Upload
kay
View
23
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Capacity Release Processes and Investment Planning. Transmission Planning Code Workshop 2 1 st May 2008. Introduction. This presentation aims to outline the interaction between the following processes Long term Entry Capacity release Offtake Capacity Statement process - PowerPoint PPT Presentation
Citation preview
Capacity Release Processes and Investment Planning
Transmission Planning Code Workshop 2
1st May 2008
Introduction
This presentation aims to outline the interaction between the following processes
Long term Entry Capacity release Offtake Capacity Statement process Annual investment plan cycle
Long Term Entry Capacity Release
Entry Capacity Auctions
Entry capacity released through a series of auctions to facilitate
Long term signals - market mechanism to inform investment Short term rationing - efficient allocation of scarce resource
Long term entry capacity auctions currently held in September each year
Entry Capacity offered up to existing obligated levels 10% held back for shorter term Additional demand for entry capacity can be signalled by users –
price steps published for capacity levels up to 150% prevailing obligated levels
Default lead-time for any further incremental obligated capacity released is 42 months
Two incentive mechanisms in Licence to vary lead-time (permits and accelerated release)
UNC Entry Capacity Products
Type of capacity BundlesTimeframe
(Capacity Years)
Firm
Quarterly (QSEC) Y+2 to Y+16
Monthly (AMSEC) Y+1 and Y+2
Monthly (RMSEC) Month ahead
Daily (DSEC)Day ahead and
within day
Interruptible Daily (DISEC) Day ahead
Incremental entry capacity release process (1)
Shippers participate in long term entry capacity auctions NGG publishes price schedule, capacity offered, lead-times, project
values prior to the auctions Bids placed in accordance with UNC rules to signal demand for entry
capacity
Information from auctions analysed after auctions close Incremental Entry Capacity Release (IECR) Methodology applied Entry Capacity Substitution (ECS) Methodology applied (if required)
If auction signal received for incremental obligated entry capacity
Licence requires NGG to make an “incremental obligated entry capacity proposal” to the Authority
Proposal must comply with IECR and ECS methodologies
Incremental entry capacity release process (2)
Incremental obligated entry capacity proposal states (for relevant ASEPs)
Amounts of firm entry capacity proposed as incremental obligated entry capacity and dates for release
Proportion of this which is substituted from other ASEPs
If Authority direct proposal Obligation to offer additional capacity for sale commences from date
in proposal
NGG may release additional capacity (non-obligated entry capacity) at its discretion
Timeline for Investment Planning - Entry
May June July Aug Sept Oct Nov Dec
end Nov
Shippers notified of
entry capacity holdings
1 Oct
Lead-time starts
(default is 42 months)
Sept
QSEC Auctions
Oct
incremental proposal made to Authority
preparatory Entry analysis confirmation of annual Plan
Dec
investment proposals
published in TYS
Nov
Authority decision
May-June
initial TBE Base Case available
July
Lead-times notified in auction
invitation letter
June-Aug
indicative Investment Plan developed against Base Case supply and demand and other
Supply Scenarios
Long Term Exit Capacity Release
Long Term Exit Capacity Release
Shippers and DNOs currently use different processes to book exit capacity
Described in the Exit Capacity Release Methodology Statement for the Interim and Transitional Periods (ExCR)
All users must provide user commitment via an Advanced Reservation of Capacity Agreement (ARCA) for long term flat capacity bookings that
Require specific reinforcement to the NTS and Are greater than 20 million therms/annum
DNOs may signal changes to their Offtake (Flat) Capacity, Offtake (Flex) Capacity and Assured Offtake Pressure requirements through the annual Offtake Capacity Statement process
If specific reinforcement is not required, Shippers may only book exit capacity from 6 months prior to the gas flow day
Offtake Capacity Statement(UNC Section B)
Signals DNOs 1 in 20 peak day requirements for Offtake Capacity and Agreed Operating Pressures
Runs in parallel to TBE process Initiated 1 June each year DNOs must submit OCS requests by 24 July Preliminary allocations by NTS required by 15 September OCS agreed by 30 September for the approaching gas year (Y) to
year Y+3
DNOs may revise bookings in future years
Long term demand forecast data (UNC OAD section H)
Process for sharing NTS demand forecast information between Transporters
Includes DN off-peak forecast data Used to inform TBE demand forecasts Split of LDZ offtake flows used as input to network analysis for off-
peak analysis
Information is not used for off-peak capacity bookings
Timeline for Investment Planning - Exit
May June July Aug Sept Oct Nov Dec
June-end July
OCS requests and
DN offtake forecasts
end July-Sept
Analysis of requests, preliminary allocations and discussions with
DNOs 30 Sept
DNOs notified of Offtake Capacity
holdings and AOPs
Exit analysis confirmation of annual Plan
May-June
initial TBE Base Case available
Dec
investment proposals
published in TYS
Timeline for Investment Planning – Entry and Exit process alignment
Exit and entry plan analysis undertaken in parallel
OCS bookings must be confirmed to DNOs ahead of decision on incremental entry capacity release
Any additional exit capability arising from entry investment will be considered in future years’ planning cycles
end Nov
Shippers notified of
entry capacity holdings
confirmation of annual Plan
end Sept
DNOs notified of Offtake Capacity
holdings and AOPs
Oct Nov Dec
Nov
Authority decision
Oct
incremental proposal made to Authority
Dec
investment proposals
published in TYS
Questions