Oak Chan Elementary School
Modernization ProjectSCHOOL PRESENTATION
MARCH 30, 2017
OVERALL SITE PLAN
PROJECT OVERVIEWPhase 1 – Milestone #1 (April 17 – July 31, 2017):
Grading, Placement of all temporary portable classroom, restroom, administration and student care buildings,
including all utilities
Multipurpose (Building B) modernization
Phase 1 – Milestone #2 (June – December 2017):
Administration (Building A) modernization
Phase 1 – Milestone #3 (June 2017 – July 2018):
Construction of Buildings C-10-plex Classroom, D – Learning/Media Center, E – 8-plex Classroom and F - Kindergarten
Phase 2 – Milestone #1 (June 2018 – July 2018):
Hardcourt, apparatus yard, parking lot
Phase 2 – Milestone #2 (July 2018 – September 2018)
Removal of temporary trailers, playfield restoration
Phase and Milestone Schedule
SITE PLAN – April and May, 2017 & July – September 2018 –
The entire playfield
SITE PLAN – Summer 2017
SITE PLAN – School Year 2017 - 2018
SITE PLAN – Summer 2018
Temporary Classroom & Restroom
Buildings
Administration Building
Kindergarten
Unit D - Learning/Media Center Building
Exterior
QUESTIONS & ANSWERS