PERENCANAAN DAN PENGENDALIAN MANUFAKTUR “CAMPUS WEDDING” Oleh : Samuel Boron 2111 201 001 Rifky Maulana Yusron 2112 201 001 Saiful Arif 2112 201 005 PROGRAM MAGISTER BIDANG KEAHLIAN SISTEM MANUFAKTUR JURUSAN TEKNIK MESIN INSTITUT TEKNOLOGI SEPULUH NOPEMBER SURABAYA 2013

Campus Wedding Projeck

Embed Size (px)

Citation preview

Page 1: Campus Wedding Projeck

PERENCANAAN DAN PENGENDALIAN MANUFAKTUR

“CAMPUS WEDDING”

Oleh : Samuel Boron 2111 201 001Rifky Maulana Yusron 2112 201 001Saiful Arif 2112 201

005

PROGRAM MAGISTERBIDANG KEAHLIAN SISTEM MANUFAKTUR

JURUSAN TEKNIK MESININSTITUT TEKNOLOGI SEPULUH NOPEMBER

SURABAYA2013

Page 2: Campus Wedding Projeck

Campus WeddingThe start node denotes the day 31st of March and the end node denote the wedding day i.e the 22nd April. (cherry blossoms)

Activity Time Extra Cost Crash Time

Reserve Church 1 Days Church Notice 17 Days $100 10 day Church Decoration 3 Days Prepare Maid of Honor (Jane) 10 Days $500

2 day Choose Cake & Table Decoration 2 Days Jack’s Catering Notice 10 Days Choose Wedding Dress Pattern 3 Days Receive Lace 8 Days $25 5 day Sewing Dress 11 Day $120/day 6 Day Final fitting of Dress 2 Days

Page 3: Campus Wedding Projeck

Campus WeddingActivitty Time - Extra Cost - Crash Time

Clean & Press the Dress 2 Days $30 1 Day Choose Invitastion Style 3 Days Receive Invitation Card 12 Days $35 5 Days Addressing 4 Day $25/Day 2 Days Invitation to Post Office 1 Days Invitation Lead Time 10 Days Prepare Guest List 4 Days Gift - Bridesmaids 1 Days Rehearsal Dinner 1 Days

Aunt Ethel Gift -8 Days - $200

Page 4: Campus Wedding Projeck

Network Diagram for the Wedding Plans

Page 5: Campus Wedding Projeck

Path 1 : Reserve Church– Church Notice – Church Decoration – Rehearsal Dinner – Wedding : Length 21 days

Path 2 : Choose Cake & Table Decoration – Jack’s Catering Notice – Rehearsal Dinner – Wedding : Length 13 days

Path 3 : Prepare Maid Of Honor– Final Fitting of Dress – Clean & Press the Dress – Rehearsal Dinner – Wedding: Length 15 Days

 Path 4 : Choose Wedding Dress Pattern – Receive lace – Sewing Dress – Final Fitting of Dress – Clean & Press the Dress – Rehearsal Dinner – Wedding: Length 27 Days

Path 5 : Choose Invitation Style – Receive Invitation Card – Addressing – Invitation to Post Office – Invitation Lead Time – Wedding: Length 30 Days

Identify the Paths. Which are Critical?

Page 6: Campus Wedding Projeck

Path 6 : Prepare Guest List – Addressing – Invitation to Post Office – Invitation Lead Time – Wedding: Length 20 Days

Path 7 : Gift (BridesMaid) – Rehearsal Dinner – Wedding : Length 2 days

Critical Path: Path 4 : Length 28 days Path 5 : Length 31 days

Identify the Paths. Which are Critical?

Page 7: Campus Wedding Projeck

Critical Path: Path 4 : Normal Length Time 27 days

Receive Lace ($25) 8 --> 5 days, Length 24 days Clean & Press the Dress ($30) 2 --> 1 day, Length 23

days Sewing Dress ($120/day), 11 --> 10 days, Length 22

days Path 5 : Normal Length Time 30 days

Receive Invitation Card ($35) 12 --> 5 days, Length 23 days

Addressing ($25/day) 4 --> 3 days,Length 22 days

Minimum Cost: Path 4 : $25 + $30 + $120 = $175 Path 5 : $35 + $25 = $60 Total Cost = $235

What is the minimum-cost plan that meet the april 22 date?

Page 8: Campus Wedding Projeck

Terima Kasih . . .