1
Head Office, UK & Export Sales Compass Works, 410 Brightside Lane, Sheffield S9 2SP Tel: +44 (0) 114 2611126 Fax: +44 (0) 114 2611165 Email: [email protected] Website: www.ekspan.com CASE STUDY Background Information The A473 Bridgend inner bypass bridge spans the River Ogmore, in Bridgend, South Wales. The ageing structure, with nearly 50 years wear and tear carrying high volumes of traffic, had developed some significant problems which had been identified by Bridgend Council as requiring major repair and maintenance work. Repairs to the bridge’s parapets, concrete supports and bearings were essential to ensure the structure remained durable and safe for continued use. The steel bearings supporting the bridge deck were excessively corroded to the extent that some had ‘seized’, and were consequently deemed as being inadequate to accommodate the expansion and rotational forces which they were originally designed for. To alleviate this increased stress transferred into the bridge deck and supports, these bearings had to be replaced. Ekspan’s Workscope Ekspan were contracted by Dyer & Butler to replace the existing 65 no Glacier steel rocker bearings with Ekspan BS5400 mechanical pot bearings on the West abutment, at the East and West piers of Bridgend inner bypass bridge. Due to the complexity of the structure’s design and the existing bearing dimensions, the new installed bearings were designed and manufactured as bespoke pot bearings. Works on this project included marking-up and prepping site for installation of temporary works / bridge propping; hydro demolition of bearing / bridge beams, piers and abutment; bearing removal; construction and installation of steelwork beams as plate/stool arrangements for the new pot bearings to be fixed to; bearing installation; concrete repairs works for encapsulation of steelworks and bearing top plates and base plate sockets; concrete repair to piers and abutments and final grouting of the new installed bearings. The A473 dual carriageway remained open with lane restrictions whilst Ekspan worked to a very tight programme schedule - this together with the extreme complexity of the installation made precise and logistical planning crucial to ensure all site work operations were timely met. A473 BRIDGEND INNER BYPASS BRIDGE, SOUTH WALES - BEARING REMOVAL & INSTALLATION Job Brief Supplied: Removal of 65 no rocker bearings. Design, manufacture, supply and installation of 65 no mechanical pot bearings. Project Team Client: Bridgend County Borough Council Main Contractor: Dyer & Butler Sub-Contractor: Ekspan Start Date: March 2015 Completion Date: June 2015 Old rocker bearing corroded and no longer functional Super props and jacks temporarily supporting the bridge deck New installed mechanical pot bearing fixed to the bridge beam and bearing shelf

CASE STUDY - media.brintex.commedia.brintex.com/Occurrence/201/Brochure/5727/brochure.pdf · CASE STUDY Background Information The A473 Bridgend inner bypass bridge spans the River

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CASE STUDY - media.brintex.commedia.brintex.com/Occurrence/201/Brochure/5727/brochure.pdf · CASE STUDY Background Information The A473 Bridgend inner bypass bridge spans the River

Head Office, UK & Export SalesCompass Works, 410 Brightside Lane, Sheffield S9 2SP

Tel: +44 (0) 114 2611126 • Fax: +44 (0) 114 2611165 • Email: [email protected]: www.ekspan.com

CASE STUDY

Background Information

The A473 Bridgend inner bypass bridge spans the River Ogmore, in Bridgend, South Wales. The ageing structure, with nearly 50 years wear and tear carrying high volumes of traffic, had developed some significant problems which had been identified by Bridgend Council as requiring major repair and maintenance work. Repairs to the bridge’s parapets, concrete supports and bearings were essential to ensure the structure remained durable and safe for continued use.

The steel bearings supporting the bridge deck were excessively corroded to the extent that some had ‘seized’, and were consequently deemed as being inadequate to accommodate the expansion and rotational forces which they were originally designed for. To alleviate this increased stress transferred into the bridge deck and supports, these bearings had to be replaced.

Ekspan’s Workscope

Ekspan were contracted by Dyer & Butler to replace the existing 65 no Glacier steel rocker bearings with Ekspan BS5400 mechanical pot bearings on the West abutment, at the East and West piers of Bridgend inner bypass bridge. Due to the complexity of the structure’s design and the existing bearing dimensions, the new installed bearings were designed and manufactured as bespoke pot bearings.

Works on this project included marking-up and prepping site for installation of temporary works / bridge propping; hydro demolition of bearing / bridge beams, piers and abutment; bearing removal; construction and installation of steelwork beams as plate/stool arrangements for the new pot bearings to be fixed to; bearing installation; concrete repairs works for encapsulation of steelworks and bearing top plates and base plate sockets; concrete repair to piers and abutments and final grouting of the new installed bearings.

The A473 dual carriageway remained open with lane restrictions whilst Ekspan worked to a very tight programme schedule - this together with the extreme complexity of the installation made precise and logistical planning crucial to ensure all site work operations were timely met.

A473 BRIDGEND INNER BYPASS BRIDGE,SOUTH WALES - BEARING REMOVAL& INSTALLATION

Job BriefSupplied: Removal of 65 no rocker bearings. Design, manufacture, supply and installation of 65 no mechanical pot bearings.

Project TeamClient: Bridgend County Borough CouncilMain Contractor: Dyer & ButlerSub-Contractor: EkspanStart Date: March 2015Completion Date: June 2015

Old rocker bearing corroded and no longer functional

Super props and jacks temporarily supporting the bridge deck

New installed mechanical pot bearing fixed to the bridge beam and bearing shelf