Buchi Final Project

Embed Size (px)

Citation preview

  • 7/31/2019 Buchi Final Project

    1/62

    Individual Project

    BSM 080

    MSc Project Management

    The Robert Gordon University

    2010

    AN ASSESSMENT OF COMMUNICATION AS A CRITICAL

    SUCCESS FACTOR IN CONSTRUCTION PROJECTS

    An Individual Project submitted in partial fulfilment of the

    requirements for the MSc Degree in Project Management to be

    awarded by The Robert Gordon University.

    Author: Eze Kingsley Onyebuchi

    Student No: 0800769

    Supervisor: Dr Bassam F BjeirmiWord Count: 7544

  • 7/31/2019 Buchi Final Project

    2/62

    ii

    ABSTRACT

    The intention of this dissertation is to investigate communication as a

    critical success factor with emphasis on the identification of the best

    communication strategy to adapt within UK construction project. Mostof the materials that will be use to carry out this research work are

    gotten from the documented secondary research work such as books,

    journals, articles and reports construction company report from

    previous projects. The information obtained from the material review

    will be use to study project management best practices on the

    effective communication strategy in construction project.

    APM Bok (2006 pp 102) defines communication as the process of

    giving, receiving, processing and interpretation of information.

    Based on the finding from deferent journal, articles and books, it is

    agree that most project fails because of lack of effective

    communication. It could be suggested that the effectiveness of

    communication in every project depends on the communication

    strategies adopted for that project.

    Sommerville et al (2004) suggested that proper management of project

    documents in a construction project is one of the key factors in a project

    that enhance the project success. They later suggested that the best

    communication strategy to achieve success is through the use of Electronic

    Document Management System (EDMS). Meanwhile Maslej (2006) from the

    research carried out in the Greater Toronto area concluded that the best

    communication strategies to adapt in most of the construction project is the

    use of phone such as Walkie-Talkie (Radio Massage) and Mike.

    The goal of this report will focus on the identification of the best

    effective communication strategies to adapt for project success in

    most construction projects.

  • 7/31/2019 Buchi Final Project

    3/62

    iii

    ACKNOWLEDGEMENTI wish to use this medium to show my deep appreciation to those who have

    help me in one way or the other to ensure the success of this research work.

    First, to my project supervisor, Dr Bassam F Bjeirmi, for his kind gesture and

    advice throughout the period of this research work. Secondly to Dr Eddy

    Ochieng for his kindness and support in ensuring that this work is feasible and

    completed on time.

    My immense gratitude also goes to my Mother and my elder brother for alltheir encouragement and support throughout my MSc. program. I will also

    thank all my friends for all there support throughout the MSc Project

    management course.

    DEDICATION

    I dedicate this work to my late father, Mr. Daniel Udoye Eze. Dad, may you

    continue to rest in bosom of the Lord. I LOVE you Dad.

  • 7/31/2019 Buchi Final Project

    4/62

    iv

    Table of Contents

    ABSTRACT ...................................................................................................

    ACKNOWLEDGEMENT ................................................................................. i

    DEDICATION .............................................................................................. i

    PROJECT RESEARCH PLAN ..........................................................................

    1.1 Introduction ..........................................................................................

    1.2 Overview of the research ........................................................................

    1.3 Research Rationale ................................................................................

    1.3.1 Academic ........................................................................................

    1.3.2 Business .........................................................................................

    1.3.3 Personal .........................................................................................

    1.4 Aims and Objectives ..............................................................................

    1.5 Expectation from the Research Objectives ................................................ 1.6 Scope inclusion/Exclusion .......................................................................

    1.7 Deliverables ..........................................................................................

    1.8 Constrains/Assumption/Consideration ......................................................

    1.9 Methodology .........................................................................................

    1.10 Research Outline .................................................................................

    1.11 Research Structure ..............................................................................

    LITERATURE REVIEW ................................................................................ 1

    2.1 Introduction ......................................................................................... 1

    2.2 Overview of Communication in Project .................................................... 1

    2.3 Importance of communication in construction project ............................... 1

    2.4 Communication in construction industry .................................................. 1

    2.5 Relationship between theory and practice of communication strategy in

    construction projects. ................................................................................. 1

  • 7/31/2019 Buchi Final Project

    5/62

    v

    2.6 Challenges of communication in construction project ................................ 2

    2.7 Process and Procedures of Communication in construction Project. ............. 2

    2.8 Conclusion ........................................................................................... 2

    RESEARCH METHODOLOGY ....................................................................... 2

    3.1 Introduction ......................................................................................... 2

    3.2 Research Design Review ........................................................................ 2

    3.3 Methodology ........................................................................................ 2

    3.4 Data collection ..................................................................................... 2

    3.5 Ethical considerations ........................................................................... 3

    3.6 Proposal for carrying out Primary Research .............................................. 3

    3.6.1 Stage 1 Qualitative Research method .............................................. 3

    3.6.2 Stage 2 Semi-Structured Interviews ............................................... 3

    3.6.3 Data Analysis & Verification .............................................................. 3

    3.7 Limitations .......................................................................................... 3

    3.8 Conclusion ........................................................................................... 3

    CONCLUSION AND RECOMMENDATION ..................................................... 3

    4.1 Introduction ......................................................................................... 3

    4.2 Conclusion ........................................................................................... 3

    4.2.1 Evaluation of Project Proposalagainst Objectives ................................ 3

    4.3 Recommendations ................................................................................ 4

    4.4 Lessons Learned .................................................................................. 4

    REFERENCES/BIBLIOGRAPHY ................................................................... 4

    APPENDICES ............................................................................................. 5

    LIST OF APPENDICES

    Appendix 1 - Gant Chat for the research

    work 51

    Appendix 2 - Sample of how information flows in construction

    project. 52

    Appendix 3 - Strategic Communication

    process 53

  • 7/31/2019 Buchi Final Project

    6/62

    vi

    Appendix 4 - Interview outline and

    Question. 54

    List of Tables

    Table 1: Research Objectives...........................................................................................................

    Table 2: Project Deliverables .............................................................................................................

    Table 3: Research Constrains/Assumption/Considerations ...................................................

    Table 4: Top 5 critical success factors in a construction project ....................................... 1

    Table 5. Claimed features of qualitative and quantitative research method. ............... 2

    Table 6: Qualitative data collection method .............................................................................. 2

    Table 7: Quantitative data collection method ........................................................................... 3

    Table 8: Ethical Considerations ..................................................................................................... 3

    Table 9: Interview schedule............................................................................................................. 3

    Table 10: Research Work Recommendation.............................................................................. 4

    List of Figures

    Figure 1: Triple constraint in Project management ................................................................ 1

    Figure 2: Literature Review Mind Map......................................................................................... 1

    Figure 3: Interaction to manage building construction information ................................. 1

    Figure 4: Communication Process ................................................................................................. 2

    Figure 5: Project Research Stages ................................................................................................ 2

    Figure 6: Research Design Plan ...................................................................................................... 2

    Figure 7: Primary Research Process Plan ................................................................................... 3

  • 7/31/2019 Buchi Final Project

    7/62

    1

    CHAPTER 1

    PROJECT RESEARCH PLAN

    1.1 Introduction

    According to Sears et al (2008), construction projects are project that are intricate

    which consists of several phases with a diverse range of specialized services.

    Construction project can range from small scale, medium or complex depending on

    the purpose in which it is meant for (Ochieng and Price 2010). There are six typesof construction project according to Sears et al (2008), which include; housing,

    nonresidential building, heavy, highway, utility and industrial. However,

    construction project are being manage by the project manager and the expertise in

    various department of the project who make sure that the work done is at a stated

    quality.

    Furthermore, among the factors that lead to the success of every construction

    project according to Chen and Chen (2007)is COMMUNICATION. Gardiner (2005)commented that most of the communication link that usually affects any

    construction project occurs when there is any communication lapse between two

    different groups in the project. In other words, it could be suggested that the

    effectiveness of communication in any construction project depends on the kind of

    communication strategies adapted. According to Bateman and Snell (1999), in their

    research reported that only twenty (20%) of information meant for site workers

    from the top management actually reach to them, and among the key factor that

    cause that is inappropriate communication strategy. (Cheng et al 2001).

    For the purpose of this research, more focus will be on how communication is being

    managed in construction project with special emphasis in building construction

    project. The target of this research is to provide background and recommendations

  • 7/31/2019 Buchi Final Project

    8/62

    2

    for the best strategy to employ for effective communication among all the parties

    involve within these construction projects in other to achieve project success.

    1.2 Overview of the research

    Before now, within the construction industries, a lot of project has been fail due to

    one factor or the other. These has led to many project management researchers to

    explore which critical area of the project plan that if not properly managed, will led

    to project failure. Research has shown that lack of effective communication among

    the team members in the project are often the cause of project delays, expensive

    reworking and building defect (Ahuja et al 2008). This was supported by Leung et

    al (2008) who stated that the most area of communication that often cause delay in

    a project is between designers and contractors. This is to say that having effective

    communication is one of the critical areas in the project which the project manager

    has to plan properly during project planning.

    Construction industry is one of the areas that encompasses different individual

    from different cultural background and location. Due to its complexity in nature,

    most project manager is finding it difficult to coordinate and manage the ways in

    which information is being disseminated to all the project participants and the

    consequences of these in construction projects is failure. (Belassi and Tukel 1996).

    It could also be argued that the strategy in which project information are being

    communicated accurately to all the project participants determine the effectiveness

    of communication. However, Sommerville et al (2004),Forcadaet al (2007) and

    Ahuja et al (2008) concluded in their research that the best communication

    strategy in a construction project is the use of web base document flow

    called Electronic Document Management System (EDMS). This EDMS is often

    used to transfer document through internet to the entire project participant

    and as well store all the project documents in the company project

    management database for reference use. (Sommerville et al 2004). It could

    be argue that most of the project team might not have the basic knowledge

    of computer or how to access internet since this might not be one of the

    requirements needed to select all the project team. Similarly, Maslej (2006)

  • 7/31/2019 Buchi Final Project

    9/62

    3

    from the research carried out in a construction project suggested the use of phone

    such as Walkie-Talkie/Radio massage, Mike and onsite meeting among all the

    project participants as the best communication strategy to adopt in any

    construction project. It could also be argue that noise from the heavy duty

    equipment usually affect the communication when such a strategy are used thereby

    causing communication lapse to the users. In addition, Cheng et al (2001) reported

    that face to- face communication strategy (such as meeting and visit) is the best

    channel to communicate in a construction project. It could be argued that this

    strategy can be visible only when the project manager is in physical contact with

    the team. In other word, this strategy will not be visible when managing a virtual

    project team. What is then the best communication strategy in a construction

    project? Winch (1998) and Chen and Chen (2007) as well as Pinto and Mantel(1990) has suggested that proper and effective information flow within the project

    participant still remain the key success factor of the business process in all

    construction projects.

    This research will explore the best strategy to put in place in other to achieve

    effective communication in UK construction project.

    1.3 Research Rationale

    The research rationale of this report will be divided into three categories: Academic,

    Business and Personal.

    1.3.1 Academic

    Before now, there has been so many range of literature on communication in

    project and the best ways to manage communication in every project in other

    achieve success. However this research will focus on the best practice and theory of

    communication in construction industry as well as the best strategic way to develop

    effective communication in a construction project.

  • 7/31/2019 Buchi Final Project

    10/62

    4

    1.3.2 Business

    For any organization to carry out any project, they require the service of a project

    manager and team to carry out the work. It is the responsibility of the project

    manager to brainstorm with the project team in order to identify who are the

    stakeholders of the project and the type of information they require to receive at a

    particular time. The effective management of communication as well as sharing of

    information among the project team and all the project stakeholders usually leads

    to project success. (BSI 2003). Project success in an organization bring about profit

    as well as competitive advantage, where as failure could be devastating to such an

    organization. It is very necessary that developing effective communication strategy

    in project should not be ignored.

    1.3.3 Personal

    It is penitent that successful project manager understand the needs to have

    effective communication in managing any project. As a potential project manager,

    it is of great important to understand the best communication strategies that

    should be adopted in any construction project to ensure project success.

    1.4 Aims and Objectives

    The aim of this research is to identify the best effective communication strategies

    to adapt in construction projects within UK.

    The objectives as stated in Table 1 are as follows;

  • 7/31/2019 Buchi Final Project

    11/62

    5

    Table 1: Research Objectives

    To examine the importance of effective communication strategies in ensuring

    project success on construction projects.

    To establish relationships between theory and practice in relation to

    communication strategies being applied in construction projects.

    To examine some of the challenges of communication in construction

    projects.

    To assess the communication process and procedure in construction projects.

    To propose recommendation based on the secondary research findings.

    1.5 Expectation from the Research Objectives

    Objective 1: This will explore the importance of having effective communication in

    construction projects.

    Objective 2: This will look into how communication has been used in construction

    industry both in terms of practice and theory.

    Objective 3: This will also explore some of the challenges that have been faced for

    effective communication in most construction industries.

    Objective 4: This will talk about the process and procedure of how effective

    communication is being used in construction project.

    Objective 5: This will talk about the recommendation base on the findings from the

    above four objectives.

  • 7/31/2019 Buchi Final Project

    12/62

    6

    1.6 Scope inclusion/Exclusion

    The scope inclusion of this project research will include:

    Documentary review on the subject area of Identify the effective

    communication strategies in a construction industry.

    Provide the primary research plan that should be used as a justification for

    the secondary research.

    The scope exclusions include;

    For the study, the planned primary research plan will not be implemented.

  • 7/31/2019 Buchi Final Project

    13/62

    7

    1.7 Deliverables

    The expected deliverables for this report as shown in Table 2 is divided into two;

    internal and external.

    Table 2: Project Deliverables

    Internal Deliverables External Deliverable

    A Gantt Chart that shows the period at

    which each task has to be carried out

    within the project from start to finish.

    A detail review of the research topic

    area.

    A research report plan that will contain

    the study background, aims and

    objectives, assumptions, considerations,

    rationale, scope, constraints and

    structure of the report.

    A research flow chart showing the

    content of the report.

    A proposed primary research design

    A complete research topic report that

    contain an introduction, literature

    review, methodology, conclusion and

    recommendations.

    A report made for the organization th

    will help to enhance further research

    the topic area.

  • 7/31/2019 Buchi Final Project

    14/62

    8

    1.8 Constrains/Assumption/Consideration

    The framework of this research as regards to Constrains, assumption and

    consideration are highlighted in Table 3 below.

    Table 3: Research Constrains/Assumption/Considerations

    Constrains

    Time was the major constraint encountered in the research. This is because the

    research was carried out simultaneously with the team placement report and

    personal CPD report. Other constraint is course requirements.

    Assumption

    It is assumed that all the information, requires to conduct this research are readily

    available, accessible and up to date.

    Consideration

    The major consideration on this report is that the study is being carried out in both

    building and heavy engineering construction project within UK, which remains

    feasible.

    1.9 Methodology

    This research will focus on the use of sample to identify the effective

    communication strategies and the method in which the information is gathered will

    be a secondary approach. Meanwhile, the documents gathered which relate to this

    research will be analyzed through documentation analysis.

    1.10 Research Outline

    Research schedule plan that will be use to explore all the objectives of this report

    are presented in a Gantt chart shown in Appendix 1.

  • 7/31/2019 Buchi Final Project

    15/62

    9

    1.11 Research Structure

    Chapter 1 Introduces what the topic is all about as well as the background of the

    research topic with clearly stated aims and objectives.

    Chapter 2 Reviews various related work which has been done by deferent

    scholars on the research topic as well as presenting summary of the data gathered.

    Chapter 3 Will look into the research methodology for the data gathered and the

    analysis done and also present a proposal for primary research.

    Chapter 4 Will focus on the findings and discussion analysis of the key element of

    the research.

    Chapter 5 Will be the summary of the research project and conclusions together

    with a possible recommendations and also areas for further research.

  • 7/31/2019 Buchi Final Project

    16/62

    10

    CHAPTER 2

    LITERATURE REVIEW

    2.1 Introduction

    Kerzner (2009) stated project management encompasses both art and sciences and

    it also involve how corporate resources are being managed and controlled within

    the constraints of time, cost and performance as shown in Fig. 1 below.

    Time

    CostPerformance

    Resources

    Figure 1: Triple constraint in Project management

    In the project management context, Admin (2006) commented that project is said

    to be successful if the project manager could be able to manage successfully the

  • 7/31/2019 Buchi Final Project

    17/62

    11

    requirement of these triple constraints. However, Greene and Stellman (2007),

    suggested that project is said to be successful if it meet the following requirements;

    Delivered under the budgeted cost,

    Completed within the allocated time frame, Fulfill the need of embarking on the project.

    If the end user is happy with the project.

    Pinto and Mantel (1990), Saquid (2008) and Chen and Chen (2007) as outline in

    Table 4, rank communication as the top critical success factors in construction

    project.

    Table 4: Top 5 critical success factors in a construction project

    Rank Pinto and Mantel (1990) Saquid (2008) Chen and Chen (2007)

    1 Critical Project Communication

    and Methodology.

    Communication system Effective Communication

    2 Top Management Support Control Mechanism Technical expertise

    3 Component of project

    alignment.

    Feedback capabilities Consistent with

    objectives

    4 Proper risk management Troubleshooting Questioning attitudes

    5 Project scope definition and

    management

    Planning effort Commitment to quality

    (Source: Pinto and Mantel 1990, Saquid 2008, and Chen and Chen 2007)

    Isfahani (2008) comment that the most significant out of the stated critical success

    factors above is effective communication among all the project participants. It couldalso be suggested that the reason is because, it is only through communication that

    a project manager can convince the top management the important of the project,

    obtain the required component a project need for its success, identify risk that is

    likely to associated with the project so that early response plan can be put in place,

    and also obtain information from the sponsor about the scope of the project.

  • 7/31/2019 Buchi Final Project

    18/62

    12

    The detail of this chapter as shown in Fig. 2 will focus on the review of project

    management literature on communication strategies, its importance in construction

    project and how it is being used in construction project. It will also provide some of

    the challenges face in communication as well as identifying the strategies that could

    be used to establish effective communication among the project participants. The

    next section of this research will review the concept of communication in a project

    environment.

    Research Literature

    Review

    1. Overview of communicationin project

    2. Importance ofcommunication in

    construction project

    3. Communication in constructionindustry

    4. Relationship between theory and practice ofcommunication strategy in constructionproject

    5. Challenges ofcommunication in

    construction project

    6. Process and procedure ofcommunication in construction project

    Figure 2: Literature Review Mind Map.

    2.2 Overview of Communication in Project

    According to APMBOK (2006 pp.102 ) Communication in every project is the

    process ofgiving, receiving, and interpretation of information. Stevens and APM

    (2006) describe communication as the process of exchanging information, ideas or

    feelings within the project participants where as Eppler (2000) define

    communication as a purposeful way of transmitting and co-constructing insights,

  • 7/31/2019 Buchi Final Project

    19/62

    13

    assessments, experiences, or skills through verbal or non- verbal information.

    Similarly, Ochieng and Prince (2010 pp. 451) describe communication in a project

    as the professional practice where suitable tools and regulations can be applied in

    order to improve the utility of the data communicated, and is a social process of

    interaction between individuals. Furthermore, according to APMBOK (2006 pp.

    102), communication in project can be convey either throughverbal, non-verbal,

    actively, passively, formally, informally, consciously or unconsciouslyto all the

    project participants as project progresses. Base on the above definitions, it could be

    suggested that the definition of communication could defer from one organization

    to another depending the nature of project embarks on as well as the

    communication skills of all the project participants. (Ochieng and Prince 2010).

    Communication is said to be effective when all the groups involve in a project wereable to understand the issues in the project and take an accurate decisions for

    effective change in align with the project objective. (Brown 2009). In other words,

    effective communication is a process of clearly transmitting of unambiguous

    massage from a sender to another person (receiver) in such a way that the purpose

    of sending the information is achieved. (Juden 2010). However, it could be

    highlighted that the effectiveness of a communication in a project can be achieve if

    both the receiver and the sender understand what the information conveyed is all

    about and use it appropriately in other to achieving project objective . From the

    above definition of communication, it is quite obvious that communication has no

    definite meaning as it is said to be multidimensional particularly in this present

    days project where people of deferent background and culture with different

    communication skills often make up the project team. This is the reason while

    communication has different meaning, contexts, forms, and impact to different

    individual in a project. (Dainty et al 2006).

    Despite the difficulties faced in defining communication in project, it will be

    necessary to adopt a particular definition of communication in other to strengthen

    the analysis of this research. However, for the purpose of this research, the

    definition of communication adapted is the one put forward by APMBOK (2006) and

    Eppler 2006 which define communication as a process of giving, receiving, and

    interpretation of information from one person to another within a project, of which

  • 7/31/2019 Buchi Final Project

    20/62

    14

    can be convey through verbal or non-verbal, actively or passively, formally or

    informally, consciously or unconsciously. Therefore, it is necessary that

    communication should be a two way processes to ensure accurate understanding

    between the people involve.

    The next section of this research will review the first objective of this research

    which is To explore the importance of having effective communication in

    construction projects.

    2.3 Importance of communication in construction project

    Dobson (2004) reported that in every project, all forces to ensure project success

    normally focus on theadministration of time, scope and cost usually known as the

    triple constraint. It is suggested that in order to accomplish these triple constraints

    in a project, the project manager needs to input numerous skills and techniques in

    order to articulate all these constraints (time, scope and cost) together. Also

    according to Buehring (2009), effective management of all these constraints in a

    project does not always guarantee success in construction project, but Emmitt and

    Gorse (2003) reported that the heart of every successful project depends on the

    ability to communicate abstract ideas among all the project participants. Similarly,

    communication in project play a key role in helping the project team to pull

    together all the information on the project and see what action that need to be

    taken in order to achieve project objective. (Cleland and Ireland 2007). However

    managing people in the project can be suggested as one of the key principles of

    effective communication. (Dainty et al 2006). This is because projects are being

    executed by a group of individual and if these individuals dont understand in the

    project, what they have to do, when they are suppose to do it and of what budget

    and time constraint and quality specification they are working towards, the project

    will fail. (Buehring 2009). The importance of communication in a construction

    project as put together by Armstrong (Dainty et al 2006) is as follows:

    Achieve quality results This is in relation with people working in a

    project. Having effective communication in a project often explain the

  • 7/31/2019 Buchi Final Project

    21/62

    15

    expected task to the team and the project team work together to ensure

    actualization of the project objective.

    Manage changes As project progress, changes often occur due to

    uncertainties of which if not properly manage on time, will led to delay in

    project. However, putting effective communication strategy in a project often

    helps the project manager and the team to identify any issue as well as

    manage the changes on time.

    Team Motivation Statistics has found out that individual get motivated in

    a project if their responsibility on the project and scope to achieve the

    project objective are well communicated on time to them.

    In addition, according to Shaw (2008), effective communication in a construction

    project helps to build a strong relationship among all project participants as well as

    break every barrier that may cause misunderstanding among the project

    participants. To this effect, it could be suggested that having effective

    communication in a project creates an avenue of trust between the project

    manager and the team as well as the stakeholders. This is because, if the

    stakeholders are receiving appropriate information about the progress of their

    project at the appropriate time, they will have trust in the project manager as well

    as the team and thereby create an avenue for project success.

    It is very important to have an effective communication strategy on every

    construction project to ensure success.

    The next section of this research will focus on how this communication has been

    used in construction project.

    2.4 Communication in construction industry

    Most construction projects are often described as a complex entity simply because

    of the quantity and interdependence of the components that make up the project.

    (Froese 2010). In a heavy construction project according to Ochieng and Price

    (2010), the project teams are mostly multicultural and people from different

  • 7/31/2019 Buchi Final Project

    22/62

    16

    professions and skills. Sommerville (2004) further stated that this highly differing

    professions and there multi disciplinary skills usually affect the scope of

    communication among the project team in a project. Similarly both project

    manager and client always find it difficult to develop a strategy that will be used to

    overcome this cultural conditions and operation in a project so that effective

    communication will be achieve. (Ochieng and Price 2010). Indeed, it could be

    suggested that information flow in construction project needs not only to

    communicate between the project manager and the project team but among all the

    project participants that is directly or indirectly affected by the project. Meanwhile

    communication in project is said to be a professional practice (Cheng et al 2001),

    and the key individual in a building construction project who often make use of

    communication in construction project are the project manager, client, contractorsand the architect. (Sommerville 2004). Also communication among these parties in

    a construction project is very crucial for the success of the project. (Sambasivan

    and Soon 2007). Similarly, Emmitt and Gorse (2003) reported as shown in Fig 3

    the key groups that are highly influential in a construction project and how

    information is being managed and flow among these groups.

  • 7/31/2019 Buchi Final Project

    23/62

    17

    BuildingCommunication

    Client Body

    InterestedParties

    Professional

    Consultants

    Contractorsand Sub-

    contractors

    Legislative

    Bodies

    FormalInteraction

    InformalInteractio

    n

    Building

    information

    and action

    Figure 3: Interaction to manage building construction information

    (Source: Emmitt and Gorse 2003)

    Furthermore, Toor and Ogunlana (2008) pointed out the two major communication

    skill project manager uses for effective communication; they are frequent

    stakeholders (consultants, designers, contractors and suppliers) consultation and

    responsiveness of these stakeholders, and these two factors are naturally

    complimentary. It could be suggested that the purpose of this consultation is to

    ensure that what is required from them for the success of the project are accurately

    understood. Nevertheless it could be advisable to adapt a communication method

  • 7/31/2019 Buchi Final Project

    24/62

    18

    that will allow for an effective sharing and exchange of information and resources

    amongst the entire project participant to ensure project success.

    The next section of this review will explore the second objective of this research

    which is To establish relationships between theory and practice in relation to

    communication strategies

    2.5 Relationship between theory and practice of communication

    strategy in construction projects.

    In order to understand the way communication are being practiced within the

    construction project, Masley (2006) suggest that it is necessary to first identify the

    roles, responsibilities and authorities of all the project stakeholders and the team,

    and explain how these information will get to them. It could be suggest that the

    purpose of doing this is to avoid any misunderstanding that might cause delay in

    the project. Appendix 2 shows example of project participant in a building

    construction project and the way in which information flow amongst them. The

    project manager receives information from the sponsor and delivers it to the

    project team, and as well report to the sponsor the progress of the project and also

    report any issue(s) from the project. The team leader can also with the permission

    of the project manager report to the sponsor any issue from the project. However,

    participation of stakeholders in a building construction projects are usually

    influenced by the effectiveness of communication and the manner in which

    informations are disseminated and managed among all groups in project. (Emmitt

    and Gorse (2003). Some of the communication strategy as being practice in most

    construction projects according to Emmitt and Gorse (2003) include the use of face-

    to-face meeting and presentation, which could be inform of formal or informal. It

    could also take place onsite or offsite for effective clarification of scope of work.

    Similarly, the use of Electronic Document Management System (EDMS) according to

    Sommerville et al (2004) is another communication strategy used in construction

    project where project information is disseminated to all the project participants

    through internet. This strategy were supported by Leung et al (2008) and (Winch

    2010) which suggested the use of wireless technology and Network cameras such

  • 7/31/2019 Buchi Final Project

    25/62

    19

    General Packet Radio service (GPRS), Bluetooth, and Wireless Local Network

    (WLAN) as a means of collecting various kind of data in construction project and

    send it direct to the project management data base where the project participants

    can have access to it and see the progress of work. These strategies according to

    Mohamed and Stewart (2003) will;

    Strengthen coordination between project participants.

    Facilitate document transfer and handling.

    Helped keeping and updating records.

    Enabled immediate reporting and feedback within the project.

    It could be suggested that the use of EDMS helps for easy transferring and storing

    of some of the important project document into the company project management

    data base for easy access to all the project stakeholders.

    Also, Masley (2006) suggested the use of Waikie-Talkie/Radio massage and a

    higher version of it Mike as another strategy in which communication is practice in

    a building construction project. Adenfelt (2010) agree with this form of

    communication by stating that both the project manager and functional managers

    make use of telephone for teleconferences to discuss the progress of work in the

    project. It could be suggested that these strategies forms the faster way of

    communicating with the project team for quick solving of any issue that might come

    up on the project site.

    Other form of communication strategy as stated by Emmitt and Gorse (2003) in

    which information are being disseminated in construction project as regards to

    health and safety include; induction to all the project team, toolbox talks - which

    explain some brief safety information on site, Videos - which explain the safety

    information onsite.

    In addition, it is reported by Ochieng and Price (2010), that due to the fact that

    most building construction project team are mainly multicultural, and many of

    those who has experience of working with them are yet finding it so challenging in

    communication. The next section of this review will explore the second objective of

  • 7/31/2019 Buchi Final Project

    26/62

    20

    this research which is To examine some of the challenges of communication in

    construction project.2.6 Challenges of communication in construction project

    In most of the project like the heavy and civil construction project, air port

    construction, there are meant to be too many challenges that will face

    communication among the project players. According to Kiisel (2010), among the

    first communication challenges the project manager will face in this kind of

    construction project is being able to communicate how the project will help the key

    stakeholder to achieve their vision when it is completed.

    In other words, Torrington and Hall (cited in Dainty et al 2006 p.69) summaries

    some of the communication challenges in construction project. They include;

    Stereotyping this is a situation where the receiver do things according to their

    own socio-economic background, profession or perceived deposition. It could be

    argued that the receiver only end up in doing the wrong thing. However, this

    situation poses a serious challenge in the use of EDMS as a communication

    strategy.

    Individual Frame of reference a situation where the receiver interpret convey

    massage in such a way that will shape their own frame of reference. In other

    words, the receiver usually ends up in doing what is not in line with the project

    objective. Also, this becomes a great challenge in the use of EDMS, Radio massage,

    and teleconferencing as a means of communication strategy.

    Cognitive dissonance Because most construction project team are usually

    individuals from deferent cultural background, the way in which they understand

    information differs (Ochieng and Price 2010). When some certain information is

    convey, the pattern in which it is presented might conflicts to some individual

    beliefs of which they will find it difficult to understand or respond positively to the

    massage. It could be suggested that this kind of behavior will affect the use of

    presentation as well as face-to-face meeting as a communication strategy in

    construction project.

    Distractions: Distraction from noise going on within the area in which

    communication takes place can pose serious communication difficulties. It could

  • 7/31/2019 Buchi Final Project

    27/62

    21

    also be suggested that the noise from heavy duty equipment used in most complex

    building construction like Olympic stadium project make it difficult for people to

    hear themselves during onsite conversation. This will also create a big challenge

    when using Walkie-Talkie/Radio massage and onsite meeting as a key

    communication strategy.

    Thought pattern is another form of communication challenges in a building

    construction project. When a massage has delivered in a particular manner, some

    people understand it as sensible, rational, logical, and self-evident while some

    understand it as insensible, irrational, illogical and obscure thereby making it so

    challenging in using Presentation, Onsite meeting and Teleconferencing as

    communication strategy in the project. (Loosemore and Lee 2002).

    However, it could be argued that for communication to manage effectively in anyconstruction project, the project manager should identify both positive and negative

    stakeholder and ensure that appropriate information are given to them at the

    appropriate time.

    Moreover, it could be argue that the process and procedure in which informations

    are convey in a building construction project will help in establishing effective

    communication strategy. The next section of this report will explore the third

    objective of this research which isTo assess the communication process and

    procedure..

    2.7 Process and Procedures of Communication in construction

    Project.

    Communication process in a project is the channel through which informations are

    disseminated in the project; it can be in the form of verbal or non-verbal (APMBOK

    2006). Guffey et al (2010 pp 97) stated that "Choosing the best channel to deliver

    a massage depends on the importance of the massage, the feedback required, the

    need for a permanent record, the cost and the degree of formality needed.

    Moreover, because of the complexity of building construction project, they are

    prone of changes as work progresses, (Ochieng and Price 2010), and the project

  • 7/31/2019 Buchi Final Project

    28/62

    22

    manager must endeavor to communicate strategically with both the internal and

    external members in the project in order to achieve success. (Thakkar 2008).

    Lizotte (2008) summarizes the element of communication process as shown in Fig 4

    below;

    Encode Massage Medium Massage Decode

    Source Receiver

    Feedback

    Noise

    Figure 4: Communication Process

    (Source: Lizotte 2008 )

    Source(Encode) the person who create the massage which can be

    either be verbal or non verbal.

    Massage what need to be communicated which is send by the source

    and receive by the receiver.

    Medium themeans through which communication is conveyed

    Receiver (Decode) individuals or team who receive the massage.

  • 7/31/2019 Buchi Final Project

    29/62

    23

    It could be argued that one of the most important aspects in communication

    process is the feedback which ensures that the massage is understood exactly as

    intended.

    In addition, Thakkar (2008) stated about four important communication strategic

    processes as shown in Appendix 3 that is been practice in a building construction

    project. They include,

    1. Phase 0 which define the core massage and themes.

    2. Mission Analysis of the massage

    3. Course of action (COA) development

    4. Execution (Deliver the massage)

    Furthermore, information in construction project flows in Upward, Downward and

    Lateral directions depending on the purpose and group involved. (Charvat 2002)However, it could be suggested that the channel and the medium through which

    information is delivered in a construction project depends on the stakeholder in

    whom the massage is meant for.

    2.8 Conclusion

    Building construction project are times so complex which involve so many

    participants from deferent culture and language. Basically communication among

    these project participants is a great challenge to the project manager. However,

    effective management of this communication will reduce most of the lapses that

    can cause conflict in the construction site which might result cost over runs and

    delay in project. (Toor and Ogunlana 2008)

    The above review has given an overview of what communication is all about in

    project, its importance in construction project as well as the strategic ways of using

    it in construction project. The review further emphasis on the comparison on how

    communication is being used in terms of theory and practice. Some of the

    challenges face during communication as well as the process and procedure used

    during communication has also reviewed.

  • 7/31/2019 Buchi Final Project

    30/62

    24

    CHAPTER 3

    RESEARCH METHODOLOGY

    3.1 Introduction

    The purpose of this chapter is to show different types of factors that should be

    considered during the process of this research. This will also explore the merits,

    demerits and also some of the limitations of qualitative and quantitative of research

    methods so that the best suitable method to carry out the research will be

    identified.

    The research aim of this report is to identify and understand the effective

    communication strategies, with emphasis on a sample of building and heavy

    engineering construction (oil and gas) project management within UK. It will also

    focus on how communication is being managed among all the stakeholders and how

    it affects the outcome of the entire project.

    This chapter will be divided into two parts which will be mainly the methodology

    used in gathering all the information required to carry out this research. Such

    information was mainly from UK building construction company documents and

    books, articles and journals from deferent authors. A Primary research plan which

    will serve as a guide in carrying out this research as well as help in validating the

    documentation and analysis will also clarify within this chapter.

    The flow diagram shows in Fig. 5outline the stages adopted for this chapter.

  • 7/31/2019 Buchi Final Project

    31/62

    25

    Stage 1 Selection of topicSelecting the research topic,

    developing its rational as well asaims and objectives.

    Stage 2 Literature Review

    Review already existing research

    work that was done on the topicwhich will assist in analyzing theresearch problem.

    Stage 3Define Research

    Problem

    Identify the best effectivecommunication strategies in

    construction industries.

    Stage 4 Research DesignCase study on a selectedConstruction Industries

    Stage 5Choosing Research

    MethodQuantitative and Qualitative

    methods

    Stage 6Collection of data for

    evaluationDocumentaries and Semi-

    Structured Interviews

    Stage 7 Findings and AnalysisSummary of key findings base on

    the data collected

    Stage 8Verification and

    Validation

    Semi Structured interviewquestions were develop to be

    administered as a validation ofthe documentary analysis

    Stage 9 Final write upPresenting the final management

    report on the research

    Implement findings in thebuilding construction project

    Project ManagementStage 10

    Figure 5: Project Research Stages

  • 7/31/2019 Buchi Final Project

    32/62

    26

    3.2 Research Design Review

    Saunders et al (2007) describe research design as a general plan of how to address

    the research question(s) about a topic, which usually contain the clear objectivesthat derive from the research question(s), specify the sources through which the

    data should be collected, the constraint expected in collecting data as well as the

    ethical issues. In addition, Bryman and Bell (2007) agree with these authors by

    stating that research design is like a framework that connects the research

    questions together with the data collected and its interpretation.

    The design research of this report is focus on a single case study of the construction

    industries, exploring the effective communication strategies in a construction

    project performance and success. Dul and Hak (2008) describe case study as a

    process of study either one case or a small number of cases in a real life context

    that are selected, and the scores obtain from these cases are analyzed based on

    the visual inspection of the case in contrast to statistical analysis. Also McGivern

    (2009) agree with Dul and Hak by stating that case study is an in-depth

    investigation of a case for exploratory, descriptive or explanatory research

    purposes. The use of case study in this research is to find out how the theory

    gotten from the literature review will be used to discover the best communication

    strategy in a selected building construction project within UK.

    The selected sample case study strategy adapted by the author for this research

    will help the author to get the full picture of the case and also to achieve an in-

    depth understanding as well as the detailed description of the case. (MacGiver

    2009). However, in spite of frequent use of case study, Xiao and Smith (2006) have

    describe it as a weak approach of research stating that it only focus on exploratory

    studies, which often leads to illogical conclusions. They also stated that case study

    strategy should only be used as a method of last resort. Meanwhile, Punch (2005)

    has countered the statement made by Xiao and Smith (2006) by giving positive

    reasons that single case study strategy helps to develop a unique case and as well

    provides an understanding of the important aspects of the research area.

  • 7/31/2019 Buchi Final Project

    33/62

    27

    Research Question Research Design

    Data Collection

    Data Analysis

    Figure 6: Research Design Plan

    (Source: The Author)

    Figure. 6 illustrates the process of conducting this research. It starts with aresearch question of the topic i.e. (What is the best strategy to develop an effective

    communication in a building construction project?). This question is being justified

    with the help of useful literature by deferent authors as well as collection of

    deferent data through documentary analysis and interviews as a method of

    empirical validation for the research question.

    3.3 Methodology

    Research method as describe by Kumar (2008), are all those methods or

    techniques used by the researcher for conducting research operation. The

    methodology is thus the study of the various steps that are generally adopted by a

    researcher in studying the research problem along with the logic behind them.

  • 7/31/2019 Buchi Final Project

    34/62

    28

    (Kumar 2008). In other words, methodology is basically the study of the

    procedures that is used to gain an in-depth knowledge about the research topic

    area.

    In addition methodology compares both the qualitative and quantitative methods ofthis research and the best method suitable for data collection will also be identified.

    It could be suggested that the research method adopted by any researcher depends

    on what the researcher is trying to find out. In addition, qualitative method

    basically deals with exploring peoples life histories or everyday behaviors where as

    quantitative method make use of statistical techniques and mechanics in survey

    research. (Silverman 2004). The differences in qualitative and quantitative features

    are shown in Table 5. below.

    Table 5. Claimed features of qualitative and quantitative research method.

    Qualitative Method Quantitative Method

    Soft Hard

    Flexible Fixed

    Subjective Objective

    Political Value- free

    Case study Survey

    Speculative Hypothesis testing

    Grounded Abstract

    (Source: Silverman 2004)

    Owing to the nature of scope of this research topic, together with the features of

    the research methods detail above, qualitative research method is adapted as the

    best research strategy for this research. This is because it entails the use of

    inductive research, in-depth case study approach as well as documentary reviews.

    In both qualitative and quantitative method, the only factor in which they have in

    common is data collection and the details of how it is use on both methods are

    explored in the following section.

  • 7/31/2019 Buchi Final Project

    35/62

    29

    3.4 Data collection

    According to National Statistics (2005), data collection simply means how

    information about a particular research is gathered. It is also enable for the robustdevelopment of the research area.

    However, in other to find out the best suitable means for data collection of this

    research, it is suggested that the various data collection methods that are

    associated with both qualitative and quantitative research strategies be reviewed.

    Table 6: Qualitative data collection method

    Method Purpose Merit Demerit Rational &Outcome

    Interviews Open-endedquestion tosmall samples

    a, It gives opportunity to

    ask in-depth question

    about the research area.

    b, It provides

    opportunity to access

    the social cues of the

    interviewer.

    c, Tape recorder can be

    used to gather accurate

    information.

    d, It create room for

    flexibility in order of

    question or approach to

    questioning.

    a, It is expensive

    when compare to

    other method.

    b, Transcription of

    data collected is

    time consuming.

    c, It need high skills

    in other to get

    accurate information

    needed.

    ACCEPTED: Theauthor needs in-depth and robusinformation thatwill corroboratethe theoreticalaspect of theresearch. A faceto-face interviewresearch methodis adopted. Theinterview will bebetween the

    author and theproject managerand projectteam.

    Observation Fundamentaltounderstandinganotherculture.

    a, It provide information

    previously unknown to

    researcher that is crucial

    to the topic.

    b, It can be relatively

    a, It is time

    consuming.

    b, Documentation

    relies on memory,

    personal discipline

    REJECTED: Dueto the fact thatthis method istime consumingit is not feasibleto this researchas the durationallocated for it is

  • 7/31/2019 Buchi Final Project

    36/62

    30

    Source: (Dew 2006; Family health international 2004; Opdenakker 2006;

    Silverman 2004 and Tashakkori and Teddlie 2003)

    unstructured.

    c, It allows insight into

    contexts, relationship

    and behavior.

    and diligence of

    researcher.

    c, It is mainly

    subjective.

    limited.

    Transcripts/Documentary

    Used tounderstandhowparticipantsorganize theirtalk and bodymovement.

    a, It is easily accessible.

    b, It does not intrude

    into peoples lives.

    c, It is inexpensive.

    d, It has high level of

    accuracy.

    a, Any script that

    lost might

    jeopardize the

    research.

    b, Bias in selection

    of transcript.

    ACCEPTED: Thimethod will helpthe author toexplore in detailall the documentavailable to theresearch area.

    Focus group Understandingparticipants

    categories.

    a, It allow good

    interpretive validity.b, It allow probing.

    c, It allow quick

    turnaround.

    d, It allow study of how

    participants react to

    each other.

    a, It is dominated by

    one or two

    participants.

    b, The measurement

    validity is possibly

    low.

    c, Focus group

    moderator might be

    possibly biased.

    REJECTED:Because that

    severalparticipants areinvolve and thevalidity of data ilow, this methodis rejected due ttime constrainand the nature othe researcharea.

  • 7/31/2019 Buchi Final Project

    37/62

    31

    Table 7: Quantitative data collection method

    ethod Purpose Merit Demerit Rational &Outcome

    urvey Mainly fixed-choice

    questions torandom samples.

    a, It allows greater

    objectivity and accuracyof results.

    b, It is relatively

    inexpensive.

    c, It can be administer

    from anywhere

    irrespective of the

    location.

    d, It is reliable and easy

    to obtain.

    a, It involves large

    amount of samplesto reply thereby

    making it tedious

    and time

    consuming.

    b, The participants

    may find it difficult

    to tell the truth

    about any

    controversial

    question.

    REJECTED:

    Irrespective offact that it con

    standard quest

    it is best suitab

    for primary

    research due t

    time constrain

    uestionnaire Used infrequently

    to check the

    accuracy of

    interview records.

    a, It is cost effective.

    b, It is easy to analyze.

    c, It reduces

    interviewers biasness.

    d, It gives respondent

    opportunity to answer

    questions at their

    convenient time.

    a, Response from

    the respondent are

    relatively low

    b, Respondents may

    answer superficially

    if the questions are

    too many.

    c, It lacks probing of

    the research area.

    d, It is time

    consuming.

    REJECTED: Th

    method is best

    adopted for

    primary resear

    which is out of

    authors scope

    tructured

    bservation

    Preliminary work. a, It is very systematic

    b, It helps to compares

    between settings and

    situations

    c, It shows reliability

    and applicability of data

    a, It requires

    excellent skills and

    knowledge before

    use.

    b, The process is

    complex and rigid.

    c, It is time

    consuming.

    REJECTED:

    Because this

    method is com

    and also takes

    time to carry o

    it is better off

    primary resear

    which is out of

    authors scope

    extual

    nalysis

    To measure

    attitudes,

    personality, self

    perception and

    performance.

    a, Its data can be easily

    analyze.

    b, It has high validity

    measurement.

    c, Can provide good

    measures of many

    a, Can be expensive

    if test must be

    purchase for each

    research participant.

    b, It can be biased

    against to some

    REJECTED: Th

    method will re

    a particular sk

    other to use it

    effectively. Thi

    will take the

  • 7/31/2019 Buchi Final Project

    38/62

    32

    characteristics of people.

    d, The response rate is

    high.

    certain people.

    c, It posed to have

    non- response error

    to selected items on

    the test.

    author more ti

    to acquire.

    (Source: Cohen et al 2007; Colorado state university 2010; ONeill 2006; Silverman

    2000 and Tashakkori and Teddlie 2003)

    Tables 2 and 3 shows the various methods that are associated with both

    quantitative and qualitative research methods, there advantages and disadvantages

    as well as the rational for adoption or rejection.

    From the above tables, methods through which the data collections were made are

    justified. The documentary gathered was review and employed to understand the

    effect of effective communication in a construction projects. Gathering of data and

    information were done through exploration, review and examination of some

    construction company documents and reports, journals, articles and books from

    deferent authors. All these were carried out to explore the best effective

    communication strategies to adopt for successful execution of construction project.

    3.5 Ethical considerations

    The ethical issues that will be considered in carryout this research work are shown

    in Table 8

    Table 8: Ethical Considerations

    The Participants should have the right to be informed of the purpose of this

    study.

    Participants may withdraw at any time during the research.

    All information should be treated as strictly confidential.

    Participants should be debriefed after the research program.

    Interviews will be conducted with informed consent and interviewees will berespected and have the right to anonymity.

    Copyright law will be respected.

    (Gratton and Jones 2004)

  • 7/31/2019 Buchi Final Project

    39/62

    33

    3.6 Proposal for carrying out Primary Research

    Due to the fact that the scope of this research restricts the author only to carry out

    secondary research, a primary research plan will be drawn to serve as a way to

    justify the documentary review. The Fig. 7 below shows the suggested primary

    research plan adopted by the author as regards to this research.

    RESEARCH METHOD

    (Qualitative research

    method of data

    collection)

    Data

    Collection

    (Semi-structuredInterviews and

    documentary)

    Findings & Analysis

    (Summary and analysis

    of key findings)

    Report presentation

    (Final presentation of

    findings and management

    report)

    Stage 1 Stage 2 Stage 3 Stage 4

    Figure 7: Primary Research Process Plan

    (Source: The Author)

    3.6.1 Stage 1 Qualitative Research method

    The methodology adopted to conduct this research plan is qualitative research

    strategy. An open ended, semi-structured face-to- face interview will be adopt tocarry out this research. Also, it is suggested that the use of tape recorder during

    the interview should be adopted but only with the permission of the interviewee.

    This is because it will give the researcher the opportunity to get an in depth and

    unbiased detail of the research question. (Opdenakker 2006)

  • 7/31/2019 Buchi Final Project

    40/62

    34

    3.6.2 Stage 2 Semi-Structured Interviews

    In this type of interview, the details of what the researcher is trying to find out

    within the research topic area should be written down; this will serve as a guide

    during the interview. Meanwhile the interviewer has the discretionary powers and

    can ask question as the interview progresses.

    3.6.2.1 Interview Question Purposes

    The purpose of asking this interview question as shown in Appendix 4 is to explore

    more on the importance of communication on project success delivery in a

    construction company, how communication has been practice among the projectparticipant in a construction project, some of the challenges project managers faces

    when communicating in construction project, and process and procedures that has

    been used when communicating in a construction project.

    Sample

    Series of interviews are to be conducted with all the key project players within at

    least 30 selected construction projects. (20 Building construction project and 10 oil

    and gas construction project within UK.). These selected construction projects will

    represent the entire construction project within UK. The schedule for the interview

    is shown in Table 9.

  • 7/31/2019 Buchi Final Project

    41/62

    35

    Table 9: Interview schedule

    Company

    Name

    Company

    Type

    Interviewees

    Position

    Interviewer Date of

    Interview

    A Oil and Gas

    Construction

    Project Manager Author

    B Oil and Gas

    Construction

    Architect Author

    C Building

    Construction

    Project Manager

    Author

    D Building

    Construction

    Quantity

    SurveyorAuthor

    E Building

    Construction

    Supply Chain

    Manager

    Author

    F Oil and Gas

    Construction

    Supply Chain

    Manager

    Author

    G Oil and Gas

    Construction

    Logistic

    Coordinator

    Author

    H Building

    Construction

    Project Manager Author

    I Building

    Construction

    Civil Engineer Author

    J Oil and gas

    Construction

    Project Manager Author

    Source: Author

    Interviews with project team: About ten (10) one-on-one interviews will be

    conducted randomly among the project team members in deferent location of

    construction project, who has at least ten (10) years working experience in a

    construction project. The interview should be in an open- ended question that is

    related to communication strategy on construction project. The purpose of this

    interview is to confirm the experience, views, concerns and expectations of the

    team towards the best communication strategy in construction project.

  • 7/31/2019 Buchi Final Project

    42/62

    36

    Interviews with project manager: All the project managers in at least ten (10)

    deferent construction projects with at least five (5) years working experience, who

    also are responsible to plan and manage a minimum of ten (10) successful projects,

    were to be interviewed. Each interview should last about 45min to 1hr. This

    interviews is to be conducted for them to share their views about communication

    issues they have encountered in their past project as well as how they will go about

    to correct this issues in their subsequent project. They will also give their views

    base on their personal experience, the best strategic method to set up an effective

    communication strategy for the success of most construction project.

    3.6.3 Data Analysis & Verification

    Stage 3 Data Analysis

    About twenty (20) interviews were to be conducted among the project players in

    selected construction project within UK; (10 project team members) and (10

    project managers). Also documentation analysis technique were to be used to

    gather information require for this research as well as reviewing most construction

    industry documents, journals and textbooks. The interview conducted with both theproject team and project manager will help to verify the information from the

    review documents.

    In addition all the information gathered were to be recorded, transcribed verbatim

    and then analyze using qualitative analysis software package NUDIST Nvivo.

    (Ochieng and Price 2010). This software will help the researcher to compare,

    contrast and synthesis opinions as regards to communication in construction

    project. The result generated from the data will serve as a verification tool for thedocumentary analysis carried out.

  • 7/31/2019 Buchi Final Project

    43/62

    37

    3.7 Limitations

    One of the greatest limitations of this research is the usage of the qualitative data

    analysis software as the author requires in-depth knowledge and skill to use it. Also

    time factor is another limitation that faces this research because the project

    requires observation in order to develop a robust solution to the research area. Due

    to the fact that the author is not allowed to carry out primary research, information

    gathered from journals, text books and Construction Company will not be enough to

    validate the research area. Unavailability of enough related work on the research

    area (identifying the best communication strategy in construction project) was aswell another form of limitations encountered.

    3.8 Conclusion

    This section has explored in details, the evaluation of research methodology, the

    suitable method of data collection and the rationale in which it is being adopted. It

    has further explored some of the advantages and disadvantages of various method

    of data collection. The chapter also provides the details of how best the primary

    research will be carried out.

    The next chapter will explore on the last objective of this research work by

    gathering together all the research work done for this project by concluding and

    proffer recommendation base on the findings as well as highlighting the lessons

    learned

  • 7/31/2019 Buchi Final Project

    44/62

    38

    CHAPTER 4

    CONCLUSION AND RECOMMENDATION

    4.1 Introduction

    This chapter will bring together all the objectives acknowledged for this research

    work to give a relevant overview of the research work carried out. This chapter also

    concludes this research work by stressing the significant findings as it relates to

    developing effective communication strategies in a construction project. Theconclusion of this research work will focus on how communication have been used

    in terms of theory and practice within construction project, some of the

    communication challenges, as well as the communication process and procedures

    within construction project.

    In all, this chapter thus gives a summary of the research structured in accordance

    with the achievement of objectives 1-4.

    4.2 Conclusion

    4.2.1 Evaluation of Project Proposalagainst Objectives

    1. To examine the importance of effective communication strategies in

    ensuring project success on construction projects.

    Chapter 2 explores all the breadth and depth of all the resources and materials that

    is review on the topics of effective communication strategy in a construction

    project.

    Construction industries require developing effective communication strategies for

    successful executing of their project. This is because in other to mange effectively

    the triple constraints or any factor(s) that determines the success of a project, the

  • 7/31/2019 Buchi Final Project

    45/62

    39

    project manager should ensure that all the abstract ideas about the project are

    communicated effectively to all the project participants just as Emmitt and Gorse

    (2003) has suggested. However, the needs for having effective communication

    strategies in a construction project should not be understated because it create an

    avenue for all the project participants to develop trust, build a strong relationship

    among themselves thereby working together in achieving coordinated results,

    manage changes effectively in project as well as get motivated on the project to

    ensure project success.

    2. To establish relationships between theory and practice in relation to

    communication strategies being applied in construction projects.

    To communicate effectively in a construction project, it is necessary to understandthe key roles and responsibilities of all the project participants in order to avoid any

    misunderstanding among different groups. Appendix 2 highlighted major groups in

    a building construction project where most of the communication strategies that are

    often practice among the groups are face-to-face meeting and presentation which

    could be onsite or offsite. However, when managing a complex project, the project

    manager should adapt the strategy of using Electronic Management System (EMDS)

    to capture, store, send images or project documents into the project management

    database where the project participants can have access to it. In addition, the use

    of automated device such as mobile phone, Waikie-Talkie and Mike has to be

    introduced for all the project participants who are working in a less noisy part of the

    project. Similarly, the use Skype for teleconferencing among the virtual project

    team from different location should be encouraged.

    3. To examine some of the challenges of communication in construction

    projects.

    Challenges of communication in a construction project are factor that is inevitable.

    Because of complexity nature of most construction project which attract people of

    different cultural background to form part of the project team. The first challenge a

    project manager will face is first, how to communicate the impact of the project in

    line with the organization goals, to the key stakeholders. The Second is how to

  • 7/31/2019 Buchi Final Project

    46/62

    40

    tackle the issue of stereotyping, individual frame of reference, cognitive dissonance

    as well as distractions when communicating in the project. The project manager

    should ensure to use different thought pattern by adapt on daily bases, onsite face-

    to-face meeting in the morning before work commence in order to avoid challenges

    of distraction of noise from heavy duty equipment.

    4. To assess the communication process and procedure in construction

    projects.

    In communicating to sponsor or project board in a construction project concerning

    any issue or risk in project, the project manager should ensure to use project

    weekly status report, face-to-face meeting or email in other to strengths the buy-in

    from top management. Also, when communicating laterally for example tocontractors which often need diplomacy and tact, the project manager should

    ensure to use E-mail and statement of work. Similarly, in communicating downward

    for example, to project team, which also needs diplomacy, the project manager

    should use E-mail, issue log and verbal exchanges.

    However, in ensuring an effective communication process in a construction project,

    the project manager should, define his/her core massages and themes, define

    target and audience, develop detailed strategies and tactics, develop and

    implement a detailed communication plan, as well as monitor progress, adjust

    strategies and tactics. The project manager should also try and avoid overuse of

    slangs or acronyms when communicating to avoid confusion.

  • 7/31/2019 Buchi Final Project

    47/62

    41

    4.3 Recommendations

    The research work was aimed at exploring the best effective communication

    strategies and the way in which they are practice in the construction industrieswithin UK.

    Base on the research findings from the review literature which is from books,

    journals, articles and construction companies reports, the following

    recommendations as outline in Table 10 are proffered;

    Table 10: Research Work Recommendation

    Since this research was limited in scope to a secondary review and research,

    it recommended that the primary research is conducted in order to serve as a

    validation process for the secondary review and analysis.

    It is recommended for further research to carry out on the level of computer

    literacy of the entire project participant in construction industries.

    It is recommended that further research should be conducted on the

    processes of developing communication skill by the project manager for

    effective communication in a construction project.

    It is recommended for further research to carry out on the best approach ofcommunication skills to a virtual project team.

    4.4 Lessons Learned

    This research has thought me great things in the project management principles

    both in theory and practice. The important things i learn from this research are;

    How to critically review, criticize and analyze literatures from other authors.

    How to go about in choosing the right methodology for any chosen topic

    research

  • 7/31/2019 Buchi Final Project

    48/62

    42

    How to narrow down a research topic as well as the goals and objective

    identify in solving the problem.

    REFERENCES/BIBLIOGRAPHY

    ADENFELT, M., 2010. Exploring the performance of transnational projects: Shared

    knowledge, coordination and communication. [Online]. International Journal of

    project management. Vol. 28, pp 529-538. Available from:www.sciencedirect.com

    [Accessed 10th September 2010]

    ADMIN, E.P., 2006. The triple constraints of projects: Quality, cost and schedule.

    [Online]. Available from: http://www.enterprise-pm.com/pmbasics/triple-

    constraint. [Assessed 27th August 2010]

    AHUJA, V, YANG, J, and SHANKAR, R., 2008. Study of ICT adoption for building

    project management in the Indian construction industry. [Online].Automation in

    construction Journals. Vol.18 pp 415- 423. Available from:

    http://www.sciencedirect.com[Accessed 10th August 2010]

    APM., 2006.APM Body of Knowledge. 5th Edition. Buckinghamshire: Association for

    Project Management.

    ATKINSON, R., 1999. Project management: Cost, time and quality, two best

    guesses and a phenomenon, its time to accept others success criteria. [Online]

    International Journal of project management. Vol.17 pp 337-342. Available from:

    http://www.sciencedirect.com[Accessed 2nd August 2010]

    BATEMAN, T.S, and SNELL, S.A., 1999. Management: Building competitive

    advantage. 4th ed. London. McGraw-Hill.

    BELASSI, W, and TUKEL, O.L., 1996. A new framework for determining

    critical/failure factors in projects. [Online]. International journal of project

    http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.enterprise-pm.com/pmbasics/triple-constrainthttp://www.enterprise-pm.com/pmbasics/triple-constrainthttp://www.enterprise-pm.com/pmbasics/triple-constrainthttp://www.sciencedirect.com/http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.enterprise-pm.com/pmbasics/triple-constrainthttp://www.enterprise-pm.com/pmbasics/triple-constrainthttp://www.sciencedirect.com/
  • 7/31/2019 Buchi Final Project

    49/62

    43

    management. Vol. 14. pp 141-151.Available from: http://www.sciencedirect.com

    [Accessed 10th July 2010]

    BROWN, B., 2009. Definition of Effective Communication Skills. [online] Living

    strong. UK. Available from:http://www.livestrong.com/article/67317-definition-

    effective-communication-skills/. [Accessed 15th August 2010]

    BRYMAN, A, and BELL E., 2007. Business Research method 2nd ed. New York.

    Oxford University Press.

    BSI., 2003. Poor communication costing UK construction industry. [Online] BSI.

    London. Available from:http://www.bsigroup.com[Accessed 17th June 2010]

    BUEHRING, S., 2009. The importance of communication in project

    management.[Online]. Project Smart.UK. Available from:

    http://www.projectsmart.co.uk/the-importance-of-communication-in-project-

    management.html [Accessed 10th June 2010]

    CHARVAT, J.P., 2002. Project communications: A plan for getting your message

    across. [Online]. TechRepublic. Available from:

    http://articles.techrepublic.com.com/5100-10878_11-1061894.html [Accessed 10

    August 2010]

    CHEN, W.T, and CHEN, T.T., 2007. Critical success factors for construction

    partnering in Taiwan. [Online]. International journal of project management. Vol.25

    pp 475-484. Available from:http://www.sciencedirect.com[Accessed 15th August

    2010]

    CHENG, E.W.L, LOVE, P.E.D., and IRANI, Z. 2001. Network communication in the

    construction industry. [Online]. International Journal of Corporate Communications,

    Vol. 6, pp 61-70. Available from:www.emeraldinsight.com[Accessed 12th

    September 2010]

    CLELAND, D.I, and IRELAND, L.R., 2007. Project management strategic design and

    implementation. 5th ed. McGraw-Hill. United State of America.

    http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.livestrong.com/article/67317-definition-effective-communication-skills/http://www.livestrong.com/article/67317-definition-effective-communication-skills/http://www.livestrong.com/article/67317-definition-effective-communication-skills/http://www.livestrong.com/article/67317-definition-effective-communication-skills/http://www.bsigroup.com/http://www.bsigroup.com/http://www.bsigroup.com/http://www.projectsmart.co.uk/the-importance-of-communication-in-project-management.htmlhttp://www.projectsmart.co.uk/the-importance-of-communication-in-project-management.htmlhttp://www.projectsmart.co.uk/the-importance-of-communication-in-project-management.htmlhttp://articles.techrepublic.com.com/5100-10878_11-1061894.htmlhttp://articles.techrepublic.com.com/5100-10878_11-1061894.htmlhttp://www.sciencedirect.com/http://www.sciencedirect.com/http://www.sciencedirect.com/http://www.emeraldinsight.com/http://www.emeraldinsight.com/http://www.emeraldinsight.com/http://www.emeraldinsight.com/http://www.sciencedirect.com/http://articles.techrepublic.com.com/5100-10878_11-1061894.htmlhttp://www.projectsmart.co.uk/the-importance-of-communication-in-project-management.htmlhttp://www.projectsmart.co.uk/the-importance-of-communication-in-project-management.htmlhttp://www.bsigroup.com/http://www.livestrong.com/article/67317-definition-effective-communication-skills/http://www.livestrong.com/article/67317-definition-effective-communication-skills/http://www.sciencedirect.com/
  • 7/31/2019 Buchi Final Project

    50/62

    44

    COHEN, L, MANION, L, and MORRISON, k., 2007. Research methods in education.

    6th ed. Routhedge. USA.

    COLORADO STATE UNIVERSITY., 2010.Advantages and Disadvantages of survey

    method[Online] Colorado State University. Available from:http://www.writing.colostate.edu/guides/research/survey/com2d/cfm [Accessed

    12th August 2010]

    DAINTY, A, MOORE, D, and MURRAY, M., 2006. Communication in construction:

    Theory and practice. USA. Taylor & Francis.

    DEW, K., 2006. Documentary analysis in CAM research: Part 2. [Online]

    Complementary therapies in medicine. Vol. 4 pp77-80. Available from:

    http://www.sciencedirect.com[Accessed 14

    th

    July 2010]

    DOBSON, M.S., 2004. The triple constraints in Project Management. Management

    Concepts. USA.

    DUL, J, and HAK.T., 2008. Case study methodology in business research. [Online].

    Elservier science & technology. Available from;

    http://lib.mylibrary.com/brouse/open.asp?id=104782&loc=2787 [Accessed 7th July

    2010]

    EMMITT, S, and GORSE, C.A., 2003. Construction communication. UK. Blackwell.

    EPPLER, M.J., 2006. The concept of knowledge communication and its relivance to

    management [Online] Switzerland. University of Lugano. Available from:

    http://wwwknowledge-communication.org/pdf/research-note-knowledge-

    commuincation.pdf[Accessed 3rd June 2010]

    FAMILY HEALTH INTERNATIONAL ., 2004. Qualitative research methods: Data

    collectors field guide. [Online]. Available from:http://www.fhi.org[Accessed 4th

    July 2010]

    FROESE, T.M., 2010. The impact of emerging information technology on project

    management for construction.[Online].Automation in Construction Vol.19 Pp 531-

    538. Available from:http://www.sciencedirect.com [Accessed 18th August 2010]

    http://www.writing.colost