CAPITAL PROJECT UPDATE
Rye City School DistrictDr. Eric Byrne
Gabriella O’ConnorKaitlyn Sassone
November 12, 2019
TIMELINE
Bond Passage2019 Phases
1 & 1A2020 Phase 22021 Phase 32022/2023Anticipated Completion
of Construction
2024
Design Process• Architectural
Schematic Design• Design Team
Consultations• Final Design
Specifications
NYSED• Submission to
Engineering Department
• Response from NYSED – Changes -Resubmit
• Approval from NYSED
Bid Process• Construction
Drawings• Request for Proposals• Bid Opening• Award Bid
CONSTRUCTION
CAPITAL PROJECT PROCESS
CAPITAL PROJECT - PHASES AND PROCESS STATUS
Bond Passage2020
Phase 1 & Phase1A
Design Process
NYSED
Bid Process
Construction
2021 Phase 2
Design Process
NYSED
Bid Process
Construction
2022/2023 Phase 3
Design Process
NYSED
Bid Process
Construction
2024-Anticipated Completion
Phase 1A
High School & Middle School• Performing Arts Center A/C• Plumbing• Bathroom Renovations (for
ADA Accessibility)• Electrical Systems• Site Systems: Drainage,
Blacktop, Paving
Osborn School• Auditorium Renovation
including A/C• Gymnasium A/C• Plumbing• Bathroom Renovations (for
ADA Accessibility)
Midland School• Auditorium Renovation
including A/C• Bathroom Renovations (for
ADA Accessibility• Electrical Systems
PHASE 1 & 1A PROJECTS: 2020
Phase 1
High School & Middle School• Athletic Field Turf and Track
Replacement and Tarp• Middle School Gymnasium Lighting
Anticipated Launch Date: Summer 2020 Anticipated Launch Date: Summer 2020
Phase 2High School & Middle School• Secure Vestibule Entrances• Library Expansion – Enclosing Existing
Interior Courtyard• HS 3rd Floor Renovations for Code
Compliance• New HS/MS Elevator (ADA Accessibility)
Midland School• Secure Vestibule Entrance• Library Renovation• Gymnasium A/C• Athletic Field Drainage• Continued Bathroom Renovations• Site Systems: Drainage, Blacktop,
Paving• Exterior Envelope: Windows,
Doors, Building Façade
Milton School• Secure Vestibule Entrance• Library Renovation• Special Education Service Center• Electrical System• Exterior Envelope: Building Façade• Heating & Fresh Air Ventilation
Osborn School• Secure Vestibule Entrance• Library Renovation• Exterior Envelope: Windows,
Doors, Building Façade
PHASE 2 PROJECTS: 2021
Anticipated Launch Date: Summer 2021
NUGENT FIELD HISTORY• Nugent Stadium is one of the most heavily used
fields in Rye - District athletic teams and community athletic teams
• Original turf field installed early 2000s (Donation to the District)
• Replaced twice (2004 & 2006) since installation, at no cost to the District, both results of storm damage
• Damage from past flooding was due to the force of the water and debris
• FEMA has studied the field and brook numerous times, and there are no plans to mitigate flooding
• FEMA and multiple other state and local agencies would have to approve raising the turf. Estimated time to get approval: 5-10 years
• District engineers have evaluated and designed an improved drainage system and specified infill that is more effective and longer lasting in flood-prone areas
• Custom tarp system will be designed to prevent damage
• Turf and associated materials to be installed meet the highest level of regulations in the U.S.
• Studies show concussions are far less common on turf fields
• Construction will begin June 1, 2020; weather permitting it will take approximately three months
• RMS & RHS PE classes will take place on the back field and the three gymnasiums during construction as needed