93
Stormwater and Flood Control System Assessment and Utility Plan Northampton, Massachusetts Department of Public Works Volume I Final Report May 2012

CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Embed Size (px)

Citation preview

Page 1: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Stormwater and Flood Control System Assessment and Utility Plan

Northampton, Massachusetts Department of Public Works

Volume I Final Report

May 2012

Page 2: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1
Page 3: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1
Page 4: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

51147‐71479‐03‐11 

Table of Contents

Executive Summary 

Section 1 ‐ Introduction 1.1  Introduction ................................................................................................... 1‐1 

1.2  Federal Stormwater Management Regulations – Historical Overview ............. 1‐5 

1.3  Federal Stormwater Management Regulations – Pending Changes  ................ 1‐5 

1.4  Flood Control – Regulatory Mandates ............................................................ 1‐7 

1.5  Infrastructure Funding ................................................................................... 1‐8 

1.6  Project Summary ........................................................................................... 1‐8 

1.7  Scope of Work ............................................................................................... 1‐9 

Section 2 ‐ Existing Conditions and Alternatives Analyses 2.1  Introduction ................................................................................................... 2‐1 

2.2  Stormwater Drainage and Flood Control System Overview ............................. 2‐1 

2.2.1  Field Inspection Approach .................................................................. 2‐4 

2.2.2  Drainage Analysis Approach ............................................................... 2‐4 

2.3  Flooding Problems ......................................................................................... 2‐5 

2.3.1  Bridge Street/Meadows Area ............................................................. 2‐5 

2.3.1.1  Site Inspection and Area Description ..................................... 2‐5 

2.3.1.2  Existing Conditions Hydraulic Model ..................................... 2‐8 

2.3.1.3  Preliminary Review of Alternatives ....................................... 2‐8 

2.3.2  Elm Street Brook/Florence Area ......................................................... 2‐9 

2.3.2.1  Site Inspection and Area Description ..................................... 2‐9 

2.3.2.2  Existing Conditions Hydraulic Model ................................... 2‐11 

2.3.2.3  Preliminary Review of Alternatives ..................................... 2‐12 

2.3.3  King Street/Market Street/Downtown Area ..................................... 2‐13 

2.3.3.1  Site Inspection and Area Description ................................... 2‐13 

2.3.3.2  Existing Conditions Hydraulic Model ................................... 2‐14 

2.3.3.3  Preliminary Review of Alternatives ..................................... 2‐14 

2.3.4  Austin Circle/Ryan Road Area ........................................................... 2‐16 

2.3.4.1  Site Inspection and Area Description ................................... 2‐16 

2.3.4.2  Existing Conditions Hydraulic Model ................................... 2‐16 

2.3.4.3  Preliminary Review of Alternatives ..................................... 2‐19 

2.4  Flood Control Systems .................................................................................. 2‐20 

2.4.1  East Levee Description ...................................................................... 2‐20 

2.4.2  West Levee Description .................................................................... 2‐20 

2.4.3  East and West Levee Inspection ........................................................ 2‐21 

2.4.4  East/West Levee Recommended Improvements ............................... 2‐22 

Page 5: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

ii 51147‐71479‐03‐11 

2.4.5  Northampton Flood Control Pumping Station – Hockanum Road – 

Inspection ........................................................................................ 2‐24 

2.4.5.1  Recommended Improvements ............................................ 2‐25 

2.4.6  West Street Stormwater Pumping Station ‐ Inspection ...................... 2‐26 

2.4.6.1  Recommended Improvements ............................................ 2‐27 

2.5  River Erosion ................................................................................................ 2‐27 

2.5.1  River Road – Mill River ..................................................................... 2‐27 

2.5.2  Federal Street Flood Wall ................................................................. 2‐28 

2.5.3  Roberts Meadow Brook Channel ...................................................... 2‐28 

2.6  Current Operational Cost and Funding Levels ............................................... 2‐28 

2.6.1  Regulatory Compliance ..................................................................... 2‐28 

2.6.2  Stormwater Drainage Operations Staffing ........................................ 2‐28 

2.6.3  Flood Control Operations Staffing ..................................................... 2‐29 

Section 3 ‐ Capital Improvements Plan and Operational Budget Requirements 3.1  Introduction ................................................................................................... 3‐1 

3.2  Summary of Recommended Plan .................................................................... 3‐1 

3.2.1  Street Improvement Projects .............................................................. 3‐1 

3.2.2  Municipal Green Infrastructure/Building Project Retrofit/Capital 

Allowance .......................................................................................... 3‐5 

3.2.3  Bridge Street/Meadows Area ............................................................. 3‐5 

3.2.4  Elm Street Brook/Florence Area ......................................................... 3‐6 

3.2.5  King Street/Market Street Area .......................................................... 3‐6 

3.2.6  Austin Circle/Ryan Road Area ............................................................. 3‐7 

3.2.7  Flood Control/Pumping Station Improvements ................................... 3‐7 

3.2.8  Levee Improvements .......................................................................... 3‐7 

3.2.9  River Erosion Improvements ............................................................... 3‐7 

3.3  Future Operational Cost Projections ............................................................... 3‐8 

3.4  Estimated Costs and Preliminary Schedule ..................................................... 3‐8 

3.5  Project Prioritization .................................................................................... 3‐15 

Section 4 ‐ Environmental Permitting 4.1  Introduction ................................................................................................... 4‐1 

4.2  Description of Applicable Permits ................................................................... 4‐2 

4.2.1  Federal Permits/Approvals ................................................................. 4‐2 

4.2.1.1  Clean Water Act, Section 404 ................................................ 4‐2 

4.2.1.2  Federal Endangered Species Act of 1973 ................................ 4‐3 

4.2.1.3  National Pollutant Discharge Elimination System (NPDES) – 

Construction General Permit ................................................. 4‐3 

4.2.2  State Permits/Approvals .................................................................... 4‐3 

4.2.2.1  Certificate from the Executive Office of Environmental Affairs 

(MEPA Approval) .................................................................. 4‐3 

4.2.2.2  Massachusetts Wetlands Protection Act (M.G.L. c131, s.40; 310 

CMR 10.00) ........................................................................... 4‐4 

4.2.2.3  Massachusetts Rivers Potection Act (Ch. 258 of the Acts of 

1996; 310 CMR 10.58) ........................................................... 4‐4 

Page 6: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

iii 51147‐71479‐03‐11 

4.2.2.4  401 Water Quality Certification Program (314 CMR 9.00) ...... 4‐4 

4.2.2.5  Massachusetts Endangered Species Act (M.G.L. c.131A; 321 

CMR 10.00) ........................................................................... 4‐5 

4.2.2.6  Waterways Licensing Program (M.G.L. Chapter 91; 310 CMR 

9.00) ..................................................................................... 4‐5 

4.2.2.7  Environmental Results Program (310 CMR 7.26 [42:43]) ........ 4‐5 

4.2.3  Local Permits/Approvals ..................................................................... 4‐5 

5.2.3.1  Wetlands Protection Act and City Ordinance ......................... 4‐5 

4.3  Conclusion ..................................................................................................... 4‐6 

Section 5 – Stormwater and Flood Control Utility 5.1  Introduction ................................................................................................... 5‐1 

5.1.1   Objectives ......................................................................................... 5‐1 

5.1.2  Stormwater Utilities in Other Communities ........................................ 5‐1 

5.1.3  Methodology ..................................................................................... 5‐4 

5.1.4  Key Findings ....................................................................................... 5‐4 

5.2  Stormwater and Flood Control Utility Implementation Considerations ........... 5‐5 

5.2.1  Stormwater and Flood Control Utility Background .............................. 5‐5 

5.2.2  Structural Considerations ................................................................... 5‐6 

5.2.3  Public Education and Involvement ...................................................... 5‐7 

5.2.4  Management and Budgeting .............................................................. 5‐7 

5.2.4.1  Budgeting ............................................................................. 5‐8 

5.2.4.2  Billing ................................................................................... 5‐8 

5.2.5  Funding Options ................................................................................. 5‐8 

5.2.6  Stormwater Credits .......................................................................... 5‐10 

5.3  Project Revenue Requirement ...................................................................... 5‐11 

5.3.1  General Assumptions ....................................................................... 5‐11 

5.3.2  Operations and Maintenance Expenses ............................................ 5‐12 

5.3.2.1  Incremental O&M ............................................................... 5‐12 

5.3.2.2  Allocated O&M ................................................................... 5‐13 

5.3.3  Debt Service Expenses ...................................................................... 5‐13 

5.3.4  Revenue Requirement ...................................................................... 5‐14 

5.4  Parcel Analysis and Equivalent Residential Unit Calculation .......................... 5‐15 

5.4.1  Impervious Area ............................................................................... 5‐15 

5.4.2  Equivalent Residential Unit Calculation............................................. 5‐17 

5.4.3  Estimated Total Billing Units ............................................................. 5‐18 

5.5  Calculation of Stormwater and Flood Control Fee ......................................... 5‐18 

5.6  Recommendations ....................................................................................... 5‐20 

 

Appendices 

Appendix A – Field Inspection Memoranda and Photographs 

Appendix B – Drainage Analysis 

Appendix C – Pipe Capacity Analysis 

Appendix D – Detailed Debt Service Schedule 

Page 7: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

ES‐1 

106678‐80349‐03‐11 

Executive Summary

Drainage and flood control systems, while often taken for granted, are critical to the economic 

wellbeing of any community, as these systems are vital to the protection of property and the safety 

of individuals that reside within the community.  In recent years, the deteriorating condition of 

drainage and flood control infrastructure across the country has been well documented and, in 

combination with extreme weather events, has resulted in several dramatic flooding events that have 

created enormous economic disruption and damage to personal and public property.   

Like Northampton, many communities across the country have aging infrastructure that is in urgent 

need of refurbishment or replacement, followed by periodic maintenance.  In many instances, 

infrastructure constructed decades ago has now exceeded its useful life and/or is now operating 

beyond its intended capacity due to the impact of continued development and increased impervious 

area within urban areas and upstream watersheds.  Additionally, new regulatory mandates place 

further burden on communities to monitor and control both the quantity and quality of stormwater 

discharged to ponds, streams and rivers, resulting in new capital and ongoing maintenance 

requirements. 

While the challenges are daunting, many communities are taking steps to address these challenges in 

a thoughtful, systematic manner.  Fundamental to this effort is the need to evaluate existing drainage 

and flood control systems, identify weaknesses and deficiencies in these systems, and develop a 

technically sound, cost‐effective plan to address these deficiencies. However, in the past, such plans 

often lacked a sustainable source of funds to finance the implementation of needed improvements.   

Accordingly, progressive communities such as Northampton are considering a critical new component 

to their stormwater management plan – the implementation of a new stormwater fee that is fair and 

equitable, and provides a reliable, dedicated source of revenue to fund needed improvements to 

drainage and flood control systems.  This new fee would be administered by a newly formed 

Stormwater and Flood Control Utility and, as with other utilities, the stormwater fee would be based 

directly on the cost of service provided.  The process undertaken by Northampton to evaluate such a 

fee and the results of the evaluation are described in this Stormwater and Flood Control System 

Assessment and Utility Plan.  

Existing Infrastructure Condition 

The City of Northampton owns and is responsible for the operation and maintenance of 

approximately 3,750 catch basins and inlets and approximately 108 miles of drainage that lead to 

more than 280 outfalls.  A large percentage of these drain lines are over 100 years old and require 

replacement because of their deteriorated condition, the need for additional stormwater conveyance 

capacity, or both.   

 

Page 8: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Executive Summary  

ES‐2 

106678‐80349003‐11 

Additionally, the City owns and is responsible for the operation and maintenance of a flood control system that 

was constructed by the Army Corp of Engineers (USACE) in 1940 to provide protection against flooding from the 

Connecticut and Mill Rivers.  This system requires significant refurbishment, as levees and retaining walls that 

protect the downtown area from high river waters need maintenance to ensure their structural integrity, and 

the 70‐year old flood control pumping station that diverts floodwater through the levee under flood conditions 

requires replacement. 

The City faces many serious challenges in restoring and maintaining fully functional drainage and flood control 

systems, including: 

Replacement and refurbishment of older drainage and flood control infrastructure that no longer fulfills 

its intended purpose 

Upgrades of the existing drainage system to serve areas of the City that now experience flooding 

Compliance with new EPA regulations governing stormwater management that will mandate a wide 

range of system improvements and monitoring of stormwater quality and quantity 

Compliance with USACE requirements that will require the City to repair and certify that existing flood 

control systems meet USACE standards. 

All of the above represent real and significant costs to the City that must be addressed to avoid the risk of non‐

compliance or, worse, the risk of serious damage to public and private property and the associated financial and 

quality of life impacts on Northampton residents, business owners, and visitors.  

Financial Need Assessment 

To develop realistic estimates of the level of funding required to address drainage system and flood control 

needs, preliminary engineering was performed and a recommended plan developed to address representative 

known drainage system deficiencies in the following areas of the City: 

Bridge Street / Meadows Area 

Elm Street Brook / Florence Area 

King Street / Market Street Area 

Austin Circle / Ryan Road Area 

Additionally, recommendations were developed to address needed flood control system improvements, 

including repairs to levees, replacement of the West Street Stormwater Pumping Station with a portable pump, 

and replacement of the Northampton Flood Control Pumping Station with a new facility.  Allowances were also 

made for compliance with new EPA permit requirements, river erosion improvements, general drainage 

infrastructure improvements, and gradual implementation of green stormwater management practices (which 

are strongly encouraged by new regulations).   

These prioritized recommendations form the basis of a $95.6 million program of capital improvements to be 

implemented over a 20‐year period, as shown in Table ES‐1. In the initial five years of the program, it is 

estimated that an expenditure of approximately $33.1 million is required to implement high priority projects, 

including drainage improvements in the Bridge Street / Meadows area and Elm Street Brook/Florence area, 

River Road floodwall improvements, Roberts Meadows Brook channel improvements, levee improvements and 

certification, West Street Stormwater Pumping Station improvements, and replacement of the Flood Control 

Pumping Station (note that replacement of the Flood Control Pumping Station represents about $17.4 million of 

the required expenditure – the largest single item in the recommended improvements program).

Page 9: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Executive Summary  

ES‐3 

106678‐80349003‐11 

 

 

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

Bridge Street/Meadows Phase 1 Improvements $441,000 $5,072,000

River Road Floodwall Improvements  $155,000 $1,453,000

Roberts Meadow Brook Channel Improvements $43,680 $502,320

Federal Street Retaining Wall Improvements $120,000 $1,380,000

Elm Street Brook/Florence Area Phase 1 Improvements $516,000 $5,939,000

King Street/Market Street Area Phase 1 and 2 Improvements $911,000 $5,160,000 $5,315,000

Levee Certification $275,000 $275,000

Levee Capital Improvements $280,000 $275,000 $56,000 $647,000

Flood Control Pumping Station Upgrades $1,391,000 $15,998,000

West Street Portable Pumps    $46,000 $533,000

Austin Circle/Ryan Road Area Phase 2 Improvements $327,000 $3,757,000

Bridge Street/Meadows Area Phase 3 Improvements $448,000 $5,156,000

Elm Street Brook/Florence Area Phase 3 Improvements $1,033,000 $5,850,000 $6,025,000

King Street/Market Street Area Phase 3 and 4  Improvements $643,000 $3,643,000 $3,752,000

EPA MS4 Permit Requirements Allowance $250,000 $250,000 $250,000 $250,000 $250,000

Annual Allowance for Drainage Infrastructure  $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000

Municipal Green Design/Construction Allowance $258,000 $265,000 $273,000 $281,000 $290,000 $299,000 $307,000 $317,000 $326,000 $336,000 $346,000 $356,000 $367,000 $378,000 $389,000 $401,000 $413,000 $426,000 $438,000 $452,000

Total Costs per Year $1,761,680 $3,961,320 $6,151,000 $3,115,000 $18,087,000 $7,769,000 $7,347,000 $6,132,000 $1,153,000 $4,593,000 $1,294,000 $7,045,000 $6,717,000 $7,546,000 $4,532,000 $4,653,000 $913,000 $926,000 $938,000 $952,000

Grand Total $95,586,000

Planning/Operations

Design

Construction

YearProject Description

Table ES.1

Summary Project Cost Schedule

Page 10: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Executive Summary  

ES‐4 

106678‐80349003‐11 

This 20‐year program of capital improvements forms the basis for evaluation of a stormwater fee, with capital 

costs annualized on the assumption that projects will be financed through the issuance of 20‐year bonds.  By 

completing preliminary engineering and developing capital cost estimates for specific priority projects (as 

opposed to allowances for generic projects), the City can have greater confidence that the stormwater fee 

estimates developed as part of this study are realistic and reflect the current infrastructure investment needs of 

the City. 

Basis of a Northampton Stormwater and Flood Control Utility 

While there are a relatively small number of stormwater utilities in New England and across the country, interest 

in such utilities has grown dramatically in recent years as communities have recognized the need for a reliable, 

dedicated source of revenue to fund needed improvements to drainage and flood control infrastructure.  While 

the details of specific utilities can vary, the underlying premise of all stormwater utilities is that costs for 

drainage and stormwater improvements should be shared equitably, with the amount of impervious area 

associated with a particular parcel serving as a proxy for the contribution of stormwater generated by that 

particular parcel (parcels with more impervious area generate more stormwater and therefore place a greater 

burden on drainage and flood control systems).  Because there is a direct and proven relationship between 

impervious area and the rate and volume of stormwater generated, allocation of stormwater‐related costs 

based on impervious area is more equitable than traditional methods of cost allocation, such as allocation based 

on water consumption or property values.   

Essentially, there are three steps to determining a defensible stormwater fee: 

1.  Step 1: Estimate the revenue requirements for the Stormwater and Flood Control Utility.  The annual 

revenue requirements for the utility are based on annualized capital program requirements (debt service), 

system operation, and system maintenance costs.  Estimates of annualized debt service for a Northampton 

utility have been developed based on the capital program previously discussed, as well as requirements for 

system operation and maintenance based on analysis of current system expenditures and estimates of 

increased expenditures required to comply with new permit requirements.  The results of these analyses 

are shown in Table ES‐2 and Figure ES‐1, and show an initial annual revenue requirement of approximately 

$1.5 million growing to approximately $3.9 million over a five‐year period. 

2.  Step 2: Assess the City’s impervious area and use it to develop an ERU‐type billing system.  It is 

recommended that an Equivalent Residential Unit (ERU) system be used as the basis of the stormwater fee. 

Under an ERU system, residential units are assigned one billing unit per dwelling unit, a duplex is assigned 

two billing units, and a three‐family home is assigned three billing units. Additionally, larger residential and 

non‐residential parcels are assigned billing units based on the amount of impervious area for a specific 

parcel relative to the impervious area associated with an equivalent residential unit.  The amount of 

impervious area for a given ERU is determined using the City’s Geographic Information System (GIS) 

database, which allows for calculation of a typical ERU based on analysis of impervious area at residential 

parcels across the city. For Northampton, one ERU is estimated to be 2,671 square feet.   

3.  Step 3: Calculate a rate per equivalent unit and the impact on typical rate payers.  Based on the annual 

revenue required (Step 1) and the impervious area identified within the City (Step 2), a rate for each ERU is 

determined. For Northampton, a stormwater rate of $66.63 per ERU has been estimated for FY2012, with 

the impact on various types of properties summarized in Table ES‐3. So, if implemented, a single‐family 

home will pay an annual stormwater fee of $66.63, with larger residential and commercial properties paying 

proportionally higher fees based on the ERU system.     

Page 11: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Executive Summary  

ES‐5 

106678‐80349003‐11 

Table ES‐2 Revenue Requirement 

2011  2012  2013  2014  2015  2016 

O&M  $1,470,232   $1,567,960  $1,615,279   $1,664,031    $1,714,261    $1,766,013  

Existing Debt Service  $48,340  $54,644  $41,944  $38,684  $37,484  $35,474 

Anticipated Debt Service  $0  $69,850  $316,548  $789,821  $1,337,643  $2,048,693 

Revenue Requirement  $1,518,572  $1,692,454  $1,973,771  $2,492,536  $3,089,388  $3,850,180 

Figure ES‐1 Revenue Requirement (thousands) 

 

Table ES‐3 Proposed Equivalent Residential Unit Stormwater Fee Schedule, FY 2012 

Classification  Billing Units  ERU  Rate per ERU 

Single‐Family  1  1.00  $66.63 

Two‐Family  2  2.00  $133.26 

Three‐Family  3  3.00  $199.90 

Classification Impervious 

Area ERU  Rate per ERU 

Large Residential  10,821  4.05  $269.95 

Commercial/Industrial with 1,000 square feet of IA  1,000  0.37  $24.95 

Commercial/Industrial with 10,000 square feet of IA  10,000  3.74  $249.46 

Commercial/Industrial with 100,000 square feet of IA  100,000  37.44  $2,494.58 

 

$‐

$500 

$1,000 

$1,500 

$2,000 

$2,500 

$3,000 

$3,500 

$4,000 

$4,500 

2011 2012 2013 2014 2015 2016

O&M Existing Debt Service Anticipated Debt Service

Page 12: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Executive Summary  

ES‐6 

106678‐80349003‐11 

Policy Considerations for a Stormwater and Flood Control Utility 

In addition to financial considerations and rate equity, a number of policy issues should be considered as part of 

the implementation of a stormwater and flood control utility. These considerations include: 

Public Education:  A critical component of any implementation plan is a public education program that will 

explain to both residents and the business community the need for investment in stormwater and flood control 

infrastructure and the benefits of raising this revenue through a stormwater fee as opposed to alternate cost 

allocation metrics such as water consumption or property valuation.  Examples of public education activities 

include distribution of press releases that describe the role and purpose of the stormwater and flood control 

utility, incorporating the basics of stormwater management into school curriculum, and holding public meetings 

to discuss the new utility.   

Stormwater Credits:  To help alleviate the immediate impact of a stormwater fee on customers with large 

impervious areas and/or encourage practices that reduce the magnitude of stormwater discharges, the City may 

consider a program of stormwater credits that can serve to reduce the overall stormwater fee paid by certain 

property owners. Stormwater credits may be provided when a property owner has put in place stormwater 

controls that provide relief beyond what may have been required as a condition of property development. 

Examples of practices where stormwater credits may be applied include the construction of detention ponds or 

green rooftops, the conservation of natural areas in new development, and the application of low income 

credits for residential customers with financial hardship. In addition to stormwater treatment practices, some 

utilities and municipalities also provide credit related to stormwater education, as well as for stormwater 

systems that are separate from the municipal system, but have been required to comply with MS4 permitting 

requirements.  While stormwater credits can provide benefits in terms of equity and “good practice” incentives, it 

is recommended that the City develop clear guidelines for such credits prior to full implementation of the 

stormwater utility so that the public understands the rules for such credits prior to receiving an initial 

stormwater fee assessment. 

Summary 

Implementation of a Stormwater and Flood Control Utility will provide the City with a dedicated means of 

funding for needed investment in stormwater and flood control infrastructure.  The methodology described in 

this evaluation seeks to align the cost of providing stormwater and flood control protection with the cost burden 

imposed by individual customers on stormwater and flood protection systems, and thereby provides an 

equitable allocation of these necessary costs. Additionally, the direct relationship between the quantity of 

stormwater generated by a particular parcel (using impervious area as a proxy) and the stormwater fee applied 

to a parcel directly encourages customers and new developers to find ways to minimize stormwater impacts. 

These behavioral incentives will help the City achieve compliance with new stormwater management 

regulations that encourage green design practices and a reduction in the volume of stormwater generated. 

As a result of this evaluation, the City has a defensible basis for estimating the magnitude of such a stormwater 

fee. This estimate is not based on generic or hypothetical costs, but on preliminary engineering used to develop 

site‐specific cost estimates to address several of the more serious deficiencies to the City’s drainage and flood 

control systems. Based on this analysis, it is recommended that, for Fiscal Year 2012, the City adopt a 

stormwater charge of $66.63 based on an ERU with an impervious area of 2,671 sq. ft.  As the City begins to 

undertake specific stormwater‐related capital improvements, this stormwater fee can be adjusted by the City to 

fund infrastructure priorities. Such a fee will allow the City to undertake a reasonable program of needed capital 

Page 13: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Executive Summary  

ES‐7 

106678‐80349003‐11 

improvements, provide needed maintenance of existing assets, and maintain compliance with increasingly 

stringent stormwater management regulations.  

The ability of a Stormwater and Flood Control Utility to address the real and serious issues of stormwater 

management and flood control in a careful, considered manner with costs allocated fairly and rationally will 

benefit the residents and businesses of Northampton for decades to come.  It will provide security against the 

disruption and economic damage that can result from the failure of aging infrastructure that has exceeded its 

useful life and/or is operating beyond its intended capacity.   

Page 14: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

1‐1 106678‐80349‐03‐11.docx 

Section 1 ‐ Introduction 

1.1  Introduction The City of Northampton’s (City) storm drainage system includes about 3,750 catch basins and inlets 

and approximately 108 miles of drainage pipes that lead to more than 280 outfalls (Figure 1.1).  A 

large percentage of the drain lines are over 100 years old. These systems are in need of replacement 

and many areas of the City require improved drainage infrastructure. 

The City adopted the Sustainable Northampton Comprehensive Plan (Sustainable Plan) on December 

19, 2007.  The plan outlined many sustainability goals including Goal IC‐3 – Upgrade the City’s Aging 

Stormwater Management System. The objectives of this goal include: 

1. Develop and implement a plan to maintain, repair, replace, and improve aging infrastructure 

throughout the City. 

2. Include “low impact” and National Pollution Discharge Elimination System drainage 

improvements concurrently with any pavement management program or project. 

3. Invest in stormwater management improvements. 

4. Make certain that investments in stormwater are distributed by comparable infrastructure 

needs. 

The strategy and actions outlined for accomplishing these objectives are as follows: “Complete an 

engineering assessment on the ability to meet present and future stormwater management 

requirements. Include low impact and green design considerations in the assessment. Create a long‐

term priority improvement plan.” 

The City is provided flood protection from the Connecticut and Mill Rivers via a flood control system 

that was constructed in 1940 by the Army Corps of Engineers (USACE). Another goal in the 

Sustainable Plan is Goal EEC‐7 Develop Strategies to Protect the City from the Impacts of Natural 

Hazards. The need to cost‐effectively maintain the City’s flood control facilities is in keeping with the 

goals of the Sustainability Plan. 

This study presents an approach to meet the goals of the Sustainable Plan. It describes the types of 

stormwater and flood control improvements that the City requires and also presents the framework 

to implement a new Stormwater and Flood Control Utility. If adopted by the City, this new Utility 

would establish an Enterprise Fund to manage a comprehensive program that will provide funding for 

capital projects and the annual operation and maintenance of the City’s stormwater system and flood 

control systems. 

The City faces challenges on many levels related to management of its stormwater management and 

flood control systems.  Briefly, these challenges include:

Page 15: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

BRIDGE ROAD

SP

RING

STREET

SOUTH STREET

PRINCE STREET

LEO

NA

RD

ST

RE

ET

BL

ISS

ST

RE

ET

PLEA

SA

NT

ST

RE

ET

LOCUST STREET

NO

RTH

MA

IN S

TRE

ET

NO

RT

H M

AP

LE

ST

RE

ET

GROVE STREET

VE

RN

ON

ST

RE

ET

NO

RTH

STRE

ET

DAMON ROAD

RIVERBANK

ROAD

KIN

G S

TR

EE

T

CH

ES

TN

UT

ST

RE

ET

FRA

NK

LIN

ST

RE

ET

HO

CKANUM RO

AD

RYAN RO

AD

GL

EN

DA

LE R

OA

D

PROSPECT STREET

ST

AT

E S

TR

EE

T

FIR

ST

SQ

UA

RE

ROAD

ROCKY HILL ROAD

PARK HILL ROAD

INDUSTRIAL

DR

IVE

KEN

NE

DY

RO

AD

MAIN STR

EET

CONZ STREET

NO

RT

H K

ING

ST

RE

ET

CHAPEL STREET

OLD FERRY ROAD

RO

UN

D H

ILL

RO

AD

BRIDGE

S

TR

EE

T

FLO

R

ENC E STREET

FL

OR

EN

CE

RO

AD

HAWLEY

ST

RE

ET

ACREBROOK DRIVE

TURKEY HILL ROAD

MO

UN

T T

OM

RO

AD

MEADOW STREET

WA

TE

R S

TR

EE

T

FR

ONT

HIL

L R

OAD

JAC

KS

ON

ST

RE

ET

FORT STR

EE

T

CO

LE

S M

EADO

W

ROA

D

PA

RK

ST

RE

ET

NONOTUCK STREET

ELM STREET

CHESTERFIELD ROAD

BR

OO

K

SIDE CIR

CLE

R IVERSIDE

DRIVE

HI

NC

KL

EY

ST

RE

ET

YOUNG R

AINBOW

RO

AD

WINTER

BER

RY

LA

NE

WESTHAMPTON ROAD

WIL

LO

W S

TREET

RIV

ER

RO

AD

LOWE

R M

EM

OR

IA L PARK DRIV E

MA

PL

E R ID G

E

ROAD

OLD

SPRING

FIE

LD RO

AD

HA

YD

EN

VIL

LE

RO

AD

BURTS PIT ROAD

U

PPER FA R

M

ROAD

MA

SS

AS

OIT

STR

EE

T

PINE STREET

GR

EE

NLE

AF

DRIV

E

RA

N

GE

ROAD

WE

BB

S H

OLL

OW

RO

AD

CL

EM

EN

T S

TREET

SO

UT

H M

AIN

STR

EET

DUNPHY DRIVE

OU

TE

R O

V

A L

UN

ITED M

ETH

ODIST

DRIVE

ISLAND ROAD

DR

UR

Y L

AN

E

LYMAN ROAD

N

ORTH FA

RMS

RO

AD

PY

NC

HO

N M

EA

D

OW

ROAD

POND

ROAD

RICK DRIVE

WILSON

RO

AD

P OTASH ROAD

LA

KE

ST

RE

ET

WE

ST

FA

RM

S R

OA

D

WO

OD

S R

OA

D

S HE

PAR

DS

RO

AD

HUNTS ROAD

A UDUBON ROAD

HIL

LC

RE

ST

DR

IVE

NOOK ROAD

FA

IR S

TR

EET

WO

OD

LAND DRIVE

LAD

YS

LIP

PER LANE

OX BO W ROA D

CR

OS

S P

AT

H R

OA

D

KIN

GS

HIG

HW

AY

OLD RAINBOW ROAD

CURTIS NO

OK

RO

AD

SY

LV

ESTE

R ROAD

WALNUT T

RE

ES

PAT

H

VEN

TU

RER

S F

IEL

D R

OA

D

CAR

DIN

A L WAY

EASTHAMPTON ROAD

RE

SE

RV

OIR

RO

AD

OLD MILL RIVER

O x b o w

MILL RIVER

WILLOW LAKE

MILL RIVER

Hu l b e r t s

P o n d

BROOKWOOD MARSH POND

BAYE PO

ND

BAYE POND 2

FITZG ERALD LA KE

Danks

Pond

Rob

erts

Meadow

Rese

rvior

Lower Robert Meadow Res.

Parsons or Bassett Brook

C o n n e c t i c u t R i v e r

ICE P

OND BR

OO

K

Elm S t.

Broo

k

Lower M

eadow Brook

Barr ett S t B

roo k

Br

oad B

rook

H ANNUM B

RO

OK

SAN

DY H IL

L BROO

K

Halfway Brook

Day

Brook

Rober

t’s Me ad

o w Bro

o k

Brough

to ns Brook

PI N

E B R

OOK

Clark

Broo k

Bea ver B rook

Man

ha

n R

iver -

- No

rth

Br an

ch

Ba s set Brook

Bas s ett or

Parso n’s Br ook

Broad Broo k

Basset

B roo k

Broa d Bro okRobe

rts Meadow Brook Channe

l

Roar ing B

r oo k

Roberts Meadow

Broo

k

Pars ons B rook

Mar

b le B

rook

91

WESTHAMPTON

HATFIELD

HADLEY

EASTHAMPTON

SOUTHHADLEY

WILLIAMSBURG

HOLYOKE

West Street Pumping Station

West Levee

East Levee

0 2,000 4,000Feet

\\Camgissvr1\Projects\M_Billings\Northampton\mxd\Figure2_1.mxd JD 11/21/11

Northampton Flood Control Pumping Station

City ofNorthampton

Stormwater and FloodControl SystemAssessment and

Utility Plan

Figure 1.1City-Wide Drainageand Flood Control

System Map

LegendTown Boundary

Stormwater Pumping Station

Stormwater Pipe < 12"

Stormwater Pipe 12" to 24"

Stormwater Pipe > 24" to 82"

Levee

Drainage Areas

Parcel Boundary

Streams

Lakes and Rivers

DEP Wetlands

Wetlands (MassGIS)

Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)

Page 16: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 1     Introduction   

1‐3 106678‐80349‐03‐11 

Aging Stormwater Infrastructure ‐ Much of the City’s 

stormwater infrastructure is over 100 years old and in 

need of repair or replacement.  Photo 1.1 is a 

photograph of a 2010 drain failure on Florence Road. 

New Stormwater Infrastructure is Needed ‐ Where the 

need for new stormwater systems have been 

identified, no source of funding exists to construct 

needed improvements.  Photo 1.2 a photograph of 

flooding in the Austin Circle and Ryan Road area.    

Aging Flood Control Infrastructure ‐ The City has an extensive flood control pumping system and levee 

system that was built in the 1940’s by the USACE after 

the historic floods of 1936 and 1938.  This important 

infrastructure protects much of the downtown area 

from flooding by the Connecticut River and the Mill 

River.  Important components of this system need 

capital improvements or replacement.  Photo 1.3 a 

photograph of flooding downtown in 1936 and Photo 

1.4 is a photograph of the West Street flood wall that 

was erected in August 2011 prior to Hurricane Irene. 

River Erosion ‐ The City is blessed with scenic brooks and rivers. However, the Mill River and other brooks 

cause streambank erosion that threatens both private 

and public property if not controlled.  There is no 

funding available for erosion control projects that are 

important to protect private and public property from 

damage.  Photo 1.5 is a photograph showing the 

dilapidated condition of the Mill River retaining wall. 

New Stormwater Regulatory Mandates – Revised U.S.  

Environmental Protection Agency (EPA) regulations 

governing stormwater management (National 

Pollutant Discharge Elimination System or NPDES) 

regulations are anticipated to be released in the next 

few months. These regulations will include new 

mandates such as additional maintenance activities, 

outfall monitoring requirements, as well as stormwater 

retrofit capital projects. Photo 1.6 is a photograph of a 

small diameter outfall off Ward Avenue and Photo 1.7 is a photograph of a large‐diameter outfall off 

Hampton Avenue.  

Photo 1.1 Florence Road Drain Failure

Photo 1.2 Austin Circle/Ryan Road 

Photo 1.3 1936 Flood 

Page 17: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 1     Introduction   

1‐4 106678‐80349‐03‐11 

New Flood Control Regulatory Mandates ‐ The USACE is 

requiring a complete engineering assessment and upgrade of 

the City’s flood control system. In addition, the Federal 

Emergency Management Agency (FEMA) is also in the process 

of updating Flood Insurance Rate Maps (FIRM) in several 

Massachusetts Counties. As part of map updating, FEMA will 

require that the City certify that the flood control systems meet 

USACE standards. The FIRM mapping update for Hampshire 

County is not yet scheduled but is expected in the near term. 

Photo 1.8 is a photograph of the Connecticut River levee in 

August 2011. 

Inadequate Funding ‐ Currently, the City provides very little funding on an annual basis for stormwater and 

flood control‐related work. In the last decade or more the capital funding amount has typically been under 

$100,000 per year, with funding for capital projects zeroed out of the budget three years ago. Current 

funding is from the General Budget where City‐wide demands are great. A new source of sustainable 

funding is needed to meet the needs described above.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

Photo 1.4 West Street Flood Wall 

Photo 1.5 Mill River Retaining Wall  Photo 1.6 Ward Avenue Outfall 

Photo 1.7 Hampton Avenue Outfall  Photo 1.8 Connecticut River Levee 

Page 18: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 1     Introduction   

1‐5 106678‐80349‐03‐11 

1.2  Federal Stormwater Management Regulations – Historical Overview 

The City’s storm drain discharges are subject to the NPDES Stormwater Phase II Municipal Separate Storm Sewer 

System (MS4) General Permit.   

Since 2003, the City has complied with the EPA’s NPDES Stormwater Phase II permit for smaller communities 

with municipal separate storm sewer systems. The NPDES Stormwater Permit regulates discharges from 

Northampton’s municipal storm system and mandates steps the City must take to control the quantity and 

quality of water discharged from the storm drain system. Over the first five years of the NPDES Stormwater 

Permit coverage, the City met the EPA’s requirements to implement a stormwater management program that 

included the following six minimum controls: Public Education, Public Involvement, Illicit Discharge Detection 

and Elimination, Construction Site Stormwater Runoff Control, Post Construction Stormwater Management, 

Good Housekeeping and Pollution Prevention.  

In June of 2004 the Northampton City Council approved both the Illicit Connections and Discharges to the 

Municipal Storm Drain System Ordinance and the Erosion and Sediment Control and Post‐Construction 

Stormwater Management Ordinance. Since that time the main focus of the Northampton Stormwater 

Management Program has been the implementation of the Stormwater Management Permit program.  Between 

June 2004 and August 2011 the Northampton Department of Public Works (DPW) issued a total of 61 

Stormwater Management Permits for development projects disturbing over one Acre. The fees collected are 

directly dependent on the number and size of development projects each year. A revolving fund was established 

that was intended to fund the implementation of the Stormwater Management Program. However, the revenue 

from the stormwater permit fees proved to be inadequate to consistently pay for the cost of maintaining 

compliance with the City’s NPDES Stormwater MS4 Permit. In 2006 the revolving fund was ended and 

stormwater permit fees are now deposited directly in the City’s General Fund.  

The stormwater system is operated and maintained on a limited budget funded through the City’s General Fund. 

The budget is used for emergency repairs of the system, catch basin cleaning and repair, engineering, new 

connection permits, and compliance with the NPDES permit. Over the past 25 years the City has performed 

repairs on the stormwater system on an emergency basis only. Other than catch basin cleaning, no routine 

inspection, maintenance, and repair takes place, and each year the system condition continues to deteriorate.    

In March 2011 the City completed the eighth year of implementation of the Stormwater Management Program 

as required by the EPA. The program has been implemented with the smallest budget possible to keep the City 

in compliance. The ability to comply with regulatory requirements is a function of consistent funding needed for 

staffing and equipment costs needed to properly operate and maintain the municipal storm drain system, 

including activities such as street sweeping and catch basin cleaning. Looking ahead, the City’s NPDES 

Stormwater permit compliance costs will likely increase four to five‐fold when the new EPA regulations are 

instituted.  

1.3  Federal Stormwater Management Regulations – Pending Changes 

In December 2010 the EPA issued a Draft of proposed changes to the Massachusetts Interstate, Merrimack, and 

South Coastal Small MS4 General Permit (Draft Permit) for public comments. Information about this Draft Permit 

can be found on the EPA website (www.epa.gov/region1/npdes/stormwater/mimsc_sms4.html) It is projected 

Page 19: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 1     Introduction   

1‐6 106678‐80349‐03‐11 

that the final permit changes will be issued by early 2012. The proposed changes to this MS4 permit include 

many new and costly obligations for the City. A small sample of the new requirements is discussed below. 

Data Requirements: The Draft Permit requires the gathering, and in some cases mapping, of an enormous 

quantity of data. Much of this information is required in the first two years in order to perform the analyses 

required to meet the permit milestones. Even though Northampton has a well‐established Geographic 

Information System (GIS) system, the data compilation and analysis alone could consume the better part of the 

five‐year permit cycle.  The individual data requirements by themselves may be feasible to obtain, but 

collectively they present a considerable effort involving personnel with a high level of knowledge and skill. 

Proposed Outfall Sampling: The new permit requires sampling 25 percent of the drainage outfalls each year 

during both dry and wet weather.  The City of Northampton has about 287 stormwater outfalls. The sampling of 

this many outfalls is costly and would require either City staff time, or hiring a consultant to complete the 

sampling. New sampling equipment and analytical costs will also be incurred to comply with this new 

requirement.   

Illicit Discharge Detection and Elimination (IDDE) Program: The discharge of sanitary sewage and other 

pollutants through stormwater systems is prohibited and any illicit connections found through sampling need to 

be corrected within 30 days.  In some cases the connections are the responsibility of private land‐owners to fix 

and in other cases the City may be responsible for constructing the improvement and the associated repair cost. 

Nitrogen Reduction Requirements: Since the City is located within the Connecticut River basin and thus 

ultimately discharges to Long Island Sound, a 10 percent reduction in nitrogen is proposed to meet water quality 

standards.  Given the level of attention Northampton has paid to our stormwater sampling and mitigation 

program to date, we are concerned that even the best efforts may result in failure to comply, and we are 

concerned about the associated consequences if additional appropriate Best Management Practices (BMPs) 

cannot be implemented in a timely and cost‐effective manner.  The types and cost of BMPs is expected to be 

significant.  

BMPs ‐ Constructed Retrofits: The Draft Permit requires that the City complete an inventory and priority ranking 

of City‐owned property and infrastructure (including public right of ways) that may have the potential to be 

retrofitted with BMPs designed to reduce the frequency, volume, and peak intensity of stormwater discharges. 

By year 3 of the permit, EPA requires that some BMP retrofit projects be completed.  The inventory and priority 

for the entire City is a large undertaking. The design, permitting, and construction of BMP retrofits will be time 

consuming and costly.    

Public Education and Outreach: The Draft Permit includes the production and distribution of eight public 

education notices, in addition to several ordinances and programs intended to teach the public how to minimize 

their impacts on stormwater quality.   

Catch Basin Inspection and Cleaning: The Draft permit requires inspection and cleaning of every catch basin 

such that no sump is more than 50 percent full.  This may require cleaning catch basins more often than one per 

year.  Currently, the City cleans catch basins annually. 

Floor Drain Inspections:  The draft permit requires Identifying and determining the outlet of every floor drain in 

every municipal building within one year of the effective date of the permit. In older cities like Northampton, 

plumbing plans are not available for many municipal buildings, and dye testing would be required to understand 

the plumbing configuration and outlet location of every floor drain. Again, additional City staff time or the use of 

contractors would be needed to comply with this requirement. 

Page 20: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 1     Introduction   

1‐7 106678‐80349‐03‐11 

There are many other costly requirements to comply with this new permit. The costs to maintain compliance 

with the Draft permit may require spending nearly three times the current budget or approximately $250,000 

per year for the City of Northampton. 

1.4  Flood Control – Regulatory Mandates The City is provided flood protection from the Connecticut and Mill Rivers via a flood control system that was 

constructed in 1940 by the USACE. The City is responsible for maintaining flood control infrastructure. The levees 

(or dikes) and pumping stations along both rivers protect the City from flooding in critical low lying elevations. 

The flood control system for the City consists of two main parts. An earthen levee about a mile in length on the 

eastern part of the City provides protection against high water from the Connecticut River.  In addition, an 

earthen levee and concrete flood wall about a half mile in length in conjunction with the Mill River diversion 

canal provides protection against flash floods on the Mill River and backwater from the Connecticut River via the 

Ox Bow. The City maintains a flood control pumping station located at the wastewater treatment plant on 

Hockanum Road. Wastewater treatment plant staff operates the pumping stations while the entire DPW is 

engaged in the maintenance and operation of the flood control levees and Mill River diversion channel.  A 

smaller pumping station is located on West Street adjacent to the Mill River. 

The USACE issued inspection reports dated August 26, 2011 for the Mill River Flood Control System and for the 

Connecticut River Flood Control System. These reports included a long list of required improvements that must 

be completed by September 2012. Generally, these improvements were related to removal of trees and 

vegetation, establishing new turf on levee systems, video inspections of toe drain systems, and related work.   

The completion of this work is beyond the means of the DPW staff. Bidding of the completion of this work is 

needed, in order to have a contractor complete the improvements.  Currently, there is no funding source to 

complete this work other than the General Fund budget. 

Also, in a meeting at the USACE office in Concord, Massachusetts on August 26, 2011, the City was informed that 

notification will be sent in the next few months that significant engineering studies must be completed by the 

City for all flood system components. These engineering studies will be required to include: 

Preparation of topographic surveys to determine elevations and freeboard allowances; 

Geotechnical borings; 

Hydraulic and hydrologic analyses; 

Seepage and slope stability analyses of dikes; stability analyses of floodwalls; settlement analyses for dikes, 

pumping stations, and floodwalls; and seismic assessment for flood control structures; and  

Inspections of all penetrations through the levees. 

The USACE had preliminarily indicated that these studies will be required to be completed within two years of 

receiving written notification of this requirement. The City anticipates receiving this notification by the end of 

2011, resulting in an estimated deadline of the end of 2013 for completion of this work. These studies are 

expected to cost hundreds of thousands of dollars to perform. Other Cities along the Connecticut River such as 

Chicopee, Springfield and Hartford have completed these studies and found that millions of dollars of levee and 

flood control pumping station improvements were required. 

In addition to the USACE requirements, FEMA is in the process of updating Flood Insurance Rate Maps (FIRM) 

across Massachusetts, with Hampshire County maps scheduled for updating in 2012 or later. As part of the FIRM 

updates, FEMA will require the City to certify that flood control systems, including levees, meet current USACE 

Page 21: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 1     Introduction   

1‐8 106678‐80349‐03‐11 

standards.  This certification process includes engineering assessment similar to the above‐listed studies and 

associated flood control capital improvements. The certification process has cost other Massachusetts 

communities millions of dollars. If the City flood control system is not certified, the properties currently 

protected by this system would no longer be protected. Property owners in the flood zone that have federally 

backed mortgages would then be required to purchase expensive flood insurance.  

1.5  Infrastructure Funding The use of the General Fund to pay for stormwater infrastructure is nearly universal in Massachusetts, but in 

most cases the General Fund is insufficient to meet all of the needs of aging and inadequate infrastructure, nor is 

there funding to meet the increasingly stringent regulations.  There is inadequate funding to meet the 

stormwater, flood control and stream erosion project needs in the City. Very limited funding for this 

infrastructure has been provided through the City’s General Fund. The financial resources of the City to fund 

infrastructure through the General Fund appears to be very limited, where General Fund resources are used for 

all City operations such as schools, Fire and Police Departments. Monies from the General Fund have been 

unable to keep pace with the requirements to maintain and/or replace existing infrastructure or construct new 

infrastructure in locations where the need is great. 

Since tax exempt properties, such as colleges, state and federal properties do not pay property taxes, they do 

not contribute to the General Fund. Many tax exempt properties have large expanses of impervious area that 

generate significant stormwater flows. The costs associated with the City managing this stormwater is paid by 

tax payers.  Stormwater utilities have been established in other communities on an equitable fee for service 

basis where fees are determined based on usage (amount of impervious area is one alternative for determining 

fees).   

Many Cities and Towns have implemented, or are in the process of evaluating the formation of new utilities for 

the management of stormwater and related infrastructure. Locally in western Massachusetts, Chicopee and 

Westfield have implemented a stormwater utility. The charging of user fees for stormwater management is 

authorized under state law (MGL c.83 s.16). The implementation of a stormwater utility is an equitable means to 

provide the stable revenue source needed to manage stormwater infrastructure and to meet the ever expanding 

regulatory state and federal mandates. Also, shifting infrastructure costs to a utility fee basis provides some 

relief to the General Fund budget by removing stormwater‐related costs from that budget.   

1.6  Project Summary This project consists of two parts. The first part of the study involved identifying drainage, river erosion and 

flood control improvements projects. Preliminary cost estimates were prepared for these projects and 

summarized in a 20‐year capital improvements plan. The second part of the study considered establishing a 

stormwater and flood control utility and the various approaches used successfully by other communities. The 

20‐year capital improvements plan and projected operational costs were used to evaluate various utility rate 

structures.  

The drainage projects that were evaluated included areas that are flood‐prone or are known to have stormwater 

capacity issues. These drainage projects are considered representative of projects that may be needed across 

the City. The projects analyzed include: 

King Street/Market Street/Downtown Area; 

Bridge Street/Meadows Area; 

Page 22: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 1     Introduction   

1‐9 106678‐80349‐03‐11 

Elm Street Brook Area (Florence Area); and 

Ryan Road/Austin Circle Area. 

River erosion projects considered are known problem areas where various grant funding has been sought for 

repairs. The projects include: 

River Road Retaining Wall/Floodwall improvements (Mill River); 

Roberts Meadow Brook channel improvements and erosion repair; and 

Federal Street retaining wall repair (Mill River). 

Flood Control projects were selected based on an engineering inspection of these City flood control systems.  

The projects included: 

Flood Control pumping station replacement; and 

Levee system evaluations and improvements. 

The recommended plan focuses on improvements to alleviate existing flooding and river erosion problems in 

these representative areas. Flood control projects are also identified and included. The study presents a 

preliminary 20‐year capital improvement plan.  In addition, future operations and maintenance costs were 

estimated as needed to comply with the Draft EPA MS4 Stormwater Permit.  The capital improvements plan and 

operating costs were used in the evaluation of various stormwater utility options. 

1.7  Scope of Work Specific tasks completed for this study include: 

1. Inventory and assessment of existing stormwater drainage infrastructure, including stream erosion projects.  

Work included field inspections and hydraulic modeling of sample problem areas identified by the City. 

2. Inventory and assessment of existing flood control infrastructure including pumping stations and levee 

systems. 

3. Review and accounting of current operational budgets for drainage and flood control operations. 

4. Determination of a 20‐year Capital Improvement Plan for stormwater drainage, river erosion and flood 

control projects. 

5. Determination of future budget allocations needed to meet regulatory mandates. 

6. Evaluation of a new Stormwater and Flood Control Utility, including revenue requirements, rate structure 

options, rate modifiers, discounts and exemptions, billing options, and implementation steps.   

Page 23: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

                        2‐1 

106678‐80349 03 11 

 

Section 2 ‐ Existing Conditions and Alternatives Analyses 

 

2.1  Introduction This section provides an assessment of the existing conditions for representative areas of the 

stormwater drainage system, areas currently experiencing river erosion (Figure 2.1) and the flood 

control system.  This section also discusses the Department of Public Works’ current operational cost 

and funding levels to manage the City’s stormwater drainage and flood control operations.  For the 

stormwater drainage system, a summary of modeling results and alternatives analyses for four flood‐

prone areas selected by the City as being representative of the types of projects that would require 

funding is provided.  For the flood control system, recommendations to address deficiencies in the 

levee system and pumping stations are provided. 

2.2  Stormwater Drainage and Flood Control System Overview 

Figure 1.1 in Section 1 is a map of the Northampton drainage and flood control systems, including the 

West Street stormwater pumping station, Northampton Flood Control Pumping Station and levees.  

Overall, the drainage system includes approximately 108 miles of drain pipe, ranging in diameter 

from 4 to 82 inches.  There are approximately 3,750 catch basins and more than 280 outfalls 

discharging to rivers, brooks, wetlands, and ponds.  At many locations, the City stormwater was 

initially managed through a combined sewer overflow (CSO) system, with only one pipe (combined 

sewer) collecting sanitary sewer flow and stormwater runoff, instead of two separate pipes (sewers 

and drains).  During wet weather, combined sewer flow that exceeded the capacity of the system 

would overflow to rivers and streams around the City.  As the City performed sewer separation, many 

of the original combined sewers were converted into storm drains and new sewers were constructed 

to collect sanitary flow separately.  As a result, many of the drains are smaller than 12 inches in 

diameter (the recommended minimum drain size to reduce clogging problems, highlighted in red on 

Figure 1.1).  Also, a significant portion of the stormwater drainage system, consisting of turn‐of‐the‐

century vitrified clay, iron, stone and brick pipe, and asbestos cement pipe from the 1950s, is aging, 

deteriorating, lacking hydraulic capacity, and may need to be replaced.  A review of the stormwater 

drainage system within the King Street/Market Street, Bridge Street/Meadows, and Elm Street 

Brook/Florence areas indicates that nearly 47 percent of the pipes (approximately 6.1 miles) are 

made of vitrified clay, iron, stone, brick, or asbestos cement.  The large percentage of clay pipe, stone 

and brick pipe is an indication of the age of this infrastructure.  Table 2.1 provides the breakdown of 

pipe lengths by material for these areas.   

   

Page 24: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

ELM STREET

WIL L

IAM

S S

TR

EE

T

WEST-HAMPTON

WILLIAMSBURG

EASTHAMPTON

HADLEY

SOUTHHADLEY

HOLYOKE

HATFIELD

Ryan Road/Austin Circle Area

Elm Street Brook Area

King Street/Market Street/Downtown Area

Bridge Street/Meadows Area

Federal StreetRetaining Wall Repair

River Road Retaining Wall/Floodwall Improvements

Roberts Meadow BrookChannel Improvements

and Erosion Repair

A1

D

G

B

A2

A3

A4

BRIDGE ROAD

SPRING STREET

PRINCE STREET

LEO

NA

RD

STR

EE

T

LOCUST STREET

NO

RTH

MAIN

STREE

T

NO

RT

H M

AP

LE

ST

RE

ET

DAMON ROAD

RIVERBANK

ROAD

KIN

G S

TR

EE

T

CH

ES

TN

UT

ST

RE

ET

FR

AN

KL

IN S

TR

EE

T

HOCKA

NUM RO

AD

RYAN ROAD

GL

EN

DA

LE R

OAD

PROSPECT STREET

FIR

ST

SQ

UA

RE

ROAD

ROCKY HILL ROAD

PARK HILL ROAD

KE

NN

ED

Y R

OA

D

CONZ STREET

NO

RT

H K

ING

ST

RE

ET

OLD FERRY ROAD

RO

UN

D H

ILL

RO

A

D

BR

IDG

E S

TR

EE

T

FL

OR

EN CE STREET

FL

OR

EN

CE

RO

AD

TURKEY HILL ROAD

MO

UN

T T

OM

RO

AD

MEADOW STREET

WA

TE

R S

TR

EE

T

FR

ON

T

HIL

L R

OAD

JAC

KS

ON

ST

RE

ET

CO

LE

S M

EAD

OW

ROA

D

PA

RK

ST

RE

ET

ELM STREET

KIN

G S

TR

EE

T

CHESTERFIELD ROAD

BR

OO

K

SID E CIR

CL

E

BRIDGE ROAD

R

IVE R SIDE DRIV

E

HI

NC

KL

EY

ST

RE

ET

WINTER

BER

RY

LA

NE

WESTHAMPTON ROAD

RIV

ER

RO

AD

LOWE

R M

EM

OR

IA L PARK DRIV E

MA

P

LE RI DGE

ROAD

OLD SPR

IN

GFIE

LD

RO

AD

HA

YD

EN

VIL

LE

RO

AD

BURTS PIT ROAD

UPPER FA

RM

ROAD

MA

SS

AS

OIT

STR

EE

T

GREE

NLE

AF

DR

IV

E

RA

N

GE

ROAD

WE

BB

S H

OL

LO

W R

OA

D

CL

EM

EN

T S

TREET

MA

IN S

TR

EE

T L

EE

DS

DUNPHY DRIVE

RYAN ROAD

OU

TE

R O

V

A L

UN

ITED M

ET

HODIST

DRIVE

ISLAND ROAD

DR

UR

Y L

AN

E

LYMAN ROAD

NO

RT

H FA

RM

S R

OA

D

PY

NC

HO

N M

EA

DOW

ROAD

FLOR

ENCE

RO

AD

POND

ROAD

RICK DRIVE

WILSON

ROAD

POTASH ROAD

WA

LN

UT

TR

EE

S P

AT

H

BURTS PIT ROAD

LA

KE

ST

RE

ET

WE

ST

FA

RM

S R

OA

D

WO

OD

S R

OAD

SH

EPA

RD

S R

OA

D

HUNTS ROAD

A UDUBON ROAD

NOOK ROAD

FA

IR S

TR

EE

T

WO

OD

LAND D RIVE

LAD

YS

LI

PPER

LA NE

OX BOW ROA D

CR

OS

S P

AT

H R

OA

D

KIN

GS

HIG

HW

AY

CURTIS NO

OK

RO

AD

SY

LV

ESTER ROAD

CAR

DIN

A L WAY

EAS

THA

MP

TO

N R

OA

D

RES

ER

VOIR

ROAD

Oxbow

Oxbow

BAYE PO

ND

BAY

E PO

ND

Oxbow

Connecticut River

Day B

rook Broad

Bro ok

P INE BRO O K

Lo wer M

ea dow Brook

Ro ar ing Broo k

Barrett St B

rook

B road

Br ook

Br

oad B

rook

Roar ing Brook

I c e Po

nd Brook

HANNUM B

RO

OK

Hal fway Brook

Day

Brook

Roarin g B

ro o k

Rob

ert

’s Me ad

o w Bro

o k

Bro ugh

tons Brook

PIN

E BR

OOK

Clark B

rook Bea ver B rook

Bass ett or P arson’s B

r o ok

Man

ha

n R

iver --

North

Bran

ch

Ba s set Brook

Broad Broo k

Basset

B roo k

Broad BrookRoberts Meadow Brook Chann

el

Roar i ng B

r ook

Robert s Mea dow

Broo

k

Parsons Brook

Mar

ble

Bro

ok

91

91

\\camgissvr1\Projects\M_Billings\Northampton\mxds\WatershedOverviewMap_11x17.mxd MB 4/2012

0 3,5001,750

Feet

Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)

City ofNorthampton

Stormwater and FloodControl SystemAssessment and

Utility Plan

Figure 2.1RepresentativeProject Areas

Legend

Town Boundary

Parcel Boundary

Streams

DEP Wetlands

Wetlands (MassGIS)

Lakes and Rivers

Page 25: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐3 

106678‐80349‐03‐11 

Table 2.1 

Summary of Pipe Material in Four Study Areas 

Pipe Type  Total Feet  Total Miles  % Total 

Concrete   35,943   6.81  53% 

Vitrified Clay (VC)  24,055   4.55  35% 

Iron   1,017   0.19  1.5% 

Stone  1,870   0.35  2.7% 

Brick  1,890   0.36  2.8% 

Asbestos Cement (AC)  3,238   0.61  4.8% 

Polyvinyl Chloride (PVC)  78   0.01  0.1% 

Total  68,090   12.87  100% 

The City has not assessed the City’s drainage system in a comprehensive way since 1971.  Portions of the 

drainage system have been inspected since that time. For example, in July 1981, Almer Huntley Jr. & Associates 

performed an inspection of the Market Street Brook system in the King Street area, presenting the results in the 

report North Industrial Park Drainage Study (“Almer Huntley report”).  The Market Street Brook system 

discharges into the Historic Mill River bed, downstream of Hockanum Road.  The report documented the 

condition of this 1800s‐vintage system from the outfall to its beginning upstream of North Street.  Inspections 

revealed that the Market Street Brook system is a composite of various pipe diameters, shapes, and materials, at 

times going under existing buildings and through private property.  One of the earliest sections is located in the 

vicinity of Holyoke Street.  Constructed in 1846, it is mostly a 5‐t by 6‐ft brick box with a brick arch roof and 

wooden plank floor.  Between Holyoke and Bridge Streets, the drainage system is comprised mostly of a stone or 

brick box with a brick arch roof and wooden plank floor.  Even though this section was constructed between 

1846 and 1893, it was found to be in good overall condition.  However, from Bridge Street to the beginning of 

this system upstream of North Street, the pipes were found to be in overall poor condition.  Constructed mostly 

in the mid‐ to late 1800s, the pipe varies between a double brick ring and a stone box with a brick arch.  The 

inspection found sections of the brick ring out of round, longitudinal cracking, and missing bricks and stones.  

This system has not been inspected since 1981. 

The levee flood control system was constructed by the U.S. Army Corps of Engineers (USACE) as part of the 

Comprehensive Plan for Control of Flood in the Connecticut River Basin.  Construction of the flood protection 

system was started in December 1938 and completed in June 1941. The levee flood control system consists of 

two levees, as shown on Figure 2.1: the eastern part of the system (East Levee) includes an earth embankment 

about one mile long with three concrete flood walls that provides flood protection against rising waters of the 

Connecticut River, and the western part (West Levee) includes earth embankment segments and a concrete 

flood wall designed to protect against rising waters and flash floods from the Mill River and backwater from a 

diversion canal linked to the Connecticut River.  As part of this project, a diversion dike, consisting of an earthen 

embankment with a core of selected impervious material, was constructed just downstream from the West 

Street Bridge at the Smith College power plant.  It diverts the Mill River from the diversion dike through the 

former Hulberts Pond to the Connecticut River Oxbow Lake via an 11,000‐foot‐long diversion canal.  The 

purpose of diverting the Mill River was to eliminate flooding in the City’s downtown area.  Existing closed 

drainage systems in the King Street/Market Street area currently discharge to the original Mill River bed, 

referred to as the “Historic Mill River” in this report.   

Page 26: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐4 

106678‐80349‐03‐11 

2.2.1  Field Inspection Approach 

As discussed in Section 1, the City Department of Public Works (DPW) identified the following areas within the 

City as being indicative of the types of projects that will require funding:   

King Street/Market Street area 

Bridge Street/Meadows area 

Elm Street Brook/Florence area 

Ryan Road area 

These projects illustrate the scale and cost of typical capital projects.  There are similar capital projects needed 

across the City. 

Camp Dresser & McKee Inc. (CDM) conducted field inspections of these areas to assess the current condition of 

the drainage systems. This was accomplished by physically walking the system and inspecting selected 

structures, land use types, topography, verifying Geographic Information System (GIS) mapping, and noting 

defects or other conditions that should be considered during hydrologic modeling.  Highlights of the field 

inspections are provided here in the following sections; Appendix A provides detailed field inspection 

memoranda and photographs. 

2.2.2  Drainage Analysis Approach 

CDM performed drainage analyses of these four flood‐prone and critical drainage areas under existing and 

future build‐out conditions to examine the drainage systems’ capacities and size new drains if needed.  The 

drainage analyses determined peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events using 

the U.S. Army Corps of Engineers HEC‐HMS Flood Hydrograph Package, version 3.5.  This computer model 

simulates runoff and routing of stormwater flows through the watersheds, and is based on the Soil Conservation 

Service (SCS) Method.  CDM used spreadsheets based on Manning’s Equation and the Orifice Equation (allowing 

system surcharging to within one foot of the manhole cover) to evaluate the capacity of selected closed 

drainage systems to control peak rates of runoff during a 10‐year 24‐hour storm under future build‐out 

conditions.  Chapter 290, Section 52 of the City Code requires that closed drainage systems be designed for a 

minimum 10‐year storm event.  Open channels and culverts serving major drainage areas, as well as stormwater 

detention/retention basins, where flooding would produce property damage or a safety hazard, are designed to 

control peak rates of runoff during a minimum 25‐year 24‐hour storm, and if possible, a 100‐year 24‐hour storm.   

Precipitation data for standard storms used in the models were taken from Cornell University “Atlas of 

Precipitation Extremes for the Northeastern United States and Southeastern Canada” (September 1993).  The 

estimated precipitation depths during the 2‐, 10‐, 25‐, and 100‐year 24‐hour storms are 3.11, 4.38, 5.37, and 

7.35 inches, respectively.  Compared to rainfall depths in Technical Paper No. 40 (“Rainfall Frequency Atlas of 

the United States”), the rainfall depths from the Cornell University study are higher for storms greater than a 10‐

year 24‐hour storm, and provide a more conservative evaluation and design of existing and proposed 

stormwater management facilities, as well as a factor of safety for potential climate change.  

CDM delineated sub‐drainage areas within each study area using topographic and existing drainage system 

information taken from the City’s Geographic Information System (GIS) mapping.  The GIS mapping was also 

used to determine the land use, hydrologic soil group (HSG), and impervious area within each sub‐drainage area.  

Curve numbers (CNs) were assigned to each land use based on the HSG to develop a weighted CN for each sub‐

drainage area.   

Page 27: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐5 

106678‐80349‐03‐11 

To determine future build‐out conditions, CDM consulted with the Director of the Northampton Office of 

Planning and Development to determine which sub‐drainage areas are likely to undergo development in the 

future.  Curve numbers in the HEC‐HMS computer model were adjusted to reflect future build‐out conditions. 

Runoff velocities for estimating time of concentration (Tc) were based on the “SCS National Engineering 

Handbook, Figure 15.2 – Velocities for Upland Method of estimating Tc.”  A minimum Tc of 10 minutes was used 

for all sub‐drainage areas less than 1 acre, while a minimum Tc of 15 minutes was used for all sub‐drainage areas 

greater than 1 acre.  CDM used Muskingum routing to account for attenuation of peak flows within drainage 

areas. 

2.3  Flooding Problems As discussed in Section 1, the DPW identified four drainage areas that are prone to significant flooding and/or 

are in critical areas (Figure 1.1).  For each study area, CDM performed a field inspection of the drainage system, 

developed an existing conditions HEC‐HMS computer model, and developed potential alternatives to relieve 

flooding.  This section provides a summary of this effort.  In Appendix B, Tables B.1 through B.4 present the HEC‐

HMS modeling results under existing conditions for the four study areas.  Similarly, Tables B.5 through B.8 

present the HEC‐HMS modeling results under future build‐out conditions. 

CDM also performed pipe capacity analyses for existing and future build‐out pipe conditions for major drain lines 

and for streets known to have flooding problems in the King Street/Market Street area, Bridge Street/Meadows 

area, and Elm Street Brook/Florence areas. Tables in Appendix C provide the existing and future build‐out pipe 

capacity analyses. The pipe capacity analysis evaluated the adequacy of the pipes for peak rates of runoff during 

a 10‐year 24‐hour storm event.  A Manning’s n‐value of 0.013 was used for all proposed reinforced concrete 

pipes.  Pipes that have inadequate hydraulic capacity and are recommended for improvements are highlighted 

in the Tables in Appendix C.  In some cases, some pipes that are shown to not have sufficient capacity are not 

recommended for improvements and justification is provided in the table.  This section of the report describes 

the major drain lines that need to be improved, but additional smaller lines are presented in this appendix.  All 

pipes less than 12‐inch in diameter are also highlighted and recommended for replacement with a minimum 12‐

inch diameter pipe.  Upgrading of these pipes is not as critical as other recommended drainage system 

improvements and should be targeted for the later phases of the Capital Improvement Plan. 

2.3.1  Bridge Street/Meadows Area 

2.3.1.1 Site Inspection and Area Description 

Area Description 

The Bridge Street/Meadows area is currently served by two separate drainage systems. Portions of the area are 

located in the Connecticut River floodplain on the eastern side of the City and upstream portions lie at higher 

elevations west and north of the floodplain.  The drainage system is shown on Figure 2.2.  The open drainage 

channel along Cross Path Road down to the levee in the vicinity of Eastern Avenue, and the cross‐country closed 

drainage system parallel to Bridge Street are prone to flooding. 

On the west side of Bridge Street, the Day Avenue Brook drainage area is connected to a low‐lying drain line that 

runs through residential backyards between Day Avenue and Marshall Street and flows in a northeasterly 

direction across Damon Road discharging to the Connecticut River through the 42‐inch MassDOT outfall. This 

outfall recently collapsed on a river bank that washed out.  The large industrial area northwest of these 

neighborhoods also discharges to this outfall, and is a potential area for managing stormwater on‐site with Best 

Management Practices (BMPs), such as rain gardens, permeable pavement and street planters. MassDOT is 

currently preparing drawings to repair the collapsed outfall. 

Page 28: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

CONNECTICUT RIVER

MILL RIVER

LL RIVER

Northampton Flood ControlPumping Station

West StreetStormwater

Pumping Station

Approximate Wetland Boundary Estimated by City

HISTO

RIC MILL RIVER

13

6

A

2

5

I

O

S

12

G

8

Q

N

1

K

J

B

L

D

R

9

4

7T

Fairgrounds

W

U

10

3

H

M

X

V

11

P

C

E

F

91

91

DAMON ROAD

STA

TE

ST

RE

ET

NOOK ROAD

OLD FERRY ROAD

NORTH

STR

EET

PRO

SPE

CT S

TRE

ET

RIVER

BANK R

OAD

CONZ STREET

KIN

G S

TR

EE

T

PLE

AS

AN

T S

TR

EE

T

KIN

GS

HIG

HW

AY

MAIN STREET

FAIR

ST

RE

ET

VENTURERS FIE

LD R

OAD

HOCKANUM ROAD

RO

UN

D H

ILL RO

AD

CR

OS

S P

AT

H

RUSSELL STREET

CR

OS

S P

AT

H R

OA

D

BARRETT STREET

BRIDGE ROAD

SOUTH STREET

LYMAN ROAD

INDUSTRIAL DRIVE

AQ

UA

VIT

AE

RO

AD

CO

LLEG

E LA

NE

BA

Y R

OA

D

CRESCENT STREET

CE

ME

TE

RY

RO

AD

LANE PLANT ROAD

FINN STREET

GOTHIC STREET

DAY AVENUE

FRUIT STREET

BRADFORD STREET

UNION S

TREET

FAC

TO

RY

ST

RE

ET

CR

OSB

Y ST

REE

T

STRONGS R

OAD

MUNROE STREET

ORCHARD STREET

RA

ILRO

AD

AVE

NU

E

SUMMER STREET

HENRY STR

EET

BRIDG

E STREET

CENTER STREET

GREEN STREET

SMITH COLLEGE DRIVE

CHERRY STREET

SHERMAN AVENUE

ELIZABETH STREET

PH

EA

SA

NT

HIL

L D

RIV

E

SO

UT

H B

RA

NC

H R

OA

D

NORTH KING STREET

BELMO

NT AVENUE

PIN

E B

RO

OK

CU

RV

E

WOODMONT ROAD

GRANT AVENUE

COOLIDGE AVENUE

CLARK AVENUE

HOLYOKE STREET

PERKINS AVENUE

BATES

STRE

ET

STODDARD STREET

DE

NIS

E C

OU

RT

FR

AN

KLI

N S

TR

EE

T

BRIGHT STREET

HAMPSHIRE HEIGHTS

WALNUT TREES PATH

JAC

KS

ON

ST

RE

ET

SERVICE CENTER

EAST

STR

EET

SCHOOL STREETFO

RT

HIL

L TE

RR

AC

E

HAYES AVENUE

EASTERN AVENUE

MYRTLE STREET

MONTVIEW AVENUE

NORTHERN AVENUE

SMIT

H STR

EET

CR

AF

TS

AV

EN

UE

WINTER STREET

HIGHLAND AVENUE

CLARK SCHOOL DRIVE

KINGSLE

Y AVENUE

DEWEY COURT

TYLER COURT

HE

BE

RT

AV

EN

UE

BANK AVENUE

ED

WA

RD

S S

QU

AR

E

HANCOCK STREET

ISABELLA STREET

ARM

ORY S

TREE

T

TEXAS ROAD

WARFIELD PLACE

PAQ

UE

TTE

AVE

NU

E

LAWN AVENUE

UN

NA

ME

D R

OA

D

HAMPTON MANOR DRIVE

FLORID

A AVENUE

BUTTON STREET

EDGEW

OOD TERRACE

VIEW AVENUE

IND

USTR

IAL DR

IVE

FAIR STREET

BAY ROAD

CR

OS

S PAT

H R

OA

D

UNION STREET

118

147

137

127

108

216

226

206

236

246

177

255

265

196

167

275

187

157

108

187

137

147

127

127

137

147

157

137

118

127

147

118

137

147137

118

118

137

137

157

167

137

157

147

127

137

127

118

127

147

137

118

108

187

127

127

147

108

118

108

118

137

137

137

127

147

127

127

196

147

108

147

118

157

157

118

157

177

177

157

118

157

137

157

118

177

137

167

127

177

196

147

118

118

147

127

177

137

177

177

147

137

127

147

147

127

187

118

108

118

137

118

127

118

147

137

167

118

127

157

127

118

157

127

147

187

137

118

137

118

118

108

137

137

118

137

147

147

167

137

127

147

127

157

157

127

137

157

137

127

187

147

127

118

118

147

118

187

167

147

167

167

147

147

127

118

118

137

137

127

147

137

177

118

118

118

147

137

137

108

147

147

72’’

44’’

14’’

8’’

48’’

24’’

6’’

82’’

30’’

10’’

12’’

60’’

54’’

66’’

25’’

15’’

18’’

16’’

36’’

21’’

42’’

10’’

10’’

15’’

18’’

15’’

8’’

54’’

12’’

48’’

8’’

12’’

15’’

24’’

18’’

18’’

16’’

12’’

8’’

12’’

15’’

18’’

12’’

24’’

6’’

30’’

30’’

6’’

12’’

12’’

18’’

18’’

48’’

12’’

15’’

15’’

18’’

15’’

10’’

10’’

8’’

12’’

12’’

15’’

36’’

18’’

24’’

12’’

15’’

8’’

15’’

12’’

36’’

36’’

12’’

12’’

48’’

6’’

18’’

12’’

21’’

24’’

21’’

14’’

36’’

6’’

18’’

12’’

15’’

24’’

18’’

12’’

12’’

15’’

10’’

15’’

24’’

15’’

12’’

12’’

12’’

12’’

60’’

24’’

48’’

24’’

6’’

12’’

15’’

12’’

12’’

6’’

8’’

8’’

24’’

12’’

24’’

15’’

8’’

60’’

18’’

60’’

12’’

10’’

66’’

15’’

10’’

12’’

12’’

12’’

15’’

10’’

12’’

24’’

24’’

12’’

12’’

6’’

12’’

21’’

21’’

10’’

8’’

15’’

12’’

24’’

12’’

60’’

12’’

18’’

12’’

8’’

15’’

12’’

10’’

66’’

15’’

15’’

12’’

8’’

18’’

12’’

12’’

8’’

24’’

8’’

18’’

54’’

12’’

12’’

12’’

21’’

30’’

15’’

12’’

12’’

12’’

12’’

18’’

15’’

12’’

10’’

18’’

18’’

12’’

18’’

18’’

12’’

36’’

12’’

24’’

12’’

12’’

12’’

10’’

10’’

10’’

6’’

12’’

36’’

12’’

18’’

12’’

36’’

15’’

10’’

8’’

24’’

24’’

8’’

12’’

36’’

12’’

12’’

8’’

18’’

18’’

12’’

12’’

10’’

12’’

15’’

30’’

15’’

18’’

30’’

10’’

24’’

21’’

12’’

12’’

6’’

15’’

15’’

24’’

15’’

6’’

15’’

18’’

12’’

12’’

15’’

12’’

66’’

12’’

15’’

21’’

15’’

12’’

8’’

24’’

48’’

18’’

18’’

8’’

36’’

12’’

10’’

18’’

24’’

8’’

12’’

12’’

15’’

18’’

15’’

8’’

12’’

24’’

24’’

10’’

12’’

21’’

12’’

12’’

18’’

18’’

24’’

6’’

12’’

18’’

54’’

10’’8’’

36’’

24’’

18’’

66’’

15’’

36’’

10’’

18’’

12’’

36’’

15’’

15’’

18’’

44’’

24’’

18’’

12’’

12’’

12’’

36’’

12’’

8’’

24’’

18’’

30’’

18’’

66’’

10’’

18’’

12’’

36’’

12’’

12’’

12’’

18’’

18’’

15’’

10’’

18’’

18’’

8’’

36’’

8’’

12’’

12’’

12’’

12’’

12’’

18’’

12’’

18’’

15’’

30’’

12’’

18’’

24’’

12’’

15’’

10’’

12’’

16’’

15’’

12’’

10’’

12’’

18’’

6’’

8’’

24’’

12’’

24’’

12’’

12’’

12’’

24’’

6’’

6’’

12’’

36’’

15’’

24’’

30’’

12’’

12’’

18’’

12’’

10’’

10’’

8’’

15’’

48’’

36’’

8’’

10’’

8’’

12’’

10’’

12’’

10’’

10’’

12’’

10’’

24’’

18’’

12’’

15’’

12’’

10’’

12’’

15’’

12’’

12’’

12’’

15’’

10’’

10’’

12’’

15’’

18’’

12’’

12’’

157

147

\\Camgissvr1\Projects\M_Billings\Northampton\mxd\KingSt_WilliamSt_DrainageArea_Map.mxd JD 11/21/2011

Legend

91

91

350 0 350 700175

Feet

Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)

Drain Pipe

Drain Lateral

Culvert

Drainage Channel

Detention/Retention Basin

Stormwater Pumping StationDrainage Area Boundary

Drain Manhole

Catch Basin/Inlet

Stormwater Outfall

Area Prone to Flooding

King Street Brook Drainage Area ID

Williams Street Brook Drainage Area ID

City of NorthamptonStormwater and Flood Control System

Assessment and Utility PlanFigure 2.2

King Street/Market Street andBridge Street/Meadows Drainage Areas

Contour

Parcel Boundary

Building

DEP Wetlands

Wetlands (MassGIS)

Levee

Page 29: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐7 

106678‐80349‐03‐11 

 

The second drainage system in this area is the Williams Street Brook drainage system which includes developed 

areas along and west of Bridge Street, Pomeroy Terrace, and Williams Street, as well as less developed areas 

east of Bridge Street in the Connecticut River floodplain. The Williams Street Brook drain line flows south and 

discharges to the Historic Mill River. The floodplain area has experienced repetitive flooding particularly in the 

following areas: Sheldon Field and Parking Lot, the Three County Fairgrounds, Old Ferry Road, Cross Path Road, 

Fair Street, and the undeveloped area to the south of Fair Street particularly to the west of Cross Path Road and 

along the alignment of the Williams Street Brook drainage pipe. This flooding has caused local roads to become 

impassible in moderate storms and caused icing problems in the winter in this low‐lying floodplain. The drainage 

system passes through the East Levee (described below) and includes a valve structure with the purpose of 

preventing flood waters from passing through the dike.  The valve is shut only when the Connecticut River has 

reached a level of 115 feet at the gauging station at the Northampton Flood Control Pumping Station, a rare 

occurrence which results in a the system being temporarily out of service. A large redevelopment of the Three 

County Fairgrounds is planned in the near future; thus, upgrades to existing drainage infrastructure to improve 

the drainage systems in this area are needed in concert with this project’s completion. 

Field Inspection 

On Tuesday November 30, 2010, CDM conducted a field survey of the 

Bridge Street/Meadows area drainage system.  

The Williams Street Brook system’s outfall is located in the east bank of 

the Historic Mill River near the wastewater treatment plant entrance.  The 

24‐inch concrete pipe was about 30 percent filled in with silt and 

sediment. It was also observed that the Historic Mill River itself was highly 

silted.  

Upstream, the main trunk line of the drainage system runs cross country 

between Williams Street and Valley Street. There is also a branch of 15‐ 

and 12‐inch drains on Williams Street, which combines with the main 

trunk line on Hockanum Road.  There was no sign of recent street flooding in this area.  

In the wooded wetland area in the flood plain adjacent to the East Levee, several inlets to the stormwater 

system were found, along with a network of drainage ditches.  These shallow ditches convey stormwater from 

upstream field areas during high water events.  The inlets to the stormwater system in this area act as relief for 

the drain during peak flows and also allow flooded areas to drain after rain events have subsided. 

There is a collapsed 42‐inch diameter Massachusetts Department of Transportation (MassDOT) outfall at the 

Connecticut River near Damon Road that is connected to drains in the nearby industrial park and residential 

areas.  The outfall area has fallen into significant disrepair and includes pipes other than the 42‐inch drain.  

Severe bank erosion at the outfall site has sloughed off soil about 50 feet back from the original bank of the 

river.  Approximately 50 yards upstream, a manhole adjacent to Damon Road was inspected and found to be in 

excellent condition.  

Lastly the flood plain area around the Three County Fairgrounds was inspected, including Fair Street, Old Ferry 

Road, and Cross Path Road and assessed for the potential location for stormwater management facilities.   

Photo 2.1  Williams Street Brook Outfall 

Page 30: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐8 

106678‐80349‐03‐11 

2.3.1.2 Existing Conditions Hydraulic Model 

The Bridge Street/Meadows area watershed is approximately 185 acres and is a mixture of industrial, dense 

urban residential, and special conservancy districts.  This area includes the Three County Fairgrounds and 

agricultural land.  Figure 2.2 shows the sub‐drainage area delineations (identified by numbers) and drainage 

systems for the Bridge Street/Meadows area. 

The Bridge Street/Meadows area closed drainage system consists of two main lines, one flowing south and the 

other flowing north.  The dividing line between the south and north systems is at Lincoln Avenue.  The south‐

flowing drain line (Williams Street Brook) ranges in size from 12 to 24 inches in diameter.  It originates on Bridge 

Street (Route 9) and becomes a cross‐country system at the Three County Fairgrounds at Old Ferry Road.  It 

traverses through residential and agricultural land and goes through the East Levee before discharging to the 

Historic Mill River.  The north‐flowing drain line (Day Avenue Brook) ranges in size from 12 to 42 inches in 

diameter.  It originates at Lincoln Avenue and travels cross‐country through an old streambed until the 

intersection of Marshall and Crosby Streets.  At the intersection of Crosby Street and the Norwottuck Rail Trail, 

the drain line converges with a drain line from the industrial park, and then crosses under Interstate Route 91, 

discharging to the Connecticut River at Damon Road via the MassDOT 42‐inch diameter collapsed pipe   

The peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events for each sub‐drainage area can 

be found on Table B.1 in Appendix B.  The pipe capacity analysis for existing conditions found that several pipes 

are under capacity, as shown on the tables in Appendix C.  The results of the pipe capacity analysis are discussed 

in greater depth in the following section. 

2.3.1.3 Preliminary Review of Alternatives 

To address flooding that occurs in the floodplain area between Bridge Street and Route I‐91, including the 

Fairground area, CDM considered three alternatives.   

1. Create a flood storage area upstream of the East Levee near Pomeroy Terrace.  This area currently floods 

when the 24‐inch system is above capacity.  Preliminary modeling indicates that the proposed flood storage 

area would have a surface area of approximately three acres and a 25‐year storm maximum stage depth of 

3.5 feet.  However, this alternative was eliminated from consideration because a field investigation of the 

area by Northampton staff indicates that the proposed flood storage area location is a wetland, as shown on 

Figure 3.1.  CDM has received permission from permitting agencies in Massachusetts in the past to enhance 

the flood storage capabilities of wetlands as a measure to protect properties from extreme flooding; 

however, the Massachusetts Department of Environmental Protection prefers that this not be done.  

Stormwater detention/retention basins are generally designed to protect wetland areas, not to use them as 

basins. 

2. Collect stormwater runoff from sub‐drainage areas 2 and 4 and route the flows north through the existing 

cross‐country drainage system to the existing MassDOT 42‐inch diameter pipe that discharges to the 

Connecticut River.  The additional flow to the north‐flowing drainage system from areas 2 and 4 is 40 cfs.  

The pipe capacity analysis under existing conditions indicates that the 42‐inch diameter pipe is undersized 

and needs to be a 66‐inch diameter pipe.  Similarly, the cross‐country pipes from Lincoln Avenue to Marshall 

Street are undersized under existing conditions and need to be replaced with a 18‐inch to 36‐inch diameter 

drains. Construction of this replacement drainage system would require obtaining easements from all the 

private property owners abutting the pipe.  CDM also considered directing the flows from areas 2 and 4 to 

Bridge Street.  However, Bridge Street is a busy state road (Route 9), whose ground elevation is nearly 10 

feet higher than the ground elevation of the cross‐country pipe.  Thus, because of the differences in the 

ground elevations, it would be difficult to convey flows to the existing 42‐inch diameter pipe via gravity 

flow.   

Page 31: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐9 

106678‐80349‐03‐11 

3. Redirect flows from the Three County Fairgrounds, and sub‐drainage areas 1, 2, and 3 to Old Ferry Road, 

through the airport, to the Connecticut River in order to address the flooding in the floodplain area.  An 

alternative alignment is directing flows to Old Ferry Road, then to Cross Path Road, discharging at the 

Connecticut River.  The total flow collected is 90 cfs and requires a 48‐inch diameter pipe.  The pipe 

alignment from Old Ferry Road to Cross Path Road remains on all public roads, avoiding the need for 

easements at the airport, but it is longer than the pipe alignment through the airport.  Both alignments 

create a new discharge to the Connecticut River.  Despite the logistical and permitting considerations 

associated with this alternative, it achieves the objective of reducing the flooding to the agricultural land 

adjacent to Pomeroy Terrace, while still continuing to provide flows to the existing wetland located adjacent 

to the levee.   

As previously stated, the pipe capacity analysis indicates that the existing MassDOT 42‐inch diameter pipe that 

discharges to the Connecticut River needs to be upsized to a 66‐inch diameter pipe.  Calculations indicate that 

the 48‐inch diameter pipe serving the industrial area just upstream of this pipe should be upsized to a 60‐inch 

diameter pipe.  Similar to the commercial area upstream of Church Street in the King Street area, there are 

opportunities in this industrial area to install on‐site stormwater BMPs to reduce peak stormwater discharges.  

CDM recommends that the property owners in the industrial park manage stormwater on‐site with BMPs to 

reduce flows instead of upsizing the existing 48‐inch diameter pipe.  CDM does recommend that the MassDOT 

upsize the existing 42‐inch diameter outfall to a 66‐inch diameter pipe when they repair the pipe in the near 

future.  Repairing the existing 42‐inch diameter pipe and using the existing parallel 24‐inch diameter pipe does 

not provide sufficient capacity to convey the calculated flows. 

The pipe capacity analysis indicates that other sections of the Bridge Street/Meadows area drainage systems 

need to be upsized to convey future build‐out flows.  In sub‐drainage area 12, the existing 12‐to 18‐inch 

diameter cross‐country system needs to be replaced with 18‐ to 36‐inch diameter pipes.  However, given that 

this system is located in a former streambed, obtaining sufficient cover for those pipes may be difficult. Twin 

pipes or alternative box culvert or oval pipe systems may need to be used here.  In sub‐drainage area 9 the 

existing system in Williams Street needs to be replaced with 18‐ to 24‐inch diameter pipes.  The 24‐inch 

diameter pipe at the downstream end of the Williams Street Brook needs to be upsized to a 42‐inch diameter 

pipe from the outfall at the Historic Mill River to just upstream of Hockunam Road and then upsized to a 30‐inch 

diameter pipe to just upstream of Montview Avenue.  See Section 3.2.3 for a discussion of the recommended 

plan and preliminary cost estimate. 

2.3.2  Elm Street Brook/Florence Area 

2.3.2.1 Site Inspection and Area Description 

Area Description 

The Elm Street Brook watershed includes a mixture of rural/lightly developed land and moderate density 

development including: a large portion of the Florence downtown area, residential areas, Cooley Dickinson 

Hospital, Northampton High School (NHS), and Smith Vocational and Agricultural High School. The brook enters 

a closed drainage system at the MassDOT property on Locust Street and at the Northampton High School and 

ultimately discharges to the Mill River. Flooding currently occurs at the intersection of Elm Street, Milton Street 

and Riverside Drive, along and south of Elm Street west of this intersection, Nutting Avenue, and at the 

intersection of Milton Street and Ormond Drive.  The flooding causes these roads to become impassable at 

times.  The drainage system is shown on Figure 2.3. 

   

Page 32: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

MILL RIVER

MILL RIV

ER

U

CC

L

B

A

S

Z

W

Q

N

M

V

G

T

X

J

R

P

H

I

BB

EE

O

Y

AA

K

D

DD

C

F

E

12’’

10’’

8’’

15’’

10’’

12’’

24’’

8’’

12’’

12’’

12’’

10’’

12’’

24’’

10’’

8’’

8’’

6’’

8’’

10’’

12’’

15’’

10’’

10’’

6’’

10’’

24’’

8’’

18’’

18’’

12’’

18’’

10’’

12’’

10’’

8’’

6’’

10’’

12’’

15’’

12’’

18’’

15’’

48’’

10’’

24’’

12’’

10’’

36’’

12’’

10’’

10’’

18’’

12’’

15’’

12’’

12’’

10’’

30’’

10’’

12’’

36’’

15’’

24’’

8’’

12’’

15’’

10’’

8’’

12’’

8’’

18’’

18’’

10’’

36’’

15’’

12’’

12’’

10’’

8’’

12’’

18’’

12’’

10’’

24’’

12’’

10’’

4’’

15’’

15’’

18’’

8’’

10’’

36’’

12’’

15’’

12’’

12’’

12’’

12’’

12’’

20’’

12’’

18’’

10’’

12’’

10’’

12’’

8’’

10’’

8’’

8’’

8’’

12’’

12’’

10’’

18’’

12’’

12’’

18’’

8’’

8’’

18’’

12’’

10’’

12’’

15’’

15’’

21’’

15’’

8’’

8’’

12’’

10’’

12’’

10’’

10’’

8’’

18’’

18’’

15’’

12’’

12’’

12’’

15’’

12’’

12’’

12’’

8’’

12’’

12’’

12’’

24’’

12’’

12’’

12’’

8’’

8’’

10’’

15’’

12’’

12’’

12’’

12’’

8’’

12’’

21’’

12’’

12’’

24’’

8’’

30’’

12’’

12’’

15’’

12’’

48’’

10’’

15’’

8’’

12’’

12’’

12’’

24’’

12’’

24’’

18’’

12’’

12’’

12’’

15’’

18’’

10’’

12’’

10’’

12’’

8’’

10’’

12’’

12’’

10’’

10’’

8’’

12’’

8’’

8’’

12’’

8’’

10’’

15’’ 10’’

10’’

15’’

15’’

24’’

27’’

12’’

24’’

8’’

12’’

12’’

10’’

12’’

15’’

21’’

15’’

12’’

15’’

18’’

12’’

10’’

18’’

12’’

10’’

15’’

12’’

30’’

15’’

10’’

12’’

18’’

15’’

12’’

12’’

15’’

21’’

12’’

10’’

12’’

12’’

21’’

18’’

12’’

10’’

12’’

12’’

15’’

12’’

15’’

10’’

8’’

12’’

12’’

10’’

12’’

15’’

12’’

15’’

12’’

12’’

33’’

12’’

18’’

18’’

15’’

137

177

275

187

255

177

285

265

167

187

275

196

246

206

265

216

187

295255

167

285

196

246

246

285

187

265

206

275

275

295

255

167

246

187

216

275

236

196

187

305

196

216

265

226

236

295

255

196

246

196

275

167

246

187

246

236

206

236

216

314

167

206

157

255

246

285

255

285

196

236

196

177

187

275

305

196

236

275

216

265

147

324

324

295

206

305

137

157

187

206

157

236

167

285

206

334

157

187

226

265 147

255

196

177

275

167

236

275

255

137

157

265

206

167

206

255

275

255

275

275

157

147

206

246

246

177

246

314

255

216

206

265

236

295

206

196

187

265

226

167

324

216

246

314

226

285

255

226

216

236

305

206

216

295

ASP

ENLA

NE

BRIDGE ROAD

ELMSTREET

PIN

ES

ED

GE

DR

IVE

GA

RF

IELD

ST

RE

ET

FED

ER

AL

ST

RE

ET

NORTH

ELM

STREET

BARDWELLSTREET

ST

RA

W A

VE

NU

E

AS

PE

N L

AN

E

LOCUSTSTREET

NORTHMAINSTREET

ASPENLANE

NO

RT

H E

LM S

TR

EE

T

NO

RT

HM

AP

LE

ST

RE

ET

NO

RT

H E

LM

ST

RE

ET

VERNO

NST

REET

SH

ALL

OW

BR

OO

K D

RIV

E

HATFIE

LD S

TREET

WARDAVENUE

KEAR

NEY

FIEL

DR

OAD

ELM STREET

JAC

KS

ON

ST

RE

ET

WASHINGTO

N

PLACE

ST

ILS

ON

AV

EN

UE

NO

RTH

ELM

ST

RE

ET

WARNER STREET

NORTH ELMSTREETBRANCH

NO

RT

H E

LM

ST

RE

ET

NO

RTH

ELM

STREE

T

CH

ES

TN

UT

ST

RE

ET

PROSPECT

STREET

ELM

ST

RE

ET

DRYADS

GREEN

EXTENSIO

N

PINESTREET

CH

ILD

S P

AR

K R

OA

D A

ELM

STR

EE

T

ARLINGTON

STREET

GOLDENCHAINLANE

PROSPECT STREET

PARADIS

E RO

AD

PAR

KS

TR

EE

T

NO

RTH

ELM

ST

RE

ET

PINES

EDGE

DRIVE

HATFI

ELD S

TREET

BURNCOLT

ROAD

KIMBALL STREET

MARCCIRCLE

DRYADS GREEN

CH

ES

TN

UT

ST

RE

ET

COSMIAN

AVENUE

SANDERSONAVENUE

BRIDGE ROAD

FR

AN

CIS

ST

RE

ET

DANA STREET

GLEASON ROAD

MAIN STREETFLORENCE

CO

OKE

AVE

NU

E

PLYMOUTH STREET

MA

PL

E S

TR

EE

T

LOCUST

STREET

DANA STREET

WARRENSTREET

OAK

STREET

CHILDS PARK ROAD B

CALVINTERRACE

PR

OS

PE

CT

AVE

NU

E

BR

AT

TO

NC

OU

RT

NO

RTH

ELM

STREE

T

HIG

HM

EA

DO

WR

OA

D

SMITH SCHOOLSERVICEROAD

NORTH ELM

STREET

HO

LLY

WO

OD

HE

IGH

TS

BRIDGEROAD

CLO

VE

RD

ALE

ST

RE

ET

MEADOW

STREET

HA

WT

HO

RN

LAN

E

LIBE

RT

Y

ST

RE

ET

KIN

GA

VE

NU

E

LAD

D

AVE

NU

E

ST

ER

LIN

G R

OA

D

TR

INIT

Y R

OW

NO

RT

H E

LM S

TR

EE

T

FLOR

EN

CE

RO

AD

MA

RY

JAN

ELA

NE

FR

AN

CIS

ST

RE

ET

FED

ERA

L STR

EE

T

HO

LLY

WO

OD

HE

IGH

TS

LAURELRIDGEDRIVE

WOOD

AVENUE

BEACONSTREET

HIGH STREET

WILLOWSTREET

SU

N H

ILL

DR

IVE

CO

OK

E AV

EN

UE

BLACKBERRYLANE

KE

YE

S S

TR

EE

T

PAR

KS

TR

EE

T

MAINSTREET

FLORENCE

NONOTUCK STREET

CAROLYN

STREET

EMILY

LANE

WIL

DE

R P

LAC

E

ALLISON STREET

VERONA STREET

GARFIELDAVENUE

ELM STREET

PLY

MO

UT

H A

VE

NU

E

MAPLE

STR

EET

ELMSTREET

RIDGEWOODTERRACE

HATFIELD S

TREET

FORBES

AVENUE

KENSINGTO

N

AVENUE

FAIR

FIE

LD A

VE

NU

E

SU

MN

ER

AV

EN

UE

ORMOND DRIVE

TAYLOR STREET

FR

AN

KLI

N S

TR

EE

T

DICKINSON

STREET

PROSPECTHEIGHTS

MANDELLE ROAD

PINESTREET

JEWETT STREET

STRAWBERRYHILL

DEPOT STREET

HAROLD STREET

RIVE

RS

IDE

DR

IVE

HIN

CK

LEY

ST

RE

ET

MU

RP

HY

TE

RR

AC

E

MA

PLE

ST

RE

ET

NE

W S

TRE

ET

HASTINGS

HEIGHTS

LEENO

TERRACE

CH

ILD

S P

AR

K R

OA

D A

POWELLSTREET

SHEFFIELD LANE

CLA

IRE

AV

EN

UE

DA

NA

ST

RE

ET

HIG

H M

EAD

OW

RO

AD

HO

WE

S S

TR

EE

T

BA

KE

R H

ILL

RO

AD

NONOTUCK STREET

LEX

ING

TON

AVE

NU

E

WEST CENTER STREET

PIO

NE

ER

VALL

EY

DR

IVE

MEADOWBROOK

DRIVE

EMILY LANE

MA

SSA

SO

ITST

REE

T

PINE

STREET

JAMES AVENUE

HAT

FIE

LD S

TR

EE

T

HIGH STREET

GLEASON ROAD

WO

OD

LAW

N A

VE

NU

E

PILGRIM DRIVE

HIN

CK

LEY

ST

RE

ET

MIL

TON

ST

RE

ET

CLEMENT

STREET

SOU

TH

MA

IN

STREE

T

GR

AN

DV

IEW

STR

EE

T

SMITH SCHOOL DRIVE

ARLINGTON

STREET

CH

ES

TN

UT

ST

RE

ET

RIVERSIDE DRIVE

WINSLOW

AVENUE

TERRACE LANE

LAN

DY

AV

EN

UE

DENNISTON PLACE

MO

UN

TAIN

STR

EE

T

BE

RK

SH

IRE

TE

RR

AC

E

NO

RFO

LKAV

EN

UE

HO

SP

ITA

L R

OA

D

RO

E A

VE

NU

E

RIDGEWOODTERRACE

NO

RW

OO

D AV

ENU

E

NU

TT

ING

AVE

NU

E

KEAR

NEY

FIE

LD R

OAD

CHILDS PARK ROAD B

WARNER

STREET

MANN TERRACE

WASHIN

GTON

AVENUE

NO

RT

HM

AP

LES

TR

EE

T

MIDDLESTREET

HARRISO

N AVENUE

FEDERAL

STREET

MA

PLE

WO

OD

TER

RAC

E

MAYNARD R

OAD

BOTTO

M RO

AD

FO

X F

AR

MS

RO

ADLA

KE

ST

RE

ET

CH

ILD

S PA

RK

RO

AD C

HIL

LCR

ES

T D

RIV

E

MEADOWBROOKDRIVE

WI L L O W

L A KE

N SH I C

E P

ON

D

Brough

tons

Brook

Elm St. Brook

SANDY H I

LL

B ROO K

Broughtons Brook

KING ST BROOK

SANDY HIL L

BROOK

Broughtons

Brook

Bro

ugh

tons

Br ook

Broughtons

Brook

Broughtons Brook

Brou g ht o

ns

Bro ok

PINE BROOK

Brou

ghto

ns Broo

k

Broughtons Brook

Elm St. Brook

Broughtons

Brook

Br ought ons Brook

PINE BROOK

\\camgissvr1\Projects\M_Billings\Northampton\mxd\ElmSt_DrainageArea_Map.mxd SCC July 2011

91

91

Drain Pipe

Drain Lateral

Culvert

Drainage Channel

Detention/Retention Basin

LegendDrainage Area Boundary

Area Prone to Flooding

Drain Manhole

Catch Basin/Inlet

Stormwater Outfall

Stormwater Pumping Station

City of NorthamptonStormwater and Flood Control System

Assessment and Utility Plan

Figure 2.3Elm Street Brook/Florence Drainage Areas

Contour

Parcel Boundary

Building

DEP Wetlands

Wetlands (MassGIS) 350 0 350 700175

Feet

Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)

Page 33: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐11 

106678‐80349‐03‐11 

Field Inspection 

On Wednesday, December 22, 2010 CDM conducted a field survey of the Elm Street Brook drainage system. 

The stormwater retention pond located adjacent to Federal Street, south of the Northampton High School 

athletic fields, is fed by a 36‐inch high density polyethylene (HDPE) drain pipe originating on Elm Street. The 

retention pond was found to need some routine maintenance to remove some of the vegetation in the pond. 

Elm Street Brook (Brook) crosses underneath Federal Street and empties into the Mill River through a channel 

that is about 10 feet wide and 4 to 5 feet deep.  The box culvert under Federal Street is in poor condition.  

Headwalls on both sides show advanced degradation; the concrete has chipped away to expose a significant 

amount of rebar.  

At the intersection of Elm and Milton Streets the Brook is conveyed via 36‐inch and 48‐inch culverts under Elm 

Street and the high school grounds, re‐emerging south of the track.  No blockages were present during the time 

of inspection, however some large branches were found in the downstream manhole near the high school 

parking lot.   

Upstream of the 36‐inch and 48‐inch culverts, Elm Street Brook flows along the northern side of Elm Street.  The 

stream is well established and is migrating very close to Elm Street, exposing existing gas lines.  Upstream of this 

section, the brook veers off away from Elm Street towards the Smith Vocational and Agricultural High School’s 

land.  This area was assessed for the potential location of a stormwater management basin.  

The Brook crosses under Route 9 through a culvert and meanders upstream through an area that is generally 

heavily wooded and undeveloped.   

2.3.2.2 Existing Conditions Hydraulic Model 

The Elm Street Brook area watershed is approximately 690 

acres and is primarily a moderately dense residential area with 

small areas of industrial and business development, as well as a 

special conservancy district.  The  

watershed also includes the Smith Vocational and Agricultural 

High School, Cooley Dickenson Hospital and NHS.  Sub‐drainage 

area delineations and drainage systems are shown on Figure 

2.3. 

The drainage system for the Elm Street Brook area watershed 

consists of an extensive network of closed pipes and open 

channels, as shown on Figure 2.3.  Most of the sub‐drainage areas (totaling approximately 535 acres) drain to an 

open channel located along the north side of Elm Street.  This channel crosses under Elm Street in 36‐ and 48‐

inch diameter culverts at NHS.  The 36‐inch culvert conveys flows to a detention basin on school property, which 

outlets under Federal Street to a channel that discharges to the Mill River.  The 48‐inch culvert under the playing 

fields daylights into an open channel on school property that flows under Federal Street, discharging to the same 

channel as the outlet from the detention basin.   

The peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events for each sub‐drainage area can 

be found on Table B.2 in Appendix B.  The pipe capacity analysis for existing conditions found that several pipes 

are under capacity, as shown on the tables in Appendix C.  The results of the pipe capacity analysis are discussed 

in greater depth in the following section. 

Photo 2.2  Elm Street Brook

Page 34: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐12 

106678‐80349‐03‐11 

2.3.2.3 Preliminary Review of Alternatives 

Flooding at Elm Street near Nutting Avenue is the primary flooding issue in this drainage area.  CDM considered 

three alternatives to alleviate flooding in these areas. 

1. Construct flood storage area just downstream of the dirt road on the Smith Vocational and Agricultural High 

School property.  The drainage area tributary to the flood storage area is very large – 478 acres.  Preliminary 

modeling indicates that the surface area of the flood storage area would need to be correspondingly large, 

32 acres, with a four‐foot design flow depth, to have a significant effect on reducing downstream flows. A 

flood storage area of this size is not feasible at this site. 

2. Eliminate the 18‐inch pipe discharge to Elm Street Brook at the intersection of South Main Street and Elm 

Street, and upsize the existing pipe in Federal Street to convey an additional 32 cfs.  The pipe capacity 

analysis under future build‐out conditions for this alternative indicates that the existing 18‐inch diameter 

pipe at the discharge point to the Mill River needs to be upsized to a 54‐inch diameter pipe.  This alternative 

was eliminated because approximately 2,600 feet of pipe in Federal Street needs to be upsized and will not 

provide relief of the localized flooding along Elm Street.  

3. Modify the Elm Street Brook channel to provide relief at the location of flooding.  Analysis of the Elm Street 

Brook channel adjacent to Elm Street indicates that its capacity at its narrowest point is approximately 90 

cfs.  The narrowest section of the channel is closest to the street and results in flooding of Elm Street when 

it overtops.  The 10‐year storm peak rate of runoff entering the channel at this location is 270 cfs.  The 

channel is an environmental resource area that permitting agencies will want to preserve.  Any 

improvements to enlarge the channel to convey more flow must preserve the channels natural path and 

characteristics.  An alternative to enlarging the brook is to install a 7‐foot by 4‐foot box culvert in Elm Street 

to convey brook overflows to Milton Street.  A weir structure installed in the channel can redirect the 

overflows into this culvert.  The existing drainage system in Elm Street will tie into this system.  The existing 

12‐ inch diameter pipe in Milton Street will be replaced with a 48‐inch diameter pipe from Elm Street to 

Federal Street.  The box culvert will tie directly into this pipe and any surcharging will back up into the Elm 

Street Brook channel and flow into the existing 36‐ and 48‐inch culverts that cross under Elm Street.  In 

Federal Street, the existing 18‐inch diameter pipe will be upsized to a 48‐inch pipe and convey flows west to 

a new discharge point.   

A new 72‐inch diameter pipe will be constructed from Federal Street and go through a parking lot, 

discharging upstream of existing wetlands adjacent to the Mill River.  A new discharge point to the Mill River 

protects the existing channel and abutters between Federal Street and the Mill River from flooding.  The 

proposed discharge pipe size is 72 inches to accommodate future flows from Federal Street as part of 

needed future upgrades to the drainage system.  Installing a new pipe at Milton Street provides relief at the 

source of flooding near NHS and will also reduce flows to the detention basin at the high school.  Milton 

Street is scheduled for full‐depth reconstruction, making it more practical to install a new pipe in Milton 

Street and in a shorter section of Federal Street, rather than constructing nearly 2,600 feet of new pipe in 

Federal Street.  

The pipe capacity analysis for the major drain lines in the Elm Street Brook area indicates that several pipes need 

to be enlarged to accommodate 10‐year 24‐hour peak rates of runoff.  In Federal Street, from Warner Street to 

the proposed new 72‐inch diameter discharge point, it is recommended the existing system be replaced with 

new pipes ranging in diameter from 24 to 48 inches.  In addition, in Federal Street, from Vernon Street to the 

existing outfall to the Mill River, the existing 10‐inch diameter pipe needs to be upsized to a 36‐inch diameter 

pipe.  Within sub‐drainage area F, from High Street to Straw Avenue, the existing drainage system should be 

Page 35: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐13 

106678‐80349‐03‐11 

replaced with a new system with diameters ranging from 12 to 36 inches.  See Section 3.2.4 for a discussion of 

the recommended plan and preliminary cost estimate. 

2.3.3  King Street/Market Street/Downtown Area 

2.3.3.1 Site Inspection and Area Description 

Area Description 

The two main trunk lines in the King Street system (i.e., King Street and Market Street Brook systems) have an 

interconnection at Main Street (Rte. 9) underneath the railroad bridge. This interconnection was inspected by 

CDM and City staff.  It was confirmed that the old culvert (carrying sanitary and storm flows) located in the 

Fitzwilly’s Pub parking lot was abandoned and a new diversion structure constructed in Main Street.  The King 

Street main trunk line enters the diversion structure as a 66‐inch pipe and exits the structure as a 60‐ inch pipe.  

A 36‐inch relief pipe in the diversion structure connects to the Market Street Brook system.  

The downtown King Street area has two main drain lines.  The King Street drain line conveys stormwater runoff 

from the highly developed commercial area along Route 5 (King Street) and discharges to the Historic Mill River 

bed.  The Market Street Brook drain line (discussed above) originates along the existing abandoned railroad bed 

in the vicinity of North Street, between Woodmont Road and Highland Avenue, and it discharges to the Historic 

Mill River bed.  The two drainage systems are connected to each other through a diversion structure located on 

Main Street.    These drainage systems are shown on Figure 2.2.  The section of Main Street under the railroad 

bridge and State Street from just north of Main Street to Summer Street are prone to localized flooding. 

Field Inspection 

On Tuesday December 7, 2010 CDM conducted a field survey of the King 

Street area drainage system. 

There are two drainage systems, both of which discharge to the Historic 

Mill River bed: a 60‐inch circular concrete pipe located under the 

railroad bridge off Hockanum Road, and a 66‐inch circular concrete pipe 

located behind the condominiums on Randolph Place near the bikeway.  

The river bed has significant sediment accumulation in areas; however, 

the outfalls had less than 20 percent sediment at the end of the pipes 

and look to be in good condition. 

The field crew met with DPW staff to discuss some specific areas 

where localized flooding had occurred in a recent storm. These areas 

were the North Street underpass between Market and King Streets, 

condominiums on Gothic Street, and State Street at Stoddard Street.  

On North Street, two catch basins at the low point of the underpass 

directly connect to the old Market Street Brook culvert and flooding 

may be due to the need for more frequent catch basin maintenance or 

additional grate. 

Photo 2.4  60‐in Outfall at Hockanum Road

Photo 2.3  66‐in Outfall at Randolph Place

Page 36: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐14 

106678‐80349‐03‐11 

Stoddard Street is experiencing flooding from backwater coming from the wetland behind Stop & Shop.  Heavy 

beaver activity has caused water to pool upstream of the wetlands sediment trap and migrate through 

homeowners’ yards into the street along the side of the bikeway.  

State Street had been observed with large puddles during high‐intensity downpours.   

2.3.3.2 Existing Conditions Hydraulic Model 

The King Street area watershed is approximately 397 acres and is a mixture of industrial, business and urban 

residential districts.  Business and residential development is dense, and includes sections of downtown 

Northampton.  The highly impervious business district is generally centered along King Street.  This drainage 

area also includes portions of the Smith College campus.  Sub‐drainage area delineations and the King Street 

area drainage systems are shown on Figure 2.2. The King Street/Market Street area sub‐systems are identified 

by letters and the Bridge Street/Meadows area sub‐systems are identified by numbers on this figure. 

The King Street closed drainage system consists of two main lines, with the overall drainage area nearly equally 

divided between the two systems.  The King Street drain line ranges in size from 12 inches to 66 inches in 

diameter.  It follows King Street to Merrick Lane, and then travels down Strong Avenue, Pearl Street and 

Pleasant Street before discharging to the Historic Mill River bed.   

The Market Street Brook drain line originates along the existing abandoned railroad bed in the vicinity of North 

Street, between Woodmont Road and Highland Avenue.  It generally follows the railroad bed to Hockanum 

Road, before discharging to the Historic Mill River bed.  It begins as a 36‐inch diameter pipe and then gradually 

increases in size through a varying series of circular, box and arch pipes.  The approximate maximum equivalent 

diameter in the system is 82 inches.  Upstream of the Market Street Brook closed drainage system, there is a 

series of open channels that conveys stormwater runoff from the industrial park to the Market Street Brook 

system.  Additionally, there is a private 12‐inch closed drainage system that originates from a rear section of 

retail businesses along King Street, which also ties into the upstream end of the Market Street Brook system.  At 

the intersection of Main Street and Strong Avenue, there is a diversion structure in the King Street system that 

diverts flows to the Market Street system via a 36‐inch diameter pipe.   

The peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events for each sub‐drainage area can 

be found on Table B.3 in Appendix B.  The pipe capacity analysis for existing conditions found that several pipes 

are undercapacity, as shown on the tables in Appendix C.  The results of the pipe capacity analysis are discussed 

in greater depth in the following section. 

2.3.3.3 Preliminary Review of Alternatives 

Within the King Street area, Church Street is currently prone to localized flooding.  The pipe capacity analysis 

indicates that the existing 21‐inch diameter pipe in this street cannot adequately convey flows under existing 

and future build‐out conditions during a 10‐year 24‐hour storm event.  A 36‐inch diameter pipe along the entire 

street length is needed to relieve flooding on Church Street.   

Upstream of Church Street, the King Street system is slightly undersized for a 10‐year 24‐hour design storm 

(there is an existing 30‐inch drain and a 36‐inch drain is needed).  There are opportunities on largely impervious 

commercial properties in this area to manage stormwater on‐site with Best Management Practices (BMPs), such 

as bioretention street planters, rain gardens, green roofs and porous pavement.  A recommended alternative to 

upsizing the pipe from 30 to 36 inches is to install these types of BMPs to reduce rates and volumes of 

stormwater runoff to the drainage system in this section of King Street.  If the proposed stormwater utility 

program described in Section 5 is adopted, property owners can be provided the option of receiving credit and 

Page 37: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐15 

106678‐80349‐03‐11 

reducing the cost of their utility bills for installing BMPs that reduce stormwater runoff and improve the water 

quality of receiving waters.   

Downstream of Church Street, it is recommended that the King Street system be upsized to a 48‐inch diameter 

pipe at Church Street and gradually increased to a 72‐inch diameter pipe at Trumbull Road.  These pipes were 

sized assuming that BMPs are not installed in the upstream retail properties. 

In State Street near Trumbull Road, the pipe capacity analysis indicates that a 36‐inch diameter pipe is needed to 

alleviate flooding that currently occurs near Trumbull Road.  Upstream of the 36‐inch diameter pipe, it is 

recommended the existing 10‐inch lateral system that ties into State Street be upsized to 12‐ to 24‐inch 

diameter pipes.  In sub‐drainage area M (see Figure 3.1), it is recommended the existing 12‐inch diameter 

system be replaced with a new system that ranges from 12 to 18 inches in diameter. The existing 24‐ to 36‐inch 

diameter pipe in Trumbull Road should be replaced with a new system that ranges from 48 to 54 inches in 

diameter. 

Downstream of Trumbull Road to the diversion manhole, the pipe capacity analysis indicates that the existing 

48‐ to 66‐inch diameter pipe in King Street needs to be upsized to a 78‐inch diameter pipe.  The pipes 

downstream of the diversion manhole are adequate to convey flows and do not need to be upsized.  

In general, the Market Street Brook system has nearly sufficient capacity to convey flows associated with the 10‐

year 24‐hour storm event to the Historic Mill River bed; however, upstream of Bridge Street, the pipes are in 

poor structural condition, which may contribute to flooding problems.  Upstream of North Street, the pipe 

capacity analysis indicates that the 48 inch diameter equivalent system described in Section 2 is adequate to 

convey flows.  However, the 1981 North Industrial Park Drainage Study prepared by Almer Huntley (“Almer 

Huntley report”) on this system noted that the overall condition of this section of pipe is poor. Between Bridge 

Street and North Street, Almer Huntley was not able to inspect the pipe because the manholes were not 

accessible.  They did inspect the pipe just downstream of North Street and just upstream of Bridge Street, and 

found the condition to be poor.  In these areas, the Almer Huntley report documented longitudinal cracks and 

missing bricks and stones.  Between North Street and Bridge Street, the average equivalent pipe diameter is 44 

inches and CDM’s pipe capacity analysis indicates that a 48‐inch diameter pipe is needed to adequately convey 

flows.  Thus, given the poor condition of the existing system and the lack of sufficient capacity in some sections 

of the system, CDM recommends replacing the 44‐ and 48‐inch diameter equivalent pipes with a 48‐inch 

diameter pipe. Repairing and upsizing this section of pipe will reduce the localized flooding that currently occurs 

at North Street. 

Downstream of Bridge Street, Almer Huntley found the existing Market Street Brook system to be in good 

condition.  However, an inspection is recommended to confirm the current condition.  The pipe continues to be 

a composite of pipe diameters, shapes and materials, such as a brick box with a brick arch roof and a wooden 

plank floor.  CDM’s pipe capacity analysis indicates that from Bridge Street to the outfall at the Historic Mill River 

bed the Market Street Brook system has the capacity to convey future build‐out flows and, thus, it is not 

recommended that this section of pipe be upsized.   

The drainage system associated with Market Street currently ties into the Market Street Brook system at Bridge 

Street.  The system begins as a 12‐inch diameter pipe near Walnut Street and gradually increases to a 24‐inch 

diameter pipe at Bridge Street.  The pipe capacity analysis indicates that the drainage system in Market Street is 

insufficient to convey flows during a 10‐year 24‐hour storm.  It is recommended that the system be replaced 

with a 24‐inch diameter pipe beginning at Walnut Street and gradually increased to a 48‐inch diameter pipe 

towards Bridge Street.   

Page 38: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐16 

106678‐80349‐03‐11 

Photo 2.5  Swale behind Austin Circle

Sub‐drainage area D shown on Figure 3.1 is currently served by a private 12‐inch diameter drainage line that 

connects into the Market Street Brook drainage system.  The feasibility of re‐routing this drainage line to the 

King Street system was considered in the future build‐out analysis.  Modeling indicates that redirecting flows 

from sub‐drainage area D from the Market Street Brook system to the King Street system would have a minor 

effect on either system.  For the 10‐year 24‐hour storm event, it accounts for only 3 and 4 percent (6 to 8 cfs) of 

the total flows to the King Street and Market Street Brook systems, respectively.  Thus, if one or both systems 

are enlarged, the drainage system from sub‐drainage area D could be conveyed in either system.   

Overall, the King Street/Market Street business district is highly impervious and is likely to see extensive 

redevelopment over the next 10 to 20 years.  This is a potential area for incorporating green infrastructure/Best 

Management Practices (BMPs), such as green roofs, porous pavement and bioretention systems in the form of 

street planters and rain gardens, during redevelopment. In areas where soils are not conducive for infiltration 

(i.e., clay) these BMPs can still provide stormwater treatment prior to discharge to the storm drain system via an 

underdrain system.  See Section 3.2.5 for a discussion of the recommended plan and preliminary cost estimate. 

2.3.4  Austin Circle/Ryan Road Area 

2.3.4.1 Site Inspection and Area Description 

On Wednesday, December 22, 2010 CDM conducted a field survey 

of the Ryan Road area. Between Austin Circle and the elementary 

school on Ryan Road, there is a drainage ditch that periodically 

overtops and floods into the backyards and basements of residents 

living on Austin Circle.  This flat ditch receives storm flows from 

Ryan Road school, Ryan Road, and the area north of Ryan Road, in 

the vicinity of the Matthew Drive area.  Further downstream in the 

channel, the build‐up of sediment is occurring at the culvert 

crossings at Brierwood Drive and Acrebrook Drive.  These sections 

of channel are in need of sediment removal.  

Matthew Drive is also affected by drainage problems. The top of the 

hill above Matthew Drive has a perched pond that at the time of 

inspection had no freeboard and was discharging to a seasonal 

streambed which flows down the hill, through a resident’s yard, 

onto the street and into a catch basin.  

The culverts under Brierwood Drive and Acrebrook Drive show 

evidence of significant sediment build‐up resulting from ponding 

and slow flow velocities through this area.  The drainage system is 

shown on Figure 2.4.  The drainage ditch between Austin Circle 

and the elementary school, as well as the low‐lying grassed area 

along Ryan Road on the school property, are prone to flooding. 

2.3.4.2 Existing Conditions Hydraulic Model 

The Ryan Road area watershed is approximately 121 acres and is a medium density residential area.  Most of the 

area north of Ryan Road is wooded and undeveloped land, with the exception of one housing subdivision and a 

shooting range.  This wooded area contains a small natural pond that overflows down the hill, causing erosion 

on a property at the corner of Matthew Drive and Gregory Lane.  The Ryan Road Elementary School is located 

within this drainage area.  Sub‐drainage delineations and drainage systems are shown on Figure 2.4. 

Page 39: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

A1

D

G

B

A2

A3

RYAN ROAD

OVERLOOK DRIVE

ACREBROO

K DRIVE

BRIE

RW

OO

D D

RIV

E

BRO

OK

SID

E CIR

CLE

WO

OD

S R

OA

D

SPRUCE HILL AVENUE

DEERFIELD DRIVE

PIONEER KNO

LLS

AUSTIN CIRCLE

GILR

AIN TER

RAC

E

MAT

THE

W D

RIV

E

BIRCH HILL ROAD

LON

GV

IEW

DR

IVE

PEN

CA

SAL D

RIV

E

BEATTIE

DR

IVE

ALAMO COURT

HOLLY COURT

HIC

KOR

Y D

RIV

E

GOLDEN DRIVE

GREGORY L

ANE

TARA CIRCLE

CA

HIL

LAN

E T

ER

RA

CE

FO

RE

ST

GL

EN

DR

IVE

SUMMERFIELD STREET

BR

OO

KS

IDE

CIR

CLE

314

324

334

344

403

383

374

413

423

364

354

305

433

275

452

295

285

462

393

442

393

314

285

423

305

413

442

305

285

275

393

354

324

275

364

275

295

295

285

364

295

285

374

344

334

275

314

295

285

305

305

295

305

433

314

383

285

393

18’’

15’’

24’’

10’’

60’’

16’’

12’’

8’’

30’’

48’’

18’’

12’’

12’’

12’’

12’’

12’’

12’’

12’’

15’’

12’’

15’’

12’’

12’’

15’’

12’’

10’’

12’’

12’’

12’’

18’’

15’’

10’’

12’’

12’’

12’’

12’’

12’’

12’’

12’’

18’’

12’’

12’’

12’’

12’’

12’’

12’’

18’’

8’’

12’’

12’’

12’’

15’’

\\camgissvr1\Projects\M_Billings\Northampton\mxd\RyanRoad_DrainageArea_Map.mxd JD 11/21/2011

Drain Pipe

Drain Lateral

Culvert

Drainage Channel

Detention/Retention Basin

LegendDrainage Area Boundary

Area Prone to Flooding

Drain Manhole

Catch Basin/Inlet

Stormwater Outfall

Stormwater Pumping Station

91

91

City of NorthamptonStormwater and Flood Control System

Assessment and Utility Plan

Figure 2.4Austin Circle/Ryan Road

Drainage Areas

Contour

Parcel Boundary

Building

DEP Wetlands

Wetlands (Delineated by City)

Wetlands (MassGIS) Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)

150 0 150 30075

Feet

Page 40: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐18 

106678‐80349‐03‐11 

Approximately 45 acres of the area north of Ryan Road are routed through the two detention basins associated 

with the housing subdivision.  The remaining northern area sheet flows to Ryan Road.  Stormwater runoff from 

the area north of Ryan Road and from the elementary school building and parking lots is collected in a 15‐inch 

diameter pipe that crosses the elementary school property and discharges upward through a grate that is 

adjacent to an open channel that runs through the backyards of residences on Austin Circle.  Most of the 

remaining drainage area sheet flows directly to this channel.  Local street drainage associated with Brierwood 

and Acrebrook Drives discharges directly into 36‐inch diameter culverts located under these streets. 

The peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events for each sub‐drainage area can 

be found on Table B.4 in Appendix B. 

2.3.4.3 Preliminary Review of Alternatives 

Three alternatives were considered for Ryan Road to address the drainage ditch that periodically overtops and 

floods into the backyards and basements of residents living on Austin Circle.  

1. Install a new street drainage system that intercepts the existing 15‐inch diameter pipe that crosses Ryan 

Road with a 30‐inch diameter relief pipe in Ryan Road.  This system would convey flow to Brierwood Drive 

and then down Brierwood Drive, discharging just upstream of the 36‐inch diameter culvert in Brierwood 

Drive.  A variation of this alternative is intercepting the 15‐inch diameter pipe with a 30‐inch diameter relief 

pipe and crossing diagonally across the elementary school’s athletic fields, discharging just upstream of the 

36‐inch culvert.  This alternative conveys flows from the drainage area north of Ryan Road.  It increases the 

peak flow at the culvert from 21 to 37 cfs, causing an increase in the hydraulic grade line at the culvert by 

approximately one foot.  The 36‐inch diameter culvert would need to be increased in size to lower the grade 

line, which would increase peak rates of runoff to downstream properties. 

2. Upsize the 15‐inch diameter pipe across the elementary school property to a 30‐inch diameter pipe to 

convey runoff from a 25‐year storm event, and provide channel improvements in the channel adjacent to 

Austin Circle.  The improved conveyance of flow through the 30‐inch pipe will result in a downstream 

increase in the hydraulic grade line at the Brierwood Drive culvert.  Thus, this alternative and the first 

alternative do not effectively address the flooding problems that residents of the Austin Circle currently 

experience.  The Brierwood Drive culvert acts as a control and the headwater backs up into the channel, a 

condition the first two alternatives will exacerbate because of the increased flows to the culvert. 

3. Create a flood storage area just upstream of the Brierwood Drive culvert and use the culvert as the outlet 

control for the flood storage area.  With a surface area of approximately 1.3 acres, the flood storage area 

has a total depth of four feet (25‐year storm maximum stage plus one foot of freeboard).  A 24‐inch 

diameter pipe will intercept the 15‐inch diameter pipe at Ryan Road and convey runoff from the drainage 

area north of Ryan Road diagonally across the athletic fields to the flood storage area.  The 15‐inch diameter 

pipe will continue to convey runoff from the elementary school to the existing channel, which will discharge 

into the flood storage area.  This alternative lowers the hydraulic grade line by approximately 0.8 feet, 

resulting in less water backing up into the channel.  It also reduces flows downstream of the culvert by 13 

cfs during a 2‐ year 24‐hour storm event.  The City performed a wetlands survey along the drainage ditch in 

September 2011.  The wetlands survey indicates that there are bordering vegetated wetlands along the 

alignment of the ditch.  The flood storage area has been located to not impact these wetland areas.   

4. This alternative is a variation of Alternative #3.  Because of the high degree of imperviousness of the school 

and the short time of concentration, the runoff from the school was calculated to be 19 cfs for the 25‐year 

storm. The existing 15‐inch diameter pipe would convey this flow to the channel.  However, a channel to 

convey a flow of this magnitude would have a top width of approximately 26 feet.  Thus, instead of installing 

Page 41: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐19 

106678‐80349‐03‐11 

a 24‐inch diameter pipe from Ryan Road across the athletic fields to the flood storage area, the 15‐inch pipe 

through the school property would be upsized to a 30‐inch pipe to collect and convey flows from the 

drainage area north of Ryan Road and from the elementary school, and then turn easterly at the 

southeastern corner of the elementary school, crossing the fields, to the flood storage area.  This option 

significantly reduces the flow to the channel to approximately 10 cfs.  The channel would have a total depth 

of 3 ft and a top width of 21 ft.  

For all four alternatives, channel improvements are recommended to improve conveyance of flows.  Currently, 

the channel between the Brierwood Drive culvert and Acrebrook Drive culvert is not well‐defined and it is 

recommended that a better defined channel be created.  The channel along Austin Circle needs to be cleaned to 

remove brush and other debris.  It is noted that theses channels are on private property, have no easements to 

the City and were created by the developer for these subdivisions.  See Section 3.2.6 for a discussion of the 

recommended plan and preliminary cost estimate. 

2.4  Flood Control Systems 2.4.1  East Levee Description 

The East Levee flood control system is an earthen fill levee and three concrete flood walls, with a total length of 

approximately 4,950 feet and a maximum height of approximately 23 feet.  The width of the crest is about 10 

feet with an 8‐foot‐wide gravel surface and grass‐covered edges. The crest of the levee was constructed at an 

elevation of about El. 131.6 to El. 131.3 NAVD88. 

As shown on Figure 2.1, the earth embankment starts at the intersection of Pomeroy Terrace and Hancock 

Street, continues southeasterly and crosses Ventures Field Road. Beyond the Ventures Field Road crossing, the 

embankment bends and the alignment extends southwesterly and crosses Hockanum Road and meets the 

Northampton Flood Control Pumping Station at the Old Mill River.  From the pumping station, the earth 

embankment bends and crosses the Boston & Maine railroad tracks and then Route 5. Concrete retaining 

walls/abutments are constructed at the railroad crossing and the highway crossing and function as stop‐log 

structures during a potential flood event.  Stop‐logs are stored in corrugated metal storage houses constructed 

next to the crossings. The earth embankment extends westerly beyond Route 5 approximately 500 feet where 

the embankment is in contact with the natural earth high ground.  

Design and record drawings show that the core of the embankment is constructed with a random soil material. 

The embankment material river‐side of the core is an impervious clay‐like blanket material, and a sandy pervious 

material is shown land‐side of the core. Based on the record plans, most of the river‐side slope of the levee was 

presented as a 2.5 horizontal: 1 vertical (2.5H:1V) slope, and a 3H:1V slope at the segment between Ventures 

Field Road and Hockanum Road.  Most of the land‐side slope of the levee was shown to be a 2H:1V slope, and a 

3H:1V slope at the segment between Ventures Field Road and Hockanum Road.   

A toe drain system consisting of 8‐inch to 15‐inch porous concrete pipe in gravel bedding filter trenches exists 

below grade along most of the embankment toe of slope. Intermittent manholes are installed to service the toe 

drain system. The toe drain system collects the seepage water through the levee fill and discharges to the 

stormwater collection system. 

2.4.2  West Levee Description 

The West Levee flood control system consists of earthen fill levee segments and a concrete flood wall, with a 

total length of approximately 2,300 feet. Based on the record plans, the crest of the levee segments is shown to 

be generally 10 feet wide and grass‐covered. The crest of the levee segment north of West Street was 

Page 42: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐20 

106678‐80349‐03‐11 

constructed at elevations ranging from El. 145.5 to El. 144.8 ft NAVD88. The crest of the levee segment south of 

the bridge of the former railroad crossing was constructed at an elevation of about El. 139.1 NAVD88.  The 

embankment is approximately 16 feet high. 

The system begins at high ground near Paradise Pond just northeast of the Paradise Pond Dam, and adjacent to 

College Lane on the property of Smith College (Figure 2.1). The embankment extends southerly, parallel with the 

east bank of the Mill River for about 1,100 feet to the crossing at West Street.  A concrete “T” flood wall extends 

southerly from West Street to the current bike path bridge crossing, formerly the New York, New Haven & 

Hartford Railroad.  The concrete flood wall is about 450 feet long and contacts the stone abutment of the bridge 

of the former railroad.  Most of the length of the wall is about 10 feet above ground surface with a top elevation 

of about El. 140 NAVD88.  The top of the wall and stop‐log structure at the West Street south curb is about El. 

145.3 NAVD88 to match the elevation of the levee and stop‐log retaining wall at the north curb. A concrete flood 

wall and an earth embankment with slight curvature extend from the former railroad crossing abutment in a 

southerly direction about 900 feet to the natural earth abutment and high ground at Hebert Avenue.  This last 

earth embankment segment serves as a dam, which permitted the Mill River to be diverted into the Diversion 

Canal. 

Based on the record drawings, the river‐side slope of the northerly levee segment is shown as a 2.5H:1V slope. 

The levee segment south of the flood wall was built with a 3H:1V slope to the end at Hebert Avenue. The slope 

surface is protected with a one‐foot layer of hand‐placed riprap. Most of the land‐side slope of the levee is 

shown to be a 2H:1V slope. 

A toe drain system consisting of 8‐inch to 10‐inch porous concrete pipe in filtered trenches exists below grade 

along most of the embankment toe of slope. Intermittent manholes are installed to service the toe drain system. 

The construction of the Northampton Flood Control Pumping Station at the East Levee involved the diversion of 

the Mill River, which originally flowed through the City.  Flows originating from the upstream Mill River were 

diverted into the new diversion canal, which begins at the southern portion of the West Levee and directs flow 

to the old Connecticut River Ox Bow, currently called Ox Bow Lake.  The diversion route made it necessary to 

close Grove Street and to build a new bridge with a drop structure where the canal crosses South Street.  

Downstream of the drop structure, the canal bottom is about 35 feet wide, with 3H: 1V side‐slopes. The bottom 

and side slopes are lined with stone riprap.  The canal extends about 8,000 feet beyond the end of the drop 

structure to the discharge point at Ox Bow Lake. 

2.4.3  East and West Levee Inspection 

On December 22, 2010, CDM, accompanied by a representative from the City, performed a general visual 

inspection of the levee system.  A separate, more detailed inspection and evaluation of the levee system is 

currently being performed by others for the USACE.  

In general, the levee systems were found to be in very good condition. Only isolated areas were noted to have 

deficiencies that would usually be corrected with normal maintenance practices. In general, the deficiencies 

included: 

1.  A few trees and thick brush growing near the toe of the river‐side slopes of the levee and at the river‐side 

face of the concrete flood wall at isolated areas; 

2.  Ruts, small depressions on the crest of the earth embankments;  

3.  The grass on the crest of the earth embankments worn by foot traffic exposing bare soil to potential 

erosion;  

Page 43: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐21 

106678‐80349‐03‐11 

4.  Isolated area of missing riprap on the slope of the diversion channel near the end of the West Levee; and  

5.  Potential clogging of the toe drain system as reported by recent USACE inspection.  

Recently, the USACE has inspected the levees on two separate occasions: September 18, 2009 and on December 

10, 2010/January 14, 2011. 

The 2009 inspection found the levees to be in a “Minimally Acceptable” condition, meaning that no deficiencies 

were identified that would prevent the system from performing as intended during a flood event.  The report 

noted deficiencies that included: 

1.  Heavy vegetation, including large bushes, trees, and tall grass, growing on and along the toe of slope of the 

levees; 

2.  Heavy vegetation, including trees, growing in the riprap channel banks of the diversion canal;  

3.  Sections of the levee crown and slope with little to no sod cover due to pedestrian traffic;  

4.  Areas of riprap along the levee toe have been displaced;  

5.  Animal burrows on the crown and slope of the levee;  

6.  Vegetation and sediment in the intake pond at the pump station. 

Similarly, the 2010/2011 inspection found the levees to be in a “Minimally Acceptable” condition.  The report 

noted the same deficiencies as those found during the 2009 inspection.  The inspection also found some spalling 

occurring on the concrete flood walls. The USACE has required that deficiencies be repaired by January 2013 or 

2014, depending on the item. 

2.4.4  East/West Levee Recommended Improvements 

Based on the visual inspection of the East and West Levees performed by CDM, we recommend the following 

activities that improve the overall conditions of the levees, but do not alter the current design.  

Cut and clear trees and thick brush on the levee and at least 15 feet beyond the abutments and at the toe 

of the levee.  This is the current (new) USACE requirements.  The removal of the trees greater than four 

inches in diameter and any planned excavation of roots should be designed by a qualified levee/dam 

engineer.  Holes should be filled with low‐permeability fill on the river‐side slope and compacted fill on 

the land‐side slope. 

Remove burrowing animals and backfill holes with compacted fill.  Alternatively, flowable fill could be 

used to fill the hole.  The material may have to be rodded to force the mix further into the hole. After the 

mix is installed, the upper 6 in. +/‐ of the hole should be backfilled with soil and seeded to promote grass 

growth 

Repair areas of sparse vegetation and small depressions on the crest and land‐side slope by establishing a 

healthy stand of grass to prevent future erosion.  Continue to monitor for new bare spots, and maintain 

grass since the crest of the levee system is used for hiking/walking by the public.  

Potential clogging of the toe drain system at the land‐side toe of the embankments should be 

investigated, and sediment should be removed from the toe drain pipe and manholes. 

Page 44: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐22 

106678‐80349‐03‐11 

Remove the salt shed located against the land‐side face of the concrete flood wall of the west levee 

system at the physical plant property of Smith College. 

Update the Operation and Maintenance Manual to include inspection schedules, annual training, and 

operational and maintenance procedures required to ensure satisfactory operation of the levee system 

to reduce the potential for deterioration to the facility.  

When flood control levee system accreditation is required, follow the general guidelines outlined in the 

memo in Appendix A in accordance with CFR 65.10. 

These recommendations will require design by a professional engineer, application for applicable permits, and 

construction by a contractor experienced in levee repair.  CDM also recommends the following activities be 

undertaken on a regular or yearly basis.   

Regular maintenance activities should be performed at least twice a year or as conditions warrant from 

the Spring to Fall seasons to control and limit growth of vegetation on the levee and the banks of the 

diversion canal. 

Monitor areas for dislodged riprap, and replace riprap stones to protect exposed embankment soils. 

Annual training to responsible staff for erection of flood control stop log structures. 

The 2009 and 2010/2011 inspections made similar recommendations for repairing the levees.   

Excess vegetation should be removed and vegetative growth controlled in the long term with a 

maintenance program.   

Sod should be reestablished on the bare areas of the levee crown and maintained. 

Animal borrows should be excavated and backfilled, and an animal control program established. 

Areas of missing riprap should be replaced with new riprap. 

The toe drain system should be inspected by remote camera every five years. 

The intake pond at the pump station should be cleared of vegetation.   

In addition, the 2010/2011 USACE Report identified several system data gaps that will require extensive 

engineering to be completed by January 2014. The most notable system data gaps include: 

Recent topographic survey information and comparison to the design height/available freeboard;  

Hydraulic and hydrologic analyses of the entire flood control system;  

Seepage and slope stability analyses for the dikes, floodwalls and diversion canal; 

Settlement analyses for the dike, pumping station, and floodwalls;  

Confirmation with additional test boring that the “artificial fill” was removed down to the moderately 

impervious formation prior to constructing the dike near Smith College; and 

Pipe inspection reports for all pipes that pass through or under the flood control system. 

Page 45: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐23 

106678‐80349‐03‐11 

For flood control projects to be recognized by FEMA on the NFIP maps, adequate evidence must be provided 

showing the flood control system provides reasonable assurance that protection from the base flood exists in 

accordance with CFR 65.10. The accreditation process with respect to the stability of the earthen embankment 

levees and flood walls includes: 

A topographic survey of the system to confirm system geometry and the 3‐foot freeboard requirement ; 

A subsurface exploration program to evaluate the composition and in‐situ strength of embankment and 

foundation materials; 

Evaluating erosion protection from currents and/or wave action; 

Embankment and foundation stability and seepage analyses of the earthen embankments in accordance 

with USACE EM‐1110‐2‐1913, Design and Construction of Levees; 

Stability and seepage analyses of the flood walls  in accordance with the USACE Phase II Interim Guidance 

for Evaluating Existing I‐Walls, dated October 25, 2006; and 

Settlement evaluations to assess the potential and magnitude of loss of freeboard. 

Several of the system data gaps that have been identified by the USACE are consistent with the data 

requirements (shown above) for the accreditation process.  Data gap analyses to be completed for the USACE 

should also include all scope items that are needed for FEMA accreditation.  

2.4.5  Northampton Flood Control Pumping Station – Hockanum Road – Inspection  

The Northampton Flood Control Pumping Station was constructed in 1940 by the USACE as part of the 

Northampton Flood Control System in conjunction with the Connecticut River Flood Control Project.  It is located 

on the Old Mill River approximately 1.4 miles upstream of the 

confluence with the Connecticut River, and provides flood 

protection for a major portion of the City, including the downtown 

business district.  Stormwater flow during normal river level is by 

gravity.  The primary function of the pumping station is to pump 

stormwater through the levee when the Connecticut River is in 

flood stage.  The pumping station is currently manually operated 

by DPW employees.   

The pumping station is a brick building constructed between two 

earth embankments of the levee with interconnecting concrete 

counterfort flood walls.  It houses four pumps: three 48‐inch 

propeller pumps that can pump a total of 150,000 gpm, two 

powered by gasoline engines and one powered by diesel engine; 

and a single 16‐inch Worthington trash pump that is designed to pass up to 6‐inch diameter solids, powered by 

an electric motor.  When flood stage is reached, stormwater is diverted from the gravity flow chamber to the 

pumping chambers using two electrically operated sluice gates.  While in operation, the pump inlet chambers 

are protected from large debris by two trash racks located upstream of the inlet sluice gate.  The pumping 

station includes a gasoline fueled emergency standby generator if the main power feeder fails.  The standby 

generator is sized to provide power for the 16‐inch pump, valve operators and lighting. 

Photo 2.6  Northampton Flood Control Pumping Station 

Page 46: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐24 

106678‐80349‐03‐11 

CDM accompanied Northampton staff on field inspections of the Northampton Flood Control and Stormwater 

Pumping Stations. 

Interviews with DPW staff and inspection of the Northampton Flood Control Pumping Station revealed that 

there are only minor imminent mechanical problems with the pumping equipment and the drives.  The major 

issue at the station is that it is manually operated, and it must be monitored continuously when operating or 

when operation may be expected to commence.  Other deficiencies noted during the inspection include: 

1.  Influent Screen Area: Access for a portable mechanical device to reach and clean the upstream face of the 

influent screens is poor because of the configuration of the screen structure.  In addition, raising and 

lowering of the existing screens is a manual operation, and is potentially dangerous to City workers.  The 

screens are left lowered in place throughout times of the year when the station may need to operate.  This 

causes debris to be collected, even when pumps are not operating. 

2.  Sluice Gates: The City workers are concerned that the operators for the main sluice gates may not work 

reliably in electric mode.  If they fail to work, opening the gates manually will be a lengthy operation for City 

workers.  

3.  Standby Generator: Because of safety concerns, gasoline‐powered standby generators are no longer used; 

they are typically fueled by diesel, natural gas, or propane.  In addition, current codes no longer allow 

standby generators to be cooled by municipal water supplies because of reliability concerns.  The City 

currently uses its water supply to cool the generator, which could fail during a flooding situation.  

In general, the pumping station is over 70 years old and at this advanced age, the City runs the increased risk 

that the pumping station will not operate reliably under flood conditions.  In addition, because of the age of the 

pumping station, the availability of repair parts is questionable.  The City runs the risk of having significant 

downtime at the pumping station, while the City searches for, or possibly fabricates, repair parts.  Thus, CDM 

recommends the City take a proactive approach to improve the reliability of the pumping station by 

implementing the recommended improvements described in the following section. 

2.4.5.1 Recommended Improvements 

If the City opts to keep the existing facility and only repair/replace the deficiencies identified during the 

inspection to potentially save money, CDM recommends the following activities in order of importance. 

1.  Replace both of the electric motor‐operated sluice gate operators because of the concerns over their 

current reliability.   

2.  Rework the influent screen area.   

a.  The existing screens with their hazardous manual operators should be removed. 

b.  Install a mechanically‐cleaned screen because the screens need to be cleaned frequently during station 

operation.  The screens should be coarse type, with 3‐to 4‐inch clear openings.  Screen width is 8 feet.  

c.  For reliability, a bypass manually cleaned screen should be provided in case the mechanically cleaned 

screen experiences operational problems.   

d.  The screen area should also be made easily accessible to catch basin cleaning type equipment so that 

objects too large for the mechanically cleaned screen can be removed. 

Page 47: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐25 

106678‐80349‐03‐11 

e.  Modification of the influent screen structure will require demolition of the existing screen structure and 

construction of a new structure. 

3.  Replace the existing gasoline‐engine‐driven standby generator.  The generator should be replaced with a 

radiator‐cooled diesel‐engine‐driven generator capable of running all building systems (lights, heat, gate 

operators, sump pump, etc.) plus the electric motor‐driven pump.  We do not recommend a natural gas 

engine because the engine needs to be physically larger than a diesel engine in order to get the required 

horsepower, and is therefore more expensive.  Also, in a flooding situation, the supply of natural gas may be 

cut off, leaving the station inoperable. 

4.  Replace the existing electric‐motor‐driven pump.  Because of its advanced age, it may not operate reliably in 

the future.  Thus, it should be replaced with a new pump that has the same capacity of the existing 50 

horsepower pump. 

5.  Because of their age, replace the three existing stormwater pumps, including their engine drives and right‐

angle gear drives in‐ kind, with three new diesel‐engine‐driven pumps.  Similar to the generator, the 

replacement engine drives must be radiator cooled with unit mounted radiators.  This will require major 

revisions to the ventilation and air handling systems in the building to obtain adequate ventilation air and 

exhaust the heated air outdoors.   

6.  In conjunction with replacement of the pumps, the existing pump discharge piping, isolation valves, and 

outlet flap valves should be replaced because the pipe will need to be reworked to align with replacement 

pumps. 

7.  Existing electrical, lighting, and ventilation systems should be replaced because of the age of these systems. 

8.  Upgrade the pumping station building to meet current accessibility and egress requirements.  Implementing 

the recommendations listed above, such as replacement of the ventilation system, will result in 

modifications to the physical structure of the building.  These changes to the building will trigger compliance 

with current building codes for accessibility and egress.  

9.  Assuming the preceding recommendations are implemented, new monitoring and automated control 

systems should be provided to allow the station to operate automatically with minimal supervision to 

reduce personnel costs for pumping station operation.  This task will require replacement or upgrade of 

existing level monitors on the Connecticut River side of the dike, as well as in the influent channel and pump 

wells.  A Supervisory Control and Data Acquisition (SCADA) type panel should be provided to coordinate 

monitoring with control of the pumps. 

Alternatively, based on a field evaluation of the Northampton Flood Control Pumping Station, CDM recommends 

replacing the existing pumping station with an entirely new facility.  The new facility will replace the engine‐

driven pumps and standby generator in‐kind with three new diesel engines, right angle gear drives, stormwater 

pumps, and one standby generator. Because the pump engines are the only source of power for operation of the 

pumps, they will be evaluated as continuous duty application, requiring a high degree of emissions control (EPA 

Tier 4).  The design of the new facility will need to take into account the potential for increased flows to the 

pumping station due to the recommended upgrades in the upstream drainage systems.  The cost estimate 

provided in this report assumes a new facility. 

2.4.6  West Street Stormwater Pumping Station– Inspection  

The West Street Stormwater Pumping Station is located on the Mill River, adjacent to the West Street river 

crossing.  Similar to the Northampton Flood Control Pumping Station, its primary function is to divert 

Page 48: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐26 

106678‐80349‐03‐11 

Photo 2.7  West Street Pumping Station 

stormwater that collects behind the levee and flood wall through the levee when the Mill River is in flood stage.  

The manually‐operated West Street Stormwater Pumping Station serves a 14.6‐acre area inside the levee that is 

a low point for collection of stormwater runoff.   

The pumping station is an on‐grade structure, with exterior dimensions of approximately 12 by 9 feet.  The 

building houses one engine‐driven self‐priming type pump.  The pumping station was built after the flood of 

1955 in 1957.  

The pump is connected to the West Street stormwater collection system by a 6‐inch steel suction pipe that rises 

just outside the building from a manhole.  The self‐priming pump is a 6‐inch Rex Chainbelt.  No rating data plate 

could be identified, but its capacity is likely to be approximately 800 to 1,000 gpm.  The pump is driven by a 

spark‐ignited engine power unit (assembled by Hanlon Waters) fueled by propane.  The propane fuel tank is a 

300‐lb propane bottle located outside the station.  

CDM accompanied Northampton staff on a field inspection of the West Street pumping station. 

No obvious deficiencies at the West Street Pumping Station were 

observed during the inspection.  However, the future reliability of 

the pumping station is questionable because it is rarely used.   

Near the pumping station, two stormwater collection system 

outlets were observed.  They discharge into the river, one higher 

than the other, and both were built into the retaining wall along 

the river bank.  Both have cast iron flap valves, which appear to 

open freely.  The lower of the two flap valves appears to be new, 

and uses a resilient seat.  However, the seat appears to have 

swollen to the point that the flap cannot close onto its seat.  The flap 

cannot be forced manually to full closure, resulting in flooding of the 

stormwater collection system tributary to this flap gate when the river elevation is high.  Thus, the leakage may 

fully negate the capacity of the pumping station. 

Similar to the Northampton Flood Control Pumping Station, this pumping station is manually operated.  When 

the station must be operated, an operator must be on‐site at all times.  Because the pumping station is not 

automated, determination of the need to operate the pumping station is dependent upon visual observations of 

flooding in the storm system on West Street.  

2.4.6.1 Recommended Improvements 

The West Street Stormwater Pumping Station does not have the capacity to discharge adequate flow to prevent 

flooding of the West Street drainage area.  Assuming that utility power is not available during flooding 

conditions, a pump at this location should be engine‐driven.  Instead of installing a permanent pump at this 

location, CDM recommends the City purchase a portable diesel‐engine driven pump with capacity of 

approximately 6,000 gpm, which can be brought to the site and set up temporarily for flood control.   

2.5  River Erosion 2.5.1  River Road – Mill River 

The proposed River Road Retaining Wall/Floodwall improvements are located in the Leeds Village section of 

Northampton (see Figure 2.1 and Photo 1.5).  Flows from the Mill River have scoured and undercut significant 

sections of the wall, and surface runoff has compromised the integrity of the upper portions of the wall.  In 

Page 49: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐27 

106678‐80349‐03‐11 

Photo 2.8  Federal Street Flood Wall 

Photo 2.9  Roberts Meadow Brook Channel 

addition, the Williamsburg sanitary sewer interceptor is located within River Road and is in danger of collapsing 

due to river erosion.  The City is proposing to remove the existing stone masonry wall and replace it with a cast‐

in‐place concrete retaining wall that will protect the road and sewer from the 100‐year flood event. 

2.5.2  Federal Street Flood Wall 

The Federal Street retaining wall improvements are proposed along 

the Mill River in the vicinity of Vernon Street and Ward Avenue (see 

Figure 2.1 and Photo 2.8).  The purpose of this project is to protect a 

30‐inch sewer interceptor.  Erosion is occurring along the sharp bank 

angle, which is leading to the exposure of the interceptor.   

2.5.3  Roberts Meadow Brook Channel  

The Roberts Meadow Brook channel is located between the Lower 

Roberts Meadow Reservoir Dam and Reservoir Road in Leeds (see Figure 2.1 

and Photo 2.9).  The channel is comprised primarily of dry masonry sidewalls 

and a naturalized boulder and cobble bottom.  High flow events 

have resulted in significant erosion of the channel sidewalls, which is 

threatening the dwellings and driveways of adjacent private 

properties.  The City has proposed to extend the floodwall upstream 

from the Reservoir Road bridge to the critical area in the channel.  

The new floodwall would be a cast‐in‐place concrete retaining wall 

with sufficient height to protect adjacent properties from the 100‐

year flood event.   

2.6  Current Operational Cost and Funding Levels 2.6.1  Regulatory Compliance 

The City is currently complying with all requirements of the 2003 NPDES Phase II permit.  The City maintains a 

public education and participation program, which includes educational brochures, stormwater education in the 

high school, availability of rain barrels, storm drain labeling, outfall monitoring by volunteer groups, household 

hazardous waste collection days, and community cleanups.  The storm drain maps, with outfalls, have been put 

into a Geographic Information System (GIS) and are continuously updated.  In 2004, the City approved both the 

Illicit Connections and Discharges to the Municipal Storm Drain System Ordinance and the Erosion and Sediment 

Control and Post‐Construction Stormwater Management Ordinance.  These ordinances are currently enforced.  

The City’s street sweeping program sweeps all wards once per year and all streets in the downtown business 

district every week from mid‐April to June.  The City’s 3,750 catch basins are cleaned once per year, generating 

20 tons of debris.  In total, the City has spent in excess of $l00,000 annually on implementing the requirements 

of this permit.   

2.6.2  Stormwater Drainage Operations Staffing 

Operation and maintenance activities associated with stormwater drainage operations fall mainly under the 

Streets Division and the Sewer/Drain Division.  Currently, funds to pay the compensation for sewer and drain 

staff are allocated 2/3 from the sewer Enterprise Fund and 1/3 from the General Fund. Compensation for 

Page 50: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 2    Existing Conditions  

2‐28 

106678‐80349‐03‐11 

overtime is split 50 percent between the enterprise and General Funds.  Storm drain materials and equipment‐ 

related costs are funded through the General Fund.  

Generally, the current staffing is as follows: 

Streets Division: Three staff spend about half‐time on street sweeping operations. 

Sewer/Drain Division:  Nine staff provide maintenance activities on the City sewer and drain systems, including 

television inspections of drains, cleaning catch basins with a clamshell or vactor truck and infrastructure repairs. 

Vehicle Maintenance:  One vehicle maintenance staff person is assigned to vehicle maintenance on sweepers 

and drain‐related equipment. 

Regulatory Compliance: Currently, one part‐time planner is mainly responsible for compliance with the NPDES 

Phase II permit.  He is assisted by the GIS Coordinator, when compliance requires GIS mapping.  Other 

engineering and scientist staff may provide technical support as needed. The part‐time planner is funded 

through the General Fund.  Other technical staff are funded through various Enterprise Funds and the General 

Fund. 

2.6.3  Flood Control Operations Staffing 

Flood control activities are paid for through the General Fund.  Labor associated with flood control activities is 

paid for through the Sewer Enterprise Fund for straight time and the General Fund for overtime.  Staffing for 

flood control activities are assigned to the Wastewater Treatment Division.  Typically, the staff includes two to 

three flood control technicians plus one supervisor.  During flooding situations, staff from other departments 

participate in flood control activities as needed, such as erecting the West Street flood wall.  

 

 

 

 

Page 51: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

3‐1 

106678‐80349‐03‐11 

Section 3 ‐ Capital Improvements Plan and Operational Budget Requirements

3.1  Introduction This section summarizes the recommended drainage system and flood control improvements plan, 

including construction phasing, additional television inspection needs for final design, cost estimates 

and schedules.  It also includes the following proposed river erosion control projects:  River Road 

floodwall improvements, Roberts Meadow Brook channel improvements, and Federal Street 

retaining wall improvements.   

The recommended drainage system improvements have been phased as follows:   

Phase 1 and 2 projects – needed to address high priority flooding problems or other issues, 

such as pipe collapses; and 

Phase 3 and 4 projects – are in areas with less flooding problems, designed to provide capacity 

to control 10‐year 24‐hour storm peak rates of runoff. 

3.2  Summary of Recommended Plan Figures 3.1 through 3.3 illustrate the recommended plans for each of the project areas.  These maps 

also provide locations of City‐owned property where there are opportunities for the City to install 

stormwater Best Management Practices (BMPs)/green design facilities to reduce stormwater runoff 

to drainage systems, improve the water quality of receiving waters and comply with the upcoming 

new Environmental Protection Agency (EPA) Municipal Separate Storm System (MS4) permit. 

3.2.1  Street Improvement Projects 

The DPW maintains a conditional assessment database of all city streets pavement.  This pavement 

condition database is updated yearly.  The purpose of the database is to determine the priority listing 

for street work ranging from crack sealing, to asphalt mill and overlay, to full depth reconstruction.  

Funding for roadway repair projects is primarily provided by the state under the Chapter 90 program.  

Chapter 90 funding provides for the cost of asphalt resurfacing.  The construction funding for new 

sewer lines that may be needed as part of a street reconstruction project is provided through the 

City’s Sewer Enterprise Fund.  If new water lines are required, the funding is provided by the Water 

Enterprise Fund.  Historically, the City has funded drainage improvements through the General Fund, 

as determined by the City Council through the capital improvements process.  Because of the lack of 

available monies in the General Fund, funding for storm drain construction has been extremely 

limited. The DPW reports that a $62,000 budget line item for storm drain construction was removed 

from the budget in 2010 as part of a DPW budget cut.  If a street is identified as a high priority and in 

need of reconstruction, and funding is not available for construction of a new drainage system, that 

street is removed from the priority paving list.   A good example of this funding dilemma is Milton 

Street, a street that is desperately in need of reconstruction, but is on hold because of the lack of 

funding to install a new drainage system. 

Page 52: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Alignment #2New 48" RCP Drain

Alignment #1New 48" RCP Drain

CONNECTICUT RIVER

MILL RIVER

CONNECTICUT RIVERManage StormwaterOn-Site with BMPs

Manage StormwaterOn-Site with BMPs

Northampton Flood ControlPumping Station

West StreetStormwater

Pumping Station

Phase 2 Northampton FloodControl Pumping Station

Phase 1 and 2Levee Improvements

Phase 1 and 2Levee Improvements

Phase 2 Portable StormwaterPumping Station

66"

Nelson/Nygaard Design Charrette Area

Approximate Wetland Boundary Estimated by City

HISTORIC M

ILL RIVE

R

I

Fairgrounds

6’’

12’’

36’’

15’’

12’’

12’’

12’’

6’’

8’’

10’’

36’’

10’’

12’’

8’’

12’’

12’’

12’’

6’’

18’’

12’’

12’’

10’’

14’’

12’’

12’’

12’’

36’’

12’’

24’’

12’’

12’’

12’’

12’’

12’’

12’’

12’’

8’’

12’’

12’’

12’’

12’’

30’’

21’’

12’’

12’’

12’’

10’’

12’’

18’’

12’’

12’’

12’’

12’’

12’’

24’’

12’’

18’’

24’’

12’’

12’’

10’’

12’’

10’’

18’’12’’

15’’

18’’

12’’

10’’

6’’

12’’

6’’

21’’

48’’

15’’

15’’

12’’

15’’

8’’

6’’

36’’

12’’

10’’

12’’

12’’

36’’

12’’

10’’

21’’

6’’

18’’

12’’

54’’

54’’

24’’

18’’

8’’

10’’

14’’

12’’

18’’

15’’

12’’

18’’

24’’

15’’

24’’

36’’

12’’

6’’

12’’

24’’

12’’

30’’8’’

12’’

12’’

18’’

12’’

8’’

36’’

8’’

6’’

18’’

15’’

12’’

18’’

24’’

8’’

36’’

15’’

48’’

15’’

12’’

10’’

16’’

60’’

18’’

18’’

8’’

18’’

12’’

12’’

12’’

15’’

12’’

18’’

12’’

12’’

6’’

24’’

36’’

21’’

42’’

12’’

30’’

18’’

18’’

64’’

12’’

8’’

18’’

18’’

12’’

8’’

12’’

15’’

10’’

18’’

15’’

8’’

15’’

12’’

10’’

18’’

24’’

18’’

12’’

8’’

8’’

18’’

15’’

8’’

12’’

15’’

12’’

21’’

18’’

18’’

18’’

15’’

12’’

21’’

12’’

12’’

30’’

12’’

44’’

8’’

10’’

15’’

12’’

36’’

18’’

10’’

12’’

12’’

60’’10’’

10’’

12’’

12’’

15’’

15’’

10’’

10’’

18’’

15’’

12’’

24’’

8’’

12’’

25’’

36’’

10’’

10’’

8’’

54’’

15’’

66’’

10’’

12’’

12’’

15’’

48’’

6’’

12’’

12’’

54’’

12’’

36’’

12’’

12’’

10’’

10’’

12’’

15’’

15’’

12’’

12’’

10’’

18’’

16’’

12’’

8’’

12’’

12’’

15’’

12’’

10’’

15’’

15’’

12’’

15’’

12’’

8’’

18’’

12’’

10’’

18’’

24’’

12’’

18’’

6’’

10’’

15’’

24’’

24’’

12’’

18’’

30’’

8’’

12’’

10’’

15’’

10’’

15’’

12’’

18’’

12’’

21’’

21’’

10’’

12’’

12’’

24’’

18’’

15’’

15’’

18’’

12’’

10’’

24’’

8’’

12’’

12’’

12’’

12’’

18’’

24’’

36’’

15’’

10’’

12’’

30’’

12’’

15’’

12’’

12’’

24’’12’’

24’’

12’’

8’’

12’’

82’’

12’’

6’’

15’’

10’’

15’’18

’’

48’’

30’’

6’’

15’’

16’’

18’’

12’’

10’’

12’’

12’’

24’’

48’’

36’’

12’’

12’’

12’’

12’’

15’’

66’’

18’’

15’’

12’’

15’’

36’’

15’’

12’’

15’’

12’’

12’’

10’’

24’’

60’’

15’’

15’’

12’’

24’’

6’’

44’’

72’’

24’’

12’’

118

127

118

246

196

177

127

127

157

147

137

147

118

255

137

127

137

118

177

177

118

137

118

118

157

137

127

147

137

147

147

167

137

167

157

118

147

118

127

127

187

137

147

147

118

137

118

118

177

108

147

137

187

127

127

177

118

137

127

108

137

127

137

147

147

118

108

118

275

118

137

147

147

137

118

177

157

127

167

118

127

187

127

137

137

147

127

157

167

118

108

147

127

147

147

127

127

157

137

118

118

118

127

147

147

127

118

157

177

127

108

108

118

196

157

118

127

147

127

118

147

157

118

147

118

137

177

167

265

177

147

127

108

118

167

147

236

118

226

118

216

137

157

167

137

206

137

157

118

118

127

127

137

118

118

HOLYOKE STREET

BRIDG

E STREET

MAIN

STREET

SOUTH STREET

CEMETERY ROAD

HA

MP

TO

NG

AR

DE

ND

RIV

E

CENTERSTREET

ELMSTREET

WE

ST

ST

RE

ET

FRUITSTREET

STA

TE

ST

RE

ET

HOCKANUM ROAD

CONZ STREET

GREEN

STREET

SCHOOLSTREET

PARSONS

STREET

SO

UT

H

ST

RE

ET

NORTH STREET

UNION

STREET

NE

W

SO

UT

H

ST

RE

ET

PR

OS

PE

CT

ST

RE

ET

DAMON ROAD

KIN

GS

TR

EE

T

BARRETTSTREET

FAIRGROUNDSROAD

BR

IDG

ES

TR

EE

TP

OM

ER

OY

TER

RA

CE

BAN

CR

OFT

RO

AD

PRO

SPE

CT S

TRE

ET

ST

AT

ES

TR

EE

T

MO

UN

T T

OM

RO

AD

CO

LLEG

E LA

NE

WILLIA

MS

ST

RE

ET

INDUSTRIAL DRIVE

HE

NS

HA

W A

VE

NU

E

CONZSTREET

TRUMBULL ROAD

BRID

GE

STR

EET

RO

UN

D H

ILL

RO

AD

WARFIELD

PLACE

BELMO

NT

AVENUE

MARSHALLSTREET

ST

AT

E S

TR

EE

T

RA

ILRO

AD

AVE

NU

E

BEDFORD

TERRACE

HAW

LEY

STREET

WO

OD

MO

NT R

OA

D

BARRETTSTREET

FINN STREETFINN

STREET

MUNROESTREET

MONTVIEW AVENUE

NORTH KING

STREET

BRIGHT STREET

HUBBARDAVENUE

CR

ES

CE

NT

ST

RE

ET

KINGSLE

Y AVENUE

RUSSELL STREET

FO

RT

ST

RE

ET

STA

TE

ST

RE

ET

LANE PLANT ROAD

HAM

PTO

N M

AN

OR

DR

IVE

CROSBY STREET

KIN

G

ST

RE

ET

ELM STREET

SHERMANAVENUE

INDUSTRIAL

DRIVEROTARY

WR

IGH

TAV

ENU

E

CR

AF

TS

AV

EN

UE

BAY ROAD

HILLSIDEROAD

CR

OS

SPA

TH

RO

AD

VALL

EYST

REE

T

HAM

PTO

NAV

ENU

E

HAYES

AVENUE

BA

Y R

OA

D

WOODBINE

AVENUE

HIGHLAND AVENUE

CHURCHSTREET

ED

WA

RD

SS

QU

AR

E

PH

EA

SA

NT

HIL

L D

RIV

E

MYRTLE

STREET

SMITH COLLEGE DRIVE

FAIR STREET

PH

EA

SA

NT

HIL

L D

RIV

E

CE

ME

TE

RY

RO

AD

GRAVES

AVENUE

NO

RTH

KIN

G

ST

RE

ET

HENRY STR

EET

IND

USTR

IAL

DR

IVE

SUMMER

STREET WALNUT

STREET

DE

NIS

E C

OU

RT

BATES

STRE

ET

ALD

RIC

H

ST

RE

ET

REVELL AVENUE

DYKE ROAD

CRESCENT STREET

BUTLER

PLACE

NORTHERN

AVENUE

HAMPSHIRE HEIGHTS

KIN

G

ST

RE

ET

BAR

RET

TPL

ACE

KIN

G

ST

RE

ET

RIVER

BANK R

OAD

WOODMONT

ROAD

LINDEN

STREET

MUNROESTREET

KIN

GS

HIG

HW

AY

MAN

HAN

STREET

SERVICE CENTER

CLARK SCHOOL DRIVE

GRANT AVENUE

COLUMBUS

AVENUE

FO

RT

HILL T

ER

RA

CE

PERKINS

AVENUE

HE

BE

RT

AVE

NU

E

BAY ROAD

BRIDGE ROAD

PHILLIPS

PLACE

FAIRVIEWAVENUE

STODDARD

STREET

OLD FERRY ROAD

OLD

FE

RR

Y R

OA

D

CLARK

AVENUE

COOLIDGE AVENUE

GOTHICSTREET

LINCOLN

AVENUE

DAY AVENUE

CHERRY

STREET

ELIZABETH STREET

CR

OS

S PAT

H R

OA

D

OLIVE STREET

HUNTS ROAD

ORCHARD

STREET

FAC

TO

RY

ST

RE

ET

BAY ROAD

KIN

GS

HIG

HW

AY

LYMAN ROAD

CR

OS

SPA

TH

RO

AD

PIN

E B

RO

OK

CU

RV

E

BRADFORD STREET

FAIR STREET

NOOK ROAD

KIN

GS

HIG

HW

AY

STRONG

S RO

AD

SO

UT

H B

RA

NC

H R

OA

D

CR

OS

S P

AT

H

OLD FERRY ROAD

HUNTS ROAD

NOOK ROAD

FAIR

ST

RE

ET

CR

OS

S P

AT

H R

OA

D

AQUAVITAE ROAD

WA

LNU

T TR

EE

S PATH

VEN

TUR

ER

S F

IELD

RO

AD

BRADFO

RD BR

OOK

KING

ST BR

OOK

BRADFO

RD

BROO

K

KIN

G ST

BROO

K

KING

ST BR

OO

K

KING

ST BRO

OK

BRADFORD BROOK

Viaduct

Brook

Barr

ett St

Broo

k

BRADFORD

BROOK

Barrett St Brook

91

91

12’’

66’’

54’’

24’’

48’’

12’’

48’’

12’’

42’’

30’’

12’’

12’’

36’’

42’’

48’’

18’’

12’’

24’’

18’’

78’’

24’’

12’’

72’’

78’’

36’’

12’’

24’’

12’’

12’’

12’’

36’’

18’’

60’’

36’’

24’’

36’’

12’’

18’’

’’

12’’

18’’

48’’

18’’

30’’

12’’

5

5

10

10

5

5

9

9

9

9

5

66

5

5

\\camgissvr1\Projects\M_Billings\Northampton\mxd\KingSt_WilliamSt_Recommendations.mxd JD 11/21/2011

91

91

City of NorthamptonStormwater and Flood Control System

Assessment and Utility PlanFigure 3.1

King Street/Market Street and Bridge Street/Meadows Areas Recommended Plan

Proposed DrainageSystem Improvements

( )Existing Pipe Diameter

Proposed Pipe Diameter24"10"

9’ x 5’ Box

Legend

Drain Manhole

Catch Basin/Inlet

Stormwater Outfall

Stormwater Pumping Station

Contour

Drain Lateral

Culvert

Drainage Channel

Detention/Retention Basin

Drain Pipe

Parcel Boundary

Building

DEP Wetlands

Wetlands (MassGIS)

City of Northampton Property

LeveeDrainage Area Boundary

Area Prone to Flooding

Manage Stormwater On-Sitewith BMPs

400 0 400 800200

Feet

Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)

Phase 2Phase 3Phase 4

Phase 1

Page 53: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

New 48" RCP Drain

New 72" RCP Drain

MILL RIVER

Manage StormwaterOn-Site with BMPs

New 7’x4’ Box Drain

NU

TTIN

G A

VE

NU

E

147

Federal Street Retaining Wall Improvements

Weir Structure

10’’

8’’

15’’

10’’

12’’

12’’

12’’

24’’

8’’

12’’

12’’

12’’

10’’

14’’

24’’

12’’

24’’

10’’

8’’

6’’

8’’

12’’

10’’

10’’

6’’

8’’

24’’

8’’

18’’

18’’

12’’

18’’

10’’

12’’

8’’

6’’

12’’

10’’

12’’

15’’

12’’

18’’

48’’

24’’

12’’

10’’

8’’

36’’

12’’

10’’

10’’

18’’

12’’

12’’

15’’

12’’

12’’

12’’

10’’

30’’

8’’

36’’

15’’

24’’

12’’

15’’

10’’

8’’

12’’

8’’

18’’

10’’

36’’

15’’

12’’

10’’

8’’

12’’

10’’

18’’

12’’

15’’

12’’

10’’

12’’

4’’

15’’

15’’

18’’

8’’

10’’

10’’

12’’

15’’

10’’

8’’

12’’

12’’

12’’

60’’

20’’

12’’

18’’

10’’

12’’

10’’

18’’

10’’

12’’

8’’

8’’

8’’

12’’

12’’

10’’

18’’

12’’

12’’

18’’

8’’

18’’

12’’

8’’

10’’

18’’

12’’

15’’

15’’

15’’

15’’

30’’

21’’

15’’

8’’

12’’

10’’

12’’

10’’

8’’

18’’

10’’

24’’

18’’

15’’

12’’

12’’

12’’

15’’

12’’

12’’

12’’

8’’

12’’

12’’

12’’

12’’

8’’

18’’

15’’

12’’

12’’

12’’

8’’

12’’

21’’

12’’

12’’

24’’

8’’

30’’

12’’

42’’

12’’

12’’

48’’

10’’

15’’

8’’

12’’

12’’

12’’

24’’

12’’

12’’

15’’

18’’

12’’

12’’

12’’

15’’

18’’

10’’

12’’

12’’

10’’

8’’

10’’

12’’

8’’

12’’

10’’

12’’

8’’

12’’

8’’

8’’

15’’

10’’

10’’

15’’

12’’

8’’

15’’

24’’

27’’

12’’

8’’

12’’

10’’

12’’

36’’

15’’

21’’

24’’

15’’

10’’

15’’

18’’

12’’

10’’

24’’

18’’

12’’

8’’

10’’

12’’

10’’

15’’

15’’

30’’

36’’

12’’

8’’

15’’

10’’

15’’

12’’

12’’

12’’

15’’

15’’

21’’

12’’

12’’

10’’

12’’

21’’

18’’

12’’

10’’

12’’

12’’

8’’

15’’

12’’

15’’

8’’

12’’

12’’

10’’

12’’

12’’

12’’

33’’

12’’

12’’

18’’

12’’

15’’

236

17

157

285

216

275275

206

255

147

314

265

246

196

206

255

275

285

206

285

295

285

246

206

246

285

265

187

206

187

275

187

137

255

236

196

246

305

324

177

265

226

147

147

236

295

157

255

196

187

196

275

167

246

246

206

246

167

236

167

236

216

314

206

177

137

157

187

255

285

255

285

196

236

177

275

305

196

236

275

216

187

147

265

177

324

324

206

187

157

226

295

137

206

236

167

285

246

334

147

167

157

265

187

255

275

167

255

236

137

275

157

177

265

324

206

167

255

206

314

255

275

275

275

206

246

255

187

196

246

187

295

246

314

206

265

147

236

206

157

187

177

285

196

246

265

216

167

157

226

216

265

255

226

216

236

226

305

206

216

295

WO

OD

LAW

N

AVEN

UE

WO

OD

LAW

N

AV

EN

UE

BANCROFT ROAD

PROSPECT STREET

BRIDGE ROAD

BRIDGE ROAD

BRIDGE ROAD

BARDWELL STREET

GA

RF

IEL

D S

TR

EE

T

FE

DE

RA

L S

TRE

ET

FED

ER

AL

STR

EE

T

FEDERAL STREET

ST

RA

W

AV

EN

UE

LOCUST STREET

LOCUST STREET

NO

RT

H E

LM

ST

RE

ET

NO

RT

H M

AP

LE

ST

RE

ET

ELM STREET

ELM STREET

ELM STREET

VER

NO

N ST

REET

SH

AL

LO

W B

RO

OK

DR

I VE

HATFIELD

STREET

WARD AVENUE

WASHINGTON

PLACE

ST

ILS

ON

AV

EN

UE

WARNER STREET

JAC

KS

ON

ST

RE

ET

NO

RT

H E

LM S

TR

EE

T

CH

ES

TN

UT

ST

RE

ET

CH

ES

TN

UT

ST

RE

ET

HATFIELD STREET

HA

TF

IEL

D S

TR

EE

T

CH

ILD

S P

AR

K R

OA

D A

FR

AN

KLI

N

ST

RE

ET

FR

AN

KLI

N

ST

RE

ET

LOCUST

STREET PR

OS

PE

CT

AV

EN

UE

PR

OS

PE

CT

AVE

NU

E

NONOTUCK STREET

MEADOWBROOK DRIVE

ME

AD

OW

BR

OO

K D

RIV

E

PINE STREET

PINE

STREET

KIMBALL STREET

DRYADS GREEN

SANDERSON AVENUE

BRIDGE ROAD

FR

AN

CIS

ST

RE

ET

DANA STREET

GLEASON ROAD

MAIN STREET FLORENCE

CO

OK

E

AV

EN

UE

PLYMOUTH STREET

BR

AT

TO

N C

OU

RT

PARADISE

ROAD

MAPLE

STREET

HA

WT

HO

RN

LANE

KIN

G A

VE

NU

E

CLO

VE

RD

AL

E S

TR

EE

T

LAD

D AVE

NU

E

WOOD AVENUE

FIFTH AVENUE

BEACON STREET

LAUR

EL RIDGE DRIVE

HIGH STREET

SU

N H

ILL

DR

IVE

MA

RY

JA

NE

LA

NE

BLACKBERRY LANE

KE

YE

S S

TR

EE

TCAROLYN STREET

WIL

DE

R P

LAC

E

ALLISON STREET

BARRETT STREET

VERONA STREET

PLY

MO

UT

H A

VE

NU

E

RIDGEWOOD TERRACE

FORBES A

VENUE

SU

MN

ER

AV

EN

UE

ORMOND DRIVE

TAYLOR STREET

PROSPECT HEIGHTS

JEWETT STREET

HAROLD STREET

RIVERSIDE DRIVE

RIV

ER

SID

E D

RIV

E

RIVERSIDE DRIVE

RIVERSID

E DRIV

E

HIN

CK

LEY

ST

RE

ET

NE

W S

TR

EE

T

POWELL STREET

SHEFFIELD LANE

KENSINGTON AVENUE

MANDELLE ROAD

HO

WE

S S

TR

EE

T

AD

AR

E P

LAC

E

BA

KE

R H

ILL

RO

AD

MA

SS

AS

OIT

STR

EE

T

MA

SS

AS

OIT

S

TR

EE

T

JAMES AVENUE

MU

RP

HY

TE

RR

AC

E

MIL

TON

ST

RE

ET

CL

EM

EN

T S

TR

EE

T

SO

UTH

MA

IN S

TRE

ET

GR

AN

DV

IEW

STR

EE

T

ARLI

NG

TON

ST

REE

T

WILLOW STREET

WINSLOW AVENUE

TERRACE LANE

LAN

DY

AV

EN

UE

DENNISTON PLACE

BE

RK

SH

IRE

TE

RR

AC

E

NO

RFO

LK A

VE

NU

E

RO

E A

VE

NU

E

NO

RW

OO

D AV

EN

UE

NU

TT

ING

AV

EN

UE

MANN TERRACE

WASHIN

GTON A

VENUE

MIDDLE STREET

HARRISO

N AVENUE

MA

PLE

WO

OD

TE

RR

AC

E

MAYNARD R

OAD

BOTTO

M RO

AD

FO

X F

AR

MS

RO

AD

HIL

LCR

ES

T

DR

IVE

PINES

ED

GE

DR

IVE

EMILY LANE

KEARNEY

FIE

LD R

OA

D

HO

LLY

WO

OD

HE

IGH

TS

LIBE

RT

Y S

TR

EE

T

TR

INIT

Y R

OW

ST

ER

LIN

G R

OA

D

FAIR

FIE

LD

AV

EN

UE

CLA

IRE

AV

EN

UE

LEX

ING

TON

AVE

NU

E

MO

UN

TAIN

STR

EET

HO

SP

ITA

L R

OA

D

FLO

RE

NC

E R

OA

D

9

5

9

M IL L R I V E R

M I L L R I V E R

WIL

LO

W L

AK

E

N S H I C

E P

ON

D

Broughtons

Brook

Elm St.

Brook

SANDY HI LL

B ROO K

Broughtons Brook

KING ST BROOK

Broughtons

Brook

Bro

ugh

tons

Brook

Broughtons

Brook

Broughtons Brook

Bro

u g ht o

ns

BrookBr

ough

tons

Broo

k

Broughtons Brook

Elm St. Brook

P IN E BROO K

Broughtons

Brook

Brou ghtons Brook

PINE BROOK

18’’24’’

12’’

36’’

24’’

12’’

24’’

36’’

24’’

12’’

24’’

12’’

12’’

12’’

12’’

30’’

18’’

12’’

12’’

18’’

36’’

12’’

12’’

18’’

12’’

12’’

18’’

48’’

12’’

12’’

24’’

18’’

12’’

18’’

30’’

36’’

12’’

\\camgissvr1\Projects\M_Billings\Northampton\mxd\ElmSt_Recommendations.mxd SCC July 2011

91

91

Legend

350 0 350 700175

Feet

Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)

City of NorthamptonStormwater and Flood Control System

Assessment and Utility Plan

Figure 3.2Elm Street Brook/Florence Area

Recommended Plan

Proposed DrainageSystem Improvements

Phase I

10"

24"Phase 3 ( )

Existing Pipe Diameter

Proposed Pipe Diameter

Drainage Area Boundary

Area Prone to Flooding

Drain Manhole

Catch Basin/Inlet

Stormwater Outfall

Stormwater Pumping Station

Parcel Boundary

Building

DEP Wetlands

Wetlands (MassGIS)

City of Northampton Property

ContourDrain Pipe

Drain Lateral

Culvert

Drainage Channel

Detention/Retention Basin

Page 54: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

New 30" RCP Drain

ChannelImprovements

ChannelImprovements

Flood Storage AreaNew 30" RCP Drain

Plug and AbandonExisting Pipe

12’’

10’’

48’’

12’’

18’’

12’’

12’’

8’’

12’’

12’’

15’’

12’’

12’’

12’’

18’’

18’’

10’’

30’’

12’’

12’’

48’’

12’’

12’’

16’’

60’’

12’’

15’’

10’’

12’’

15’’

18’’

12’’

24’’

12’’

12’’

12’’

10’’

12’’

15’’

12’’

12’’

12’’

15’’

12’’

15’’

18’’

442

383

295

314

285

295

324

423

344

413

364

305

393

462

275

275

393275

285

305

433

295

305

423

295

364

314

334

285

354

285

285

285

413

275

393

295

305

374

452

442

383

433

324

423

275

295

295

305

314

393

403

324

314

334

344

BR

OO

KS

IDE

CIR

CLE

MA

TT

HE

W D

RIV

E

RYA

N R

OA

D

RYAN

RO

AD

ALAMO COURT

OVERLOOK DRIVE

BIRCH HILL ROAD

ACREBROOK

DRIVE

AC

RE

BR

OO

K

DR

IVE

BR

OO

KS

IDE

CIR

CLE

TARA CIRCLE

SUMMERFIELD STREET

CA

HIL

LAN

E T

ER

RA

CE

HOLLY COURT

GREGORY LA

NE

BR

OO

KS

IDE

CIR

CLE

HIC

KOR

Y D

RIV

E

OV

ER

LOO

K D

RIV

E

LONG

VIEW

DRIVE

BRIE

RW

OO

D D

RIV

E

PEN

CA

SAL D

RIV

E

GILR

AIN TE

RR

AC

E

PIONEER KNOLLS

WO

OD

S R

OA

D

FO

RE

ST

GL

EN

DR

IVE

DEERFIELD DRIVE

SPRUCE HILL AVENUE

SP

RU

CE

HIL

L A

VE

NU

E

BE

ATTIE

DR

IVE

GOLDEN DRIVE

GOLDEN DRIVE

AUS

TIN C

IRC

LE

AUSTIN CIRCLE

\\camgissvr1\Projects\M_Billings\Northampton\mxd\RyanRoad_Recommendations.mxd JD 11/21/2011

City of NorthamptonStormwater and Flood Control System

Assessment and Utility Plan

Figure 3.3Austin Circle/Ryan Road

Area Recommended Plan

Legend

91

91

Drainage Area Boundary

Area Prone to Flooding

Drain Manhole

Catch Basin/Inlet

Stormwater Outfall

Flood Storage Area

Proposed DrainageSystem Improvements

Phase 2

Drain Pipe

Drain Lateral

Culvert

Drainage Channel

Detention/Retention Basin

Stormwater Pumping Station

150 0 150 30075

Feet

Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)

Contour

Parcel Boundary

Building

DEP Wetlands

Wetlands (MassGIS)

City of Northampton Property

Wetlands (Delineated by City)

Page 55: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐5 

106678‐80349‐03‐11 

In the future reestablishing an annual budget amount for new drain system construction would allow the DPW 

to better prioritize street reconstruction projects because complete funding would be available for paving and 

all street utilities.  The annual budget would need to be significantly greater than previous budgets in order to 

maintain the city stormwater system.  This funding would result in an improvement in the management of city 

streets and related utilities.  

Based on conversations with the City, an annual budget of $500,000 is suggested for construction of new storm 

drains or replacement of old drains as part of street improvement projects.  This is comparable to the annual 

amount budgeted by the City for water line and sewer line improvements. 

3.2.2  Municipal Green Infrastructure/Building Project Retrofit/ Capital Allowance 

The proposed NPDES permit contains requirements for “Good House Keeping and Pollution Prevention for 

Permittee Owned Operations.”  The section of the proposed permit has wide ranging requirements that will 

involve one‐time capital expenditures and annual maintenance requirements beyond what is currently done.  

These requirements include small and large obligations.  The following provides some information about the 

capital requirements, while the operational requirements are discussed in Section 3.3: 

Parks and Open Space: Where waterfowl may congregate and feeding by the public occurs, the City is required 

to install educational signage about the threat posed to receiving waters. Pet waste requirements include 

preparation and distribution of educational flyers, signage, provision of pet waste bags, and disposal receptacles.   

Buildings and Facilities: An inventory of all floor drains in City‐owned buildings must be prepared and all floor 

drain connections that are connected to the drain system must be disconnected and piped to the sewer system.  

Given the age of many City buildings, many floor drains may not be properly connected to the sewer.  The design 

and construction of new connections from floor drains to the sewer system will be required.   

Vehicles and Equipment: City vehicles with fluid leaks must be stored indoors or in a contained area until 

repaired and all vehicle washing must be discharged to the sewer system.  Construction of improvements  to 

DPW facilities and other city facilities may be needed to meet this requirement. 

City property and rights of way – retrofits: The draft permit requires the city to construct BMPs on City property 

and within right of ways for City streets.  These BMPS are to be designed to reduce the frequency, volume, and 

peak intensity of stormwater discharges, as well as to reduce pollutant loadings into the drainage system and 

receiving waters. The costs associated with these capital projects could be considerable given that the 

construction of detention basins, water quality swales, rain gardens, permeable pavement and other capital 

intensive BMPs would be required. 

 Based on conversations with the City, an annual budget of $200,000 is suggested for green infrastructure and 

other retrofit construction.  This budget is escalated with time in Table 3.6. 

3.2.3  Bridge Street/Meadows Area 

The recommended Phase 1 Bridge Street/Meadows area drainage improvements (Figure 3.1) consist of 

approximately 5,500 feet of new drainage pipe ranging from 48‐ to 66‐inches in diameter.  These improvements 

include the 48‐inch diameter drain from the Three County Fairgrounds to the Connecticut River and the 66‐inch 

diameter Massachusetts Department of Transportation (MassDOT) drain replacement at Damon Road.  On‐site 

management of stormwater with BMPs is recommended in the industrial area, instead of increasing pipe sizes in 

Page 56: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐6 

106678‐80349‐03‐11 

that area. Phase 3 improvements consist of 7,500 feet of new drainage pipe, ranging from 12‐to‐42‐inches in 

diameter.   The preliminary project cost estimate for these improvements is $11,117,000.  See Table 3.1 for a 

breakdown of these costs.  

3.2.4  Elm Street Brook/Florence Area 

The recommended Phase 1 Elm Street Brook area drainage improvements (Figure 3.2) consist of approximately 

1,900 feet of new 48‐inch diameter drainage pipe and 1,600 feet of 7‐ by 4‐foot box culvert.   The recommended 

Phase 3 Elm Street Brook area drainage improvements (Figure 3.2) consist of approximately 15,000 feet of new 

drainage pipe ranging from 12‐ to 72‐inches in diameter. The Smith Vocational and Agricultural High School is 

located on a City‐owned parcel and on‐site management of stormwater with BMPs is recommended at this 

location. The total estimated cost for drainage improvements in this area is $19,364,000.  See Table 3.2 for a 

breakdown of costs and phasing. 

3.2.5  King Street/Market Street Area 

The recommended Phases 1 and 2 King Street area drainage improvements (Figure 3.1) consist of approximately 

5,400 feet of new drainage pipe ranging from 36‐ to 78‐inches in diameter, and 560 feet of 9‐foot by 5‐foot box 

culvert in the Historic Mill River.  Drainage pipe improvements include replacement of pipes in the Market Street 

Brook system from North Street to Bridge Street, and replacement of pipes in King Street.  Television inspections 

of the drains in the Market Street Brook system upstream of Main Street should be performed during the final 

design of improvements in this area to determine the condition of this system and whether it needs to be 

replaced.  

The recommended Phases 3 and 4 King Street area drainage improvements (Figure 3.1) consist of approximately 

7,200 feet of new drainage pipe ranging from 12‐ to 60‐inches in diameter. On‐site management of stormwater 

with BMPs is recommended in the retail area along upper King Street instead of increasing pipe sizes in that 

area.  These BMPs could be required during the planning board approval process or as part of the City’s 

stormwater permit program. 

On March 14‐16, 2011 Nelson\Nygaard conducted a three‐day design charrette with the City to address bicycle 

and pedestrian access, while maintaining levels of vehicle throughput, for portions of King and Main Streets.  

The charrette identified the need to reduce King and Main Streets from a four‐lane cross‐section to a two‐lane 

cross‐section (also known as a “road diet”) to improve pedestrian and bicycle safety, while also creating several 

opportunities for new public spaces. 

The road diet also provides several opportunities for the installation of stormwater BMPs on Main and King 

Streets.  On Main Street, the Nelson/Nygaard study recommended using the additional space to widen sidewalks 

to allow outdoor dining, street trees and other vegetation.  Opportunities for BMPs on Main Street include 

permeable pavers on the sidewalks for infiltration and street planters and bioretention gardens to collect and 

treat stormwater runoff from the street.  On lower King Street, the study recommended center left‐turn lanes 

with vegetated medians. These vegetated medians could be designed as bioretention areas or street planters to 

collect and treat stormwater.   

On upper King Street, in addition to center left‐turn lanes, the study recommended one‐way cycletracks 

constructed at‐grade with the sidewalks, but separated from the sidewalk by a 10‐foot‐wide vegetated strip.  

Opportunities for green infrastructure include permeable pavers for the sidewalks, porous pavement for the 

cycletracks, bioretention areas in the vegetated strip, and street planters in the vegetated median.  All of these 

stormwater BMPs will reduce peak runoff to the King Street drainage system and provide treatment of 

Page 57: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐7 

106678‐80349‐03‐11 

stormwater, improving receiving water quality.  It is recommended that pipe capacity improvement design for 

the King Street drainage system occur concurrently with modifications to King and Main Streets because 

detailed hydrologic/hydraulic analyses associated with the proposed stormwater BMPs may indicate that pipe 

sizes smaller than those shown on the recommended plan (Figure 3.1) may be feasible. . The total estimated 

cost for drainage improvements in this area is $19,424,000.  See Table 3.3 for a breakdown of costs and phasing. 

3.2.6  Austin Circle/Ryan Road Area 

The recommended Phase 2 Austin Circle/Ryan Road area drainage improvements (Figure 3.3) consist of 

approximately 1,300 feet of new 30‐inch diameter drainage pipe, a 1.3‐acre flood storage area, and 1,500 feet of 

channel improvements.  The total estimated cost for drainage improvements in this area is $4,084,000.  See 

Table 3.4 for a breakdown of costs. 

3.2.7  Flood Control Pumping Station Improvements 

Recommendations for the Northampton Flood Control Pumping Station and the West Street stormwater 

pumping station are discussed in Sections 2.3.5.1 and 2.3.6.1.  For the Northampton Flood Control Pumping 

Station, the cost estimate is based on a complete new facility.  For the West Street Pumping Station, it is 

recommended that the City purchase a portable diesel‐engine‐driven pump with capacity on the order of 6,000 

gpm, instead of installing a permanent pump at this location. Pumping station improvements are scheduled for 

Phase 2.  The total estimated cost for the Flood Control Pumping Station improvements is $23,653,000.  See 

Table 3.5 for a breakdown of costs and phasing. 

3.2.8  Levee Improvements 

As discussed in Section 2.3.4, the levee improvements mandated by USACE include repairing areas with ruts, 

small depressions, sparse vegetation, and missing riprap, and removing trees and thick brush on the levee and at 

least 15 feet beyond the abutments and at the toe of the levee.  Regular maintenance activities are also 

recommended at least twice a year, or as conditions warrant, to control and limit growth of vegetation on the 

levee and the banks of the diversion canal.  The USACE has also mandated an engineering evaluation of the 

levees to assess data gaps.  Levee improvements must be completed by January 2013 or 2014, depending on the 

item, as discussed in Section 2.  

3.2.9  River Erosion Improvements 

The proposed River Road Retaining Wall/Floodwall Improvements are located in the Leeds Village section of 

Northampton (See Figure 1.1).  Flows from the Mill River have scoured and undercut significant sections of the 

wall, and surface runoff has compromised the integrity of the upper portions of the wall.  In addition, the 

Williamsburg sanitary sewer interceptor is located within River Road and is in danger of collapsing due to river 

erosion.  The City is proposing to remove the existing stone masonry wall and replace it with a cast‐in‐place 

concrete retaining wall that will protect the road and sewer from the 100‐year flood event.   This project is 

scheduled for Phase 1. 

The Roberts Meadow Brook channel is located between the Lower Roberts Meadow Reservoir Dam and 

Reservoir Road in Leeds (see Figure 1.1).  The channel is comprised primarily of dry masonry sidewalls and a 

naturalized boulder and cobble bottom.  High flow events have resulted in significant erosion of the channel 

sidewalls, which is threatening the dwellings and driveways of adjacent private properties.  The City has 

proposed to extend the floodwall upstream from the Reservoir Road bridge to the critical area in the channel.  

The new floodwall would be a cast‐in‐place concrete retaining wall with sufficient height to protect adjacent 

properties from the 100‐year flood event.  This project will be performed during Phase 1. 

Page 58: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐8 

106678‐80349‐03‐11 

The third project improves the Federal Street retaining wall along the Mill River, as shown in Figure 3.2.  The 

purpose of this project is to protect a 30‐inch sewer interceptor.  Erosion is occurring along the sharp bank 

angle, which is leading to the exposure of the interceptor.  This project will be performed during Phase 2.  

3.3  Future Operational Cost Projections Additional operational staff, equipment and funding will be needed to address the maintenance and 

replacement needs of the City’s aging drainage infrastructure and to comply with the new requirements of the 

pending changes to the NPDES Phase II permit.  The proposed NPDES permit has many requirements that will 

require both operational and technical staff, as well as new equipment needs.  Some of these requirements are 

discussed below. 

Data Requirements: The Draft NPDES Permit requires the gathering, and in some cases mapping, of an 

enormous quantity of data.  Much of this information is required in the first two years after permit issuance in 

order to perform the analyses required to meet the permit milestones.  Northampton has a well‐established 

Geographic Information System (GIS), but a significant amount of professional staff time will be required for the 

data compilation and analysis.   

Proposed Outfall Sampling:  The new permit requires sampling 25 percent of each community’s outfalls each 

year during both dry and wet weather.  The City of Northampton has almost 300 stormwater outfalls that 

discharge to various brooks, streams, and rivers, resulting in the need to sample about 75 outfalls two times per 

year.  These sampling events will require DPW staff labor and sampling equipment to accomplish, as well as 

possible laboratory testing fees. 

Nitrogen Reduction Requirements and Best Management Practices (BMPs):  The Draft NPDES Permit requires 

the use of both structural and non‐structural BMPs to ensure water quality standards will be met.  The draft 

NPDES permit requires a 10 percent reduction in the amount of nitrogen discharged in stormwater.   This will be 

required since the City is located within the Connecticut River basin and thus ultimately discharges to Long 

Island Sound.  The construction of many BMPs within the City stormwater system will be required to reduce the 

amount of nitrogen discharged.  These types of BMPs are stormwater retrofit construction projects that will 

require capital funding to accomplish. 

Public Education and Outreach: The Draft Permit includes the production and distribution of eight public 

education notices, in addition to several ordinances and programs intended to teach the public how to minimize 

their impacts on stormwater quality.  Professional DPW staff will be required to manage the requirements of the 

public education and outreach program.   

Catch Basin Inspection and Cleaning:  The draft permit requires street sweeping twice per year (spring and fall) 

and a catch basin cleaning frequency that ensures that no catch basin will be more than 50 percent full of debris.   

Currently, most City streets are swept once per year and only certain catch basins are cleaned on a regular basis.  

The City has over 150 miles of paved streets and over 3,750 catch basins.  Additional DPW staff and equipment 

will be required to meet these new regulatory requirements.   

3.4  Estimated Costs and Preliminary Schedule Tables 3.1 through 3.5 present the estimated project costs and projected schedules for construction of the 

recommended drainage and flood control facilities.  Table 3.6 summarizes the total project costs for the 20‐year 

plan.   

Page 59: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐9 

106678‐80349‐03‐11 

Project costs include estimated construction costs, a 25 percent construction contingency, engineering and 

implementation costs.  The need for land acquisition and easements was not determined and those costs are 

not included.  Estimated mid‐points of construction used in the cost estimates vary for each project and are 

provided in Tables 3.1 through 3.5.   

Table 3.1 

Bridge Street/Meadows Area Drainage Improvements Preliminary Project Cost Estimate 

Location/Description Pipe 

Size (in) Quantity  Unit 

Unit Cost Depth 0 to 8 ft 

Construction Cost 

Phase 1 

New Drains  48  4,700  lf  $670   $3,149,000  

   66  770  lf  $950   MassDOT Project 

Headwalls and Riprap Pads (42‐ to 84‐in pipe) 

   1  ea  $80,000   $80,000  

Subtotal   5,470  lf  $3,229,000  

Construction Contingencies (25%)  $807,250  

Total Construction Cost (April 2011 ENR 9027)  $4,036,250  

Construction Cost at Mid‐Point of Phase 1 Construction*  $4,410,519  

Engineering and Implementation Costs (25 %)  $1,102,630  

Phase 1 Opinion of Probable Project Costs (Rounded)  $5,513,000  

Phase 3 

New Drains  12  3,650  lf  $255   $930,750  

   18  1,225  lf  $330   $404,250  

   24  500  lf  $370   $185,000  

   30  1,300  lf  $400   $520,000  

   36  350  lf  $470   $164,500  

   42  490  lf  $635   $311,150  

Subtotal   7,515  lf  $2,515,650  

Construction Contingencies (25%)  $628,913  

Total Construction Cost (April 2011 ENR 9027)  $3,144,563  

Construction Cost at Mid‐Point of Phase 3 Construction*  $4,483,394  

Engineering and Implementation Costs (25 %)  $1,120,849  

Phase 3 Opinion of Probable Project Costs (Rounded)  $5,604,000  

Total Opinion of Probable Project Costs (Rounded)  $11,117,000  

Notes: 

Land acquisition/easement costs not included 

Costs are April 2011 dollars (ENR 9027) 

*Phase 1: Apr '11 to Apr'14, 3% per year; Phase 3: Apr '11 to Apr '23, 3% per year 

 

Page 60: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐10 

106678‐80349‐03‐11 

Table 3.2 

Elm Street Brook/Florence Area Drainage Improvements Preliminary Project Cost Estimate 

Location/Description Pipe Size 

(in) Quantity  Unit 

Unit Cost Depth 0 to 8 ft 

Construction Cost 

Phase 1 

New Drains  48  1,860  lf  $670   $1,246,200  

New Box Culvert  7‐ft x 4‐ft  1,645  lf  $1,200   $1,974,000  

Headwalls and Riprap Pads (42‐ to 84‐in pipe) 

   3  ea  $80,000   $240,000  

Subtotal  3,505  lf  $3,460,200  

Construction Contingencies (25%)  $865,050  

Total Construction Cost (April 2011 ENR 9027)  $4,325,250  

Construction Cost at Mid‐Point of Phase 1 Construction*  $5,164,575  

Engineering and Implementation Costs (25 percent)  $1,291,144  

Phase 1 Opinion of Probable Project Costs (Rounded)  $6,456,000  

Phase 3 

New Drains  12  8,000  lf  $255   $2,040,000  

   18  1,750  lf  $330   $577,500  

   24  1,580  lf  $370   $584,600  

   36  1,200  lf  $470   $564,000  

   48  1,860  lf  $670   $1,246,200  

   72  530  lf  $1,000   $530,000  

Subtotal  14,920  lf  $5,542,300  

Construction Contingencies (25%)  $1,385,575  

Total Construction Cost (April 2011 ENR 9027)  $6,927,875  

Construction Cost at Mid‐Point of Phase 3 Construction*  $10,326,425  

Engineering and Implementation Costs (25 percent)  $2,581,606  

Phase 3 Opinion of Probable Project Costs (Rounded)  $12,908,000  

Total Opinion of Probable Project Costs (Rounded)  $19,364,000  

Notes: Land acquisition/easement costs not included Costs are April 2011 dollars (ENR 9027) * Phase 1: Apr '11 to Apr '17, 3% per year; Phase 3 Apr '11 to Apr '24/'25, 3% per year 

   

Page 61: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐11 

106678‐80349‐03‐11 

Table 3.3 

King Street/Market Street Area Drainage Improvements Preliminary Project Cost Estimate 

Location/Description Pipe Size 

(in)  Quantity  Unit Unit Cost Depth 0 to 8 ft 

Construction Cost 

Phases 1 and 2 

New Drains  36  320  lf  $470   $150,400  

   48  2,800  lf  $670   $1,876,000  

   66  420  lf  $950   $399,000  

   72  400  lf  $1,000   $400,000  

   78  1,480  lf  $1,300   $1,924,000  

New Box Culvert  9‐ft x 5‐ft  560  lf  $1,800   $1,008,000  

Subtotal   5,981  lf  $5,837,400  

Construction Contingencies (25%)  $1,459,350  

Total Construction Cost (April 2011 ENR 9027)  $7,296,750  

Construction Cost at Mid‐Point of Phase 1/2 Construction*  $9,108,690  

Engineering and Implementation Costs (25 %)  $2,277,170  

Phase 1/2 Opinion of Probable Project Costs (Rounded)  $11,386,000  

Phases 3 and 4 

New Drains  12  1,500  lf  $255   $382,500  

   18  950  lf  $330   $313,500  

   24  2,000  lf  $370   $740,000  

   36  1,360  lf  $470   $639,200  

   54  800  lf  $740   $592,000  

   60  630  lf  $930   $585,900  

Subtotal   7,240  lf  $3,253,100  

Construction Contingencies (25%)  $813,275  

Total Construction Cost (April 2011 ENR 9027)  $4,066,375  

Construction Cost at Mid‐Point of Phase 3/4 Construction*  $6,430,309  

Engineering and Implementation Costs (25 %)  $1,607,577  

Phase 3/4 Opinion of Probable Project Costs (Rounded)  $8,038,000  

Total Opinion of Probable Project Costs (Rounded)  $19,424,000  

Notes: 

Land acquisition/easement costs not included 

Costs are April 2011 dollars (ENR 9027) 

*Phase 1/2: Apr '11 to Apr'18/'19, 3% per year; Phase 3/4: Apr '11 to Apr '26/'27, 3% per year 

  

   

Page 62: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐12 

106678‐80349‐03‐11 

Table 3.4 

Austin Circle/Ryan Road Area Drainage Improvements Preliminary Project Cost Estimate 

Location/Description Pipe 

Size (in) Quantity  Unit 

Unit Cost Depth 0 to 8 ft 

Construction Cost 

Phase 2 

New Drains  30  1,300  lf  $400   $520,000  

Headwalls and Riprap Pads (up to 36‐in pipe) 

   4  ea  $25,000   $100,000  

Flood Storage Area     1.3  acre  $500,000   $650,000  

Channel Improvements     1,500   lf  $450   $675,000  

Subtotal  2,800   lf  $1,945,000  

Construction Contingencies (25%)  $486,250  

Total Construction Cost (April 2011 ENR 9027)  $2,431,250  

Construction Cost at Mid‐Point of Phase 2 Construction*  $3,267,400  

Engineering and Implementation Costs (25 percent)  $816,800  

Opinion of Probable Project Costs (Rounded)  $4,084,000  

Notes: 

Land acquisition/easement costs not included 

Costs are April 2011 dollars (ENR 9027) 

*Phase 2: Apr '11 to Apr '21, 3% per year 

    

Page 63: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvements Plan and Operational Budget Requirements  

3‐13 

106678‐80349‐03‐11 

Table 3.5 

Flood Control System Improvements Preliminary Project Cost Estimate 

Description of Capital Improvement  Construction Costs 

Phase 1  

Levee Capital Improvements  $436,000  

Levee Certification Allowance  $445,000  

Subtotal  $881,000  

Construction Contingencies (25 percent) 

Capital Improvements Only $109,000 

Total Construction Cost   $990,000 

Construction Cost at Mid‐Point of Construction*  $1,019,700  

Phase 1 Opinion of Probable Project Costs (Rounded)  $1,020,000 

Phase 2  

Levee Capital Improvements Allowance  $500,000  

Flood Control Pumping Station Upgrades  $12,000,000  

West Street Portable Pumps   $400,000  

Subtotal  $12,900,000  

Construction Contingencies (25%)  $3,225,000  

Total Construction Cost (April 2011 ENR 9207 )  $16,125,000 

Construction Cost at Mid‐Point of Construction**  $18,106,000 

Engineering and Implementation Costs (25 percent)  $4,526,500 

Phase 1 Opinion of Probable Costs (Rounded)  $22,633,000 

Opinion of Probable Project Costs (Rounded)  $23,653,000  

Notes: 

Land acquisition/easement costs not included 

Costs are April 2011 dollars (ENR 9207 Estimated) 

*Mar '12 3% per year 

**April 2011 to April 2012 to Apr '18 (levee improvements), '15 (stormwater P.S.),'16 (West St P.S.) 

 

Page 64: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvement Plan and Operational Budget   

3‐14 

106678‐80349‐03‐11 

 

 

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

Bridge Street/Meadows Phase 1 Improvements $441,000 $5,072,000

River Road Floodwall Improvements  $155,000 $1,453,000

Roberts Meadow Brook Channel Improvements $43,680 $502,320

Federal Street Retaining Wall Improvements $120,000 $1,380,000

Elm Street Brook/Florence Area Phase 1 Improvements $516,000 $5,939,000

King Street/Market Street Area Phase 1 and 2 Improvements $911,000 $5,160,000 $5,315,000

Levee Certification $275,000 $275,000

Levee Capital Improvements $280,000 $275,000 $56,000 $647,000

Flood Control Pumping Station Upgrades $1,391,000 $15,998,000

West Street Portable Pumps    $46,000 $533,000

Austin Circle/Ryan Road Area Phase 2 Improvements $327,000 $3,757,000

Bridge Street/Meadows Area Phase 3 Improvements $448,000 $5,156,000

Elm Street Brook/Florence Area Phase 3 Improvements $1,033,000 $5,850,000 $6,025,000

King Street/Market Street Area Phase 3 and 4  Improvements $643,000 $3,643,000 $3,752,000

EPA MS4 Permit Requirements Allowance $250,000 $250,000 $250,000 $250,000 $250,000

Annual Allowance for Drainage Infrastructure  $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000

Municipal Green Design/Construction Allowance $258,000 $265,000 $273,000 $281,000 $290,000 $299,000 $307,000 $317,000 $326,000 $336,000 $346,000 $356,000 $367,000 $378,000 $389,000 $401,000 $413,000 $426,000 $438,000 $452,000

Total Costs per Year $1,761,680 $3,961,320 $6,151,000 $3,115,000 $18,087,000 $7,769,000 $7,347,000 $6,132,000 $1,153,000 $4,593,000 $1,294,000 $7,045,000 $6,717,000 $7,546,000 $4,532,000 $4,653,000 $913,000 $926,000 $938,000 $952,000

Grand Total $95,586,000

Planning/Operations

Design

Construction

YearProject Description

Table 3.6

Summary Project Cost Schedule

Page 65: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvement Plan and Budget Operational Requirements  

3‐15 

106678‐80349‐03‐11 

3.5  Project Prioritization Construction phasing of the recommended drainage and flood control improvements will depend upon the 

City’s availability of funding to implement these improvements.  Twenty‐year bonds will likely be issued to 

accomplish the projects.  Section 5 uses the costs summarized in Section 3.4 above, assuming issuance of 20‐

year bonds, to evaluate creation of a Stormwater and Flood Control Utility to fund the recommended 

stormwater and flood control improvement projects, as well as annual maintenance of drainage infrastructure 

and permitting requirements. 

The highest priorities are flood control, street improvements, the Bridge Street/Meadows area, which includes 

the Fairgrounds, and the Elm Street Brook area where chronic flooding limits access to the area around 

Northampton High School.  As discussed above, the recommended drainage system improvements consist of 

two types of projects:   

Phase 1 and 2 projects – needed to address high priority flooding problems or other issues, such as pipe 

collapses 

Phase 3 and 4 projects ‐ designed to provide capacity to control 10‐year 24‐hour storm peak rates of runoff in 

areas with less significant flooding problems 

Table 3.7 provides a preliminary prioritization ranking system for the drainage and flood control projects that 

can be used by the City for future stormwater and flood control system asset management using the City’s 

VUEworks program.  The prioritization ranking system includes a list of key qualitative (non‐cost) and 

quantitative (cost) assessment criteria used to screen each project.  Each project is rated based on key 

assessment criteria, and the criteria is assigned weighting factors to account for varying degrees of importance.  

It is recommended that the matrix be re‐evaluated every few years to determine whether it would be more 

beneficial to re‐order project priorities. 

Page 66: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 3    Capital Improvement Plan and Budget Operational Requirements  

3‐16 

106678‐80349‐03‐11 

Table 3.7 Stormwater Capital Improvement Projects – Prioritization Ranking Summary 

 

5.0% 10.0% 2.5% 10.0% 15.0% 22.5% 25.0% 10.0%

Watershed Improvement Nature of Problem Sys

tem

Des

ign

Cap

acity

(ye

ar)

Cos

t (E

ngin

eerin

g D

esig

n,

Per

mitt

ing

&

Con

stru

ctio

n)

Pro

ject

aff

ects

pa

rcel

s in

F

EM

A

flood

plai

n

Acr

es I

mpa

cted

Fac

ility

C

apac

ity

Env

ironm

enta

l Q

ualit

y

Acc

ess

&

Eas

emen

ts

Con

nect

ion

to

City

-Pla

nned

P

roje

cts

Con

stru

ctab

ility

Roa

dway

s/P

rop

erty

Flo

oded

To

tal C

ost

Sco

re

Bridge Street/Meadows Area48" drain from 3C Fairgrounds to Connecticut River, 66" drain replacement at Damon Road. (Phase 1) Flooding at Fairgrounds and lower Williams Street 10

$5,513,000YES 5 4 0 4 5 4 5 3 4.250

Elm Street Brook/Florence AreaInstall weir structure and box drain in Elm Street, new drain in Milton and Federal Streets, and new outfall from Federal Street to Mill River. (Phase 1)

Flooding along Elm Street, particularly at the intersection of Milton Street. 10

$6,085,000NO 4 4 0 4 4 3 5 3 3.825

King Street/Market Street Area

48" drain in Market Street Brook from North Street to Bridge Street, 36" drain in Market Street, 66" to 78" drain in King Street from North Street to Main Street, 9' x 5' box culvert in Old Mill River. (Phase 1 and 2)

Drainage systems do not accommodate 10-year storm

10

$11,386,000

NO 4 3 0 3 4 2 3 5 3.100

Austin Circle/Ryan Road AreaCreation of a Flood Storage Area, installation of 24" drain, and improvements to existing channel.

Flooding along existing channel25

$3,225,000No 2 4 5 3 0 3 5 2 3.050

Bridge Street/Meadows AreaUpsize all pipes <12" to 12" pipes, upsize cross-country drainage system near Coolidge Avenue, upsize pipes in Pomeroy Terrace, upsize pipes in Williams Street. (Phase 3)

Drainage systems do not accommodate 10-year storm10

$6,456,000No 3 5 0 2 1 1 5 3 2.775

Elm Street Brook/Florence Area

Upsize all pipes <12" to 12" pipes, upsize pipes in Federal Street, North Elm Street, Locust Street, Stitson Avenue, High Street, Straw Avenue, Fox Farms Road, Bridge Road, Strawberry Hill Street, and Chestnut Street. (Phase 3)

Drainage systems do not accommodate 10-year storm

10

$12,908,000

No 3 4 0 4 1 3 2 5 2.775

King Street/Market Street AreaUpsize all pipes <12" to 12" pies, upsize pipes in Upper King Street, Walnut Street, State Street, Trumbull Avenue and Church Street. (Phase 3 and 4)

Drainage systems do not accommodate 10-year storm10

$8,038,000No 3 2 0 4 2 2 3 4 2.650

LEGEND: Ranking Based on Quantifiable Data

Notes:(1) Costs that occur annually - MS4 permitting, drainage infrastructure, and municipal green design projects - are not included in this table.(2) Capital projects that are subject to a FEMA grant - River Road floodwall improvements, Roberts Meadow Brook channel improvements and Federal Street retaining wall improvements - are not included in this table.(3) Levee accreditation not included because subject to FEMA scheduling.

Project Affects Parcels in FEMA Floodplain

Page 67: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

4‐1 10678‐80349 

Section 4 – Environmental Permitting 

4.1  Introduction Section 3 presented the recommended plans for the King Street/Market Street Area, Bridge 

Street/Meadows Area, Elm Street Brook/Florence Area, Austin Circle/Ryan Road area drainage areas, 

to be designed, permitted and constructed in four phases, as well as the Northampton flood control 

system and river erosion recommended improvements.   

These anticipated projects can proceed as standalone projects.  Hence each phase of the work in 

each watershed and the flood control improvements will be designed, permitted and built separately.   

Following are the anticipated environmental permits and approvals for each watershed for Phases 1 

through 4, and for the flood control and river erosion improvements: 

Location 

Federal Approvals 

State Approvals Local 

Approvals 

USACE Permit 

NPDES Permit 

MEPA Water Quality 

Certification 

CH. 91 License 

Order of Conditions 

Phase 1 and 2 

King Street/Market Street Area 

X  X    X    X 

Bridge Street/Meadows Area 

X  X  X  X  X  X 

Elm Street Brook/Florence Area 

X  X  X  X    X 

Austin Circle/Ryan Road Area 

X  X  X  X    X 

Phase 3 and 4 

King Street/Market Street Area 

X  X    X    X 

Bridge Street/ Meadows Area 

X  X    X    X 

Elm Street Brook/Florence Area 

X  X    X    X 

             

Flood Control Projects  X  X    X    X 

River Erosion Projects  X  X    X    X 

Page 68: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 4     Environmental Permitting   

4‐2 10678‐80349 

In addition, the new pump engines and emergency standby generator for the replacement Flood Control 

Pumping Station will need to obtain Installation Compliance Certification as part of the MassDEP Environmental 

Results Program. 

During preliminary design the proposed improvements will be evaluated to determine what permits and 

approvals are needed and a strategy to effectively navigate the approval process will be prepared.  A “permitting 

plan” will be incorporated into the preliminary design report for each project. 

4.2  Description of Applicable Permits There are a number of federal, state and local permits required to implement the drainage improvements.  

Because city drainage systems are linked to, or incorporate water courses and wetlands, e.g. Elm Street Brook 

and the Connecticut River, permits and approvals will be required to work in or adjacent to these resources.   

The following identifies federal, state and local permits/approvals required to work in or adjacent to regulated 

natural resources. 

4.2.1  Federal Permits/Approvals 

4.2.1.1  Clean Water Act, Section 404 

Section 404 of the Clean Water Act (CWA) regulates the discharge of dredged or fill materials into the Waters of 

the U.S., including adjacent wetlands. Any discharge of dredged or fill material into Waters of the U.S. and/or 

adjacent wetlands to prosecute drainage improvements, will require approval from the U.S. Army Corps of 

Engineers (USACE) in accordance with Section 404 of the CWA.  

In Massachusetts, the USACE issued a General Permit (GP) to streamline the permitting process. The GP 

establishes three categories of review: Category I involves a pre‐discharge notification but no formal review by 

the USACE provided all applicable GP conditions are met; Category II activities require screening by the USACE 

for compliance with GP conditions; and, an Individual Permit is required for large‐scale projects (e.g., those 

altering more than 1 acre of vegetated wetland or landfill bank) which do not meet the terms and general 

conditions of the GP based on concerns for the aquatic environment or for other factor of the public interest. 

Section 10 of the Rivers and Harbors Act 

Section 10 of the Rivers and Harbors Act of 1899 (Section 10) requires approval from the USACE to place fill or 

construct structures in Navigable Waters. Note, the Massachusetts GP was issued pursuant to Section 404 of the 

CWA and Section 10 of the Rivers and Harbors Act of 1899. Therefore, review for work subject to Section 10 is 

the same as described above for Section 404 of the CWA. 

Executive Order 11988 (E.O. 11988), Protection of Floodplains 

E.O. 11988 directs that federal actions (i.e. federal funding or approvals) occurring within floodplains must be 

performed so as to avoid adverse impact to the floodplain, and to minimize potential harm and to restore and 

preserve the natural and beneficial values of the floodplain.  

This requirement is addressed by the USACE concurrent with their review pursuant to CWA Section 404, 

described above. Floodplain associated with the Connecticut River will be altered during construction, including 

excavation and refill.  Preliminary design calculations have indicated that there will be no net loss of floodplain 

storage capacity. This will be confirmed during future design work. 

 

Page 69: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 4     Environmental Permitting   

4‐3 10678‐80349 

Executive Order 11990 (E.O. 11990), Protection of Wetlands 

E.O. 11990 directs that federal actions (i.e. federal funding or approvals) occurring within a federal jurisdictional 

wetland must be performed so as to minimize the destruction, loss, or degradation of wetlands.  This 

requirement is addressed by the USACE concurrent with their review pursuant to Section 404 of the CWA 

described above. 

4.2.1.2 Federal Endangered Species Act of 1973  

Section 10 of the Endangered Species Act (ESA) is designed to regulate a wide range of activities affecting plants 

and animals designated as Endangered or Threatened, and the habitats upon which they depend. With some 

exceptions, the ESA prohibits activities affecting these protected species and their habitats unless authorized by 

a permit from the U.S. Fish and Wildlife Service (USFWS) or the National Marine Fisheries Service (NMFS). 

Permitted activities are designed to be consistent with the conservation of the protected species.  

The ESA makes it unlawful to import or export; deliver, receive, carry, transport, or ship in interstate or foreign 

commerce in the course of a commercial activity; sell or offer for sale in interstate or foreign commerce; take 

(includes harm, harass, pursue, hunt, shoot, wound, kill, trap, capture, or collect any wildlife within the United 

States); take on the high seas; possess, ship, deliver, carry, transport, sell, or receive unlawfully taken wildlife; 

remove and reduce to possession any plant from areas under Federal jurisdiction; maliciously damage or destroy 

an endangered plant on areas under Federal jurisdiction; and, remove, cut, dig up, or damage or destroy any 

endangered plant in knowing violation of any State law or regulation or in the course of a violation of a State 

criminal trespass law. These prohibitions apply to live or dead animals or plants, their progeny (seeds in the case 

of plants), and parts or products derived from them.  

Section 7 of the ESA requires Federal agencies to consult with the USFWS to ensure that actions they fund, 

authorize, permit, or otherwise carry out will not jeopardize the continued existence of any listed species or 

adversely modify designated critical habitats.  

The presence or absence of federally protected species will be determined during preliminary design. 

4.2.1.3 National Pollutant Discharge Elimination System (NPDES) – Construction General Permit 

The NPDES Construction General Permit (CGP) authorizes stormwater discharges from construction activities 

that result in a total land disturbance of equal to or greater than one acre, where those discharges enter Waters 

of the United States or a municipal separate storm sewer system (MS4) leading to Waters of the United States 

subject to the conditions set forth in this permit. The proposed drainage and flood improvement projects will 

alter more than 1 acre of land and stormwater will be discharged to the Waters of the U.S.; therefore, 

compliance with the CGP is required. 

Pursuant to the requirements of the CGP, the project proponent, or designee, will prepare a Storm Water 

Pollution Prevention Pollution Plan (SWPPP) to document stormwater control measures during the construction 

periods for the projects. Following completion of the SWPPP, the proponent or designee will complete and 

submit to EPA a Notice of Intent to discharge stormwater. 

4.2.2  State Permits/Approvals 

4.2.2.1 Certificate from the Executive Office of Environmental Affairs (MEPA Approval)   

The Massachusetts Environmental Policy Act (MEPA) requires the review and evaluation of certain large‐scale 

projects to describe the environmental impact and requires that permit granting agencies identify feasible 

Page 70: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 4     Environmental Permitting   

4‐4 10678‐80349 

measures to mitigate potential environmental damage.  The MEPA Regulations (301 CMR 11.00) establish 

thresholds, a procedure, and time line for a two‐tiered review process, which generally proceeds as follows:  the 

project proponent submits an Environmental Notification Form (ENF) to the Secretary of Environmental Affairs 

(Secretary).  A twenty day public comment period follows during which time the Secretary receives comments 

from the public and agencies, and holds a site visit and consultation session.  Up to ten days following the close 

of the comment period, the Secretary issues a Certificate stating whether an Environmental Impact Report (EIR) 

is needed and what the scope of the EIR should include, if required.  If no EIR is needed the state permitting 

agencies can issue the required permits and the project can go forward.  Please note, MEPA approval is not 

required before an Order of Conditions is issued by a local Conservation Commission.  If an EIR is required, it is 

prepared by the proponent and submitted to the Secretary.  The EIR is reviewed and commented on at both 

Draft and Final stages by the public, state agencies, the Secretary, and the MEPA Unit.  After completion of 

review the Secretary issues a Certificate approving the project.   

Approximate time required to file an ENF is about two to four  weeks.  The approximate agency review time is 

five weeks (including the public comment period).  Approximate time to complete the EIR process is dependent 

upon the time needed to prepare the EIRs, but it is normally completed in twelve to twenty four months.  

4.2.2.2 Massachusetts Wetlands Protection Act (M.G.L. c.131, s.40; 310 CMR 10.00) 

The Massachusetts Wetlands Protection Act (MWPA) regulates alteration of state‐ defined wetland resource 

areas and the Massachusetts Wetlands Protection Regulations (310 CMR 10.00) identify wetland resource areas 

subject to protection and present the regulations for work in these wetland resource areas. Although a state 

law, the MWPA is administered at the local level by the municipal Conservation Commission. Areas known to be 

subject to protection at this time, based on Mass GIS datasource and City investigations, are shown on the 

recommended plan figures, and along the Connecticut, Mill and Old Mill Rivers.  

A Notice of Intent (NOI) will be prepared and submitted to the Northampton Conservation Commission for 

activities within areas subject to protection under the Massachusetts Wetlands Protection Act.   

4.2.2.3  Massachusetts Rivers Protection Act (Ch. 258 of the Acts of 1996; 310 CMR 10.58) 

The Rivers Protection Act protects perennial rivers, streams, brooks, etc., in the Commonwealth and is enacted 

through Section 10.58 of the Massachusetts Wetlands Protection Regulations. It establishes a 200‐foot wide 

Riverfront Area that extends horizontally on both sides of perennial waterways. In certain urban areas, the 

Riverfront Area is only 25 feet wide. The Connecticut, Mill and Old Mill Rivers are perennial rivers and have an 

associated 200‐foot wide Riverfront Area.   

Because the Rivers Protection Act is administered through the Wetlands Protection Regulations, the NOIs for the 

projects, described above, will address compliance with the Rivers Protection Act.  

4.2.2.4  401 Water Quality Certification Program (314 CMR 9.00) 

Section 401 of the Clean Water Act requires that states certify that federal actions will not prevent the 

attainment of state water quality criteria. The proposed projects will involve work in the Connecticut, Mill and 

Old Mill Rivers and associated wetlands, thereby requiring a permit from the USACE per Section 404 of the Clean 

Water Act. Consequently, a Water Quality Certification is required from the MassDEP per 314 CMR 9.00. For 

minor impact projects [projects that alter less than 5,000 square feet of federal and state jurisdictional wetlands 

and/or involve dredging less than 100 cubic yards of material and receive an Order of Conditions (wetlands 

permit) per the Massachusetts Wetlands Protection Act] no individual Water Quality Certification is needed. For 

projects that exceed those thresholds, an Individual Water Quality Certification is needed from the MassDEP. 

Page 71: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 4     Environmental Permitting   

4‐5 10678‐80349 

Massachusetts Stormwater Regulations: Recent revisions to 314 CMR 9.00 establish stormwater standards as a 

regulatory requirement. These standards were developed to regulate the quantity (flow) and quality of 

stormwater runoff from project sites. The proposed drainage and flood control improvements will require 

stormwater runoff control features and will need to comply with the standards to the maximum extent 

practicable. These provisions are reviewed by the Conservation Commission pursuant to the WPA and MassDEP 

via WQC application review. 

4.2.2.5  Massachusetts Endangered Species Act (M.G.L c.131A; 321 CMR 10.00) 

The Massachusetts Endangered Species Act (MESA) prohibits the "take" of any rare plant or animal species listed 

as Endangered, Threatened, or of Special Concern by the Massachusetts Division of Fisheries & Wildlife (MDFW). 

"Take" is defined in the Act as to harass, harm, pursue, hunt, shoot, hound, kill, trap, capture, collect, process, 

disrupt the nesting, breeding, feeding or migratory activity of an animal or to collect, pick, kill, transplant, cut or 

process a plant. Drainage improvements are located with estimated habitats and will involve work in the 

Connecticut, Mill and Historic Mill Rivers, which are also mapped as habitat for protected aquatic species.   

When projects involve MESA review and also require approval pursuant to the Massachusetts Wetlands 

Protection Act, MESA review can be initiated by submitting the NOI (wetland permit application) to MDFW. 

Through this joint review, the MDFW will determine whether a Take Permit is needed.  

4.2.2.6 Waterways Licensing Program (M.G.L. Chapter 91; 310 CMR 9.00) 

The Waterways Licensing Program was formally established in 1866 with the passage of M.G.L. Chapter 91. 

Chapter 91 jurisdiction extends to the mean high water mark of tidal water bodies and the ordinary high water 

mark of non‐tidal water bodies, and also includes "filled tidelands.” A Waterways License will be required for 

placement of fill or structures below ordinary high water line, of the Connecticut, Mill and Historic Mill Rivers. 

4.2.2.7 Environmental Results Program (310 CMR 7.26[42:43]) 

Under the Environmental Results Program (ERP), operators of new engines and new emergency engines are 

required to certify to MassDEP that they are complying with the environmental protection requirements that 

apply to the new engines.  Operators complete the Installation Compliance Certification Form, which has three 

sections.  The first section identifies the facility and contact information. The second part is a series of questions 

about whether the facility is following applicable environmental requirements.  The last part is the certification 

statement.  The certification needs to be completed within 60 days of starting operation. 

4.2.3  Local Permits/Approvals 

4.2.3.1 Wetlands Protection Act and City Ordinance 

The Massachusetts Wetlands Protection Act and Regulations were established to protect wetland resource areas 

because of the valuable functions wetlands provide such as: protection of public and private water supply; 

protection of groundwater supply; flood control; storm damage prevention; prevention of pollution; protection 

of land containing shellfish; protection of fisheries; and protection of wildlife habitat.  Authorization is required 

from the municipal Conservation Commission for any work in and adjacent to protected wetland resource areas 

as described above. 

In addition to the state law, the City adopted a wetlands protection ordinance to augment wetland protection. 

The work subject to the ordinance will be addressed in a single joint application (NOI) to address both state and 

local requirements.  

Please note, additional local approvals may be required by local Zoning Board of Appeals for work with the 

floodplain, Planning Board Review, and authorization to connect to municipal drainage systems.  Since this 

Page 72: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 4     Environmental Permitting   

4‐6 10678‐80349 

project is currently in the conceptual design stage, evaluation of these permitting requirements is beyond the 

scope of this document.  These issues will be evaluated in their entirety as needed.  

4.3  Conclusion The proposed drainage improvement, flood relief and river erosion improvement projects will require work in 

regulated resources, e.g. rivers and wetlands, and thus meeting applicable statutory and regulatory 

requirements is a critical project component during the preliminary design phase.  A program‐specific permitting 

plan will be developed to identify anticipated project impacts to regulated resources; permit thresholds; 

required permits; suggested measures to mitigate anticipated impacts; and a strategy and schedule to apply for 

environmental permits and approvals. 

Page 73: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

 

5‐1 106678‐80349‐03‐11.docx 

Section 5 ‐ Stormwater and Flood Control Utility 

5.1  Introduction Below is a summary of the drivers and main objectives of this section, a brief overview of the 

approach and methodology used in developing this report and a summary of the key findings. 

5.1.1  Objectives  

The City of Northampton (the “City” or “Northampton”) has actively begun to evaluate the funding 

needs to maintain the City’s flood control and stormwater infrastructure.  As part of this evaluation, 

the City requested that Camp Dresser & McKee Inc. (CDM) assess the option of implementing a 

stormwater and flood control utility by developing a financial framework and stormwater fee that 

could be used to recover costs incurred by the utility.  To provide the City with an understanding of 

how Stormwater and Flood Control Utility fees are structured, we have developed the following 

information: 

A planning level budget for the Stormwater and Flood Control Utility, which includes stormwater‐

related expenses currently funded through the sewer rate and General Fund, as well as 

anticipated capital improvements. 

An analysis of Geographic Information System (GIS) data and application of a standard industry 

methodology to determine the City’s equivalent residential unit (ERU) based on impervious area. 

A financial model that combines budgetary data with GIS/ERU data to develop a stormwater fee 

and assess its impact on typical customers.   

A discussion on some of the important policy considerations that are important to take into 

account when developing a Stormwater and Flood Control Utility and the associated fees.  

The remainder of this section will present the results of this evaluation. 

5.1.2  Stormwater Utilities in Other Communities 

In order to provide the City with a basis of comparison for stormwater and flood control utility 

implementation practices, CDM developed a comparison table which provides information on 

population, organizational structure, staffing needs, budget/funding activities funded by the utility 

and rates/fees.  The table has two sections.  The first section of the table reviews stormwater utilities 

in New England.  The second section reviews stormwater utilities across the country.  This 

comparison has been compiled using information from the EPA, planning commissions and CDM 

client experience.  The following is a list of sources and follow up documents that can be used to gain 

additional detail on stormwater utility implementation: 

Page 74: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐2 

106678‐80349‐03‐11.docxSection 5_050212.docx 

Table 5.1 

Stormwater Utilities in Other Communities 

 

 

 

 

 

 

New England Comparisons

Municipality  Population  Organizational Structure  Staffing Needs  Budget/Funding  Activities Funded   Rates/Fees 

Newton, MA 85,000 

 

Stormwater Management Program within DPW 

Full‐time engineer and four laborers 

$1.149 million (2011) 

Operations: stormwater engineer, pollution prevention, water quality sampling, corrective actions, personnel training, public education and outreach. 

 

Capital improvements: drainage improvements, sediment removal, culvert replacement and pump station rehab.   

 

Originally, annual uniform rate: $25 residential and $150 commercial.  Recently switched to ERU charge of $25 per unit annually, through water and sewer bills. 

Reading, MA  25,000  Enterprise Fund 

3 ½ equivalent laborers allocated to utility, 10% of DPW director, 10% of business supervisor and 10% of health administrator.  25% of accounting/finance clerk. 

$540,350 (2007) 

 Operations: street sweeping, vacuum truck rental, materials and supplies, consulting fees and staffing. 

 

Capital improvements: GIS mapping, drainage improvements, river restoration, street sweeper, vacuum truck and dump truck. 

ERU charge of $39.84 annually, billed through water and sewer bills. 

South Burlington, VT  16,000 Stormwater Management Department, DPW 

4 DPW laborers/engineers and 10% city planner. 

$1.250 million (2007 estimate) 

Operations: legal services, consulting fees, water quality monitoring, permitting, equipment and maintenance. 

 

Capital improvements: upgrades to culverts, retention ponds, drainage and catch basins, GIS services and infrastructure maintenance. 

ERU charge of $54 annually, through the water district. 

Lewiston, ME  42,000  Enterprise Fund  N/A $2.2 million (2011  estimate) 

Operations: billing and collections, street sweeping, catch basin cleaning, drainage repairs and general O&M. 

 

Capital improvements: GIS Mapping, pipe renewal and replacement, stormwater infrastructure maintenance. 

ERU charge of $40 for single‐family and $60 for duplex, annually.  All other customers, $40 base rate and .045 cents per sq. feet of impervious area above 2,900 sq. feet. 

Chicopee, MA  55,000  Stormwater Utility Bureau, DPW  N/A  N/A  N/A  ERU charge of $100 

Westfield, MA  41,000 Stormwater Utility, Special Revenue Fund 

   

Operations: labor, catch basin cleaning, street sweeping, illicit discharge detection and elimination, stormwater control device monitoring and inspection, water quality programs and monitoring, billing and administrative costs. 

 

Capital improvements: engineering, design, financing  and construction costs for new facilities or improvement of existing facilities. 

$20 flat fee for residential and impervious area‐based fee for non‐residential: $0.045 per square foot impervious surface, with a $100 minimum and $640 maximum 

Page 75: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐3 

106678‐80349‐03‐11.docxSection 5_050212.docx 

Table 5.1 (con’t) 

Stormwater Utilities in Other Communities 

United States Comparisons

Municipality  Population  Organizational Structure  Staffing Needs  Budget/Funding  Activities Funded  Rates/Fees 

Lancaster, PA  500,000  Enterprise Fund (planning level)  N/A $1.832 million (2011 estimate) 

Operations:  public education and outreach, illicit discharge detection and elimination, construction site runoff control, street sweeping, catch basin cleaning, GIS mapping and stormwater management staff training. 

Capital Improvements: N/A 

ERU charge of $16.53 (planning stages) 

Bellevue, WA  117,000 Part of Utilities Department 

45 to 50 full time equivalent employees 

$10 million (2004)  

Gross Area and Intensity of Development, $120 annually 

Charlotte/Mecklenburg County, NC 

1,500,000  County Utility with inter‐governmental agreements 

105 full time equivalent employees 

$85 million  

Flat rate for single‐family residential with ERU basis for other customer classes.  Rates vary by location. 

Tulsa, OH  392,000 Part of Public Works 

 $12‐$14 million (2002) 

  Impervious area/ERU basis $42 annually. 

Louisville/Jefferson County Metropolitan Service District, KY 

 Part of Sewer District 

600 full time equivalent employees (includes sewer) 

$26.7 million (2006) 

 Flat rate for single‐family residential.  Impervious area/ERU basis for other2. $56.40 annually. 

Sarasota County, FL  340,000  County Utility  120 employees  $20 million (2005)    Assessments vary by geographic location. 

Griffin, GA  25,000 City Department, with shared DPW Director 

15 full time staff $1.2 million (2000) 

Operations: personnel and benefits, contracted services, supplies, debt service 

ERU charge of $35.40 annually. 

Union, OH  6,400 

Program within DPW 

7  hourly employees  $75,000 Operations: storm drain maintenance, catch basin cleaning 

Flat Fee System (Impervious area was too complex for a small community) 

 

Annual Cost: 

Residential: $36 

Commercial: $72 

Industrial: $108 

Fort Collins, CO  109,000 

Program within the Utility Department 

25 full time equivalent staff, some staffed are shared and some exclusive to the stormwater program 

$7.2 million (2000) 

Operations: storm drain maintenance and repair, water quality improvement, new construction development reviews, floodplain management and design of relevant capital projects. 

Each parcel is charged a basin fee rate, which varies by geographic location and takes into account on‐site detention reduction factor and a runoff coefficient for each parcel 

 

The runoff coefficient uses a formula that takes into account the percentages of impervious area, pervious area and semi‐pervious area on a per parcel basis 

Valparaiso, IN  25,000 Department of Stormwater Managment 

No full time employees, only reimburses City staff for labor on stormwater related business 

$520,000 (2000) Operations: collection, disposal and drainage of stormwater. 

ERU of $36, with multiplier for impervious area, which is broken into 6 ranges, the largest of which charges $1,152 annually for impervious area > 160,000 sq. feet 

 

Page 76: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐4 106678‐80349‐03‐11.docx  

1. Assessment of Stormwater Financing in New England, Charles River Watershed Authority, March 30, 2007. 

2. Guidance for Municipal Stormwater Funding, National Association of Flood and Stormwater Management 

Agencies, January, 2006. 

3. How to Create a Stormwater Utility, Pioneer Valley Planning Commission, November 13, 1998. 

4. Stormwaterfinance.urbancenter.iupui.edu, Center for Urban Policy and the Environment. 

5. Utility Stormwater Survey, Black & Veatch, 2010. 

6. South Burlington Stormwater Utility, Stormwater Credit Fee Manual, Hoyle, Tanner & Associate, Inc.s and 

AMC Earth & Removal, Inc., February, 2006. 

5.1.3  Methodology 

To develop the analysis of a separate Stormwater and Flood Control Utility, stormwater‐related costs currently 

being funded through the General Fund and Sewer Utility were identified through discussions with the City.  

Based on these discussions, the portion of General Fund and Sewer Utility costs attributable to stormwater were 

allocated to the Stormwater and Flood Control Utility.  Having combined these costs with anticipated capital 

improvements outlined in Section 3, CDM developed revenue requirement projections for the Stormwater and 

Flood Control Utility and paired our financial projections with impervious area parcel data to determine a rate 

per “ERU”.   

The results of this analysis are compiled in this report, the goal of which is to provide the City with the necessary 

information to make an informed decision on how it could implement a Stormwater and Flood Control Utility in 

order to equitably recover the costs of collecting and treating stormwater through a separate rate.  Given this 

objective, we focused on three sequential tasks in our analysis, which are as follows: 

1.  Estimated Stormwater and Flood Control Utility revenue requirements 

2.  Assessed the City’s impervious surface area and used it to develop an ERU‐type billing system 

3.  Calculated a rate per equivalent unit and summarized the impact the rate would have on typical customers 

This analysis uses FY 2011 as the base year for the projections.  The City would not anticipate implementing the 

Stormwater and Flood Control Utility within the remainder of the fiscal year.  However, it is shown as a basis for 

the projections to indicate how the rate would be calculated under the most current expense period.   

5.1.4  Key Findings 

Should the City choose to implement a stormwater utility, CDM recommends using an ERU fee, which we believe 

will most appropriately distribute the costs of the stormwater system.  This is an equitable approach that 

depends on impervious area, but simplifies the billing system and GIS data requirements needed for 

implementation.  Under the ERU system, residential units would be assigned one billing unit per dwelling unit, 

up to a three‐family unit.  Therefore, a single‐family would be assigned one billing unit; a duplex, two billing 

units; and a three‐family, three billing units.  Larger residential units (i.e. more than three units) and non‐

residential parcels would be assigned billing units based on the amount of parcel impervious area to the 

equivalent residential unit amount which CDM has estimated for purposes of this analysis to be 2,671 square 

feet (full calculation is shown in Table 5.8).  This approach equitably allocates the costs of the system, since 

customers with more impervious area create a greater burden on the system and thus should be responsible for 

more of the costs.   

Page 77: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐5 106678‐80349‐03‐11.docx  

The resulting stormwater fee from an ERU approach is shown in Table 5.2. 

Table 5.2 

Proposed FY 2012 Equivalent Residential Unit Stormwater Fee Schedule 

Classification  Billing Units  ERU  Rate per ERU 

Single‐family  1  1.00  $66.63 

2‐Family  2  2.00  $133.26 

3‐Family  3  3.00  $199.90 

Classification Impervious 

Area ERU  Rate per ERU 

Large Residential  10,821  4.05  $269.95 

Commercial/Industrial with 1,000 sq. feet of IA  1,000  0.37  $24.95 

Commercial/Industrial with 10,000 sq. feet of IA  10,000  3.74  $249.46 

Commercial/Industrial with 100,000 sq. feet of IA  100,000  37.44  $2,494.58 

 

A common concern about the implementation of a stormwater and flood control fee is the impact to 

commercial and industrial customers, which typically have a higher proportion of impervious area than small 

residential customers.   Additionally, in some cases, commercial users who do not discharge significant levels of 

wastewater may have a significant level of impervious surface area.  The shifting cost burden can be difficult for 

businesses to appropriately budget for.  If the City is concerned about the effect of stormwater and flood control 

fees on certain customer classes, there are certain measures that can be taken to mitigate their impact, such as 

stormwater management credits, phased implementation, or continuing to recover a portion of stormwater and 

flood control costs through the General Fund. 

5.2  Stormwater and Flood Control Utility Implementation Considerations 

Despite increasing state‐wide interest in Stormwater and Flood Control Utility creation as a means to effectively 

manage permit requirements and equitably distribute the cost of stormwater impacts, the concept is still 

relatively new to the world of flood control and pollution management.  Implementing stormwater utilities is a 

significant undertaking and, unfortunately, the lack of existing utilities serves to limit the number of examples 

that can be used in assessing best practices.  Given those limitations, this section combines information from 

existing utilities, planning documents and CDM’s experience in helping clients to establish stormwater utilities, in 

order to assist the City in its evaluation of creating a new utility.  

5.2.1 Stormwater and Flood Control Utility Background 

The establishment of stormwater utilities is a concept that has achieved growing popularity in the United States 

since the mid‐1970s.  The fundamental basis for the Stormwater and Flood Control Utility is that as the amount 

of impervious area increases on a parcel, the amount of runoff from that parcel increases proportionately.  

Therefore, the amount a parcel owner is charged is related to its impervious area.  The impervious area charge is 

an equitable funding mechanism, since charges assessed to each parcel of land are based upon usage of the 

drainage system..   

Page 78: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐6 106678‐80349‐03‐11.docx  

The average impervious area per dwelling unit for residential land use categories is typically designated as the 

“base unit” for the utility fee structure.  The base unit represents the impervious area discharge potential of the 

average residential dwelling and its associated lot.  It can be based upon all residential development (including 

multi‐family), on single‐family residential development only, or a combination to encompass smaller residential 

developments.  For this analysis, the average impervious area of the base unit is calculated by summing the 

impervious area for smaller residential parcels (defined as structures less than four units) and dividing by the 

total number of dwelling units within those structures.  This basic unit is referred to as an equivalent residential 

unit (ERU). 

Under this approach, large residential properties (greater than three units), and non‐residential parcels are billed 

based on the amount of impervious area on the parcel relative to the ERU amount.  For example, if a commercial 

parcel has four times as much impervious area as the base ERU unit, the commercial site would be billed four 

times the residential flat fee.   

During the initial history of stormwater utilities, it was relatively expensive to develop the necessary parcel 

information to determine billing units and assign billing units to specific parcels.  It frequently required hand 

measuring parcels and conducting samples of residential parcels to estimate the ERU.  However, as GIS 

technology has improved, the costs of developing and implementing utilities have declined.  Many municipalities 

now include impervious area as a layer within their GIS and it is possible to determine, with a high level of 

accuracy, the impervious cover on each parcel.   

Due to the declining costs and increasing ease with which impervious area can be mapped, some utilities now 

bill customers individually based on the actual amount of impervious area on the parcel regardless of whether 

the property is residential or non‐residential.  The result is that each parcel or customer’s fee is based on its 

impact on the municipal system making the stormwater charge more consistent with other utility charges (i.e., 

water, sewer, electric).  The main obstacle to this approach is developing the detailed GIS impervious area maps, 

which despite technological advancements, still requires a significant effort, specifically in instances of “open 

polygons”.  A common example of this is a driveway, which GIS applications have difficulty delineating, relative 

to something like a roof, which is a closed polygon.  

5.2.2  Structural Considerations 

The first step towards creating a Stormwater and Flood Control Utility is generally drafting appropriate language 

as part of an ordinance.  The City Council would typically approve the ordinance to establish the utility.  Some 

general guidelines to consider include: 

Citing the existing legal authority to establish the Stormwater and Flood Control Utility 

Showing evidence of the need to create the Stormwater and Flood Control Utility, and the processes 

required for its creation 

Creating the utility in a way that ensures consistency with local, state, and federal guidelines 

The ordinance should explicitly define the role and purpose of the utility, as well as the utility’s ability to charge 

and collect fees.  It should further establish the process by which the stormwater fees and charges are set, 

including the methodology behind the calculation and any potential exclusions for parcels such as undeveloped 

land or municipal properties.  The ordinance should also detail any credits that are available and the process by 

which a resident could appeal a charge.  We suggest the City begin reviewing existing stormwater ordinances in 

other communities, as well as the City’s Sewer Utility ordinance, as a basis for its own stormwater ordinance. 

Page 79: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐7 106678‐80349‐03‐11.docx  

5.2.3  Public Education and Involvement 

The City should consider developing a public education program designed to educate the community on the 

reasons behind creating a Stormwater and Flood Control Utility, highlighting the negative impacts of stormwater 

pollution.  Public support for the utility may make it easier to implement the fees and charges necessary to fund 

the utility.  Educating the public on the basics and the impact of pollutants in stormwater may also have the 

effect of creating a change in behavior and encouraging better stormwater management practices from 

residents and businesses.   

The City should identify the amount available to allocate towards public education and outreach, and formulate 

activities it believes will be most effective for public consumption.  Examples of activities include distributing 

flyers or press releases outlining the role and purpose of the Stormwater and Flood Control Utility, incorporating 

the basics of stormwater into school curriculum, and/or hosting public events.  As a planning level estimate, 

CDM has included a $20,000 line item for public education into its incremental budget in the revenue 

requirement subsection. 

In defining the steps for public education and acceptance for the creation of a Stormwater and Flood Control 

Utility, it is important to define the message the City wants to convey to the public, and the means by which to 

convey it in an effective manner.  Generally, before the creation of the utility, the focus of public outreach is to 

describe the utility and its general functions and to justify the need for a separate stormwater fee.  For the City, 

the message would most likely highlight the environmental and health impacts of stormwater pollutants and 

requirements to remain in compliance with permit guidelines.  

A common method to facilitate public education is through the distribution of flyers and educational packets, 

incorporating stormwater information into school curricula, public hearings or press releases, inserts that 

accompany water and sewer bills outlining the need for a Stormwater and Flood Control Utility, and/ a 

dedicated website with stormwater education.  Given that the City has decided to establish the utility as a 

standalone enterprise utility, establishing a separate page on the City website dedicated to the Stormwater and 

Flood Control Utility may be useful, with information on why the utility is being established, and a justification 

for the stormwater and flood control fee.  The site could also contain links to various web resources that 

facilitate public education on the topic.  See the website for the South Burlington, VT stormwater utility that 

provides detailed information about their utility (sburlstormwater.com). 

In conjunction with educating the public on the need for the new Stormwater and Flood Control Utility and fee, 

it could also be useful to highlight behaviors that would encourage stormwater pollution prevention.  Part of the 

education process for the acceptance of the utility creation will include showing the public the negative impacts 

of stormwater pollution, consistent with the EPA NPDES Phase II requirements, so the City may consider using 

that opportunity to provide the public with ways they can help reduce stormwater pollution.  It would be useful 

to continue this sort of public outreach on an ongoing basis after the creation of the Stormwater and Flood 

Control Utility and the implementation and acceptance of the fee. 

5.2.4  Management and Budgeting 

Another key aspect to creating a Stormwater and Flood Control Utility is determining how the utility is to be 

managed.  A new Stormwater and Flood Control Utility would operate as a stand‐alone enterprise utility, which 

means that the utility would have its own separate budget with line item expenses, and the stormwater charges 

would be set annually to directly offset these expenses.   

Page 80: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐8 106678‐80349‐03‐11.docx  

5.2.4.1 Budgeting 

The City worked with CDM to identify the staffing and budgetary needs to operate the Stormwater and Flood 

Control Utility.  In order to develop planning level estimates, CDM worked with the City to allocate stormwater‐

related expenses from the General Fund and Sewer Utility.  In addition to this, CDM developed incremental 

Stormwater and Flood Control Utility costs.  These are operation and maintenance (O&M) costs that will be 

required to operate the City’s Stormwater and Flood Control Utility and meet permit requirements.   

CDM also provided the Stormwater and Flood Control Utility with a capital improvements plan (CIP), which is 

included in revenue requirement projections and must be considered in the budgeting process.  In addition to 

the CDM‐prepared CIP, the City may need to consider making some additional capital outlays, such as additional 

street sweepers and maintenance vehicles, as it moves forward with its Stormwater and Flood Control Utility 

implementation.  As the City gains a better understanding of the operating costs and capital needs for the 

Stormwater and Flood Control Utility, these estimates will need to be adjusted to more accurately reflect the 

true cost of service. 

5.2.4.2 Billing 

The City will need to establish an appropriate and functioning billing system in order to ensure billing accuracy 

for the stormwater fee.  A common practice is to include the stormwater charge as part of an already existing 

municipal bill (e.g. water and sewer).  It is generally assumed that the municipality would have a master file of 

accounts through some computerized billing program, so the most reasonable way to incorporate the charge is 

to populate the master file with the relevant information pertaining to the stormwater charge.   

A potential issue with the implementation of this rate structure that the City would need to consider is land 

areas not connected to other municipal utilities.  One example of this is parcels that have private wells and 

septic systems.  Another example is vacant parcels, which do not have utility services.  The City has over 2.7 

million square feet of undevelopable impervious land area, and another 4.2 million square feet in impervious 

area with unknown classification.  If the City were to include the stormwater charge as part of another utility bill 

and incorporate the same customer listing, it would omit the vacant land.   

An alternative approach to billing would be to include the stormwater fee as part of the property tax bill.  All 

taxable property listings would be accounted for, so a property would not need to have municipal utility service 

in order to be included for the fee.  However, this approach creates a similar but separate issue – the exclusion 

of tax‐exempt properties.  Exempt (municipal, colleges, etc.) impervious area totals around 16.2 million square 

feet, and would not appear on the tax rolls or receive a property tax bill.  The City will need to assess the billing 

issues associated with the new stormwater fee and determine the appropriate course of action.    

A third approach would be to conduct stand‐alone utility billing.  However, CDM recommends against this 

practice, as it would be redundant with current services and would add an additional layer of administrative 

costs to the utility.  For this reason, a stand‐alone billing approach is rarely used by stormwater utilities. 

5.2.5  Funding Options 

There are a variety of rate/fee mechanisms for recovering Stormwater and Flood Control Utility revenue 

requirements.  As we have developed this report, based on discussions with the City, we have taken an ERU 

approach.  We have included this section on funding options for the purpose of providing the City alternative 

approaches to the one proposed in the report, as well as providing an understanding of why the ERU was used 

as the cost recovery method in this report. 

Page 81: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐9 106678‐80349‐03‐11.docx  

In large part, rate/fee setting principles focus on the equity of cost recovery.  Equity refers to setting rates at a 

level that generates adequate revenue to fund revenue requirements, while also aligning to recover the actual 

cost of service to operate and maintain the system.  

Some of the general methodologies for stormwater rate and fee setting utilized by other communities include: 

uniform charges based on property type, rates based solely on impervious area, a combination of impervious 

and gross area, impervious area and percent of impervious area, gross property area and intensity of 

development, and runoff factors.  In addition to the various rates and fees, the City may also choose to recover 

stormwater costs through the General Fund, which is largely what it does at present.  A brief analysis of these 

types of rate and fee structures follows. 

Uniform charge/flat fee based on property type ‐ Each property is defined as either residential or non‐

residential, and charged a uniform fee based on customer class.  This structure has the benefit of being easy to 

understand and easy to implement, as it only requires analysis of property data with a residential or non‐

residential designation for each property.  The main shortcoming is that it does not necessarily match the rate 

with a property’s impact on the stormwater system.  For example, a small retail store with a total of 1,000 

square feet would be paying the same non‐residential uniform charge as a large commercial building with a 

property size of 100,000 square feet.  Recently, the City of Newton, MA switched from this rate structure to an 

ERU‐based structure for its stormwater system to more closely match the rates with a customer’s burden to the 

system. 

Rates based solely on impervious area ‐ This is a common approach for stormwater utilities, as it is simple to 

understand, easy to calculate and readily justifiable to the public.  The underlying principal of an impervious area 

fee is that the more impervious area a property has, the larger the impact it has on the stormwater system.  

Thus, it should have a proportional charge to its impact on the system.  This structure is used with a calculated 

charge per ERU for small residential customers based on the average impervious area for that class category.  

Larger residential and commercial customers are charged based on actual impervious area as a multiple of the 

rate per ERU.  This is the rate structure we recommend for the City, and the detailed calculations and description 

of this structure are in Section 5.4 of this report.  

Rates based on impervious area and gross area ‐ Impervious area and gross area are both included in this 

methodology based on the logic that all land area has some impact on the stormwater system.  Setting the 

stormwater fee involves allocating either a percent distribution between impervious area and gross area, or a 

detailed cost of service that allocates costs to one or the other.  A benefit of this rate structure is the implicit 

decision to charge underdeveloped land, which expands the base for distributing the costs among the 

community residents.  One deterrent to implementing this approach is equitably determining the allocation 

factors used and effectively educating customers on the methodology. 

Impervious area and percentage of impervious cover ‐ Users are charged a rate per 100 square feet, which is 

defined by the percentage of impervious area to gross area on a property.  The rates are generally set as 

increasing in a percentage range (e.g. 0‐15%, 15‐20%, etc.), with the idea being that the more impervious area 

on a property, the greater the burden.  This rate structure is currently used by the City of Denver, CO.    

Gross area and intensity of development ‐ An intensity of development factor is assigned to properties to 

estimate the amount of impervious area per parcel.  The calculation can be as simple as taking a parcel’s gross 

area and multiplying it by the factor.  Cincinnati, OH, for example, assigns a factor of zero to undeveloped land 

up to a factor of 0.85 for commercial customers.  A potential benefit of this structure is employed by Bellevue, 

WA, in which a small rate is assessed to undeveloped properties, allowing for some cost recovery from 

Page 82: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐10 106678‐80349‐03‐11.docx  

undeveloped lands.  The justification follows the same logic as the impervious and gross area rate structure – all 

land contributes to the stormwater system, and so should be assessed some charge.   

Runoff factor ‐ This structure aims to apply a set of factors to parcels generally in land use categories in order to 

account for the amount of stormwater estimated during a storm event.  It is similar to the intensity of 

development factor, however it is usually considered a better gauge of the amount of actual stormwater by land 

use type, but more difficult to describe and justify to the public.   

5.2.6  Stormwater Credits 

The impact to customers with large amounts of impervious area can often be significant, relative to their current 

costs incurred through General Fund taxation.  While a stormwater fee is the most equitable means for 

recovering stormwater costs, relative to charging for the behavior and conditions that create stormwater runoff, 

in some cases, it may be considered over burdensome to certain users in the system.  There are several methods 

that can be used to help control costs for these users, including phasing in stormwater fees, or providing users 

with stormwater credits.  This subsection focuses on the latter of the three alternatives. 

As discussed in Sections 2 and 3, credits or exemptions can be used to incentivize certain practices or to provide 

relief from utility fees based on specific types of land uses. Stormwater utilities typically provide credits in two 

circumstances. The first is when a property owner has put in place stormwater controls that provide relief 

beyond what may have been required as a condition of property development.  The second is for properties that 

can demonstrate that they have mitigated their impact on the municipal stormwater infrastructure through 

improved stormwater treatment practices, whether it is a reduction in quantity or improvement in water quality 

of stormwater runoff. 

Some examples of practices where stormwater credits may be applied are: 

Detention ponds 

Stream buffers and filters 

Green rooftops 

Conservation of natural areas in new development 

Reforestation  

Low income credits for residential customers proving financial hardship 

In addition to stormwater treatment practices, some utilities and municipalities also provide credit related to 

stormwater education, as well as for stormwater systems that are separate from the municipal system, but have 

been required to comply with MS4 permitting requirements. 

In order to implement a stormwater credit system, it is necessary to develop a well‐defined set of guidelines and 

procedures to govern them.  The City must define the types of credits they can offer and the specific criteria for 

meeting the credit requirements.  Some examples of specific criteria that may be necessary to develop are 

determining a minimum contiguous area for conservation areas, determining the minimum distance for a buffer 

zone, setting a maximum gradient for filters and buffers and determining the maximum amount of fee reduction 

for a given credit. 

It is also necessary to support the credit program through a permitting process that requires application, 

certification and follow‐up inspections to ensure the credit continues to be maintained and valid.   Relative to 

Page 83: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐11 106678‐80349‐03‐11.docx  

the application process it is necessary to develop the appropriate paperwork and maintain administrative staff 

to manage the process.  For certification and inspection, the City must also maintain staff that is capable of 

evaluating the structural and environmental aspects of stormwater controls.  Should the City seek to develop a 

stormwater credit program, there are numerous examples and guidelines present to help guide this process. 

In Section 3, CDM identified locations in the recommended plan where retail, commercial and industrial 

businesses should implement on‐site stormwater BMPs to reduce flows to the drainage system.  These 

businesses have a significant amount of impervious area and will pay comparatively higher fees; thus, to reduce 

their burden, they would benefit from a stormwater credit program such as the one discussed in this section. 

5.3  Projected Revenue Requirement The purpose of this section is to project the revenue requirement for the City’s hypothetical stormwater utility.  

In general, the revenue requirement is calculated by adding operations and maintenance expenses, existing and 

anticipated debt service, cash funded capital expenditures, and netting miscellaneous revenue.  Since the 

stormwater utility would have no miscellaneous revenue associated with it, the revenue requirement is simply 

the total of the allocated O&M expense and debt service on stormwater capital.   

The City identified both direct and indirect operating expense items that were applicable to operating the 

stormwater system.     

5.3.1  General Assumptions 

In order to project the stormwater expenses, a set of assumptions were used in this analysis.  CDM believes the 

assumptions to be reasonable and prudent for the purposes of the analysis.  Key assumptions are as follows: 

Projections are based on the City’s FY 2011 Revised Budget and FY 2012 Department Request; 

Operations and maintenance costs are inflated at 3.0 percent annually.  This includes personnel and 

overtime expenses; 

Energy‐related costs are inflated at 5.0 percent annually; 

The entirety of the operating expenses currently covered in the General Fund related to flood control would be allocated to the stormwater utility; 

General operations and maintenance expenses currently covered in the General Fund related to storm 

drains would be allocated to the stormwater utility.  One‐third of the personnel costs would be covered by 

the stormwater utility, with the exception of overtime which is split 50/50; 

Since no indirect cost allocation currently exists for the stormwater utility, the allocation schedule is 

assumed to follow the schedule currently used for the sewer fund.  The major exception is indirect costs for 

PILOT, which have been excluded from the allocation to the stormwater utility.   

Capital outlays are not assumed to be funded as part of the stormwater utility; 

The City currently has $250,000 in authorized borrowing not yet spent.  It is assumed that this amount will 

be bonded as General Obligation (GO) debt for stormwater‐related projects in FY 2012;  

The capital projects in the proposed CIP are inflated to the mid‐point of construction, and are assumed to be 

financed through GO bonds (i.e. no cash funded capital projects);  

Page 84: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐12 106678‐80349‐03‐11.docx  

GO debt is assumed issued at a rate of 5.5 percent with an amortization period of 20 years.  Cost of issuance 

is assumed to be 1 percent; 

Stormwater utility personnel are assumed to have a fully loaded salary, including benefits, of $50,000 

annually; 

Municipal Separate Storm Sewer System (MS4) permit compliance staff at the stormwater utility are 

assumed to have a fully loaded salary, including benefits, of $60,000; and 

Rental rates for stormwater utility vehicles have been calculated based on the 10‐year amortization period 

for the cost of the vehicle, plus a 10 percent markup for mileage costs. 

5.3.2  Operations and Maintenance Expenses 

O&M expenses for the Stormwater and Flood Control Utility have been broken into two categories.  The first is 

incremental O&M costs, which are new costs that will be incurred by the utility to meet MS4 compliance costs.  

The second category is the cost allocations presently incurred by the City that are being transferred to the 

Stormwater and Flood Control Utility. 

5.3.2.1 Incremental O&M 

Incremental expenses have been determined based on discussions with the City and best estimates for 

stormwater implementation costs.  Incremental costs included in the analysis are as shown in Table 5.3.   

Monitoring and MS4 compliance staff have been included based on estimates from CDM.  Per discussions with 

the City, two O&M staff have been included for catch basin cleaning, street sweeping and vactor operations, a 

billing clerk has been added to handle additional billing administrative responsibilities and an expense line item 

has been added for public outreach.  Additional equipment, including a street sweeper, part‐time use of a vactor 

truck and a vehicle for catch basin cleaning, have been included to support these O&M activities.  A $20,000 

increase in energy expenses has also been assumed to support these activities. 

Table 5.3 

Projected Incremental O&M 

  2011  2012  2013  2014  2015  2016 

Monitoring  $100,000   $103,000   $106,090   $109,273   $112,551   $115,927  

MS4 Staff  $60,000   $61,800   $63,654   $65,564   $67,531   $69,556  

O&M Staff  $100,000   $103,000   $106,090   $109,273   $112,551   $115,927  

O&M Vehicle  $2,877   $2,963   $3,052   $3,144   $3,238   $3,335  

Vactor Truck  $19,927   $20,525   $21,141   $21,775   $22,428   $23,101  

Street Sweeper  $29,891   $30,788   $31,711   $32,663   $33,643   $34,652  

Billing Clerk  $50,000   $51,500   $53,045   $54,636   $56,275   $57,964  

Public Education  $20,000   $20,600   $21,218   $21,855   $22,510   $23,185  

Energy Costs  $20,000  $20,600  $21,218  $21,855  $22,510  $23,185 

Total   $402,695   $414,776   $427,219   $440,036   $453,237   $466,834  

 

Page 85: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐13 106678‐80349‐03‐11.docx  

5.3.2.2 Allocated O&M 

The stormwater operating expenses have been separated into five categories: Overtime, Flood Control, Storm 

Drains Personnel, Storm Drains O&M, and Indirect Costs.  The detailed allocation factors from both the General 

Fund and the indirect cost schedule are listed in the General Assumptions (Section 5.3.1).  It should be noted 

that within this allocation are the salaries of key staff members, including engineering, administrative services 

and key management personnel. 

Table 5.4 summarizes the operating expense allocation for each category, and the total eligible for cost recovery 

through the stormwater and flood control fee.  These amounts do not include capital outlay.  Of total O&M 

expenses, incremental expenses account for slightly less than 30 percent of total O&M. 

Table 5.4 

Stormwater O&M and Capital Outlay by Category, FY 2011 ‐ FY 2016 

2011  2012  2013  2014  2015  2016 

Existing Budget Allocations 

Overtime  $23,000  $23,000  $23,690  $24,401  $25,133  $25,887 

Flood Control  $32,625  $32,625  $33,884  $35,194  $36,559  $37,980 

Storm Drains Personnel  $109,397  $109,639  $112,928  $116,316  $119,805  $123,399 

Storm Drains O&M  $54,050  $54,050  $55,672  $57,342  $59,062  $60,834 

Indirect Costs  $848,465  $933,870  $961,886  $990,743  $1,020,465  $1,051,079 

Total Allocated O&M  $1,067,537  $1,153,184  $1,188,059  $1,223,995  $1,261,024  $1,299,178 

                    

Incremental O&M  $402,695  $414,776  $427,219  $440,036  $453,237  $466,834 

                    

Total Allocated O&M Expenses  $1,470,232  $1,567,960  $1,615,279  $1,664,031  $1,714,261  $1,766,013 

 

5.3.3  Debt Service Expenses 

Table 5.5 summarizes the debt service for the Stormwater and Flood Control Utility.  The existing debt service is 

associated with the $310,000 GO bond issue in FY 2007 related to Ridgewood Terrace Reconstruction, and the 

$100,000 GO debt issue in FY 2011 pertaining to drainage projects.  The City has $250,000 in authorized 

borrowing remaining on the most recent drainage improvement spending, which for the purposes of this 

exercise is assumed to be bonded in FY 2012 for general drainage system improvements and included in the 

anticipated debt service.   Anticipated debt service also includes the proposed CIP, $95.6M in capital spending on 

the stormwater system over the next 20 years.  For the purposes of these projections, no cash funded capital 

projects assumed.   

   

Page 86: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐14 106678‐80349‐03‐11.docx  

Table 5.5 

Debt Service 

  2011  2012  2013  2014  2015  2016 

Existing Debt Service   $48,340    $54,644    $41,944    $38,684    $37,484    $35,474  

Anticipated Debt Service  $0  $69,850  $316,548  $789,821  $1,337,643  $2,048,693 

Total Annual Debt Service  $48,340  $124,494  $358,492  $828,505  $1,375,127  $2,084,167 

 

5.3.4  Revenue Requirement 

Table 5.6 shows the anticipated revenue requirement for the Stormwater and Flood Control Utility through FY 

2016.   

Table 5.6 

Revenue Requirement 

2011  2012  2013  2014  2015  2016 

O&M  $1,470,232   $1,567,960  $1,615,279   $1,664,031    $1,714,261    $1,766,013  

Existing Debt Service  $48,340  $54,644  $41,944  $38,684  $37,484  $35,474 

Anticipated Debt Service  $0  $69,850  $316,548  $789,821  $1,337,643  $2,048,693 

Revenue Requirement  $1,518,572  $1,692,454  $1,973,771  $2,492,536  $3,089,388  $3,850,180 

 

Figure 5.1 

Revenue Requirement (thousands) 

 

$‐

$500 

$1,000 

$1,500 

$2,000 

$2,500 

$3,000 

$3,500 

$4,000 

$4,500 

2011 2012 2013 2014 2015 2016

O&M Existing Debt Service Anticipated Debt Service

Page 87: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐15 106678‐80349‐03‐11.docx  

5.4  Parcel Analysis and Equivalent Residential Unit Calculation 5.4.1  Impervious Area  

In determining a stormwater and flood control fee, it is necessary to separate out impervious area data for the 

City by land use characteristics.   In undertaking this task, CDM used existing GIS information made available by 

Mass GIS to generate a sorted list of impervious area by land use. The intent of this analysis is to understand the 

impervious area characteristics in the City and in turn the financial impact of assessing impervious area‐based 

stormwater and flood control rates on a permanent basis.  

In conducting its analysis, CDM sorted available GIS data into four main categories: Residential, 

Commercial/Industrial, Tax Exempt, and Other (which includes categories such as agricultural, forestation and 

recreational).  The summary of this data is shown in Table 5.7 and displayed graphically in Figure 5.2.   

 

 

Table 5.7 

Total Impervious Area and Parcel Count by Classification 

Customer Classification  Impervious Area (square feet) 

Residential  28,595,854 

Commercial/Industrial  21,336,871 

Tax Exempt  16,191,191 

Other  1,641,422 

Total Impervious Area  67,765,338 

 

   

Page 88: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐16 106678‐80349‐03‐11.docx  

 

Figure 5.2 

Total Impervious Area and Parcel Count by Classification 

 

   

Page 89: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐17 106678‐80349‐03‐11.docx  

5.4.2  Equivalent Residential Unit Calculation 

In order to assess the potential impact of incorporating a stormwater fee with an ERU structure, it was necessary 

to determine the impervious area per equivalent residential unit (ERU). The base ERU for this analysis is defined 

as the average impervious area per ERU for small residential structures up through three‐family units.   

Determining average impervious area per ERU required matching the residential categories within the 

Massachusetts Department of Revenue land use codes with estimates on dwelling units.  Based on data 

provided by the City, Northampton contains 9,600 units defined as either single‐family, two‐family, or three‐

family (Table 5.8).  Based on the total number of residential accounts, the average impervious area per unit is 

approximately 2,671 square feet for small residential customers. 

Table 5.8 

Distribution of Dwelling Units, Impervious Area and ERU Calculation 

ERU Calculation 

Impervious Area (sq. ft. thousands) 

Single‐Family1  21,315 

Two‐Family  3,551 

Three‐Family  +  829 

Total   25,696 

Number of Units (thousands)

Single‐Family1  7.3 

Two‐Family  1.8 

Three‐Family  +  0.5 

Total  9.6 

Number of Units (thousands)

Total Impervious Area  25,696 

Total Units     9.6 

Equivalent Residential Unit (sq. ft.)   2,671 

                                                  1 Includes condominiums and mobile homes 

The next step in developing a stormwater fee is to determine the number of ERUs in each of the remaining 

customer classes.  This includes: commercial/industrial, tax exempt, large residential and other customers.  This 

data was compiled by totaling the amount of impervious area within each category and dividing it by the 

average amount of impervious area per small residential dwelling unit (i.e. the ERU).  Table 5.9 below reflects 

the calculations determining the dwelling units for the other customer classes. 

   

Page 90: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐18 106678‐80349‐03‐11.docx  

Table 5.9 

Number of Billing Units by Customer Classification (Non‐Residential) 

Non‐Residential Customers Area Square Feet Impervious 

(Total) 

Number of Equivalent Residential Units 

(thousands) 

Commercial/Industrial  21,336,871  8.0 

Tax Exempt  16,191,191  6.1 

Large Residential3  2,900,131  1.1 

Other  1,641,422  0.6 

 3Large residential is defined as apartments with 4 dwelling units or more.   

5.4.3  Estimated Total Billing Units 

Adding the large residential and non‐residential equivalent residential units to the number of small residential 

units provides a total residential equivalent for billing units.   Table 5.10 summarizes the total equivalent 

residential billing units by customer type.   

Table 5.10 

Billing Units by Customer Type 

Customer Class  Billing units (thousands) 

Small Residential  9.6 

Large Residential  1.1 

Commercial/Industrial  8.0 

Tax Exempt  6.1 

Other  0.6 

Total  25.4 

 

5.5  Calculation of Stormwater and Flood Control Fee This section evaluates the impact of funding the City‘s Stormwater and Flood Control Utility.  A stormwater fee 

recovers the costs associated with stormwater management, based on the amount of impervious area contained 

on each parcel. The fundamental basis for this approach is that there is a direct relationship between impervious 

area and stormwater runoff (i.e. the more impervious area there is on a parcel, the greater the amount of runoff 

from that parcel).  Therefore, the amount a parcel is charged using a stormwater and flood control fee is related 

to the quantity of impervious area.  A significant benefit of this approach is that it equitably distributes 

stormwater costs, in the sense that parcel owners are charged proportionally, relative to their cost imposed on 

the system.   

Prior to the availability and use of GIS, the ability to maintain a database of parcel and impervious area was 

cumbersome and costly.  Due to this implementation barrier, the trade‐off of more equitably distributing 

stormwater related costs has typically been outweighed by its complexity, even though these costs are closely 

Page 91: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐19 106678‐80349‐03‐11.docx  

tied to impervious area.  However, with the advent of GIS technology, the process of implementing a 

stormwater fee has become significantly less burdensome and is no longer cost prohibitive.   

Furthermore, a stormwater and flood control fee provides the benefit of more equitably distributing the costs 

associated with stormwater management and flood control.  This in turn has a significant benefit, in that by 

aligning the means with which stormwater treatment costs are recovered with the characteristics of customers 

that create the service requirement, it provides incentive for customers to improve stormwater management 

practices.   

Having shown the calculations for developing the ERU in the previous section, the following subsections will 

provide the basis for the stormwater fee calculation and the financial impact. 

Given projected revenue requirements and ERUs, CDM developed a stormwater fee which would be assessed to 

customers based on impervious surface area.   In order to illustrate the impact of the fee, a set of representative 

customer classes has been developed.  These customer classes are hypothetical and have been created to 

provide means by which the City can measure the impact across customer classes.  The representative customer 

types examined are as follows: 

Single‐family residence; 

Two‐family residence; 

Three‐family residence; 

20‐unit apartment (Large Residential); 

Commercial property with 1,000 square feet of impervious area; 

Commercial property with 10,000 square feet of impervious area; and 

Commercial property with 100,000 square feet of impervious area. 

The base rate per ERU is calculated by dividing the annual revenue requirement by the total calculated ERUs of 

25,400.  The necessary revenue to fully fund the baseline Stormwater and Flood Control Utility shown in Table 

5.11 is $1.692 million in FY 2012.  Dividing the projected revenue requirement by the total number of ERUs 

would yield a rate of $66.63 per ERU for FY 2012.   

Table 5.11 

Projected Annual ERU Charge 

  2011  2012  2013  2014  2015  2016 

Revenue Requirement  $1,518,572  $1,692,454  $1,973,771  $2,492,536  $3,089,388  $3,850,180 

Residential Charge per ERU  $59.79  $66.63  $77.71  $98.13  $121.63  $151.58 

 

Using the ERU system, parcels with larger amounts of impervious area are charged proportionally higher costs to 

offset their cost burden on the system.  For example, a commercial customer with 100,000 square feet of 

impervious area would be charged approximately $2,495 in order to account for the cost of stormwater that the 

parcel contributes to the system.  The impact of these rates on the various customer classes is shown in Table 

5.12. 

Page 92: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐20 106678‐80349‐03‐11.docx  

Table 5.12 

Comparison of Impacts for Standard Customer Types, FY 2012 

Classification  Billing Units  ERU  Rate per ERU 

Single‐Family  1  1.00  $66.63 

Two‐Family  2  2.00  $133.26 

Three‐Family  3  3.00  $199.90 

Classification Impervious 

Area ERU  Rate per ERU 

Large Residential  10,821  4.05  $269.95 

Commercial/Industrial with 1,000 square feet of IA  1,000  0.37  $24.95 

Commercial/Industrial with 10,000 square feet of IA  10,000  3.74  $249.46 

Commercial/Industrial with 100,000 square feet of IA  100,000  37.44  $2,494.58 

 

Table 5.13 summarizes the total revenue expected from general customer classes for FY 2011.  It can be seen 

that the revenues generated by customer class are directly proportional to the billing units, and in turn the 

impervious area of each customer class. 

Table 5.13 

Expected Revenue per Customer Class, FY 2012 

Classification  Billing units (thousands)  Approximate Revenue 

Small Residential  9.6  $639,668 

Large Residential  1.1  $73,295 

Commercial/Industrial  8  $533,056 

Tax Exempt  6.1  $406,456 

Other  0.6  $39,979 

Total  25.4  $1,692,454 

 

5.6  Recommendations As the City evaluates the option of developing a Stormwater and Flood Control Utility, and as a means for 

meeting revenue requirements, it will need to consider not only the impact of its chosen cost recovery 

mechanism, but also issues related to equity and behavioral incentives.  Relative to the equity of its stormwater 

and flood control rate structure, the City should seek to align its cost of serving customers as closely as possible 

with the charge assessed to those customers.  Using this criterion, a stormwater and flood control fee will 

accurately reflect the likely cost burden imposed by individual customers as stormwater runoff is closely tied to 

impervious area.  Relative to behavioral incentives, a stormwater and flood control fee based on impervious area 

creates a price signal for stormwater customers as to the cost associated with stormwater runoff and flood 

control.  This directly encourages customers and new developers to find ways to minimize stormwater impacts.   

Page 93: CDM Northampton Stormwater System Assessment and Plan 2012-05 Vol 1

Section 5     Stormwater and Flood Control Utility   

5‐21 106678‐80349‐03‐11.docx  

Should the City choose to move forward with implementing a stormwater and flood control fee, given its current 

stormwater‐related costs, anticipated capital costs and the City’s geographic characteristics, we have projected 

the City’s current stormwater charge for FY 2012to be $66.63.  Given the anticipated growth in the stormwater 

charge over time, should the City be interested in mitigating the impact of the stormwater and flood control fee 

on customers with high impervious area, it can seek to either maintain a portion of the stormwater costs on 

sewer rates or implement a stormwater credit program.