Bethel Park High SchoolBethel Park, PA
Weekly progress slide show
January 14,2009
Massaro
Walls Continue in Area C
Massaro
Along With The Footing
Foundations!
Massaro
Backfill of Storm Piping
Massaro
Progress Being Made in Several
Areas!
Massaro
Forms Pile Up As Poured Walls Are
Stripped
Massaro
Scheduled work for next few
weeks:• Continue site storm systems items.
• Building foundations and wall forming.
• Excavation of areas D,G, and H.
• Continue stock pile and soil stabilization items for back fill operations.
• Masonry foundation work to stage.
• Underground building MEP items.
• Steel Fabrication.
Massaro
Thank You