14
Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017

Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

Oak Chan Elementary School

Modernization ProjectSCHOOL PRESENTATION

MARCH 30, 2017

Page 2: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

OVERALL SITE PLAN

Page 3: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

PROJECT OVERVIEWPhase 1 – Milestone #1 (April 17 – July 31, 2017):

Grading, Placement of all temporary portable classroom, restroom, administration and student care buildings,

including all utilities

Multipurpose (Building B) modernization

Phase 1 – Milestone #2 (June – December 2017):

Administration (Building A) modernization

Phase 1 – Milestone #3 (June 2017 – July 2018):

Construction of Buildings C-10-plex Classroom, D – Learning/Media Center, E – 8-plex Classroom and F - Kindergarten

Phase 2 – Milestone #1 (June 2018 – July 2018):

Hardcourt, apparatus yard, parking lot

Phase 2 – Milestone #2 (July 2018 – September 2018)

Removal of temporary trailers, playfield restoration

Page 4: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

Phase and Milestone Schedule

Page 5: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

SITE PLAN – April and May, 2017 & July – September 2018 –

The entire playfield

Page 6: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

SITE PLAN – Summer 2017

Page 7: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

SITE PLAN – School Year 2017 - 2018

Page 8: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

SITE PLAN – Summer 2018

Page 9: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

Temporary Classroom & Restroom

Buildings

Page 10: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

Administration Building

Page 11: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

Kindergarten

Page 12: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

Unit D - Learning/Media Center Building

Page 13: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

Exterior

Page 14: Carl Sundahl Elementary School Modernization Project...Oak Chan Elementary School Modernization Project SCHOOL PRESENTATION MARCH 30, 2017. OVERALL SITE PLAN. PROJECT OVERVIEW Phase

QUESTIONS & ANSWERS