C+A 02_Braga

Embed Size (px)

Citation preview

  • 7/27/2019 C+A 02_Braga

    1/9

    1110

    EstadioMunicipalde BragaPortugal

    EduardoSoutode Moura

    issue02 EstadioMunicipalde Braga

  • 7/27/2019 C+A 02_Braga

    2/9

    issue02 EstadioMunicipalde Braga

    1312

    You can see the cables pulling and you cansee the concrete working against the forcesto transfer the load to the stone. The manmadestructure is dependent on the natural rockfor its stability and its makeup it is thisencounter, this meeting between the naturaland the manmade that I find interestingto deal with.

    Eduardo Souto de Moura

  • 7/27/2019 C+A 02_Braga

    3/9

    1514

    issue02 EstadioMunicipalde Braga

    1 Ticketoffice

    2 Parking

    3 Entrance square

    4 Entrance gates

    5 UEFAtemporaryparking

    6 Alley

    7 Waterline

    8 Eastsquare(lower level)

    9 Eaststand

    10 Trail

    11 Field

    12 Weststand

    13 Westsquare(upperlevel)

    14 Grassstoragebuilding

    15 VIPparking

    16 TVcompound

  • 7/27/2019 C+A 02_Braga

    4/9

    1716

    issue02 Estadio Municipalde Braga

    0 10 20m

    transversalsection

    roofplan

    longitudinalsection

    When Portugal won the right to host Euro 2004,the 12th Europeansoccer championships,the country set about an ambitious programof stadium building which,in a short period of time saw sevennew stadiums built,while three were renovated,across eight citiesat a cost of 550 million (AUD$896 million).All of the new facilities were designed by Portuguese architectsand followed the form of traditional amphitheatre-style arenasyou see in major cities around the world;save for one outstandingwork:the Estadio Municipal de Braga designed by Eduardo Soutode Moura within the Dume Sports Park, on the northwest slopeof Monte Castro overlooking the historic northern city of Braga.Shoehorned into a former stone quarry,Souto de Mouras designfor the 30,000-spectator stadium ignored the typology of thegladiatorial arena and re-envisaged it as two long stands ofreinforced concrete with deep overlapping tiers running parallelto the pitch,with a 202 metre suspension coil cable concrete roofstrung between the two stands, and no spectator stands behindeach of the goals.At one end the goals are set almost hard againstthe rock face of the quarry,while at the other end the view is ofcountryside and the city of Braga below.This juxtaposition of the natural and man-made expresses theessence of the Braga Stadium and the result is a powerful pieceof sports architecture that seems to have been carved out ofthe mountainside and quarry floor.The southwestern tribune in particular appears to g row literallyfrom the craggy rock face as it climbs to a plaza at the top of thequarry;while the northeastern stand rises free from the quarryfloor;leaning back, rhythmically articulated by 16 powerful inclined50-metre-tall ribs of reinforced concrete,each just a mere onemetre thick and designed to carry within them most of thestadiums hydraulic and electrical infrastructures.In a geotechnical feat of massive proportions,1.7 million cubicmetres of granite and rock were blasted from the quarry face intowhich the south-western stand snuggles and crushed intoaggregate for making the concrete for the structure of the stadium.The carving and shaping of the rock face was achieved througha series of small,precise blasts to shape a cleft in the walls of thequarry. A series of steel pins were then inserted into the rock wallto stabilize the rock and prevent landslides.In the southwestern stand,set barely a metre from the rock face,Souto de Moura has created a dramatic Piranesian underworldof intense darkness and light,descending from the plaza at thetop of the quarry via stairs,lifts and concourses,with light drawnin through a series of vertical shafts. The southeastern standis accessed from the quarry floor through stairs inserted betweeneach of the vertical concrete piers;with longitudinal circulationachieved through a series of large circular openings cut intothe concrete ribs to reduce overall mass.Its stability is ensuredby reinforced concrete slabs supporting the stairs to each level.It is the subtle inverted arch of the suspended roof of the BragaStadium,however,that is the highlight of Souto de Mouras design.Spanning 202 metres over the playing pitch,pairs of full-lockedcoil cables,spaced 3.75 metres apart and strung between thetwo stands,support two massive independent slabs of reinforcedconcrete just 240mm thick,slipped over the cables 50 metresabove the ground,to cover each stand of the stadium.The leadingedges of each roof over the playing field are tied by steel gantriesthat carry lighting and sound.Rainwater is drained from the roofs by large steel spoutssuspended from the concrete roof slabs and into 40-metre-longsteel aqueducts of which 27 metres is cantilevered anchoredto 8-metre concrete columns in the southeastern embankmentof the site.The water is channeled along a watercourse and storedfor later use and distribution throughout the stadium complex.AFAssociados,the structural engineers for the stadium, describethe roof as a single curvature cable roof relying on the self weightof the concrete elements to resist the effects of dynamic windloads. The behaviour of the roof was verified before constructionin wind tunnel tests on both rigid and aero elastic models.Rui Furtado,a principal of AFAssociados,says the constructionsequence of stress ribbon bridges and the Dulles Airport buildingin Washington,designed by Eero Saarinen,provided the firm withits direction for the roof, using precast planks sliding over thecables with a thin layer of concrete poured on top to minimizeproblems arising from differential directions.

    The reinforced concrete slab is 240mm thick and was determinedby balancing the need for a stabilizing mass while minimizingthe weight, he says.The prefabricated elements were assembledover the cables on top of the stands.Each new piece was linkedto the previous piece with bolts and the pieces were slid alongthe cables on Teflon sliders. When all the pieces were in positionthe transversal and longitudinal joints between the panels werecast in concrete.Souto de Moura talks of the roof in almost lyrical terms:

    The cables carry great tension loads.They are tied to a batteryof concrete pillars in the structure on either side of the field.These pillars lean outward against the pull of the cables.But thatsnot enough.To counteract the thrust,the pillars are anchoredto the stone they rest upon.So the roof is linked to the pillars whichare linked to the stone.Ultimately it is the mountain that supportsthe roof.It is this encounter,this meeting between the naturaland the manmade that I find interesting to deal with.You can seethe cables pulling and you can see the concrete working againstthe forces to transfer the load to the stone.The manmade structu reis dependent on the natural rock for its stability and its make-up.Thus having the stone wall of the mountain terminate the southeastend of the stadium instead of the usual seating is a fitting reminderthat the stadium owes its existence to the mountain. JR

  • 7/27/2019 C+A 02_Braga

    5/9

    1918

    issue02 Estadio Municipalde Braga

  • 7/27/2019 C+A 02_Braga

    6/9

    2120

    issue02 EstadioMunicipalde Braga

    northwest elevationsection

    Constructability was studied and a precast slab proved to bea feasible solution.Cost estimates revealed that it could fit withinthe budget.The design concept was then fixed and detail designbegan.The architects general approach is to allow the technicalneeds of the construction to rule the development of the design.Thus,outside of the definition of the spaces and the overallaesthetics,an intense,demanding and stimulating dialogueresulted between the architects and the engineers wh ereby thesearch for the design solutions only ended when both disciplineswere satisfied.Clear and rigorous criteria were then agreed upon to mouldthe solutions to the technical needs of the building.The resultingsolution had to be simple in form and in detail.But simplicityis only achieved through a gradual and continuous processof successive modifications that often bring up solutions that arequitedifferentfrom theoriginal ideas.Thearchitectsand engineersworked closely together to achieve a common goal,which wasnot viewed as the exclusive territory of one or the other.The concept was to build a set of suspension cables suspendedfrom the beams at the top of the rib walls, supporting twoindependent concrete slabs that covered each stand.The geometry selected resulted from a compromise betweenthe aim of the architect for an extremely subtle inverted arch andthe value of the force produced on the structure by the horizontalcomponent of the cable forces.The selection of the type of cable was also extremely importantas it would influence the definition of the shape and technologicalcharacteristics of the roof.Two cable options were possible:full locked coil strand and parallel wire strand. After studyingthe different characteristics of the two solutions in terms ofdurability,anchoring devices and dimensioning,full locked coilcables were selected,which led to smaller diameters.In additionto standardizing the concrete slab height along the roof,theonly significant modification from the initial project consistedof grouping the cables into pairs,with spacing between eachpair of 3.75m,two times the initially plann ed 1.875m.Totalkaboutthe stadiumsstructureisto talkaboutits architecture,andtoexplainitsarchitectureisto tellthestoryoftheengineeringproblems it brought up and how they were overcome.Rui Furtado,Carlos Quinaz,Renato Bastos,AFAssociados,Gaia,Portugal

    (This is an edited extract from an article published inStructural Engineering International,Issue 2, 2005)

    Project statementThe rock excavation and the roof were the big challengesfor the design team.The roof had to be compatible with the ideaof integrating the stadium and the environment.It was also to beas light and clean as possible.Therefore,arches,trusses,poles,cables and membranes were eliminated as solutions.A suspended roof such as was used in the Portuguese Pavilionin Expo 98 (Alvaro Siza) came up as the natural solution.Therockexistedtoanchorthecablesandthereactionof theroofin the cantilevered stand would help in stabilizing it. However,there were reservations in the uncertainty of the dynamicbehaviour of a 202-metre-span roof and the fact that the roofwould have to be built 50 metres high.The Portuguese PavilionRoof has a 67.5 metre span and with a lower height was builtwith a total propping system from the ground.Research on similar structures and preliminary calcul ationsshowed the feasibility of the solution and that an appropriategeometry and slab weight could lead to a desirable balanceof moments in the foundation for permanent load combinations.A structure of parallel ribswould provide the required stiffnessfor the stand and would allow for all the stairs,concourses,bars,etc.to fit in between.

    section

    section

    section

  • 7/27/2019 C+A 02_Braga

    7/9

    23

    issue02 EstadioMunicipalde Braga

    22

    The cables carry great tension loads.They are tied to a battery of concrete pillarsin the structure on either side of the field.These pillars lean outward against thepull of the cables. But thats not enough.To counteract the thrust, the pillars areanchored to the stone they rest upon .So the roof is linked to the pillars whichare linked to the stone. Ultimately itis the mountain that supports the roof.

    Eduardo Souto de Moura

  • 7/27/2019 C+A 02_Braga

    8/9

    2524

    issue02 Estadio Municipalde Braga

  • 7/27/2019 C+A 02_Braga

    9/9

    2726

    issue02 EstadioMunicipalde Braga

    -21 Parking2 Technicalgallery13 Technicalgallery24 Technicalgallery35 Technicalgallery46 Technicalgallery57 Maintenanceaccess8 Access 19 Access 2

    10 Access311 Access412 Guardshouse13 Atrium14 Hall115 Storage116 Storage217 Hall218 Storage319 Pressconferenceroom20 Regie21 Technicalarea22Mixarea23 VIP/UEFAscorridor24 Journalistscorridor25 VIP/UEFAselevatorhall26 Journalistselevatorhall27Technicalarea128Technicalarea229 UEFAscorridor 130 UEFAscorridor 231 UEFAsworkroom 132 UEFAsmeetingroom33UEFAsworkroom234UEFAsstorage35 UEFAsoffice 136 UEFAsoffice 237 UEFAsoffice 338 UEFAsoffice 439Technicalcompartment140 Medicalcentrescorridor41 Medicalcentre

    42Medicalcentre243Police44 Hall45 Cell146 Cell247 Cell348 Electricalquarter49 Tranformationpost50 Firemen51 Auditoriumcorridor52 Technicalcompartments

    corridor253Headofsecuritys

    corridor54 Staff/ballboyschanging

    room55 Storage/catering56Storage

    57Securityrestingroom58Securityroom59 Securitykitchen60Toilet161 Toilet262Toilet363Toilet464Toilet565Toilet666 Toilet767Toilet868Toilet969Toilet1070 Toilet1171 Emergencystairs72 Emergencystairs73 VIPsstaircase74 Journalistsstaircase75 Staircase176 Staircase277 Staircase578 Watertank access

    staircase

    01 R a m p2 S t a i r 13 S t a i r 24 S t a i r 35 S t a i r 46 S t a i r 57 S t a i r 68 S t a i r 79 Playersatrium

    10 Fieldaccess11 Distributioncorridor 112 Distributioncorridor 213 VIPatrium14 Journalistatrium15 UEFAroom16 Grassstorage17 Liftaccess18 Distributioncorridor19 Bar120 Bar221 Disabledtoilet22 Toilet123Disabledtoilet224Toilet225 Electricalquarteraccess26Electricalquarter127Toilet328Toilet429 Electricalquarteraccess30Electricalquarter231 Toilet532Disabledtoilet333 Toilet634Disabledtoilet435Toilet736Accesstofieldentrance137Fieldentrance138Accesstofieldentrance239Fieldentrance240Accesstofieldentrance341 Fieldentrance3

    42Accesstofieldentrance443Fieldentrance444 Acessto fieldentrance545Fieldentrance546UEFAmeetingroom47Fieldentrance648Accesstofieldentrance749Fieldentrance750Accesstofieldentrance851 Fieldentrance852Accesstofieldentrance9

    53Fieldentrance954Accesstofieldentrance1055Fieldentrance1056Accesstofieldentrance1157Fieldentrance1158Accesstofieldentrance1459Fieldentrance1460Accesstofieldentrance1561 Fieldentrance1562Accesstofieldentrance1663Fieldentrance1664Bathroom165 Technicalarea66Bathroom267Hall68 Workingfacilities69 Electricalquarter70 Workingfacilities71 Workingfacilities72 Stair8.273 Stair9.374 Stair9.475 Stair10.376 Stair10.477 Stair11.3(VIPs/UEFA)78 Technicalarea279 Stair12.3(press)80Stair13.481 Stair13.382Stair14.483Stair14.384Stair15.285Stair11.4VIP86Stair12.4press87Stair16.188 Stair17.1

    level -2 level 0

    level1

    Project name Estadio Municipal de BragaLocation Monte Crasto,Parque Norte,BragaProject January 2000Construction January 2002 December 2003Architecture Souto Moura Arquitectos,LDALandscaping Daniel MonteiroConsultants Arup Associates Dipesh Patel(Stadium Programme)Engineers AFAssociados Projectos de Engenharia,SAConsultants CG, Geotechnics;ARUP Associates,Wind study;RWDI, rigid model wind tests;Danish Maritim Institut,aeroelastic model wind tests),FEUP Construction Institute,Dynamics.Construction Ace Assoc/Soares da Costa,SAPhotographer Christian Richters

    -11Publicroute2 B a r 13 B a r 24 Toilet15 Toilet26 Toilet37 Toilet48 Toilet59 Toilet6

    10 Firstaid (waitingroom1)11 Reception1

    12 Firstaidtoilet13 Firstaid (waitingroom2)14 Reception215 Firstaidtoilet16 Atrium17 VIPcorridor18 Journalistscorridor19 VIPelevatorhall20Jounalistselevator hall21 Technicalarea22Electrical area23Braga S.C.receptiondesk24BragaS.C.room25Braga S.C.storageroom26TVstudio127TVstudio228 Deletatesroom29Storage30G amessecretaryroom31 Residentteamscorridor 132Male referecing33Resident teamscoach

    room34Resident teamsfeet

    bathing area35Resident teamsshoe

    store36Socialroom137Socialroom238Socialroom339 Visiting teamcorridor40Female referecing41 Playersmedicalcentre 142Visiting teamfeetbathing43Vistingteamshoestore44 Residentteamschanging

    roomaccess corridor245 Visiting teamcorridor246Accessatrium47 Hall48Playersmedicalcentre249Anti-dopingroom150Anti-dopingroom2

    51Laundry52Dryingarea53Resident teamswarm-up

    room54Resident teams

    gymnasium55Resident teamschanging

    roomaccess corridor356Patio157Resident teamschanging

    room 1

    58Resident teamsshowers159Resident teamsscottishshower

    60Resident teamswhirlpool61Resident team62ResidenttaemsWC163Resident teamsmassage

    room 164Resident teamsmassage

    room 265ResidentteamsWC266Resident teamsshowers267Resident teamschanging

    room 268Visiting teamswarm-up

    room69Visiting teamsgymnasium70Visiting teamschanging

    roomaccess corridor371 Patio272 Visitingteamschanging

    room 173 Visitingteamsshowers 174 Visitingteamsscottish

    shower75 Vistingteamswhirlpool76 Visitingteam77 VisitingteamsWC 178 Visitingteamsmassage

    room 179 Visitingteamsmassage

    room 280VisitingteamsWC281 Visitingteamsshowers 182Visiting teamschanging

    room 283Toilet184Toilet285Toilet386Toilet487Toilet588 Toilet689Toilet790Toilet8

    91Toilet992Players emergency

    staircase93 Players andstaff

    emergencystaircase94 VIPsstaircase95Press staircase96Public staircase97Public staircase98Public staircase99Public staircase

    100Public staircae101Public staircase102 Emergencyexit103 Emergencyexit

    11Ramp2Stair13Stair24Stair35Stair46Stair57Stair68Stair79Elevators access

    10 Distributioncorridor11 Cabin1

    12 Cabin213 Cabin314 Cabin415 Cabin516 Cabin617 Cabin718 Cabin819 Cabin920Cabin1021 Cabin1122Cabin1223Cabin1324Cabin1425Toilet male/female26Cam127Cabin1528Cabin1629Cabin1730Cabin1831 Cabin1932Cabin2033Cabin2134Cabin2235Cabin2336Cabin2437Cabin2538Cabin2639Cabin2740Cabin2841 Cabin2942VIPs Restaurant43 Restaurantskitchen44 Storage45Toilet146 VIPsatrium47 Distributioncorridor48VIPs elevatorsaccess49TechnicalArea250Press elevatorsaccess51 Technicalarea152Toilet253 TVStudio access corridor54TVStudio155TVStudio256TVStudio357TVstudio458Barkitchen59 Kitchen60Storage61 Stair9.262Stair10.263Stair11.2VIPs64Stair12.265Stair13.266Stair14.2TVstudios

    level-1

    0 10 20m