34
Casey Arborway Project First Construction Meeting January 21 st , 2015 Boston English High School 144 McBride Street, Jamaica Plain

Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

  • Upload
    vothuan

  • View
    227

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Casey Arborway Project

First Construction Meeting January 21st, 2015

Boston English High School 144 McBride Street, Jamaica Plain

Page 2: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Agenda • Welcome • Team Introductions • Project Status • Preview of Completed Project • The first 90 days of work • Elements We Monitor • Public Involvement Tools • Q&A

Page 3: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Partnership Continues

• City of Boston • BTD • BRA

• Department of Conservation & Recreation (DCR)

• MassDOT • Highway Division • MBTA

Page 4: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Construction Management: • MassDOT District 6

• General Contractor Barletta Heavy Division • Project Superintendent Tom Russo

• Dagle Electrical Construction – electrical work • DePaoli Mosaic Company – tile work • EDM Construction – metal work • Howard/Stein-Hudson – public involvement • J.A.J Co. Inc. – masonry • Construction phase design services for MassDOT:

• AECOM – transit • HNTB – roadway and bridge

Project Team

Page 5: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• MassDOT Board Awarded Project – 10/22/14 • Notice to Proceed (NTP) has been issued • Preliminary work in progress:

• Construction signage • Tree protection • Barrier placement

• Next Steps: • Complete field office set-up (500 Arborway) • Temporary roadway east and westbound along Arborway • Achieve anticipated date of Milestone 3 (Casey closed) end of

March • Stage 1 construction

Project Status

Page 6: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Project Area

Page 7: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Reconnect & Simplify Roadways

Page 8: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Roadway and Transit Highlights

Page 9: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

New Transit Connections

Page 10: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

New Entrance/Exit Head-House

Page 11: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Washington Street West of Station

Page 12: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Shea Circle Squared

Page 13: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

A New Bicycle Network

Page 14: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

A New Pedestrian Network

Page 15: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Reconnecting Neighbors – Walking & Cycling

Page 16: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Reconnecting N. Washington & SWC

Page 17: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Reconnecting the Emerald Necklace

Page 18: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Leading the Nation in Transportation Excellence

18

Reconnecting Parks: New & Upgraded Open Space

Page 19: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• From NTP to Milestone 3 • Initial demolition of bridge begins during first 90 days

• Anticipated closure of westbound overpass in February, 2015 • Casey Overpass anticipated to close fully by the end of March, 2015

• Major Steps Along the Way: • Place erosion control measures in advance of major work • Place tree protection • Clear site • Remove trees in temporary roadway areas • Construct eastbound & westbound temporary surface roadways • Implement temporary pedestrian routes • Build temporary Route 39 bus berth • Implement temporary parking conditions • Stripe and sign temporary roadways for Construction

The First 90 Days - Overview

Page 20: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

The First 90 Days - Schedule of Activities

Page 21: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Standard work day: • 7:00AM – 7:30PM on weekdays • 7:00AM – 3:30PM on Saturdays

• No night work scheduled at present • When night work is needed, 2-week

advance notice will be provided by MassDOT

The First 90 Days – Working Conditions

Page 22: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

East & West Roadway Traffic Modifications I - Diagram

Page 23: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Place erosion control measures • Place temporary walkway and ramps

adjacent to New Washington Street and at South Street/New Washington Street.

• Place temporary barrier for pedestrian access along Arborway frontage road

• Construct temporary WB Arborway • Construct temporary Route 39 busway • Construct temporary upper busway • Stripe and sign temporary roadways

East & West Roadway Traffic Modifications I – Key Work Elements

Page 24: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

East & West Roadway Traffic Modifications II - Diagram

Page 25: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Partial demolition of WB western bridge approach roadway and first span

• Construct temporary courthouse parking • Construct temporary eastbound

Arborway • Demolition of existing MBTA upper

busway and canopy

East & West Roadway Traffic Modifications II -Key Work Elements

Page 26: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Contract sets construction noise levels for: • Day 7AM-6PM • Evening 6PM-10PM • Night 10PM-7AM

• Contractor develops a construction noise control plan adhering to day, evening, and night noise levels. • If noise levels exceed limits, contractor must

implement mitigation measures • MassDOT oversees construction to ensure

noise plan compliance

Construction Noise Control

Page 27: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Dust: • Contractor develops a construction dust

control plan for the life of the project • Air Quality:

• Retrofit of older diesel equipment with oxidation catalysts or diesel particulate filters

• 5 minute idling limit on all equipment

Construction Dust Control & Air Quality

Page 28: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Removal of Materials • Will be in accordance with all State and Federal

regulations • Trucks will operate over main roads in compliance

with City and State regulations

• Employee Parking • Employee parking offered at 500 Arborway • Contractor vehicles will be present in work zones

Materials and Employee Parking

Page 29: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Snow & Ice Removal • Within project limits of work – by the contractor • Outside project limits of work

• Boston DPW • DCR • MassDOT • MBTA

Winter Weather

Page 30: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• To be maintained throughout construction • Operations coordinated with MBTA to maintain

service • 8 possible weekend diversions of Orange Line

service in 2015 allowed by contract • 56 possible early shut-downs (9PM-4AM Thursday –

Sunday) in 2015 allowed by contract • All diversions of Orange Line service will be noticed

by the project and MBTA

• First 90 days: • Route 39 to temporary bus-way

Operations at Forest Hills Station

Page 31: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

School Bus Operations • As of January 21st:

• BPS buses shifted to Hyde Park Avenue adjacent to lower bus-way with new signage implemented in coordination with Boston Public Schools

• As of January 23rd: • METCO buses shifted to surface roadway adjacent to West

Roxbury courthouse • No additional shifts required within first 90 days • Future shifts will be coordinated between BPS, METCO,

and MassDOT • Notifications will be distributed to parents via BPS or

METCO depending on the service used • Additional participation by transit police to ensure safety

Page 32: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Baseline analysis already performed • Last year with school in session • Forest Hills neighborhood • Walk Hill/Bourne neighborhood • Stonybrook neighborhood • Arborway hillside & carriage road • Asticou/Martinwood/South Street

neighborhood

Cut-through Traffic

Page 33: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

• Dedicated staff with DOT and contractor • Regular updates via:

• Public meetings • Next meeting early March 2015 (then every other month)

• Continued maintenance of project website • 3-week look ahead emails • Quarterly newsletter

• Alerts for major traffic changes via: • Public meetings • Project website • Email bursts • Local and city-wide media

Outreach during construction

Page 34: Casey Arborway Project - Welcome to · PDF fileCasey Arborway Project First Construction Meeting January 21 st, ... (DCR) • MassDOT ... • Retrofit of older diesel equipment with

Question & Answer To learn more about the project, ask a question or express a concern, please

contact:

John Romano, Legislative Affairs (857) 368-8905 James Kersten, Legislative Affairs (857) 368-9041

[email protected]

Project Hot-Line: (617) 571-7878

To sign-up for the stakeholder database, please contact:

James Kersten, Legislative Affairs (857) 368-9041 [email protected]

Project website:

www.massdot.state.ma.us/caseyarborway