PERENCANAAN DAN PENGENDALIAN MANUFAKTUR
“CAMPUS WEDDING”
Oleh : Samuel Boron 2111 201 001Rifky Maulana Yusron 2112 201 001Saiful Arif 2112 201
005
PROGRAM MAGISTERBIDANG KEAHLIAN SISTEM MANUFAKTUR
JURUSAN TEKNIK MESININSTITUT TEKNOLOGI SEPULUH NOPEMBER
SURABAYA2013
Campus WeddingThe start node denotes the day 31st of March and the end node denote the wedding day i.e the 22nd April. (cherry blossoms)
Activity Time Extra Cost Crash Time
Reserve Church 1 Days Church Notice 17 Days $100 10 day Church Decoration 3 Days Prepare Maid of Honor (Jane) 10 Days $500
2 day Choose Cake & Table Decoration 2 Days Jack’s Catering Notice 10 Days Choose Wedding Dress Pattern 3 Days Receive Lace 8 Days $25 5 day Sewing Dress 11 Day $120/day 6 Day Final fitting of Dress 2 Days
Campus WeddingActivitty Time - Extra Cost - Crash Time
Clean & Press the Dress 2 Days $30 1 Day Choose Invitastion Style 3 Days Receive Invitation Card 12 Days $35 5 Days Addressing 4 Day $25/Day 2 Days Invitation to Post Office 1 Days Invitation Lead Time 10 Days Prepare Guest List 4 Days Gift - Bridesmaids 1 Days Rehearsal Dinner 1 Days
Aunt Ethel Gift -8 Days - $200
Network Diagram for the Wedding Plans
Path 1 : Reserve Church– Church Notice – Church Decoration – Rehearsal Dinner – Wedding : Length 21 days
Path 2 : Choose Cake & Table Decoration – Jack’s Catering Notice – Rehearsal Dinner – Wedding : Length 13 days
Path 3 : Prepare Maid Of Honor– Final Fitting of Dress – Clean & Press the Dress – Rehearsal Dinner – Wedding: Length 15 Days
Path 4 : Choose Wedding Dress Pattern – Receive lace – Sewing Dress – Final Fitting of Dress – Clean & Press the Dress – Rehearsal Dinner – Wedding: Length 27 Days
Path 5 : Choose Invitation Style – Receive Invitation Card – Addressing – Invitation to Post Office – Invitation Lead Time – Wedding: Length 30 Days
Identify the Paths. Which are Critical?
Path 6 : Prepare Guest List – Addressing – Invitation to Post Office – Invitation Lead Time – Wedding: Length 20 Days
Path 7 : Gift (BridesMaid) – Rehearsal Dinner – Wedding : Length 2 days
Critical Path: Path 4 : Length 28 days Path 5 : Length 31 days
Identify the Paths. Which are Critical?
Critical Path: Path 4 : Normal Length Time 27 days
Receive Lace ($25) 8 --> 5 days, Length 24 days Clean & Press the Dress ($30) 2 --> 1 day, Length 23
days Sewing Dress ($120/day), 11 --> 10 days, Length 22
days Path 5 : Normal Length Time 30 days
Receive Invitation Card ($35) 12 --> 5 days, Length 23 days
Addressing ($25/day) 4 --> 3 days,Length 22 days
Minimum Cost: Path 4 : $25 + $30 + $120 = $175 Path 5 : $35 + $25 = $60 Total Cost = $235
What is the minimum-cost plan that meet the april 22 date?
Terima Kasih . . .