Boiler Hydro Test

Embed Size (px)

DESCRIPTION

Manual on Boiler Hydro Test

Citation preview

  • TAB - 3

  • 1 PUB.NO. 2025

    RECOMMENDEDHYDROSTATIC TEST

    PROCEDURE

  • 2CONTENTS

    1.0 GENERAL

    2.0 LIMITS OF HYDROSTATIC TEST

    3.0 TEST PROCEDURE

    4.0 PRESSURE GAUGES

    5.0 PREPARATIONS FOR THE TEST

    6.0 WATER QUALITY

    7.0 AIR TESTING THE PRESSURE PARTS

    8.0 FILLING PUMP & PRESSURISING PUMP WITH TEMPORARYCONNECTED PIPELINES

    9.0 FILLING THE SYSTEMS

    10.0 PRESSURISING THE SYSTEMS

    11.0 HYDROSTATIC TESTING

    12.0 DEPRESSURISATION OF THE PRESSURE PARTS

    13.0 INSPECTION OF THE BOILER PRESSURE PARTS AFTER TESTING

    14.0 PROCEEDINGS TO PREVENT ACCIDENTS AND ENDANGERING OFPERSONS DURING PRESSURE TEST

    15.0 HYDROSTATIC TEST REPORT

    16.0 PRESERVATION OF BOILER AFTER HYDROSTATIC TEST

  • 3TABLE - 1 TYPICAL HYD. TEST PRESSURE AND TEST PRESSURE GAUGE RANGE

    TABLE - 2 QUALITY OF WATER

    TABLE - 3 WATER VOLUME (TYPICAL FOR VARIOUS CAPACITY OF UNITS)

    FIGURE-1 HYD. TEST LIMIT BOILER

    FIGURE-2 HYD. TEST LIMIT SUPERHEATER SYSTEM

    FIGURE-3 HYD. TEST LIMIT

    FIGURE-4 HYD. TEST LIMITBOILER WATER CIRCULATION SYSTEM

    FIGURE-5 SILICA IN BOILER WATER RELATIONSHIP WITH DRUM PRESSURE

  • 41.0 GENERAL

    After installation of all pressure parts, the unit is subjected to the required initial Hydrostatic Pressuretests. The exact Hydrostatic test procedure to be followed depends on local job site conditions.The procedure outlined below is general in nature.

    2.0 LIMITS OF HYDROSTATIC TEST

    2.1 Main boiler with water circulation system (from feed check valve inlet to drum) withSH saturated connection tubes blanked). Ref. Fig. 1.

    2.2 SH SYSTEM

    From drum (with SH saturated connection tubes blanked) to MS stop valve. (Ref. Fig. 2)

    2.3 RH SYSTEM

    RH inlet header to RH -Outlet header. (Suitably blanking the RH inlet and outlet headers withthe isolating devices if provided or by means of blank langes) Ref. Fig.3.

    3.0 TEST PROCEDURE

    The Unit shall be hydro-tested for conformation to IBR Code requirement in two areas (i) PrimaryCircuitary, Drums, Economisers, Waterwalls, Superheaters at one and half times the design pressureand (ii) Reheaters at one and half times the design pressure or a t minimum 70 kg/sq.cm.(g)

    NOTE:

    It is preferable to do the hydro test at one stroke at the stipulated hydro test pressure indicated in thepressure part arrangement drawing. If it is not possible to accomplish this the hydro test may beconducted twice, once for drainable portion and another including non drainable portion at thestipulated hydro test pressure (official test 1 1/2times the design pressure). In case site would preferto conduct a hydro test at a lower pressure prior to official hydro test the same may be done once atthe design pressure. For the site hydrostatic pressure respective BOILER pressure part arrangementdrawing has to be referred.

    4.0 PRESSURE GAUGES

    During testing, atleast three properly calibrated pressure gauges are to be located one at drum level,one at operating floor level and one near pressure raising pump.

    The indicator of the pressure gauges selected should have atleast 6" dial with dials graduated overa range of double the intended maximum test procedure, but in no case the range be less than 11/2times that pressure. The pressure gauges should be calibrated as per FQAF-1 5 of FQA systemsmanual.

    For typical Test Pressure Gauge Range Refer Table 1 - TYPICAL HYD. TEST PROCEDUREAND TEST PRESSURE GAUGE RANGES.

  • 55.0 PREPARATIONS FOR THE TEST

    Prior to Hydrostatic testing, the following items should be inspected.

    i. All necessary welds completed, x-rayed and stress relieved.

    ii. All necessary valves including drain valves installed and closed.

    iii. All safety valves installed and hydrostatic plugs, should be assembled before commencingthe test.

    iv. All debris shall be removed manually from all pressure parts including headers and drums.

    v. The drain valve and test valve in the official calibrated pressure gauge sensing line must beopen.

    vi. All manhole closure plates (except drum manhole) and header handhole caps should be closed and bolted or welded tight.

    vii. The isolating valves provided in all the other branching systems like SB System tapping,SH spray connections, Pr.gauges etc.,have to be closed tightly.

    viii. All vents necess ary to prevent air entrapment during filling operation such as superheaterlink Vents, economiser link vents, drum vents etc., shall be kept open.

    ix. When valves are in TANDEM (Double valved) both valves must be closed during thehydrotest.

    x. In 500 MW Units, if the boiler circulating pumps are of the sub-merged motor or cannedmotor type, installation of the rotating elements should be defered until the hydrostatic test ofthe unit has been completed. The pump casings must be blanked off during the test.

    xi. Joint Inspection protocol prior to Hydrostatic Testing of Boiler prepared by FQA also to beduly filled up. (FQA-01-00-00-L-17 (a))

    6.0 WATER QUALITY

    6.1 It is the responsibility of the customer to provide properly treated water,as specified below at ambient temperature but in no case less than 70o F(21o C)

    NOTE: The temperature limitation for hydrostatic testing is 70o F or 21o C.The important point is that the hydrostatic pressure should not be applied whenthe water is less than this limit.It does not make any difference if the water isheated externally or once it has been pumped in to the boiler.

    The easiest way to achieve and maintain proper hydrostatic temperature in cold weatheris with an externa l steam supply. The full water is heated with a direct contact heaterand the temperature is maintained by using the steam coil air heater. For a new projectwhere no steam is available. It is advised to consider electric heaters or fuel fired spaceheaters.

  • 6The best method of maintaining non-drainable portion above freezing temperature is byuse of steam air heater. M/s.CE too had good success with fuel fired space heaters.For this the unit should be completely insulated and lagged.

    During testing, the temperature of water should in no case exceed 490o C.

    6.2 It is recommended to use demineralised or cop ensate quality water of specified purityfor both drainable and non-drainable portions (REFER NOTE BELOW).

    6.3 For Quality of Treated water, Boiler water and Feed water, Refer Table -2.

    6.4 During initial hydraulic test, one may expect some leaks requiring draining, repairingand refilling. So it will be in order to use, initially filtered water free from chlorine fordrainable portions only.

    It is necessary that the filtered water is clear, free from suspended and colloidalimpurities with a restriction of the total dissolved contents to 100 ppm. However,filtered water should not be used for Lay Up work even for drainable portions.

    6.5 For non-drainable portions only demineralised or condensate quality water shouldbe used.

    6.6 For superheater and reheater (drainable and non-drainable sections) treatedcondensate or demineralised water can also be used. The treatment shall include10 ppm arnmonia and 200 ppm hydrazine. This treated water will have a pH valueof approximately 10.

    6.7 The use of fill water treated with solid chemicals should be avoided. Deposits of solidmaterials in superheaters and reheaters are detrimental from heat transfer and corrosionpoint of view. Super-heaters and reheaters containing stainless steel tubing are particularlyvulnerable to stress corrosion cracking in the presence of chemicals as caustics andchlorides.

    In the case of 500 MW. Unit sets, the boiler water circulation pumps are to be filledwith condensate or demineralised water before putting water into the boiler for testingboiler with boiler circulating water pumps.

    NOTE:

    Demineralised or condensate quality water is defined as containing no more than ppmidentifiable solids and essentially a zero concentration (or lowest detectable level) oforganic materials.

    6.8 After chemical cleaning, steam blowing and lay up of the units, if situation warrants todo hydraulic testing of the pressure parts usage of treated DMwater or treatedcondensate is only recommended. For quality of treated DM water REFER TABLE-2.

  • 77.0 AIR TESTING THE PRESSURE PARTS

    7.1 Before filling the boiler with water an air tightness test is to be performed to detectleakages due to valve left in open position, x-ray plug forgotten, any cuts or gaugesetc., not observed by visual inspection. This will reduce the DM water consumption,as well as time.

    7.2 The air should be filtered and free from oil and dust prior to entering the unit.

    7.3 The boiler is to be pressurised not more than 2 kg/sq.cm.(g).

    7.4 Before admitting air, close all the manhole doors including drum manhole,handholeplates, isolating valves in drain lines, branching lines and vent lines including the ventvalves in SH link, eco. link and drum link, Drain and Test Valves in official pressuregauge etc.,

    7.5 After completing the air tightness testing keep the drum man hole, vent valves inSH links, etc., link and drum link and drain and test valves in official pressuregauge in open position.

    8.0 FILLING PUMP AND PRESSURISING PUMPWITH TEMPORARY CONNECTED PIPELINES

    8.1 i. Check for correct direction of rotation.

    ii. Open air vent of the pump during start-up.

    iii. Check motor current at no load as well as at full load conditions. Check whethera correct fuse is introduced in the circuit to avoid damages to the motor.

    iv. Before starting the filling pump, the delivery valve to be closed and the suctionvalve kept opened. Then open delivery valve gradually for filling. Before stoppingthe pump,delivery valve should be closed.

    v. Before starting the pressurising pump it should be ensured that the deliveryvalve is kept open.

    8.2 Connected pipe lines (temporary)

    i. Should all be welded.

    ii. Delivery line of pressurising pump should be of high pressure seamless pipe towithstand the required test pressure.

    iii. Mixing tank should be of required capacity.

    iv. Flow regulating valves, drain valves, overflow lines should be provided withthe mixing tank.

  • 89.0 FILLING THE SYSTEMS

    9.1 i. The boiler water circulation system is filled through filling lines connected to theboiler drain head or and eco. filling lines (in higher capacity boilers). If the unitis filled through the economiser recirculating line valve should be in the vide openposition.

    ii. As the water raises upto the drum manholes, the later shall be tightly closed andboiler filling shall be completed.

    iii. Then checking of the filling shall be done through the vents.

    iv. Close and open the vent valves several times in order to allow the entrappedair to vent out.

    v. Stop the fill pump and let water lay for some hours.

    9.2 In no case water entry into superheater should be permitted through the drum. This isto prevent carry over of suspended impurities into the superheater.

    9.3 Fill the superheater and reheater with the quality of water indicated under point 6.5 perSH drain header and R1 + drain header respectively until all the elements are filled andthe water overflows through the vent valves.

    CAUTION : 1. If it is decided to do the hydraulic pretest of boiler water circulatingsystem and superheaters at the same time, treatedDM water / condensate only should be used. The SH connectiontubes in the drum need not be plugged in this case. Take care ofpoint No. 9.2. Also refer Fig. 4.

    2. The water temperature during hydrostatic test should be ambienttemperature but in no case less than 21o C.

    10.0 PRESSURISING THE SYSTEMS

    10.1 The pressure shall be raised up by means of test pumps.

    10.2 The pressure shall be increased at a rate of not more than 10 kg/sq.cm.(g) per minuteupto approximately 80% of the test procedure and by 1 to 2 kg/sq.cm.(g) per minutebeyond that value.

    10.3 Raise the pressure to the hydrostatic test pressure. The pressure shall be under propercontrol at all times. The pump operator and the responsible person watching the officialtest gauge must have radio-telephonic contact. When the test pressure is reached theresponsible person watching the test gauge shall give orders to stop the test pumpsimmediately and to cut off the electric connections.

    10.4 The test pressure is held for about half an hour. During the holding time the test gaugepressure reading shall not drop noticeably.

  • 911.0 HYDROSTATIC TESTING

    11.1 The hydraulic test pressure reading will be taken from the official pressure gauge locatedat the highest point in the presence of the Inspector.

    11.2 After the hydraulic test pressure has been noted and agreed by the Inspector, thehydrostatic test pressure is then reduced to not less than the maximum allowable workingpressure and the whole pressure parts checks will be carried out.

    11.3 If leaks are found, it will be necessary to release the pressure and drain these portions.Make the repairs and refill the unit as mentioned above and repeat hydrostatic test.

    11.4 Details of the leaks noticed during Hydraulic Tests are to be furnished as given belowfor better understanding:

    a. Exact location of leak(s) component circuit, Elevation, materials etc.,

    b. Description of leak(s) such as straight tube elbow, shop or field weld, torchcut,where alugwas removed and attachment weld etc.,

    c. Magnitude of leaks-weeping/sweating, leaks, burn through, longitudinal crack.

    12.0 DEPRESSURISATION OF THE PRESSURE PARTS

    12.1 The pressure parts shall be depressurised at a depressurisation rate of1 kg/cm. sq/ minute.

    12.2 While releasing the pressure, the vents should be opened when the system pressurereaches 1 kg/sq.cm to prevent creation of vacuum in the system.

    13.0 INSPECTION OF THE BOILER PRESSURE PARTSAFTER TESTING

    13.1 After completion of the hydraulic test, the inspector shall carefully examinethe boilerinside and outside and satisfy himself that it has satisfactory with-stood the test.

    13.2 To enable the inside inspection of the boiler the interior has to be equipped with suitablescaf folding for inspecting the elements, walls, tubes and welds.

    14.0 PROCEEDINGS TO PREVENT ACCIDENTS ANDENDANGERING OF PERSONS DURING PRESSURE TEST

    14.1 Due to the fact that during the pressure test the boiler and boiler house area are underan increased risk of danger, special safety precautions have to be taken to preventaccidents. These arrangements are made by the erection and commissioning servicesaccording to the instructions of the site management.

  • 10

    14.2 During the period of raising, holding and releasing the test pressure, the entry to theboiler house is prohibited for all persons not participating in the pressure test, Worksat the pressure parts or in the direct neighbourhood are not permitted.

    14.3 All companies working on the site must be notified of the pressure test in writing.No claim based on the restriction or stopping of work will be accepted.

    15.0 HYDROSTATIC TEST REPORT

    After completion of the hydrostatic test a written report as per the IBR format shall be issuedand signed by the Inspection Authority.

    16.0 PRESERVATION OF BOILER AFTER HYDROSTATIC TEST

    16.1 There is generally sometime delay between hydrostatic test and further initial boilingout and chemical cleaning of the unit. Hence, the unit should be kept underpreservation for protecting the internal surfaces from oxidation.

    16.2 Remove all the hydrostatic gags from the safety valves and hyd. test pump with temporarypipes connections prior to filling the unit.

    16.3 Fill the unit with hydrazine and Ammonia treated DM water containing 300 ppm hydrazine and 10 ppm Ammonia with a pH value of 10.0 to 10.5 till it overflows at vents.

    16.4 The unit should be kept Under nitrogen cover with a pressure of 0.5 kg/sq.cm. In theabsence of nitrogen capping facility the unit should be pressurised with the aid of a fillpump to 5 kg/sq.cm.

    16.5 Samples can be collected pe riodically say once a week or fortnight, depending on thepressure holding worthiness of the system, tested for pH and hydrazine content.

    16.6 In case the sample-water does not meet the criteria for lay up water, the conditioningsystem shall be operated as to restore the required composition.

    16.7 No welding shall be carried out on pressure parts when the system is under preservationor the system is filled with water.

    16.8 If there is a chance of freezing, the water in the drainable circuits can be displaced bynitrogen and the unit can be laid up under nitrogen pressure. Temporary heating equipmentshould be provided to keep the non-drainable superheater (reheater) elements abovefreezing temperature.

    16.9 The reheater should be laid up under nitrogen pressure with the reheater isolating devicesclosed or with the blank flanges.

  • 11

    TABLE - 1TYPICAL HYD. TEST PRESSURE AND TEST PRESSURE

    GAUGE RANGE

    2. PR. OF AIR FOR TESTING PR. PARTS 2 KG/SQ.CM. (G)PR.AFTERREGULATOR

    RANGE OF PR. GAUGE 0-4 KG/SQ.CM.

    TABLE - 2QUALITY OF WATER

    1. DEMINERALISED WATER (SPECIFICATION)

    1. pH at 25o C : 7 0.2

    2. Electrical Conductivity at 25o C : Less than 0.2 Michromhd/cm

    3. Total Hardness(Ca + Mg) PPM CaCO 3 : Nil

    4. Total Silica : Less than 0.02

    5. SiO2 PPM : Less than 0.01 IS preferable

    6. Chloride PPM as NaCl : Nil

    7. Sodium PPM as Na : Less than 0.003

    8. Organic Matter : Should be free in any cast it shouldMgm KMnO4 /Litre not exceed 0.2 PPM on an average.

    9. General Appearance : Clear: Free from odour, colour andHaziness. No Glittering to tyndal effect.

    2. QUALITY OF TREATED DM WATER OR TREATED CONDENSATE

    The DM water or Condensate treated with 10 PPM ammonia and 200 PPM hydrazine tohave a pH value of approximately 10.

    BOILERSASSOCIATED

    WITH THEMACHINES

    BOILERS & SHHYD. TEST PR KG/SQ.CM (G)

    TEST PR.GAUGERANGE

    KG/SQ.CM

    RH HYD TESTPRESSURE

    KG/SQ.CM. (G)

    TEST PR.GAUGERANGE

    KG/SQ.CM.120 MW 237.0 0-400 70.0 0-150210 MW (LP) 237.3 0-400 70.0 0-150210 MW (HP) 263.7 0-400 70.0 0-150500 MW 306.0 0-600 76.5 0-150

  • 12

    3. QUALITY OF BOILER WATER

    Drum operating pressure 126-165 166-180 181-205kg/sq.cm.(g)

    Total Dissolved Solids - max (ppm) 50 25 15

    Specific Electrical Conductivityat 25oC (s/cm) 100 50 30

    Phosphate Residual (ppm) 5-10 5-10 2-6

    pH at 25o C 9.1-9.8 9.1-9.8 9.1-9.6

    Silica (max.) (ppm) To be controlled on the basis of silica inboiler waterand drum pressure relationship (Fig.1) to maintain lessthan 0.02 ppm in the steam leaving the drum 0.1

    4. QUALITY OF FEED WATER ( Drum operating pressure 101 kg/cm.sq.(g) and above )

    Hardness Nil

    pH at 25oC (copper alloy pre boiler system) 8.8 to 9.2

    pH at 25oC (copper free pre boiler system) 9. 0 to 9.4

    Oxygen maximum ppm 0.007

    Total Iron (Tax) ppm 0.01

    Total Copper (max) ppm 0.005

    Total CO2 Nil

    Total Silica (max) ppm 0.02

    Specific electrical conductivity at 25o Cmeasured after cation exchanger in the + fromand after CO2 removal (max) m s/cm 0.3

    Hydrazine - residual ppm 0.01 to 0.02

    Permanganate Consumption Nil

    Oil Not allowed

  • 13

    TABLE - 3WATER VOLUME (TYPICAL FOR VARIOUS CAPACITY OF UNITS)

    SYSTEM 120 MWM3

    200/21O MW(LP Unit) M3

    21OMW(HP Unit)M3

    500MWM3

    Generating Surfaces 70.4 126.5 130.0 160.0Drum 21.1(Full) 37.0(Full) 35.0(Full) 60.0(Full)Economiser 30.0 30.0 25.0 135.0Superheater(Drum to SHO Header)

    47.0 95.0 95.0 145.0

    Reheater 15.0 48.0 50.0 220.0Total 183.5 336.5 335.0 720.0

    FIGURE - 1 HYD. TEST LIMIT BOILER

  • 14

    FIGURE-2 HYD. TEST LIMIT SUPERHEATER SYSTEM

    FIGURE-3 HYD. TEST LIMIT

  • 15

    FIG-4 HYDROSTATIC TEST LIMIT-BOILER WATER CIRCULATIONSYSTEM

  • 16

    FIG-5 SILICA IN BOILER WATER RELATIONSHIP WITH DRUMPRESSURE

  • Sl. Equipment Frquency QtyNo. Description 10C HP BP BP Of Change per BIr1 Bearings-Guillotin Servogem. Lithan3 Bharat 3 Years 10 Kg

    Gates HTxx MPGrease 3

    2 Filter cum LubricatoServospin 12 Shell 1 Year 5 LitrsTellus 15HP

    3 Actuators Castrol 2 Years 1.25Alpha SP 68 - Litrsof lndrol-ServomeshSP 68

    Recommended LubricantsDUCTS, GATES AND DAMPERS

    RECOMMENDED LUBRICATION CHART

  • GO TO INDEX