Bremner Transformer StationGrowing Grids Presentation, Nov 29th 2012
Presented by:
Shaun Pinard
Toronto Hydro2 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
• Background – Why is Bremner TS required?
• Scope of Work – What work will be done?
• Status – Where are we now?
Agenda
Toronto Hydro3 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Why is Bremner TS required?
• Immediate Need – Windsor TS upgrades
• Short term need – Avoid overload at key stations
• Mid term Need - Load growth to 2030
Toronto Hydro4 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Immediate Need – Windsor TS Upgrades
Windsor TS: - Built in 1954
- Supplies key customers in
downtown core
Toronto Hydro5 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Windsor Transformer Station
Toronto Hydro6 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Short Term Need – Avoid Overload at 5 downtown Stations
UNITS OF MEASURE - MVA
Toronto Hydro7 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
WHITE = the project has had preliminary renders, but
no application has been submitted.
RED = the project has submitted an application to the
city
GREEN = the project has been approved, but has yet
to start construction
YELLOW = the project is currently in sales
BLUE = the project is currently under construction
As reported in Canadian Business Magazine
Short Term Need – Avoid Overload at 5 downtown Stations
Toronto Hydro8 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Long Term Need – Address Continuing Projected Load
Growth
Capacity
Toronto Hydro9 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Scope of entire Project
Work Why?
1. Cable Tunnel High Voltage Connection from Hydro
One at Front St & Simcoe St
2. Transformer Station High Voltage to Medium Voltage
Conversion
3. Duct Banks Medium Voltage Supply to Customers
Toronto Hydro10 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
1) Cable Tunnel
Toronto Hydro11 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Bremner Transformer Station
2) Transformer Station
• Site preparation
• Disassembly & Storage of the
Machine Shop
• Construction of the new
underground building
• Reassembly of Machine Shop
• Installation of electrical
equipment
• Site landscaping work
Toronto Hydro12 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Building Layout – TS Basement
Roundhouse
Lakeshore Blvd
Toronto Hydro13 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Building Layout – TS Main Floor
Roundhouse
Lakeshore Blvd
Toronto Hydro14 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Building Layout – TS Mezzanine
Roundhouse
Lakeshore Blvd
Toronto Hydro15 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Building Layout – TS Roof
Roundhouse
Lakeshore Blvd
Toronto Hydro16 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Bremner Transformer StationBremner Transform-r StationTransformer Station – Post-Construction (Architectural Rendering)
Toronto Hydro17 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Bremner Transformer StationTransformer Station – Post-Construction Concept
Toronto Hydro18 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Transformer Station – Post-Construction Concept
Toronto Hydro19 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Transformer Station – Post-Construction
Toronto Hydro20 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Bremner Transformer StationOther examples of site-integrated TS‟s
Location Utility Station Year
Completed
New York City, USA Con Edison Mott Haven
Substation
2012
Sydney, Australia Transgrid Haymarket
Substation
2004
Nagoya, Japan Chubu Electric
Company
Meijo Substation 1999
London, England EDF Energy Leicester Square
Substation
1989
Vancouver, British
Columbia
BC Hydro Cathedral Square
Station
1984
Toronto Hydro21 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Project Rees St:
- Civil infrastructure for underground distribution lines and feeders
- Work anticipated to be completed in November 2012
3. Duct Banks – Distribution to Customers
Toronto Hydro22 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Project Schedule
Sept – Dec 2012:
- Relocation of existing services, roadway
- Hazmat work within Machine Shop
2013 – 2014:
- Main Contract – building, equipment, etc
Toronto Hydro23 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
– Temporary Road
– Site Services (water and
sanitary relocation)
– Bell Line Relocation
– Machine Shop
environmental clean up
– Tree Relocation
Site Preparation / Hazmat
Work
Sep – Dec 2012
Toronto Hydro24 | Bremner TS, Growing Grids Presentation, Nov 29th 2012
Where are we right now
Pre-construction phase:
Work Status
Land Acquisition Complete
Detailed Design Complete
Environmental
Assessment
Complete
City Approvals In Progress
Funding Application In Progress
Site Preparation In Progress
Toronto Hydro25 | Bremner TS, Presentation to Bidders December 4, 2012
Disclaimer
The information in these materials is based on information currently available to Toronto Hydro Corporation and its affiliates
(together hereinafter referred to as “Toronto Hydro”), and is provided for information purposes only. Toronto Hydro does not
warrant the accuracy, reliability, completeness or timeliness of the information and undertakes no obligation to revise or update
these materials. Toronto Hydro (including its directors, officers, employees, agents and subcontractors) hereby waives any and
all liability for damages of whatever kind and nature which may occur or be suffered as a result of the use of these materials or
reliance on the information therein. These materials may also contain forward-looking information within the meaning of
applicable securities laws in Canada ("Forward-Looking Information"). The purpose of the Forward-Looking Information is to
provide Toronto Hydro‟s expectations about future results of operations, performance, business prospects and opportunities and
may not be appropriate for other purposes. All Forward-Looking Information is given pursuant to the "safe harbour" provisions of
applicable Canadian securities legislation. The words "anticipates", "believes", "budgets", "could", "estimates", "expects",
"forecasts", "intends", "may", "might", "plans", "projects", "schedule", "should", "will", "would" and similar expressions are often
intended to identify Forward-Looking Information, although not all Forward-Looking Information contains these identifying words.
The Forward-Looking Information reflects the current beliefs of, and is based on information currently available to, Toronto
Hydro‟s management. The Forward-Looking Information in these materials includes, but is not limited to, statements regarding
Toronto Hydro‟s future results of operations, performance, business prospects and opportunities. The statements that make up
the Forward-Looking Information are based on assumptions that include, but are not limited to, the future course of the economy
and financial markets, the receipt of applicable regulatory approvals and requested rate orders, the receipt of favourable
judgments, the level of interest rates, Toronto Hydro‟s ability to borrow, and the fair market value of Toronto Hydro‟s investments.
The Forward-Looking Information is subject to risks, uncertainties and other factors that could cause actual results to differ
materially from historical results or results anticipated by the Forward-Looking Information. The factors which could cause results
or events to differ from current expectations include, but are not limited to, the timing and amount of future cash flows generated
by Toronto Hydro's investments, market liquidity and the quality of the underlying assets and financial instruments, the timing and
extent of changes in prevailing interest rates, inflation levels, legislative, judicial and regulatory developments that could affect
revenues, and the results of borrowing efforts. Toronto Hydro cautions that this list of factors is not exclusive. All Forward-
Looking Information in these materials is qualified in its entirety by the above cautionary statements and, except as required by
law, Toronto Hydro undertakes no obligation to revise or update any Forward-Looking Information as a result of new information,
future events or otherwise after the date hereof.