July 24, 2012 BSEE BSEE and BOEM Workshop with Government of Israel Application for Permit to Drill Joe Levine BSEE

BSSE Presentation to Israel

Embed Size (px)

DESCRIPTION

BSEE regulatory description presentation

Citation preview

Page 1: BSSE Presentation to Israel

July 24, 2012 BSEE

BSEE and BOEM Workshop

with Government of Israel

Application for Permit to Drill

Joe Levine

BSEE

Page 2: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Exploration or Development Plan reviewed by BOEM

Environmental Reviews

Identify Drilling Locations

Identify Rig type (platform, MODU)

Oil Spill Contingency Plans

Worst Case Discharge (WCD)

Application for Permit to Drill reviewed by BSEE

Ensure permit and drilling operations to be conducted complies

with regulations

Page 3: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD) Overview

• BSEE Review and Written Approval Required

for

– Each Well, Sidetrack, Deepen

• Purpose

- Regulatory Compliance

- Outlines Drilling Program

• Major Areas

- Operational Characteristics of Rig

- Well Design

- Equipment Use and Testing

Page 4: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Permits are submitted through BSEE ewell system

Ewell is an electronic system that operators use to submit permits to BSEE

BSEE reviews the permit and can electronically return the permit to the operator with a list of items that need to be addressed

The operator than can resubmit the permit to BSEE when they have addressed the issues

An electronic approval is sent to the operator when BSEE approved the permit

Page 5: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Rig Information USCG Certificate of Inspection/Letter of Compliance

ABS/DNV Load Line Certificate

Safe Welding Area

Rated Rig Drilling Depth

Rated Rig Water Depth

Rig Maximum Environmental Conditions

Hurricane Season Ratings

Evacuation Plan for MODU (COCP for ice)

For platform rig - structural assessment of platform rig to be installed

Page 6: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Oil Spill Financial Responsibility Verify operator Oil Spill Financial Responsibility on file

Verify effective and expiration dates

30 CFR 253 regulations

Up to $150 million (depends on number of facilities, facility location, WCD volume)

Page 7: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Plat Information Plat drawn to scale 1” = 2000 feet

Surface and subsurface location of well

Surface and subsurface location of well shown in feet from lease line

Surface and subsurface location of previously drilled wells shown within the block of well proposed to be drilled

Page 8: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Exploration or Development Plan Verify plan approval

Check conditions of approval and or mitigations that apply to APD Shallow hazards, archeological, buoy pipelines, cementing, discharges (shunting around coral reefs)……

For moored rigs, confirm anchor pattern in APD is same as what was in plan

Page 9: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Geologic Information

Significant markers

Hydrocarbon bearing zones

Shallow hazards

Shallow water flows

Abnormally pressured zones

Lost circulation zones

Hydrogen Sulfide Presence H2S Plan

Plans for mitigating hazards

Page 10: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Drilling Prognosis Drilling procedure by hole section

Cementing programs (certified by professional engineer) Type, density, volume, top

Drilling fluids program Type, density, volume, mud onsite

Logging program Type, interval

Well testing program (if any)

– Prior Notification

– Fluid Disposal

– MMS Witness

– Data Collection

Page 11: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Engineering Calculations Casing design (certified by professional engineer)

Casing test pressures

Verify that dual mechanical barriers are installed in production casing (in addition to cement) (certified by professional engineer)

Cement volumes (certified by professional engineer)

Maximum anticipated surface pressure (MASP) calculations and assumptions

Page 12: BSSE Presentation to Israel

July 24, 2012 BSEE

Maximum Anticipated Surface Pressure (MASP)

• Formulas and Assumptions Vary From Company to Company

• Sample BSEE Calculations

– MASP Surface Shoe = FG – GG

– MASP Intermediate Shoe = BHP – Hydrostatic Pressure (70% Gas and 30 % Mud Column)

Page 13: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Well Control Well control procedure while

drilling

tripping

Well control procedure for annular preventer

Page 14: BSSE Presentation to Israel

July 24, 2012 BSEE

Diverter System

• Purpose

– Means of Directing Shallow Flows Away From Rig

– Provides Time to Abandon Facility if Needed

• As Part of APD Operator Must Submit a Variety of

equipment and operational type information

• Needs to be Installed When Drilling Conductor or

Surface Hole

Page 15: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Plan view

Elevation view

Diverter spool outlet size

Line length

Diameter (10 or 12 inch)

Burst rating

Radius of curvature

Targeted 90’s

Valve type

Valve Size

Valve location

Operating procedure

Test pressure

DIVERTER

Page 16: BSSE Presentation to Israel

July 24, 2012 BSEE

Page 17: BSSE Presentation to Israel

July 24, 2012 BSEE

Diverter Testing

• Actuate When Installed

• Actuate Every 24 Hours While in Use

• Pressure Test to 200 psi Every 7 Days

• Alternate Tests Between Control Stations

Page 18: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

One annular preventer

Two pipe rams

One blind/shear ram

Kill line with two full opening valves

Fill-up line above the uppermost

preventer

Rated working pressure of the choke manifold and components equal to or greater than working pressure of the ram BOP’s

Accumulator system provides 1.5 times the volume of fluid capacity required to close and hold all BOP components

BOP control drawings

Surface BOP

Page 19: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

One annular preventer

Two pipe rams

One blind/shear ram

Kill line with two full opening valves

Fill-up line above the uppermost

preventer

Dual pod system for independent operation

of BOP

Secondary BOP control system with ROV

intervention capabilities

Deadman and autoshear system

3rd party verification of BOP

BOP control drawings

Verify ROV can close, at a minimum, one set of pipe rams, one set of blind/shear rams and

disconnect from LMRP

Subsea BOP System

Page 20: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Rated working pressure of the choke

manifold and components equal to

or greater than working pressure of

the ram BOP’s

Accumulator system

BOP to meet or exceed API RP 53,

Section 13.3

BOP control drawings

Procedures for all ROV hot stabs

Procedure for testing deadman

system

Confirm at least one ROV hot stab will be tested on the seafloor

Review stump test procedure

Subsea BOP System Cont.

Page 21: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Blind/Shear Ram Information

Manufacturer

Type

Max. pipe size that can be sheared

Shearing pressure

3rd party verification that shear rams

can shear strongest pipe to be used

in the well at maximum anticipated

wellhead pressure

Other

BOP Sizes

BOP working pressure

BOP test pressures

Subea BOP System Cont.

Page 22: BSSE Presentation to Israel

July 24, 2012 BSEE

Blowout Preventer Pressure Testing

• Frequency

−When Installed

−Within 14 Days of Previous Test

−Before Drilling Out Each String or Liner

• Test Pressures

−Low Pressure Between 200 - 300 psi

−High Pressure to Rated Working Pressure

(RWP)

−Annular to 70% of its’ Minimum Internal Yield

Pressure (MIYP)

Page 23: BSSE Presentation to Israel

July 24, 2012 BSEE

Blowout Preventer Pressure Testing

• High pressure can be to less then RWP depending on

MASP calculations

• Each test - hold pressure for 5 minutes. If a component

does not test, remedy and retest

• Stump test subsea BOP before installation on seafloor

with water (BSEE witnesses all)

• Alternate tests between control pods and control stations

for subsea stacks

• Function tests annular/rams every 7 days between

pressure tests

• Visual inspection - once each day including riser. Use

TV camera for subsea equip.

Page 24: BSSE Presentation to Israel

July 24, 2012 BSEE

Blowout Preventer Test Records

• Record all Test Pressures on Pressure

Chart

• Chart Certification by Onsite Company

Representative

• Identify any Problems Encountered During

Test and how Remedied

• Retain all Records for 2 Years at Facility

or Onshore Location

Page 25: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Casing Design

Casing size and type

Burst rating

Collapse rating

Safety factors for tension,

collapse, and burst

Test pressures

Design calculations

Setting depth

Connection type

Page 26: BSSE Presentation to Israel

July 24, 2012 BSEE

Casing Pressure Testing

• Positive Pressure Test

‒ Imposes a force on inside of casing that

meets or exceeds formation pressure to

check for leak path from casing to annulus

– Required on conductor casing (200 psi) and

on surface, intermediate, production casings

(70% MIYP)

– Need to have 30 minute test with less than a

10% pressure decline

Page 27: BSSE Presentation to Israel

July 24, 2012 BSEE

Casing Pressure Testing

• Negative Pressure Test

– Reducing pressure from inside of casing to

check for leak path from annulus to casing

– Perform on intermediate and production

casing strings

– Operator proposes methodology to BSEE

Page 28: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Cementing Information Type(s) of cement to be used for each casing string

Volume of cement for each casing string

Wait on cement (WOC) time

Statement that they will use best practices in API RP 65 (shallow water flow), and/or Part 2 (deepwater)

Procedures for verifying top of cement

Procedures for remedial cementing

Annular washout for abandonment purposes

Page 29: BSSE Presentation to Israel

July 24, 2012 BSEE

Cementing

• Purpose – Bonds Casing to Hole

– Prevents Fluids in One Formation from Migrating to Other Formations

• Types – Variety of Oilfield Cements Based on Desired Properties

– Liquid, Foam, HPHT, Class G, Class H

• Additives – Modify Cement Properties

– Accelerators, Retarders, Weight Materials, Nitrogen, Freeze Protection (Salt)

• Pumping Equipment – High Pressure Equipment Moves Cement Down hole

Page 30: BSSE Presentation to Israel

July 24, 2012 BSEE

BSEE Cementing Requirements

• Structural Casing – Normally Driven, Cement Back to Mud Line (ML)

• Conductor Casing – Cement Back to ML

• Surface Casing – Cement at Least 200’ (61 Meters) Above Conductor Casing Shoe

• Intermediate Casing – Cover and Isolate Hydrocarbon and Abnormal Pressure Zones (at least 500’ above casing shoe or pressured zone)

• Production Casing – Isolate Hydrocarbon Zones (at least 500’ above casing shoe or pressured zone)

• Liner – Cement Lap Above Casing Shoe

• Wait on Cement (WOC) – cement must remain under pressure for 12 hours (surface, intermediate, and production casing) or 8 hours (conductor casing) before drilling resumes

Page 31: BSSE Presentation to Israel

July 24, 2012 BSEE

Application for Permit to Drill (APD)

Other Mud weight, pore pressure, fracture pressure plot

Anticipated safe drilling margin

Hydrogen sulfide contingency plan (if applicable)

Proposed well schematic

Coring program

Directional program

Departure request/alternative compliance request

Formation integrity test

Mud program

Containment

Page 32: BSSE Presentation to Israel

July 24, 2012 BSEE

32

MUD WEIGHT, PORE PRESSURE, FACTURE MUD WEIGHT, PORE PRESSURE, FACTURE

GRADIENT, AND CASING PLOTGRADIENT, AND CASING PLOT

0

500

1000

1500

2000

2500

3000

3500

4000

8 9 10 11 12 13 14 15

MUD WEIGHT (PPG)

TR

UE

VE

RT

ICA

L D

EP

TH

(F

EE

T)

PORE PRESSURE PLANNED MUD WEIGHT FACTURE GRADIENT

7-5/8”

10-3/4”

16”

24”

Page 33: BSSE Presentation to Israel

July 24, 2012 BSEE

DRILLING FLUIDS

• Volume and Type of

Fluid

• Additives

• Minimal Quantities On

Location

• Time to Re - Supply

(Barite)

Page 34: BSSE Presentation to Israel

July 24, 2012 BSEE

APD Form

Page 35: BSSE Presentation to Israel

July 24, 2012 BSEE

APD Form

Page 36: BSSE Presentation to Israel

July 24, 2012 BSEE

HYDROGEN SULFIDE

• Significant Percentage of OCS Production Contains H2S

• Requirements Apply to

– Drilling

– Completions

– Workovers

– Production

• BSEE H2S Requirements are Based on Likelihood of Encountering Gas

Page 37: BSSE Presentation to Israel

July 24, 2012 BSEE

H2S PERMITTING

• Area Classification – Absent

– Present

– Unknown

• Plan of Exploration or Development and Production Plan to Include Classification

• H2S Contingency Plan Required for Areas Classed as: – Present

– Unknown

Page 38: BSSE Presentation to Israel

July 24, 2012 BSEE

H2S CONTINGENCY PLAN REQUIREMENTS

• Key Elements Include

– Person in Charge

– Personnel Duties

– Agency Notification

– Actions to Take for 20 ppm

– Briefing (Muster) Areas

– Evacuation Criteria

Page 39: BSSE Presentation to Israel

July 24, 2012 BSEE

H2S CONTINGENCY PLAN REQUIREMENTS

• Key Elements Include

– Protective Breathing Equipment

– Precautions for Helicopters and Vessels

– H2S Detector Locations

– H2S Flaring Procedures

– Sulphur Dioxide Precautions

– Training and Drills

Page 40: BSSE Presentation to Israel

July 24, 2012 BSEE

Questions?