electrodes of ESP...

  • 7/31/2019 Boiler Erection 1

    19/30

    Agency Mobilisation

    Main agency for erection of main plant turnkeypackage - BHEL (PSWR)

    The erection work of SG package has been given tofollowing contracting agencies by BHEL.

    Boiler # 10 & ESP#9 erection work to M/s PCPIL.

    ESP # 10erection work to M/s BEEL.

    Boiler # 9 erection work to M/s TPL.

  • 7/31/2019 Boiler Erection 1

    20/30

    Pre-assembly yards

    Objective: To achieve the above target on

    stipulated time.

    Columns, Bracing and Gusset plate etc. Ceiling Structure.

    Pressure parts , down comer etc.

    Stairs, Landings, Hand rails etc. Duct , Duct support etc.

    ESP Columns and walls.

  • 7/31/2019 Boiler Erection 1

    21/30

    Other Erection Facilities

    Scrap disposal chute. Construction Elevator.

    Pre assembly area temporary weather proofing. Local area illumination. Construction power at different location. Construction water

  • 7/31/2019 Boiler Erection 1

    22/30Tools & Plants

  • 7/31/2019 Boiler Erection 1

    23/30

    Major T&P Requirement

    Sl. No. Description Qty.1 325 T FMC CRANE 1

    2 150 T Capacity crane 1

    3 CRAWLER MOUNTED CRANE 100 T 1

    4 CRAWLER MOUNTED CRANE 75 T 3

    5HYDRO CRANE/ ESCORTS/ TATA P&H-320 OR

    EQUIVALENT

    14 TONNES 2

    08 TONNES 2

  • 7/31/2019 Boiler Erection 1

    24/30

    PLANNING For EXECUTION

    Month Wisedistribution of tonnage.

    Average rate of erection (for boiler) - 1250 MT/month (25months time)

    Peak rate of erection - 1500 MT/month

    Communication with BHEL manufacturing units Reviewof the planning

    Planning for ErectionandWelding

    Activity based programs

    PG-MA wise monthly erection program

    Monthly HP welding joints completion will be programmed.

    Average rate of Eq. HP Joints - 3000 Nos/month (10months time)

    Peak rate of Eq. HP Joints - 3500 Nos/month

    Daily erection and welding program

  • 7/31/2019 Boiler Erection 1

    25/30

    Reports

    Objective: Quick and easy analysis of progress/ criticalarea and present work status.

    Daily progress monitor sheet with reflection of manpowerdeployment in each area, extra manpower required and critical

    activity, will be developed and circulated within the project sothat necessary steps could be taken in advance.

    Milestone activity based reports will be generated for accessingthe current status of the milestone to be achieved.

    Monthly progress report.

    Charts/ diagrams will be prepared for relative analysis ofprogress.

  • 7/31/2019 Boiler Erection 1

    26/30

    Cycle Time Reduction

    Welding of 2 auxiliary columns may be planned to

    erect in single lift .

    Preassembly of MBLs and erection as a single unit.

    Coal pipes will be welded at ground where ever it is

    possible.

    Welding booths at various elevations as per

    requirement

  • 7/31/2019 Boiler Erection 1

    27/30

    Field Quality Assurance

    Category of Checks

    A- class check : Critical B - class check : Major C- class check :Minor

    NTPC approved..

    Welding manual

    Installation manual,

    NDE manual,

    Heat treatment manual

    Qualified & Experienced welders are/ will be only allowed to work.

    Qualified & Experienced technicians are only allowed for Radiography/ UT

  • 7/31/2019 Boiler Erection 1

    28/30

    Safety Assurance

    PEP talk to enhance the awareness for safety.

    Demonstrations by the Fire fighting persons for emergency

    handling

    PPEs is issued by the contractor to every worker.

    While working inside the boiler drum, one exhaust fan will bealways used for better ventilation