Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden Dr. to Simmons  Loop Project Numbers: 69647000 – PLAT ( US 41 to US 301), 69656000 – PD&E 

 

Quick Facts • Location: Gibsonton/Riverview • Length: 1.25 miles, from Covington Garden 

Dr. to Simmons Loop 

• Category: Planning 

 Schedule • Project Development & Environmental Study 

complete late 2019 (FDOT & County) 

• Preliminary Design and Land Acquisition begins Early 2019 (County –transfer to FDOT) 

• Design‐Build Procurement begins Early 2020 

(FDOT) 

• Construction start begins late 2021 • Design‐Build Construction complete Late 2024 

(FDOT) 

 Overview • Widen Big Bend Road from a 4‐lane divided road, from Covington Garden Drive to Simmons Loop to 6‐lanes including enhanced pedestrian, bicycle and bus facilities. 

• Improvements to I‐75 interchange to be designed and constructed by Florida Department of Transportation (FDOT) 

• Reconstruction of bridge on Old Big Bend Road. 

• Reconstruction of bridge on Big Bend Road • Signal improvements at Covington Gardens and Simmons Loop. 

• Enhance pedestrian safety features, including wide sidewalks and enhanced crosswalks and signals. 

• Improve stormwater drainage. 

Benefits• Better accommodate growth and traffic 

volume 

• Increase the overall mobility along Big Bend and I‐75, while maximizing safety along the corridor 

 Project Funding • Total: $62.55  FDOT: $8 million 

Federal: $1.5 million 

County: $53.05 million 

  Hillsborough County has applied for a Build Grant in the amount of $25 million.            

 

Hillsborough County is also pursuing additional funding from FDOT to offset local County funds 

 

     October 2018 Note: The information on this fact sheet is subject to periodic updates. 

Questions? Manny Santos, E. I. 

Public Works Project Manager (813) 635‐5400 

  

Page 2: Capital Improvement Program Projectmediaassets.abcactionnews.com/document/2018/Big Bend Fact...Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden

 

Capital Improvement Program Project Fact Sheet Big Bend Road Widening – US 41 to Covington Gardens Drive and                                                       Simmons Loop to US Hwy 301 Project Number: 69647000 – PD&E & Design (US 41 to Covington Gardens) Project Number: 691149000 – PD&E (Simmons Loop to US Hwy 301) 

 

 Quick Facts • Location: Gibsonton/Riverview • Length: 1.75 mile, from US 41 to Covington 

Gardens Drive and Simmons Loop to US 301 

• Category: Planning 

 Schedule • Project Development & Environmental Study 

Begins mid 2019 

• Preliminary Design and Land Acquisition begins Early 2021 

• Construction begins Late 2023 

 Overview • Widen Big Bend Road from a 4‐lane divided road, from US 41 to Covington Garden Drive to 6‐lanes including enhanced pedestrian, bicycle and bus facilities. 

• Enhance pedestrian safety features, including wide sidewalks and enhanced crosswalks and signals. 

• Improve stormwater drainage. 

Benefits • Better accommodate growth and traffic 

volume 

• Increase the overall mobility along Big Bend, while maximizing safety along the corridor 

 Project Funding  Total: $ 20.3 million 

 

Cost Estimate • Total: $20.3 million 

PD&E: $1.5 million 

Land Acquisition: $4.0 million 

Design:  $2.5 million 

Construction: $12.3 million  

 

                October 2018 Note: The information on this fact sheet is subject to periodic updates. 

 

 

 

 

Questions? Manny Santos, E. I. 

Public Works Project Manager (813) 635‐5400 

 

Page 3: Capital Improvement Program Projectmediaassets.abcactionnews.com/document/2018/Big Bend Fact...Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden
Page 4: Capital Improvement Program Projectmediaassets.abcactionnews.com/document/2018/Big Bend Fact...Capital Improvement Program Project Fact Sheet Big Bend Road Widening – Covington Garden

BIG BEND ROAD 

PROJECT SCHEDULE  

 


Recommended