Gulfstream Aerospace Gulfstream Aerospace Corporation Corporation Savannah, Georgia Savannah, Georgia 0630, 23 August 2001 0630, 23 August 2001 C-37A Wing-Fuselage Joining C-37A Wing-Fuselage Joining

C-37A Wing-Fuselage Joining

  • Upload
    baby

  • View
    58

  • Download
    1

Embed Size (px)

DESCRIPTION

C-37A Wing-Fuselage Joining. Gulfstream Aerospace Corporation Savannah, Georgia 0630, 23 August 2001. Wing’s in place. Fuselage is lifted from its fabrication jig. The 100 yd. overhead trip. Fuselage is lowered onto the wing. Careful alignment. - PowerPoint PPT Presentation

Citation preview

Page 1: C-37A Wing-Fuselage Joining

Gulfstream Aerospace CorporationGulfstream Aerospace CorporationSavannah, GeorgiaSavannah, Georgia

0630, 23 August 20010630, 23 August 2001

C-37A Wing-Fuselage JoiningC-37A Wing-Fuselage Joining

Page 2: C-37A Wing-Fuselage Joining

Wing’s in placeWing’s in place

Page 3: C-37A Wing-Fuselage Joining

Fuselage is lifted from its fabrication jigFuselage is lifted from its fabrication jig

Page 4: C-37A Wing-Fuselage Joining

The 100 yd. overhead tripThe 100 yd. overhead trip

Page 5: C-37A Wing-Fuselage Joining

Fuselage is lowered onto the wingFuselage is lowered onto the wing

Page 6: C-37A Wing-Fuselage Joining

Careful alignmentCareful alignment

Page 7: C-37A Wing-Fuselage Joining

““Traditional” technology to attach – 3 in. pinsTraditional” technology to attach – 3 in. pins

Page 8: C-37A Wing-Fuselage Joining

4 attach points hold the fuselage to the wing4 attach points hold the fuselage to the wing

Page 9: C-37A Wing-Fuselage Joining

Finished in 45 minutes Finished in 45 minutes