Upload
adam-rabb-cohen
View
71
Download
0
Embed Size (px)
Citation preview
Stormwater and Flood Control System Assessment and Utility Plan
Northampton, Massachusetts Department of Public Works
Volume I Final Report
May 2012
i
51147‐71479‐03‐11
Table of Contents
Executive Summary
Section 1 ‐ Introduction 1.1 Introduction ................................................................................................... 1‐1
1.2 Federal Stormwater Management Regulations – Historical Overview ............. 1‐5
1.3 Federal Stormwater Management Regulations – Pending Changes ................ 1‐5
1.4 Flood Control – Regulatory Mandates ............................................................ 1‐7
1.5 Infrastructure Funding ................................................................................... 1‐8
1.6 Project Summary ........................................................................................... 1‐8
1.7 Scope of Work ............................................................................................... 1‐9
Section 2 ‐ Existing Conditions and Alternatives Analyses 2.1 Introduction ................................................................................................... 2‐1
2.2 Stormwater Drainage and Flood Control System Overview ............................. 2‐1
2.2.1 Field Inspection Approach .................................................................. 2‐4
2.2.2 Drainage Analysis Approach ............................................................... 2‐4
2.3 Flooding Problems ......................................................................................... 2‐5
2.3.1 Bridge Street/Meadows Area ............................................................. 2‐5
2.3.1.1 Site Inspection and Area Description ..................................... 2‐5
2.3.1.2 Existing Conditions Hydraulic Model ..................................... 2‐8
2.3.1.3 Preliminary Review of Alternatives ....................................... 2‐8
2.3.2 Elm Street Brook/Florence Area ......................................................... 2‐9
2.3.2.1 Site Inspection and Area Description ..................................... 2‐9
2.3.2.2 Existing Conditions Hydraulic Model ................................... 2‐11
2.3.2.3 Preliminary Review of Alternatives ..................................... 2‐12
2.3.3 King Street/Market Street/Downtown Area ..................................... 2‐13
2.3.3.1 Site Inspection and Area Description ................................... 2‐13
2.3.3.2 Existing Conditions Hydraulic Model ................................... 2‐14
2.3.3.3 Preliminary Review of Alternatives ..................................... 2‐14
2.3.4 Austin Circle/Ryan Road Area ........................................................... 2‐16
2.3.4.1 Site Inspection and Area Description ................................... 2‐16
2.3.4.2 Existing Conditions Hydraulic Model ................................... 2‐16
2.3.4.3 Preliminary Review of Alternatives ..................................... 2‐19
2.4 Flood Control Systems .................................................................................. 2‐20
2.4.1 East Levee Description ...................................................................... 2‐20
2.4.2 West Levee Description .................................................................... 2‐20
2.4.3 East and West Levee Inspection ........................................................ 2‐21
2.4.4 East/West Levee Recommended Improvements ............................... 2‐22
ii 51147‐71479‐03‐11
2.4.5 Northampton Flood Control Pumping Station – Hockanum Road –
Inspection ........................................................................................ 2‐24
2.4.5.1 Recommended Improvements ............................................ 2‐25
2.4.6 West Street Stormwater Pumping Station ‐ Inspection ...................... 2‐26
2.4.6.1 Recommended Improvements ............................................ 2‐27
2.5 River Erosion ................................................................................................ 2‐27
2.5.1 River Road – Mill River ..................................................................... 2‐27
2.5.2 Federal Street Flood Wall ................................................................. 2‐28
2.5.3 Roberts Meadow Brook Channel ...................................................... 2‐28
2.6 Current Operational Cost and Funding Levels ............................................... 2‐28
2.6.1 Regulatory Compliance ..................................................................... 2‐28
2.6.2 Stormwater Drainage Operations Staffing ........................................ 2‐28
2.6.3 Flood Control Operations Staffing ..................................................... 2‐29
Section 3 ‐ Capital Improvements Plan and Operational Budget Requirements 3.1 Introduction ................................................................................................... 3‐1
3.2 Summary of Recommended Plan .................................................................... 3‐1
3.2.1 Street Improvement Projects .............................................................. 3‐1
3.2.2 Municipal Green Infrastructure/Building Project Retrofit/Capital
Allowance .......................................................................................... 3‐5
3.2.3 Bridge Street/Meadows Area ............................................................. 3‐5
3.2.4 Elm Street Brook/Florence Area ......................................................... 3‐6
3.2.5 King Street/Market Street Area .......................................................... 3‐6
3.2.6 Austin Circle/Ryan Road Area ............................................................. 3‐7
3.2.7 Flood Control/Pumping Station Improvements ................................... 3‐7
3.2.8 Levee Improvements .......................................................................... 3‐7
3.2.9 River Erosion Improvements ............................................................... 3‐7
3.3 Future Operational Cost Projections ............................................................... 3‐8
3.4 Estimated Costs and Preliminary Schedule ..................................................... 3‐8
3.5 Project Prioritization .................................................................................... 3‐15
Section 4 ‐ Environmental Permitting 4.1 Introduction ................................................................................................... 4‐1
4.2 Description of Applicable Permits ................................................................... 4‐2
4.2.1 Federal Permits/Approvals ................................................................. 4‐2
4.2.1.1 Clean Water Act, Section 404 ................................................ 4‐2
4.2.1.2 Federal Endangered Species Act of 1973 ................................ 4‐3
4.2.1.3 National Pollutant Discharge Elimination System (NPDES) –
Construction General Permit ................................................. 4‐3
4.2.2 State Permits/Approvals .................................................................... 4‐3
4.2.2.1 Certificate from the Executive Office of Environmental Affairs
(MEPA Approval) .................................................................. 4‐3
4.2.2.2 Massachusetts Wetlands Protection Act (M.G.L. c131, s.40; 310
CMR 10.00) ........................................................................... 4‐4
4.2.2.3 Massachusetts Rivers Potection Act (Ch. 258 of the Acts of
1996; 310 CMR 10.58) ........................................................... 4‐4
iii 51147‐71479‐03‐11
4.2.2.4 401 Water Quality Certification Program (314 CMR 9.00) ...... 4‐4
4.2.2.5 Massachusetts Endangered Species Act (M.G.L. c.131A; 321
CMR 10.00) ........................................................................... 4‐5
4.2.2.6 Waterways Licensing Program (M.G.L. Chapter 91; 310 CMR
9.00) ..................................................................................... 4‐5
4.2.2.7 Environmental Results Program (310 CMR 7.26 [42:43]) ........ 4‐5
4.2.3 Local Permits/Approvals ..................................................................... 4‐5
5.2.3.1 Wetlands Protection Act and City Ordinance ......................... 4‐5
4.3 Conclusion ..................................................................................................... 4‐6
Section 5 – Stormwater and Flood Control Utility 5.1 Introduction ................................................................................................... 5‐1
5.1.1 Objectives ......................................................................................... 5‐1
5.1.2 Stormwater Utilities in Other Communities ........................................ 5‐1
5.1.3 Methodology ..................................................................................... 5‐4
5.1.4 Key Findings ....................................................................................... 5‐4
5.2 Stormwater and Flood Control Utility Implementation Considerations ........... 5‐5
5.2.1 Stormwater and Flood Control Utility Background .............................. 5‐5
5.2.2 Structural Considerations ................................................................... 5‐6
5.2.3 Public Education and Involvement ...................................................... 5‐7
5.2.4 Management and Budgeting .............................................................. 5‐7
5.2.4.1 Budgeting ............................................................................. 5‐8
5.2.4.2 Billing ................................................................................... 5‐8
5.2.5 Funding Options ................................................................................. 5‐8
5.2.6 Stormwater Credits .......................................................................... 5‐10
5.3 Project Revenue Requirement ...................................................................... 5‐11
5.3.1 General Assumptions ....................................................................... 5‐11
5.3.2 Operations and Maintenance Expenses ............................................ 5‐12
5.3.2.1 Incremental O&M ............................................................... 5‐12
5.3.2.2 Allocated O&M ................................................................... 5‐13
5.3.3 Debt Service Expenses ...................................................................... 5‐13
5.3.4 Revenue Requirement ...................................................................... 5‐14
5.4 Parcel Analysis and Equivalent Residential Unit Calculation .......................... 5‐15
5.4.1 Impervious Area ............................................................................... 5‐15
5.4.2 Equivalent Residential Unit Calculation............................................. 5‐17
5.4.3 Estimated Total Billing Units ............................................................. 5‐18
5.5 Calculation of Stormwater and Flood Control Fee ......................................... 5‐18
5.6 Recommendations ....................................................................................... 5‐20
Appendices
Appendix A – Field Inspection Memoranda and Photographs
Appendix B – Drainage Analysis
Appendix C – Pipe Capacity Analysis
Appendix D – Detailed Debt Service Schedule
ES‐1
106678‐80349‐03‐11
Executive Summary
Drainage and flood control systems, while often taken for granted, are critical to the economic
wellbeing of any community, as these systems are vital to the protection of property and the safety
of individuals that reside within the community. In recent years, the deteriorating condition of
drainage and flood control infrastructure across the country has been well documented and, in
combination with extreme weather events, has resulted in several dramatic flooding events that have
created enormous economic disruption and damage to personal and public property.
Like Northampton, many communities across the country have aging infrastructure that is in urgent
need of refurbishment or replacement, followed by periodic maintenance. In many instances,
infrastructure constructed decades ago has now exceeded its useful life and/or is now operating
beyond its intended capacity due to the impact of continued development and increased impervious
area within urban areas and upstream watersheds. Additionally, new regulatory mandates place
further burden on communities to monitor and control both the quantity and quality of stormwater
discharged to ponds, streams and rivers, resulting in new capital and ongoing maintenance
requirements.
While the challenges are daunting, many communities are taking steps to address these challenges in
a thoughtful, systematic manner. Fundamental to this effort is the need to evaluate existing drainage
and flood control systems, identify weaknesses and deficiencies in these systems, and develop a
technically sound, cost‐effective plan to address these deficiencies. However, in the past, such plans
often lacked a sustainable source of funds to finance the implementation of needed improvements.
Accordingly, progressive communities such as Northampton are considering a critical new component
to their stormwater management plan – the implementation of a new stormwater fee that is fair and
equitable, and provides a reliable, dedicated source of revenue to fund needed improvements to
drainage and flood control systems. This new fee would be administered by a newly formed
Stormwater and Flood Control Utility and, as with other utilities, the stormwater fee would be based
directly on the cost of service provided. The process undertaken by Northampton to evaluate such a
fee and the results of the evaluation are described in this Stormwater and Flood Control System
Assessment and Utility Plan.
Existing Infrastructure Condition
The City of Northampton owns and is responsible for the operation and maintenance of
approximately 3,750 catch basins and inlets and approximately 108 miles of drainage that lead to
more than 280 outfalls. A large percentage of these drain lines are over 100 years old and require
replacement because of their deteriorated condition, the need for additional stormwater conveyance
capacity, or both.
Executive Summary
ES‐2
106678‐80349003‐11
Additionally, the City owns and is responsible for the operation and maintenance of a flood control system that
was constructed by the Army Corp of Engineers (USACE) in 1940 to provide protection against flooding from the
Connecticut and Mill Rivers. This system requires significant refurbishment, as levees and retaining walls that
protect the downtown area from high river waters need maintenance to ensure their structural integrity, and
the 70‐year old flood control pumping station that diverts floodwater through the levee under flood conditions
requires replacement.
The City faces many serious challenges in restoring and maintaining fully functional drainage and flood control
systems, including:
Replacement and refurbishment of older drainage and flood control infrastructure that no longer fulfills
its intended purpose
Upgrades of the existing drainage system to serve areas of the City that now experience flooding
Compliance with new EPA regulations governing stormwater management that will mandate a wide
range of system improvements and monitoring of stormwater quality and quantity
Compliance with USACE requirements that will require the City to repair and certify that existing flood
control systems meet USACE standards.
All of the above represent real and significant costs to the City that must be addressed to avoid the risk of non‐
compliance or, worse, the risk of serious damage to public and private property and the associated financial and
quality of life impacts on Northampton residents, business owners, and visitors.
Financial Need Assessment
To develop realistic estimates of the level of funding required to address drainage system and flood control
needs, preliminary engineering was performed and a recommended plan developed to address representative
known drainage system deficiencies in the following areas of the City:
Bridge Street / Meadows Area
Elm Street Brook / Florence Area
King Street / Market Street Area
Austin Circle / Ryan Road Area
Additionally, recommendations were developed to address needed flood control system improvements,
including repairs to levees, replacement of the West Street Stormwater Pumping Station with a portable pump,
and replacement of the Northampton Flood Control Pumping Station with a new facility. Allowances were also
made for compliance with new EPA permit requirements, river erosion improvements, general drainage
infrastructure improvements, and gradual implementation of green stormwater management practices (which
are strongly encouraged by new regulations).
These prioritized recommendations form the basis of a $95.6 million program of capital improvements to be
implemented over a 20‐year period, as shown in Table ES‐1. In the initial five years of the program, it is
estimated that an expenditure of approximately $33.1 million is required to implement high priority projects,
including drainage improvements in the Bridge Street / Meadows area and Elm Street Brook/Florence area,
River Road floodwall improvements, Roberts Meadows Brook channel improvements, levee improvements and
certification, West Street Stormwater Pumping Station improvements, and replacement of the Flood Control
Pumping Station (note that replacement of the Flood Control Pumping Station represents about $17.4 million of
the required expenditure – the largest single item in the recommended improvements program).
Executive Summary
ES‐3
106678‐80349003‐11
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Bridge Street/Meadows Phase 1 Improvements $441,000 $5,072,000
River Road Floodwall Improvements $155,000 $1,453,000
Roberts Meadow Brook Channel Improvements $43,680 $502,320
Federal Street Retaining Wall Improvements $120,000 $1,380,000
Elm Street Brook/Florence Area Phase 1 Improvements $516,000 $5,939,000
King Street/Market Street Area Phase 1 and 2 Improvements $911,000 $5,160,000 $5,315,000
Levee Certification $275,000 $275,000
Levee Capital Improvements $280,000 $275,000 $56,000 $647,000
Flood Control Pumping Station Upgrades $1,391,000 $15,998,000
West Street Portable Pumps $46,000 $533,000
Austin Circle/Ryan Road Area Phase 2 Improvements $327,000 $3,757,000
Bridge Street/Meadows Area Phase 3 Improvements $448,000 $5,156,000
Elm Street Brook/Florence Area Phase 3 Improvements $1,033,000 $5,850,000 $6,025,000
King Street/Market Street Area Phase 3 and 4 Improvements $643,000 $3,643,000 $3,752,000
EPA MS4 Permit Requirements Allowance $250,000 $250,000 $250,000 $250,000 $250,000
Annual Allowance for Drainage Infrastructure $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Municipal Green Design/Construction Allowance $258,000 $265,000 $273,000 $281,000 $290,000 $299,000 $307,000 $317,000 $326,000 $336,000 $346,000 $356,000 $367,000 $378,000 $389,000 $401,000 $413,000 $426,000 $438,000 $452,000
Total Costs per Year $1,761,680 $3,961,320 $6,151,000 $3,115,000 $18,087,000 $7,769,000 $7,347,000 $6,132,000 $1,153,000 $4,593,000 $1,294,000 $7,045,000 $6,717,000 $7,546,000 $4,532,000 $4,653,000 $913,000 $926,000 $938,000 $952,000
Grand Total $95,586,000
Planning/Operations
Design
Construction
YearProject Description
Table ES.1
Summary Project Cost Schedule
Executive Summary
ES‐4
106678‐80349003‐11
This 20‐year program of capital improvements forms the basis for evaluation of a stormwater fee, with capital
costs annualized on the assumption that projects will be financed through the issuance of 20‐year bonds. By
completing preliminary engineering and developing capital cost estimates for specific priority projects (as
opposed to allowances for generic projects), the City can have greater confidence that the stormwater fee
estimates developed as part of this study are realistic and reflect the current infrastructure investment needs of
the City.
Basis of a Northampton Stormwater and Flood Control Utility
While there are a relatively small number of stormwater utilities in New England and across the country, interest
in such utilities has grown dramatically in recent years as communities have recognized the need for a reliable,
dedicated source of revenue to fund needed improvements to drainage and flood control infrastructure. While
the details of specific utilities can vary, the underlying premise of all stormwater utilities is that costs for
drainage and stormwater improvements should be shared equitably, with the amount of impervious area
associated with a particular parcel serving as a proxy for the contribution of stormwater generated by that
particular parcel (parcels with more impervious area generate more stormwater and therefore place a greater
burden on drainage and flood control systems). Because there is a direct and proven relationship between
impervious area and the rate and volume of stormwater generated, allocation of stormwater‐related costs
based on impervious area is more equitable than traditional methods of cost allocation, such as allocation based
on water consumption or property values.
Essentially, there are three steps to determining a defensible stormwater fee:
1. Step 1: Estimate the revenue requirements for the Stormwater and Flood Control Utility. The annual
revenue requirements for the utility are based on annualized capital program requirements (debt service),
system operation, and system maintenance costs. Estimates of annualized debt service for a Northampton
utility have been developed based on the capital program previously discussed, as well as requirements for
system operation and maintenance based on analysis of current system expenditures and estimates of
increased expenditures required to comply with new permit requirements. The results of these analyses
are shown in Table ES‐2 and Figure ES‐1, and show an initial annual revenue requirement of approximately
$1.5 million growing to approximately $3.9 million over a five‐year period.
2. Step 2: Assess the City’s impervious area and use it to develop an ERU‐type billing system. It is
recommended that an Equivalent Residential Unit (ERU) system be used as the basis of the stormwater fee.
Under an ERU system, residential units are assigned one billing unit per dwelling unit, a duplex is assigned
two billing units, and a three‐family home is assigned three billing units. Additionally, larger residential and
non‐residential parcels are assigned billing units based on the amount of impervious area for a specific
parcel relative to the impervious area associated with an equivalent residential unit. The amount of
impervious area for a given ERU is determined using the City’s Geographic Information System (GIS)
database, which allows for calculation of a typical ERU based on analysis of impervious area at residential
parcels across the city. For Northampton, one ERU is estimated to be 2,671 square feet.
3. Step 3: Calculate a rate per equivalent unit and the impact on typical rate payers. Based on the annual
revenue required (Step 1) and the impervious area identified within the City (Step 2), a rate for each ERU is
determined. For Northampton, a stormwater rate of $66.63 per ERU has been estimated for FY2012, with
the impact on various types of properties summarized in Table ES‐3. So, if implemented, a single‐family
home will pay an annual stormwater fee of $66.63, with larger residential and commercial properties paying
proportionally higher fees based on the ERU system.
Executive Summary
ES‐5
106678‐80349003‐11
Table ES‐2 Revenue Requirement
2011 2012 2013 2014 2015 2016
O&M $1,470,232 $1,567,960 $1,615,279 $1,664,031 $1,714,261 $1,766,013
Existing Debt Service $48,340 $54,644 $41,944 $38,684 $37,484 $35,474
Anticipated Debt Service $0 $69,850 $316,548 $789,821 $1,337,643 $2,048,693
Revenue Requirement $1,518,572 $1,692,454 $1,973,771 $2,492,536 $3,089,388 $3,850,180
Figure ES‐1 Revenue Requirement (thousands)
Table ES‐3 Proposed Equivalent Residential Unit Stormwater Fee Schedule, FY 2012
Classification Billing Units ERU Rate per ERU
Single‐Family 1 1.00 $66.63
Two‐Family 2 2.00 $133.26
Three‐Family 3 3.00 $199.90
Classification Impervious
Area ERU Rate per ERU
Large Residential 10,821 4.05 $269.95
Commercial/Industrial with 1,000 square feet of IA 1,000 0.37 $24.95
Commercial/Industrial with 10,000 square feet of IA 10,000 3.74 $249.46
Commercial/Industrial with 100,000 square feet of IA 100,000 37.44 $2,494.58
$‐
$500
$1,000
$1,500
$2,000
$2,500
$3,000
$3,500
$4,000
$4,500
2011 2012 2013 2014 2015 2016
O&M Existing Debt Service Anticipated Debt Service
Executive Summary
ES‐6
106678‐80349003‐11
Policy Considerations for a Stormwater and Flood Control Utility
In addition to financial considerations and rate equity, a number of policy issues should be considered as part of
the implementation of a stormwater and flood control utility. These considerations include:
Public Education: A critical component of any implementation plan is a public education program that will
explain to both residents and the business community the need for investment in stormwater and flood control
infrastructure and the benefits of raising this revenue through a stormwater fee as opposed to alternate cost
allocation metrics such as water consumption or property valuation. Examples of public education activities
include distribution of press releases that describe the role and purpose of the stormwater and flood control
utility, incorporating the basics of stormwater management into school curriculum, and holding public meetings
to discuss the new utility.
Stormwater Credits: To help alleviate the immediate impact of a stormwater fee on customers with large
impervious areas and/or encourage practices that reduce the magnitude of stormwater discharges, the City may
consider a program of stormwater credits that can serve to reduce the overall stormwater fee paid by certain
property owners. Stormwater credits may be provided when a property owner has put in place stormwater
controls that provide relief beyond what may have been required as a condition of property development.
Examples of practices where stormwater credits may be applied include the construction of detention ponds or
green rooftops, the conservation of natural areas in new development, and the application of low income
credits for residential customers with financial hardship. In addition to stormwater treatment practices, some
utilities and municipalities also provide credit related to stormwater education, as well as for stormwater
systems that are separate from the municipal system, but have been required to comply with MS4 permitting
requirements. While stormwater credits can provide benefits in terms of equity and “good practice” incentives, it
is recommended that the City develop clear guidelines for such credits prior to full implementation of the
stormwater utility so that the public understands the rules for such credits prior to receiving an initial
stormwater fee assessment.
Summary
Implementation of a Stormwater and Flood Control Utility will provide the City with a dedicated means of
funding for needed investment in stormwater and flood control infrastructure. The methodology described in
this evaluation seeks to align the cost of providing stormwater and flood control protection with the cost burden
imposed by individual customers on stormwater and flood protection systems, and thereby provides an
equitable allocation of these necessary costs. Additionally, the direct relationship between the quantity of
stormwater generated by a particular parcel (using impervious area as a proxy) and the stormwater fee applied
to a parcel directly encourages customers and new developers to find ways to minimize stormwater impacts.
These behavioral incentives will help the City achieve compliance with new stormwater management
regulations that encourage green design practices and a reduction in the volume of stormwater generated.
As a result of this evaluation, the City has a defensible basis for estimating the magnitude of such a stormwater
fee. This estimate is not based on generic or hypothetical costs, but on preliminary engineering used to develop
site‐specific cost estimates to address several of the more serious deficiencies to the City’s drainage and flood
control systems. Based on this analysis, it is recommended that, for Fiscal Year 2012, the City adopt a
stormwater charge of $66.63 based on an ERU with an impervious area of 2,671 sq. ft. As the City begins to
undertake specific stormwater‐related capital improvements, this stormwater fee can be adjusted by the City to
fund infrastructure priorities. Such a fee will allow the City to undertake a reasonable program of needed capital
Executive Summary
ES‐7
106678‐80349003‐11
improvements, provide needed maintenance of existing assets, and maintain compliance with increasingly
stringent stormwater management regulations.
The ability of a Stormwater and Flood Control Utility to address the real and serious issues of stormwater
management and flood control in a careful, considered manner with costs allocated fairly and rationally will
benefit the residents and businesses of Northampton for decades to come. It will provide security against the
disruption and economic damage that can result from the failure of aging infrastructure that has exceeded its
useful life and/or is operating beyond its intended capacity.
1‐1 106678‐80349‐03‐11.docx
Section 1 ‐ Introduction
1.1 Introduction The City of Northampton’s (City) storm drainage system includes about 3,750 catch basins and inlets
and approximately 108 miles of drainage pipes that lead to more than 280 outfalls (Figure 1.1). A
large percentage of the drain lines are over 100 years old. These systems are in need of replacement
and many areas of the City require improved drainage infrastructure.
The City adopted the Sustainable Northampton Comprehensive Plan (Sustainable Plan) on December
19, 2007. The plan outlined many sustainability goals including Goal IC‐3 – Upgrade the City’s Aging
Stormwater Management System. The objectives of this goal include:
1. Develop and implement a plan to maintain, repair, replace, and improve aging infrastructure
throughout the City.
2. Include “low impact” and National Pollution Discharge Elimination System drainage
improvements concurrently with any pavement management program or project.
3. Invest in stormwater management improvements.
4. Make certain that investments in stormwater are distributed by comparable infrastructure
needs.
The strategy and actions outlined for accomplishing these objectives are as follows: “Complete an
engineering assessment on the ability to meet present and future stormwater management
requirements. Include low impact and green design considerations in the assessment. Create a long‐
term priority improvement plan.”
The City is provided flood protection from the Connecticut and Mill Rivers via a flood control system
that was constructed in 1940 by the Army Corps of Engineers (USACE). Another goal in the
Sustainable Plan is Goal EEC‐7 Develop Strategies to Protect the City from the Impacts of Natural
Hazards. The need to cost‐effectively maintain the City’s flood control facilities is in keeping with the
goals of the Sustainability Plan.
This study presents an approach to meet the goals of the Sustainable Plan. It describes the types of
stormwater and flood control improvements that the City requires and also presents the framework
to implement a new Stormwater and Flood Control Utility. If adopted by the City, this new Utility
would establish an Enterprise Fund to manage a comprehensive program that will provide funding for
capital projects and the annual operation and maintenance of the City’s stormwater system and flood
control systems.
The City faces challenges on many levels related to management of its stormwater management and
flood control systems. Briefly, these challenges include:
BRIDGE ROAD
SP
RING
STREET
SOUTH STREET
PRINCE STREET
LEO
NA
RD
ST
RE
ET
BL
ISS
ST
RE
ET
PLEA
SA
NT
ST
RE
ET
LOCUST STREET
NO
RTH
MA
IN S
TRE
ET
NO
RT
H M
AP
LE
ST
RE
ET
GROVE STREET
VE
RN
ON
ST
RE
ET
NO
RTH
STRE
ET
DAMON ROAD
RIVERBANK
ROAD
KIN
G S
TR
EE
T
CH
ES
TN
UT
ST
RE
ET
FRA
NK
LIN
ST
RE
ET
HO
CKANUM RO
AD
RYAN RO
AD
GL
EN
DA
LE R
OA
D
PROSPECT STREET
ST
AT
E S
TR
EE
T
FIR
ST
SQ
UA
RE
ROAD
ROCKY HILL ROAD
PARK HILL ROAD
INDUSTRIAL
DR
IVE
KEN
NE
DY
RO
AD
MAIN STR
EET
CONZ STREET
NO
RT
H K
ING
ST
RE
ET
CHAPEL STREET
OLD FERRY ROAD
RO
UN
D H
ILL
RO
AD
BRIDGE
S
TR
EE
T
FLO
R
ENC E STREET
FL
OR
EN
CE
RO
AD
HAWLEY
ST
RE
ET
ACREBROOK DRIVE
TURKEY HILL ROAD
MO
UN
T T
OM
RO
AD
MEADOW STREET
WA
TE
R S
TR
EE
T
FR
ONT
HIL
L R
OAD
JAC
KS
ON
ST
RE
ET
FORT STR
EE
T
CO
LE
S M
EADO
W
ROA
D
PA
RK
ST
RE
ET
NONOTUCK STREET
ELM STREET
CHESTERFIELD ROAD
BR
OO
K
SIDE CIR
CLE
R IVERSIDE
DRIVE
HI
NC
KL
EY
ST
RE
ET
YOUNG R
AINBOW
RO
AD
WINTER
BER
RY
LA
NE
WESTHAMPTON ROAD
WIL
LO
W S
TREET
RIV
ER
RO
AD
LOWE
R M
EM
OR
IA L PARK DRIV E
MA
PL
E R ID G
E
ROAD
OLD
SPRING
FIE
LD RO
AD
HA
YD
EN
VIL
LE
RO
AD
BURTS PIT ROAD
U
PPER FA R
M
ROAD
MA
SS
AS
OIT
STR
EE
T
PINE STREET
GR
EE
NLE
AF
DRIV
E
RA
N
GE
ROAD
WE
BB
S H
OLL
OW
RO
AD
CL
EM
EN
T S
TREET
SO
UT
H M
AIN
STR
EET
DUNPHY DRIVE
OU
TE
R O
V
A L
UN
ITED M
ETH
ODIST
DRIVE
ISLAND ROAD
DR
UR
Y L
AN
E
LYMAN ROAD
N
ORTH FA
RMS
RO
AD
PY
NC
HO
N M
EA
D
OW
ROAD
POND
ROAD
RICK DRIVE
WILSON
RO
AD
P OTASH ROAD
LA
KE
ST
RE
ET
WE
ST
FA
RM
S R
OA
D
WO
OD
S R
OA
D
S HE
PAR
DS
RO
AD
HUNTS ROAD
A UDUBON ROAD
HIL
LC
RE
ST
DR
IVE
NOOK ROAD
FA
IR S
TR
EET
WO
OD
LAND DRIVE
LAD
YS
LIP
PER LANE
OX BO W ROA D
CR
OS
S P
AT
H R
OA
D
KIN
GS
HIG
HW
AY
OLD RAINBOW ROAD
CURTIS NO
OK
RO
AD
SY
LV
ESTE
R ROAD
WALNUT T
RE
ES
PAT
H
VEN
TU
RER
S F
IEL
D R
OA
D
CAR
DIN
A L WAY
EASTHAMPTON ROAD
RE
SE
RV
OIR
RO
AD
OLD MILL RIVER
O x b o w
MILL RIVER
WILLOW LAKE
MILL RIVER
Hu l b e r t s
P o n d
BROOKWOOD MARSH POND
BAYE PO
ND
BAYE POND 2
FITZG ERALD LA KE
Danks
Pond
Rob
erts
Meadow
Rese
rvior
Lower Robert Meadow Res.
Parsons or Bassett Brook
C o n n e c t i c u t R i v e r
ICE P
OND BR
OO
K
Elm S t.
Broo
k
Lower M
eadow Brook
Barr ett S t B
roo k
Br
oad B
rook
H ANNUM B
RO
OK
SAN
DY H IL
L BROO
K
Halfway Brook
Day
Brook
Rober
t’s Me ad
o w Bro
o k
Brough
to ns Brook
PI N
E B R
OOK
Clark
Broo k
Bea ver B rook
Man
ha
n R
iver -
- No
rth
Br an
ch
Ba s set Brook
Bas s ett or
Parso n’s Br ook
Broad Broo k
Basset
B roo k
Broa d Bro okRobe
rts Meadow Brook Channe
l
Roar ing B
r oo k
Roberts Meadow
Broo
k
Pars ons B rook
Mar
b le B
rook
91
WESTHAMPTON
HATFIELD
HADLEY
EASTHAMPTON
SOUTHHADLEY
WILLIAMSBURG
HOLYOKE
West Street Pumping Station
West Levee
East Levee
0 2,000 4,000Feet
\\Camgissvr1\Projects\M_Billings\Northampton\mxd\Figure2_1.mxd JD 11/21/11
Northampton Flood Control Pumping Station
City ofNorthampton
Stormwater and FloodControl SystemAssessment and
Utility Plan
Figure 1.1City-Wide Drainageand Flood Control
System Map
LegendTown Boundary
Stormwater Pumping Station
Stormwater Pipe < 12"
Stormwater Pipe 12" to 24"
Stormwater Pipe > 24" to 82"
Levee
Drainage Areas
Parcel Boundary
Streams
Lakes and Rivers
DEP Wetlands
Wetlands (MassGIS)
Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)
Section 1 Introduction
1‐3 106678‐80349‐03‐11
Aging Stormwater Infrastructure ‐ Much of the City’s
stormwater infrastructure is over 100 years old and in
need of repair or replacement. Photo 1.1 is a
photograph of a 2010 drain failure on Florence Road.
New Stormwater Infrastructure is Needed ‐ Where the
need for new stormwater systems have been
identified, no source of funding exists to construct
needed improvements. Photo 1.2 a photograph of
flooding in the Austin Circle and Ryan Road area.
Aging Flood Control Infrastructure ‐ The City has an extensive flood control pumping system and levee
system that was built in the 1940’s by the USACE after
the historic floods of 1936 and 1938. This important
infrastructure protects much of the downtown area
from flooding by the Connecticut River and the Mill
River. Important components of this system need
capital improvements or replacement. Photo 1.3 a
photograph of flooding downtown in 1936 and Photo
1.4 is a photograph of the West Street flood wall that
was erected in August 2011 prior to Hurricane Irene.
River Erosion ‐ The City is blessed with scenic brooks and rivers. However, the Mill River and other brooks
cause streambank erosion that threatens both private
and public property if not controlled. There is no
funding available for erosion control projects that are
important to protect private and public property from
damage. Photo 1.5 is a photograph showing the
dilapidated condition of the Mill River retaining wall.
New Stormwater Regulatory Mandates – Revised U.S.
Environmental Protection Agency (EPA) regulations
governing stormwater management (National
Pollutant Discharge Elimination System or NPDES)
regulations are anticipated to be released in the next
few months. These regulations will include new
mandates such as additional maintenance activities,
outfall monitoring requirements, as well as stormwater
retrofit capital projects. Photo 1.6 is a photograph of a
small diameter outfall off Ward Avenue and Photo 1.7 is a photograph of a large‐diameter outfall off
Hampton Avenue.
Photo 1.1 Florence Road Drain Failure
Photo 1.2 Austin Circle/Ryan Road
Photo 1.3 1936 Flood
Section 1 Introduction
1‐4 106678‐80349‐03‐11
New Flood Control Regulatory Mandates ‐ The USACE is
requiring a complete engineering assessment and upgrade of
the City’s flood control system. In addition, the Federal
Emergency Management Agency (FEMA) is also in the process
of updating Flood Insurance Rate Maps (FIRM) in several
Massachusetts Counties. As part of map updating, FEMA will
require that the City certify that the flood control systems meet
USACE standards. The FIRM mapping update for Hampshire
County is not yet scheduled but is expected in the near term.
Photo 1.8 is a photograph of the Connecticut River levee in
August 2011.
Inadequate Funding ‐ Currently, the City provides very little funding on an annual basis for stormwater and
flood control‐related work. In the last decade or more the capital funding amount has typically been under
$100,000 per year, with funding for capital projects zeroed out of the budget three years ago. Current
funding is from the General Budget where City‐wide demands are great. A new source of sustainable
funding is needed to meet the needs described above.
Photo 1.4 West Street Flood Wall
Photo 1.5 Mill River Retaining Wall Photo 1.6 Ward Avenue Outfall
Photo 1.7 Hampton Avenue Outfall Photo 1.8 Connecticut River Levee
Section 1 Introduction
1‐5 106678‐80349‐03‐11
1.2 Federal Stormwater Management Regulations – Historical Overview
The City’s storm drain discharges are subject to the NPDES Stormwater Phase II Municipal Separate Storm Sewer
System (MS4) General Permit.
Since 2003, the City has complied with the EPA’s NPDES Stormwater Phase II permit for smaller communities
with municipal separate storm sewer systems. The NPDES Stormwater Permit regulates discharges from
Northampton’s municipal storm system and mandates steps the City must take to control the quantity and
quality of water discharged from the storm drain system. Over the first five years of the NPDES Stormwater
Permit coverage, the City met the EPA’s requirements to implement a stormwater management program that
included the following six minimum controls: Public Education, Public Involvement, Illicit Discharge Detection
and Elimination, Construction Site Stormwater Runoff Control, Post Construction Stormwater Management,
Good Housekeeping and Pollution Prevention.
In June of 2004 the Northampton City Council approved both the Illicit Connections and Discharges to the
Municipal Storm Drain System Ordinance and the Erosion and Sediment Control and Post‐Construction
Stormwater Management Ordinance. Since that time the main focus of the Northampton Stormwater
Management Program has been the implementation of the Stormwater Management Permit program. Between
June 2004 and August 2011 the Northampton Department of Public Works (DPW) issued a total of 61
Stormwater Management Permits for development projects disturbing over one Acre. The fees collected are
directly dependent on the number and size of development projects each year. A revolving fund was established
that was intended to fund the implementation of the Stormwater Management Program. However, the revenue
from the stormwater permit fees proved to be inadequate to consistently pay for the cost of maintaining
compliance with the City’s NPDES Stormwater MS4 Permit. In 2006 the revolving fund was ended and
stormwater permit fees are now deposited directly in the City’s General Fund.
The stormwater system is operated and maintained on a limited budget funded through the City’s General Fund.
The budget is used for emergency repairs of the system, catch basin cleaning and repair, engineering, new
connection permits, and compliance with the NPDES permit. Over the past 25 years the City has performed
repairs on the stormwater system on an emergency basis only. Other than catch basin cleaning, no routine
inspection, maintenance, and repair takes place, and each year the system condition continues to deteriorate.
In March 2011 the City completed the eighth year of implementation of the Stormwater Management Program
as required by the EPA. The program has been implemented with the smallest budget possible to keep the City
in compliance. The ability to comply with regulatory requirements is a function of consistent funding needed for
staffing and equipment costs needed to properly operate and maintain the municipal storm drain system,
including activities such as street sweeping and catch basin cleaning. Looking ahead, the City’s NPDES
Stormwater permit compliance costs will likely increase four to five‐fold when the new EPA regulations are
instituted.
1.3 Federal Stormwater Management Regulations – Pending Changes
In December 2010 the EPA issued a Draft of proposed changes to the Massachusetts Interstate, Merrimack, and
South Coastal Small MS4 General Permit (Draft Permit) for public comments. Information about this Draft Permit
can be found on the EPA website (www.epa.gov/region1/npdes/stormwater/mimsc_sms4.html) It is projected
Section 1 Introduction
1‐6 106678‐80349‐03‐11
that the final permit changes will be issued by early 2012. The proposed changes to this MS4 permit include
many new and costly obligations for the City. A small sample of the new requirements is discussed below.
Data Requirements: The Draft Permit requires the gathering, and in some cases mapping, of an enormous
quantity of data. Much of this information is required in the first two years in order to perform the analyses
required to meet the permit milestones. Even though Northampton has a well‐established Geographic
Information System (GIS) system, the data compilation and analysis alone could consume the better part of the
five‐year permit cycle. The individual data requirements by themselves may be feasible to obtain, but
collectively they present a considerable effort involving personnel with a high level of knowledge and skill.
Proposed Outfall Sampling: The new permit requires sampling 25 percent of the drainage outfalls each year
during both dry and wet weather. The City of Northampton has about 287 stormwater outfalls. The sampling of
this many outfalls is costly and would require either City staff time, or hiring a consultant to complete the
sampling. New sampling equipment and analytical costs will also be incurred to comply with this new
requirement.
Illicit Discharge Detection and Elimination (IDDE) Program: The discharge of sanitary sewage and other
pollutants through stormwater systems is prohibited and any illicit connections found through sampling need to
be corrected within 30 days. In some cases the connections are the responsibility of private land‐owners to fix
and in other cases the City may be responsible for constructing the improvement and the associated repair cost.
Nitrogen Reduction Requirements: Since the City is located within the Connecticut River basin and thus
ultimately discharges to Long Island Sound, a 10 percent reduction in nitrogen is proposed to meet water quality
standards. Given the level of attention Northampton has paid to our stormwater sampling and mitigation
program to date, we are concerned that even the best efforts may result in failure to comply, and we are
concerned about the associated consequences if additional appropriate Best Management Practices (BMPs)
cannot be implemented in a timely and cost‐effective manner. The types and cost of BMPs is expected to be
significant.
BMPs ‐ Constructed Retrofits: The Draft Permit requires that the City complete an inventory and priority ranking
of City‐owned property and infrastructure (including public right of ways) that may have the potential to be
retrofitted with BMPs designed to reduce the frequency, volume, and peak intensity of stormwater discharges.
By year 3 of the permit, EPA requires that some BMP retrofit projects be completed. The inventory and priority
for the entire City is a large undertaking. The design, permitting, and construction of BMP retrofits will be time
consuming and costly.
Public Education and Outreach: The Draft Permit includes the production and distribution of eight public
education notices, in addition to several ordinances and programs intended to teach the public how to minimize
their impacts on stormwater quality.
Catch Basin Inspection and Cleaning: The Draft permit requires inspection and cleaning of every catch basin
such that no sump is more than 50 percent full. This may require cleaning catch basins more often than one per
year. Currently, the City cleans catch basins annually.
Floor Drain Inspections: The draft permit requires Identifying and determining the outlet of every floor drain in
every municipal building within one year of the effective date of the permit. In older cities like Northampton,
plumbing plans are not available for many municipal buildings, and dye testing would be required to understand
the plumbing configuration and outlet location of every floor drain. Again, additional City staff time or the use of
contractors would be needed to comply with this requirement.
Section 1 Introduction
1‐7 106678‐80349‐03‐11
There are many other costly requirements to comply with this new permit. The costs to maintain compliance
with the Draft permit may require spending nearly three times the current budget or approximately $250,000
per year for the City of Northampton.
1.4 Flood Control – Regulatory Mandates The City is provided flood protection from the Connecticut and Mill Rivers via a flood control system that was
constructed in 1940 by the USACE. The City is responsible for maintaining flood control infrastructure. The levees
(or dikes) and pumping stations along both rivers protect the City from flooding in critical low lying elevations.
The flood control system for the City consists of two main parts. An earthen levee about a mile in length on the
eastern part of the City provides protection against high water from the Connecticut River. In addition, an
earthen levee and concrete flood wall about a half mile in length in conjunction with the Mill River diversion
canal provides protection against flash floods on the Mill River and backwater from the Connecticut River via the
Ox Bow. The City maintains a flood control pumping station located at the wastewater treatment plant on
Hockanum Road. Wastewater treatment plant staff operates the pumping stations while the entire DPW is
engaged in the maintenance and operation of the flood control levees and Mill River diversion channel. A
smaller pumping station is located on West Street adjacent to the Mill River.
The USACE issued inspection reports dated August 26, 2011 for the Mill River Flood Control System and for the
Connecticut River Flood Control System. These reports included a long list of required improvements that must
be completed by September 2012. Generally, these improvements were related to removal of trees and
vegetation, establishing new turf on levee systems, video inspections of toe drain systems, and related work.
The completion of this work is beyond the means of the DPW staff. Bidding of the completion of this work is
needed, in order to have a contractor complete the improvements. Currently, there is no funding source to
complete this work other than the General Fund budget.
Also, in a meeting at the USACE office in Concord, Massachusetts on August 26, 2011, the City was informed that
notification will be sent in the next few months that significant engineering studies must be completed by the
City for all flood system components. These engineering studies will be required to include:
Preparation of topographic surveys to determine elevations and freeboard allowances;
Geotechnical borings;
Hydraulic and hydrologic analyses;
Seepage and slope stability analyses of dikes; stability analyses of floodwalls; settlement analyses for dikes,
pumping stations, and floodwalls; and seismic assessment for flood control structures; and
Inspections of all penetrations through the levees.
The USACE had preliminarily indicated that these studies will be required to be completed within two years of
receiving written notification of this requirement. The City anticipates receiving this notification by the end of
2011, resulting in an estimated deadline of the end of 2013 for completion of this work. These studies are
expected to cost hundreds of thousands of dollars to perform. Other Cities along the Connecticut River such as
Chicopee, Springfield and Hartford have completed these studies and found that millions of dollars of levee and
flood control pumping station improvements were required.
In addition to the USACE requirements, FEMA is in the process of updating Flood Insurance Rate Maps (FIRM)
across Massachusetts, with Hampshire County maps scheduled for updating in 2012 or later. As part of the FIRM
updates, FEMA will require the City to certify that flood control systems, including levees, meet current USACE
Section 1 Introduction
1‐8 106678‐80349‐03‐11
standards. This certification process includes engineering assessment similar to the above‐listed studies and
associated flood control capital improvements. The certification process has cost other Massachusetts
communities millions of dollars. If the City flood control system is not certified, the properties currently
protected by this system would no longer be protected. Property owners in the flood zone that have federally
backed mortgages would then be required to purchase expensive flood insurance.
1.5 Infrastructure Funding The use of the General Fund to pay for stormwater infrastructure is nearly universal in Massachusetts, but in
most cases the General Fund is insufficient to meet all of the needs of aging and inadequate infrastructure, nor is
there funding to meet the increasingly stringent regulations. There is inadequate funding to meet the
stormwater, flood control and stream erosion project needs in the City. Very limited funding for this
infrastructure has been provided through the City’s General Fund. The financial resources of the City to fund
infrastructure through the General Fund appears to be very limited, where General Fund resources are used for
all City operations such as schools, Fire and Police Departments. Monies from the General Fund have been
unable to keep pace with the requirements to maintain and/or replace existing infrastructure or construct new
infrastructure in locations where the need is great.
Since tax exempt properties, such as colleges, state and federal properties do not pay property taxes, they do
not contribute to the General Fund. Many tax exempt properties have large expanses of impervious area that
generate significant stormwater flows. The costs associated with the City managing this stormwater is paid by
tax payers. Stormwater utilities have been established in other communities on an equitable fee for service
basis where fees are determined based on usage (amount of impervious area is one alternative for determining
fees).
Many Cities and Towns have implemented, or are in the process of evaluating the formation of new utilities for
the management of stormwater and related infrastructure. Locally in western Massachusetts, Chicopee and
Westfield have implemented a stormwater utility. The charging of user fees for stormwater management is
authorized under state law (MGL c.83 s.16). The implementation of a stormwater utility is an equitable means to
provide the stable revenue source needed to manage stormwater infrastructure and to meet the ever expanding
regulatory state and federal mandates. Also, shifting infrastructure costs to a utility fee basis provides some
relief to the General Fund budget by removing stormwater‐related costs from that budget.
1.6 Project Summary This project consists of two parts. The first part of the study involved identifying drainage, river erosion and
flood control improvements projects. Preliminary cost estimates were prepared for these projects and
summarized in a 20‐year capital improvements plan. The second part of the study considered establishing a
stormwater and flood control utility and the various approaches used successfully by other communities. The
20‐year capital improvements plan and projected operational costs were used to evaluate various utility rate
structures.
The drainage projects that were evaluated included areas that are flood‐prone or are known to have stormwater
capacity issues. These drainage projects are considered representative of projects that may be needed across
the City. The projects analyzed include:
King Street/Market Street/Downtown Area;
Bridge Street/Meadows Area;
Section 1 Introduction
1‐9 106678‐80349‐03‐11
Elm Street Brook Area (Florence Area); and
Ryan Road/Austin Circle Area.
River erosion projects considered are known problem areas where various grant funding has been sought for
repairs. The projects include:
River Road Retaining Wall/Floodwall improvements (Mill River);
Roberts Meadow Brook channel improvements and erosion repair; and
Federal Street retaining wall repair (Mill River).
Flood Control projects were selected based on an engineering inspection of these City flood control systems.
The projects included:
Flood Control pumping station replacement; and
Levee system evaluations and improvements.
The recommended plan focuses on improvements to alleviate existing flooding and river erosion problems in
these representative areas. Flood control projects are also identified and included. The study presents a
preliminary 20‐year capital improvement plan. In addition, future operations and maintenance costs were
estimated as needed to comply with the Draft EPA MS4 Stormwater Permit. The capital improvements plan and
operating costs were used in the evaluation of various stormwater utility options.
1.7 Scope of Work Specific tasks completed for this study include:
1. Inventory and assessment of existing stormwater drainage infrastructure, including stream erosion projects.
Work included field inspections and hydraulic modeling of sample problem areas identified by the City.
2. Inventory and assessment of existing flood control infrastructure including pumping stations and levee
systems.
3. Review and accounting of current operational budgets for drainage and flood control operations.
4. Determination of a 20‐year Capital Improvement Plan for stormwater drainage, river erosion and flood
control projects.
5. Determination of future budget allocations needed to meet regulatory mandates.
6. Evaluation of a new Stormwater and Flood Control Utility, including revenue requirements, rate structure
options, rate modifiers, discounts and exemptions, billing options, and implementation steps.
2‐1
106678‐80349 03 11
Section 2 ‐ Existing Conditions and Alternatives Analyses
2.1 Introduction This section provides an assessment of the existing conditions for representative areas of the
stormwater drainage system, areas currently experiencing river erosion (Figure 2.1) and the flood
control system. This section also discusses the Department of Public Works’ current operational cost
and funding levels to manage the City’s stormwater drainage and flood control operations. For the
stormwater drainage system, a summary of modeling results and alternatives analyses for four flood‐
prone areas selected by the City as being representative of the types of projects that would require
funding is provided. For the flood control system, recommendations to address deficiencies in the
levee system and pumping stations are provided.
2.2 Stormwater Drainage and Flood Control System Overview
Figure 1.1 in Section 1 is a map of the Northampton drainage and flood control systems, including the
West Street stormwater pumping station, Northampton Flood Control Pumping Station and levees.
Overall, the drainage system includes approximately 108 miles of drain pipe, ranging in diameter
from 4 to 82 inches. There are approximately 3,750 catch basins and more than 280 outfalls
discharging to rivers, brooks, wetlands, and ponds. At many locations, the City stormwater was
initially managed through a combined sewer overflow (CSO) system, with only one pipe (combined
sewer) collecting sanitary sewer flow and stormwater runoff, instead of two separate pipes (sewers
and drains). During wet weather, combined sewer flow that exceeded the capacity of the system
would overflow to rivers and streams around the City. As the City performed sewer separation, many
of the original combined sewers were converted into storm drains and new sewers were constructed
to collect sanitary flow separately. As a result, many of the drains are smaller than 12 inches in
diameter (the recommended minimum drain size to reduce clogging problems, highlighted in red on
Figure 1.1). Also, a significant portion of the stormwater drainage system, consisting of turn‐of‐the‐
century vitrified clay, iron, stone and brick pipe, and asbestos cement pipe from the 1950s, is aging,
deteriorating, lacking hydraulic capacity, and may need to be replaced. A review of the stormwater
drainage system within the King Street/Market Street, Bridge Street/Meadows, and Elm Street
Brook/Florence areas indicates that nearly 47 percent of the pipes (approximately 6.1 miles) are
made of vitrified clay, iron, stone, brick, or asbestos cement. The large percentage of clay pipe, stone
and brick pipe is an indication of the age of this infrastructure. Table 2.1 provides the breakdown of
pipe lengths by material for these areas.
ELM STREET
WIL L
IAM
S S
TR
EE
T
WEST-HAMPTON
WILLIAMSBURG
EASTHAMPTON
HADLEY
SOUTHHADLEY
HOLYOKE
HATFIELD
Ryan Road/Austin Circle Area
Elm Street Brook Area
King Street/Market Street/Downtown Area
Bridge Street/Meadows Area
Federal StreetRetaining Wall Repair
River Road Retaining Wall/Floodwall Improvements
Roberts Meadow BrookChannel Improvements
and Erosion Repair
A1
D
G
B
A2
A3
A4
BRIDGE ROAD
SPRING STREET
PRINCE STREET
LEO
NA
RD
STR
EE
T
LOCUST STREET
NO
RTH
MAIN
STREE
T
NO
RT
H M
AP
LE
ST
RE
ET
DAMON ROAD
RIVERBANK
ROAD
KIN
G S
TR
EE
T
CH
ES
TN
UT
ST
RE
ET
FR
AN
KL
IN S
TR
EE
T
HOCKA
NUM RO
AD
RYAN ROAD
GL
EN
DA
LE R
OAD
PROSPECT STREET
FIR
ST
SQ
UA
RE
ROAD
ROCKY HILL ROAD
PARK HILL ROAD
KE
NN
ED
Y R
OA
D
CONZ STREET
NO
RT
H K
ING
ST
RE
ET
OLD FERRY ROAD
RO
UN
D H
ILL
RO
A
D
BR
IDG
E S
TR
EE
T
FL
OR
EN CE STREET
FL
OR
EN
CE
RO
AD
TURKEY HILL ROAD
MO
UN
T T
OM
RO
AD
MEADOW STREET
WA
TE
R S
TR
EE
T
FR
ON
T
HIL
L R
OAD
JAC
KS
ON
ST
RE
ET
CO
LE
S M
EAD
OW
ROA
D
PA
RK
ST
RE
ET
ELM STREET
KIN
G S
TR
EE
T
CHESTERFIELD ROAD
BR
OO
K
SID E CIR
CL
E
BRIDGE ROAD
R
IVE R SIDE DRIV
E
HI
NC
KL
EY
ST
RE
ET
WINTER
BER
RY
LA
NE
WESTHAMPTON ROAD
RIV
ER
RO
AD
LOWE
R M
EM
OR
IA L PARK DRIV E
MA
P
LE RI DGE
ROAD
OLD SPR
IN
GFIE
LD
RO
AD
HA
YD
EN
VIL
LE
RO
AD
BURTS PIT ROAD
UPPER FA
RM
ROAD
MA
SS
AS
OIT
STR
EE
T
GREE
NLE
AF
DR
IV
E
RA
N
GE
ROAD
WE
BB
S H
OL
LO
W R
OA
D
CL
EM
EN
T S
TREET
MA
IN S
TR
EE
T L
EE
DS
DUNPHY DRIVE
RYAN ROAD
OU
TE
R O
V
A L
UN
ITED M
ET
HODIST
DRIVE
ISLAND ROAD
DR
UR
Y L
AN
E
LYMAN ROAD
NO
RT
H FA
RM
S R
OA
D
PY
NC
HO
N M
EA
DOW
ROAD
FLOR
ENCE
RO
AD
POND
ROAD
RICK DRIVE
WILSON
ROAD
POTASH ROAD
WA
LN
UT
TR
EE
S P
AT
H
BURTS PIT ROAD
LA
KE
ST
RE
ET
WE
ST
FA
RM
S R
OA
D
WO
OD
S R
OAD
SH
EPA
RD
S R
OA
D
HUNTS ROAD
A UDUBON ROAD
NOOK ROAD
FA
IR S
TR
EE
T
WO
OD
LAND D RIVE
LAD
YS
LI
PPER
LA NE
OX BOW ROA D
CR
OS
S P
AT
H R
OA
D
KIN
GS
HIG
HW
AY
CURTIS NO
OK
RO
AD
SY
LV
ESTER ROAD
CAR
DIN
A L WAY
EAS
THA
MP
TO
N R
OA
D
RES
ER
VOIR
ROAD
Oxbow
Oxbow
BAYE PO
ND
BAY
E PO
ND
Oxbow
Connecticut River
Day B
rook Broad
Bro ok
P INE BRO O K
Lo wer M
ea dow Brook
Ro ar ing Broo k
Barrett St B
rook
B road
Br ook
Br
oad B
rook
Roar ing Brook
I c e Po
nd Brook
HANNUM B
RO
OK
Hal fway Brook
Day
Brook
Roarin g B
ro o k
Rob
ert
’s Me ad
o w Bro
o k
Bro ugh
tons Brook
PIN
E BR
OOK
Clark B
rook Bea ver B rook
Bass ett or P arson’s B
r o ok
Man
ha
n R
iver --
North
Bran
ch
Ba s set Brook
Broad Broo k
Basset
B roo k
Broad BrookRoberts Meadow Brook Chann
el
Roar i ng B
r ook
Robert s Mea dow
Broo
k
Parsons Brook
Mar
ble
Bro
ok
91
91
\\camgissvr1\Projects\M_Billings\Northampton\mxds\WatershedOverviewMap_11x17.mxd MB 4/2012
0 3,5001,750
Feet
Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)
City ofNorthampton
Stormwater and FloodControl SystemAssessment and
Utility Plan
Figure 2.1RepresentativeProject Areas
Legend
Town Boundary
Parcel Boundary
Streams
DEP Wetlands
Wetlands (MassGIS)
Lakes and Rivers
Section 2 Existing Conditions
2‐3
106678‐80349‐03‐11
Table 2.1
Summary of Pipe Material in Four Study Areas
Pipe Type Total Feet Total Miles % Total
Concrete 35,943 6.81 53%
Vitrified Clay (VC) 24,055 4.55 35%
Iron 1,017 0.19 1.5%
Stone 1,870 0.35 2.7%
Brick 1,890 0.36 2.8%
Asbestos Cement (AC) 3,238 0.61 4.8%
Polyvinyl Chloride (PVC) 78 0.01 0.1%
Total 68,090 12.87 100%
The City has not assessed the City’s drainage system in a comprehensive way since 1971. Portions of the
drainage system have been inspected since that time. For example, in July 1981, Almer Huntley Jr. & Associates
performed an inspection of the Market Street Brook system in the King Street area, presenting the results in the
report North Industrial Park Drainage Study (“Almer Huntley report”). The Market Street Brook system
discharges into the Historic Mill River bed, downstream of Hockanum Road. The report documented the
condition of this 1800s‐vintage system from the outfall to its beginning upstream of North Street. Inspections
revealed that the Market Street Brook system is a composite of various pipe diameters, shapes, and materials, at
times going under existing buildings and through private property. One of the earliest sections is located in the
vicinity of Holyoke Street. Constructed in 1846, it is mostly a 5‐t by 6‐ft brick box with a brick arch roof and
wooden plank floor. Between Holyoke and Bridge Streets, the drainage system is comprised mostly of a stone or
brick box with a brick arch roof and wooden plank floor. Even though this section was constructed between
1846 and 1893, it was found to be in good overall condition. However, from Bridge Street to the beginning of
this system upstream of North Street, the pipes were found to be in overall poor condition. Constructed mostly
in the mid‐ to late 1800s, the pipe varies between a double brick ring and a stone box with a brick arch. The
inspection found sections of the brick ring out of round, longitudinal cracking, and missing bricks and stones.
This system has not been inspected since 1981.
The levee flood control system was constructed by the U.S. Army Corps of Engineers (USACE) as part of the
Comprehensive Plan for Control of Flood in the Connecticut River Basin. Construction of the flood protection
system was started in December 1938 and completed in June 1941. The levee flood control system consists of
two levees, as shown on Figure 2.1: the eastern part of the system (East Levee) includes an earth embankment
about one mile long with three concrete flood walls that provides flood protection against rising waters of the
Connecticut River, and the western part (West Levee) includes earth embankment segments and a concrete
flood wall designed to protect against rising waters and flash floods from the Mill River and backwater from a
diversion canal linked to the Connecticut River. As part of this project, a diversion dike, consisting of an earthen
embankment with a core of selected impervious material, was constructed just downstream from the West
Street Bridge at the Smith College power plant. It diverts the Mill River from the diversion dike through the
former Hulberts Pond to the Connecticut River Oxbow Lake via an 11,000‐foot‐long diversion canal. The
purpose of diverting the Mill River was to eliminate flooding in the City’s downtown area. Existing closed
drainage systems in the King Street/Market Street area currently discharge to the original Mill River bed,
referred to as the “Historic Mill River” in this report.
Section 2 Existing Conditions
2‐4
106678‐80349‐03‐11
2.2.1 Field Inspection Approach
As discussed in Section 1, the City Department of Public Works (DPW) identified the following areas within the
City as being indicative of the types of projects that will require funding:
King Street/Market Street area
Bridge Street/Meadows area
Elm Street Brook/Florence area
Ryan Road area
These projects illustrate the scale and cost of typical capital projects. There are similar capital projects needed
across the City.
Camp Dresser & McKee Inc. (CDM) conducted field inspections of these areas to assess the current condition of
the drainage systems. This was accomplished by physically walking the system and inspecting selected
structures, land use types, topography, verifying Geographic Information System (GIS) mapping, and noting
defects or other conditions that should be considered during hydrologic modeling. Highlights of the field
inspections are provided here in the following sections; Appendix A provides detailed field inspection
memoranda and photographs.
2.2.2 Drainage Analysis Approach
CDM performed drainage analyses of these four flood‐prone and critical drainage areas under existing and
future build‐out conditions to examine the drainage systems’ capacities and size new drains if needed. The
drainage analyses determined peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events using
the U.S. Army Corps of Engineers HEC‐HMS Flood Hydrograph Package, version 3.5. This computer model
simulates runoff and routing of stormwater flows through the watersheds, and is based on the Soil Conservation
Service (SCS) Method. CDM used spreadsheets based on Manning’s Equation and the Orifice Equation (allowing
system surcharging to within one foot of the manhole cover) to evaluate the capacity of selected closed
drainage systems to control peak rates of runoff during a 10‐year 24‐hour storm under future build‐out
conditions. Chapter 290, Section 52 of the City Code requires that closed drainage systems be designed for a
minimum 10‐year storm event. Open channels and culverts serving major drainage areas, as well as stormwater
detention/retention basins, where flooding would produce property damage or a safety hazard, are designed to
control peak rates of runoff during a minimum 25‐year 24‐hour storm, and if possible, a 100‐year 24‐hour storm.
Precipitation data for standard storms used in the models were taken from Cornell University “Atlas of
Precipitation Extremes for the Northeastern United States and Southeastern Canada” (September 1993). The
estimated precipitation depths during the 2‐, 10‐, 25‐, and 100‐year 24‐hour storms are 3.11, 4.38, 5.37, and
7.35 inches, respectively. Compared to rainfall depths in Technical Paper No. 40 (“Rainfall Frequency Atlas of
the United States”), the rainfall depths from the Cornell University study are higher for storms greater than a 10‐
year 24‐hour storm, and provide a more conservative evaluation and design of existing and proposed
stormwater management facilities, as well as a factor of safety for potential climate change.
CDM delineated sub‐drainage areas within each study area using topographic and existing drainage system
information taken from the City’s Geographic Information System (GIS) mapping. The GIS mapping was also
used to determine the land use, hydrologic soil group (HSG), and impervious area within each sub‐drainage area.
Curve numbers (CNs) were assigned to each land use based on the HSG to develop a weighted CN for each sub‐
drainage area.
Section 2 Existing Conditions
2‐5
106678‐80349‐03‐11
To determine future build‐out conditions, CDM consulted with the Director of the Northampton Office of
Planning and Development to determine which sub‐drainage areas are likely to undergo development in the
future. Curve numbers in the HEC‐HMS computer model were adjusted to reflect future build‐out conditions.
Runoff velocities for estimating time of concentration (Tc) were based on the “SCS National Engineering
Handbook, Figure 15.2 – Velocities for Upland Method of estimating Tc.” A minimum Tc of 10 minutes was used
for all sub‐drainage areas less than 1 acre, while a minimum Tc of 15 minutes was used for all sub‐drainage areas
greater than 1 acre. CDM used Muskingum routing to account for attenuation of peak flows within drainage
areas.
2.3 Flooding Problems As discussed in Section 1, the DPW identified four drainage areas that are prone to significant flooding and/or
are in critical areas (Figure 1.1). For each study area, CDM performed a field inspection of the drainage system,
developed an existing conditions HEC‐HMS computer model, and developed potential alternatives to relieve
flooding. This section provides a summary of this effort. In Appendix B, Tables B.1 through B.4 present the HEC‐
HMS modeling results under existing conditions for the four study areas. Similarly, Tables B.5 through B.8
present the HEC‐HMS modeling results under future build‐out conditions.
CDM also performed pipe capacity analyses for existing and future build‐out pipe conditions for major drain lines
and for streets known to have flooding problems in the King Street/Market Street area, Bridge Street/Meadows
area, and Elm Street Brook/Florence areas. Tables in Appendix C provide the existing and future build‐out pipe
capacity analyses. The pipe capacity analysis evaluated the adequacy of the pipes for peak rates of runoff during
a 10‐year 24‐hour storm event. A Manning’s n‐value of 0.013 was used for all proposed reinforced concrete
pipes. Pipes that have inadequate hydraulic capacity and are recommended for improvements are highlighted
in the Tables in Appendix C. In some cases, some pipes that are shown to not have sufficient capacity are not
recommended for improvements and justification is provided in the table. This section of the report describes
the major drain lines that need to be improved, but additional smaller lines are presented in this appendix. All
pipes less than 12‐inch in diameter are also highlighted and recommended for replacement with a minimum 12‐
inch diameter pipe. Upgrading of these pipes is not as critical as other recommended drainage system
improvements and should be targeted for the later phases of the Capital Improvement Plan.
2.3.1 Bridge Street/Meadows Area
2.3.1.1 Site Inspection and Area Description
Area Description
The Bridge Street/Meadows area is currently served by two separate drainage systems. Portions of the area are
located in the Connecticut River floodplain on the eastern side of the City and upstream portions lie at higher
elevations west and north of the floodplain. The drainage system is shown on Figure 2.2. The open drainage
channel along Cross Path Road down to the levee in the vicinity of Eastern Avenue, and the cross‐country closed
drainage system parallel to Bridge Street are prone to flooding.
On the west side of Bridge Street, the Day Avenue Brook drainage area is connected to a low‐lying drain line that
runs through residential backyards between Day Avenue and Marshall Street and flows in a northeasterly
direction across Damon Road discharging to the Connecticut River through the 42‐inch MassDOT outfall. This
outfall recently collapsed on a river bank that washed out. The large industrial area northwest of these
neighborhoods also discharges to this outfall, and is a potential area for managing stormwater on‐site with Best
Management Practices (BMPs), such as rain gardens, permeable pavement and street planters. MassDOT is
currently preparing drawings to repair the collapsed outfall.
CONNECTICUT RIVER
MILL RIVER
LL RIVER
Northampton Flood ControlPumping Station
West StreetStormwater
Pumping Station
Approximate Wetland Boundary Estimated by City
HISTO
RIC MILL RIVER
13
6
A
2
5
I
O
S
12
G
8
Q
N
1
K
J
B
L
D
R
9
4
7T
Fairgrounds
W
U
10
3
H
M
X
V
11
P
C
E
F
91
91
DAMON ROAD
STA
TE
ST
RE
ET
NOOK ROAD
OLD FERRY ROAD
NORTH
STR
EET
PRO
SPE
CT S
TRE
ET
RIVER
BANK R
OAD
CONZ STREET
KIN
G S
TR
EE
T
PLE
AS
AN
T S
TR
EE
T
KIN
GS
HIG
HW
AY
MAIN STREET
FAIR
ST
RE
ET
VENTURERS FIE
LD R
OAD
HOCKANUM ROAD
RO
UN
D H
ILL RO
AD
CR
OS
S P
AT
H
RUSSELL STREET
CR
OS
S P
AT
H R
OA
D
BARRETT STREET
BRIDGE ROAD
SOUTH STREET
LYMAN ROAD
INDUSTRIAL DRIVE
AQ
UA
VIT
AE
RO
AD
CO
LLEG
E LA
NE
BA
Y R
OA
D
CRESCENT STREET
CE
ME
TE
RY
RO
AD
LANE PLANT ROAD
FINN STREET
GOTHIC STREET
DAY AVENUE
FRUIT STREET
BRADFORD STREET
UNION S
TREET
FAC
TO
RY
ST
RE
ET
CR
OSB
Y ST
REE
T
STRONGS R
OAD
MUNROE STREET
ORCHARD STREET
RA
ILRO
AD
AVE
NU
E
SUMMER STREET
HENRY STR
EET
BRIDG
E STREET
CENTER STREET
GREEN STREET
SMITH COLLEGE DRIVE
CHERRY STREET
SHERMAN AVENUE
ELIZABETH STREET
PH
EA
SA
NT
HIL
L D
RIV
E
SO
UT
H B
RA
NC
H R
OA
D
NORTH KING STREET
BELMO
NT AVENUE
PIN
E B
RO
OK
CU
RV
E
WOODMONT ROAD
GRANT AVENUE
COOLIDGE AVENUE
CLARK AVENUE
HOLYOKE STREET
PERKINS AVENUE
BATES
STRE
ET
STODDARD STREET
DE
NIS
E C
OU
RT
FR
AN
KLI
N S
TR
EE
T
BRIGHT STREET
HAMPSHIRE HEIGHTS
WALNUT TREES PATH
JAC
KS
ON
ST
RE
ET
SERVICE CENTER
EAST
STR
EET
SCHOOL STREETFO
RT
HIL
L TE
RR
AC
E
HAYES AVENUE
EASTERN AVENUE
MYRTLE STREET
MONTVIEW AVENUE
NORTHERN AVENUE
SMIT
H STR
EET
CR
AF
TS
AV
EN
UE
WINTER STREET
HIGHLAND AVENUE
CLARK SCHOOL DRIVE
KINGSLE
Y AVENUE
DEWEY COURT
TYLER COURT
HE
BE
RT
AV
EN
UE
BANK AVENUE
ED
WA
RD
S S
QU
AR
E
HANCOCK STREET
ISABELLA STREET
ARM
ORY S
TREE
T
TEXAS ROAD
WARFIELD PLACE
PAQ
UE
TTE
AVE
NU
E
LAWN AVENUE
UN
NA
ME
D R
OA
D
HAMPTON MANOR DRIVE
FLORID
A AVENUE
BUTTON STREET
EDGEW
OOD TERRACE
VIEW AVENUE
IND
USTR
IAL DR
IVE
FAIR STREET
BAY ROAD
CR
OS
S PAT
H R
OA
D
UNION STREET
118
147
137
127
108
216
226
206
236
246
177
255
265
196
167
275
187
157
108
187
137
147
127
127
137
147
157
137
118
127
147
118
137
147137
118
118
137
137
157
167
137
157
147
127
137
127
118
127
147
137
118
108
187
127
127
147
108
118
108
118
137
137
137
127
147
127
127
196
147
108
147
118
157
157
118
157
177
177
157
118
157
137
157
118
177
137
167
127
177
196
147
118
118
147
127
177
137
177
177
147
137
127
147
147
127
187
118
108
118
137
118
127
118
147
137
167
118
127
157
127
118
157
127
147
187
137
118
137
118
118
108
137
137
118
137
147
147
167
137
127
147
127
157
157
127
137
157
137
127
187
147
127
118
118
147
118
187
167
147
167
167
147
147
127
118
118
137
137
127
147
137
177
118
118
118
147
137
137
108
147
147
72’’
44’’
14’’
8’’
48’’
24’’
6’’
82’’
30’’
10’’
12’’
60’’
54’’
66’’
25’’
15’’
18’’
16’’
36’’
21’’
42’’
10’’
10’’
15’’
18’’
15’’
8’’
54’’
12’’
48’’
8’’
12’’
15’’
24’’
18’’
18’’
16’’
12’’
8’’
12’’
15’’
18’’
12’’
24’’
6’’
30’’
30’’
6’’
12’’
12’’
18’’
18’’
48’’
12’’
15’’
15’’
18’’
15’’
10’’
10’’
8’’
12’’
12’’
15’’
36’’
18’’
24’’
12’’
15’’
8’’
15’’
12’’
36’’
36’’
12’’
12’’
48’’
6’’
18’’
12’’
21’’
24’’
21’’
14’’
36’’
6’’
18’’
12’’
15’’
24’’
18’’
12’’
12’’
15’’
10’’
15’’
24’’
15’’
12’’
12’’
12’’
12’’
60’’
24’’
48’’
24’’
6’’
12’’
15’’
12’’
12’’
6’’
8’’
8’’
24’’
12’’
24’’
15’’
8’’
60’’
18’’
60’’
12’’
10’’
66’’
15’’
10’’
12’’
12’’
12’’
15’’
10’’
12’’
24’’
24’’
12’’
12’’
6’’
12’’
21’’
21’’
10’’
8’’
15’’
12’’
24’’
12’’
60’’
12’’
18’’
12’’
8’’
15’’
12’’
10’’
66’’
15’’
15’’
12’’
8’’
18’’
12’’
12’’
8’’
24’’
8’’
18’’
54’’
12’’
12’’
12’’
21’’
30’’
15’’
12’’
12’’
12’’
12’’
18’’
15’’
12’’
10’’
18’’
18’’
12’’
18’’
18’’
12’’
36’’
12’’
24’’
12’’
12’’
12’’
10’’
10’’
10’’
6’’
12’’
36’’
12’’
18’’
12’’
36’’
15’’
10’’
8’’
24’’
24’’
8’’
12’’
36’’
12’’
12’’
8’’
18’’
18’’
12’’
12’’
10’’
12’’
15’’
30’’
15’’
18’’
30’’
10’’
24’’
21’’
12’’
12’’
6’’
15’’
15’’
24’’
15’’
6’’
15’’
18’’
12’’
12’’
15’’
12’’
66’’
12’’
15’’
21’’
15’’
12’’
8’’
24’’
48’’
18’’
18’’
8’’
36’’
12’’
10’’
18’’
24’’
8’’
12’’
12’’
15’’
18’’
15’’
8’’
12’’
24’’
24’’
10’’
12’’
21’’
12’’
12’’
18’’
18’’
24’’
6’’
12’’
18’’
54’’
10’’8’’
36’’
24’’
18’’
66’’
15’’
36’’
10’’
18’’
12’’
36’’
15’’
15’’
18’’
44’’
24’’
18’’
12’’
12’’
12’’
36’’
12’’
8’’
24’’
18’’
30’’
18’’
66’’
10’’
18’’
12’’
36’’
12’’
12’’
12’’
18’’
18’’
15’’
10’’
18’’
18’’
8’’
36’’
8’’
12’’
12’’
12’’
12’’
12’’
18’’
12’’
18’’
15’’
30’’
12’’
18’’
24’’
12’’
15’’
10’’
12’’
16’’
15’’
12’’
10’’
12’’
18’’
6’’
8’’
24’’
12’’
24’’
12’’
12’’
12’’
24’’
6’’
6’’
12’’
36’’
15’’
24’’
30’’
12’’
12’’
18’’
12’’
10’’
10’’
8’’
15’’
48’’
36’’
8’’
10’’
8’’
12’’
10’’
12’’
10’’
10’’
12’’
10’’
24’’
18’’
12’’
15’’
12’’
10’’
12’’
15’’
12’’
12’’
12’’
15’’
10’’
10’’
12’’
15’’
18’’
12’’
12’’
157
147
\\Camgissvr1\Projects\M_Billings\Northampton\mxd\KingSt_WilliamSt_DrainageArea_Map.mxd JD 11/21/2011
Legend
91
91
350 0 350 700175
Feet
Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)
Drain Pipe
Drain Lateral
Culvert
Drainage Channel
Detention/Retention Basin
Stormwater Pumping StationDrainage Area Boundary
Drain Manhole
Catch Basin/Inlet
Stormwater Outfall
Area Prone to Flooding
King Street Brook Drainage Area ID
Williams Street Brook Drainage Area ID
City of NorthamptonStormwater and Flood Control System
Assessment and Utility PlanFigure 2.2
King Street/Market Street andBridge Street/Meadows Drainage Areas
Contour
Parcel Boundary
Building
DEP Wetlands
Wetlands (MassGIS)
Levee
Section 2 Existing Conditions
2‐7
106678‐80349‐03‐11
The second drainage system in this area is the Williams Street Brook drainage system which includes developed
areas along and west of Bridge Street, Pomeroy Terrace, and Williams Street, as well as less developed areas
east of Bridge Street in the Connecticut River floodplain. The Williams Street Brook drain line flows south and
discharges to the Historic Mill River. The floodplain area has experienced repetitive flooding particularly in the
following areas: Sheldon Field and Parking Lot, the Three County Fairgrounds, Old Ferry Road, Cross Path Road,
Fair Street, and the undeveloped area to the south of Fair Street particularly to the west of Cross Path Road and
along the alignment of the Williams Street Brook drainage pipe. This flooding has caused local roads to become
impassible in moderate storms and caused icing problems in the winter in this low‐lying floodplain. The drainage
system passes through the East Levee (described below) and includes a valve structure with the purpose of
preventing flood waters from passing through the dike. The valve is shut only when the Connecticut River has
reached a level of 115 feet at the gauging station at the Northampton Flood Control Pumping Station, a rare
occurrence which results in a the system being temporarily out of service. A large redevelopment of the Three
County Fairgrounds is planned in the near future; thus, upgrades to existing drainage infrastructure to improve
the drainage systems in this area are needed in concert with this project’s completion.
Field Inspection
On Tuesday November 30, 2010, CDM conducted a field survey of the
Bridge Street/Meadows area drainage system.
The Williams Street Brook system’s outfall is located in the east bank of
the Historic Mill River near the wastewater treatment plant entrance. The
24‐inch concrete pipe was about 30 percent filled in with silt and
sediment. It was also observed that the Historic Mill River itself was highly
silted.
Upstream, the main trunk line of the drainage system runs cross country
between Williams Street and Valley Street. There is also a branch of 15‐
and 12‐inch drains on Williams Street, which combines with the main
trunk line on Hockanum Road. There was no sign of recent street flooding in this area.
In the wooded wetland area in the flood plain adjacent to the East Levee, several inlets to the stormwater
system were found, along with a network of drainage ditches. These shallow ditches convey stormwater from
upstream field areas during high water events. The inlets to the stormwater system in this area act as relief for
the drain during peak flows and also allow flooded areas to drain after rain events have subsided.
There is a collapsed 42‐inch diameter Massachusetts Department of Transportation (MassDOT) outfall at the
Connecticut River near Damon Road that is connected to drains in the nearby industrial park and residential
areas. The outfall area has fallen into significant disrepair and includes pipes other than the 42‐inch drain.
Severe bank erosion at the outfall site has sloughed off soil about 50 feet back from the original bank of the
river. Approximately 50 yards upstream, a manhole adjacent to Damon Road was inspected and found to be in
excellent condition.
Lastly the flood plain area around the Three County Fairgrounds was inspected, including Fair Street, Old Ferry
Road, and Cross Path Road and assessed for the potential location for stormwater management facilities.
Photo 2.1 Williams Street Brook Outfall
Section 2 Existing Conditions
2‐8
106678‐80349‐03‐11
2.3.1.2 Existing Conditions Hydraulic Model
The Bridge Street/Meadows area watershed is approximately 185 acres and is a mixture of industrial, dense
urban residential, and special conservancy districts. This area includes the Three County Fairgrounds and
agricultural land. Figure 2.2 shows the sub‐drainage area delineations (identified by numbers) and drainage
systems for the Bridge Street/Meadows area.
The Bridge Street/Meadows area closed drainage system consists of two main lines, one flowing south and the
other flowing north. The dividing line between the south and north systems is at Lincoln Avenue. The south‐
flowing drain line (Williams Street Brook) ranges in size from 12 to 24 inches in diameter. It originates on Bridge
Street (Route 9) and becomes a cross‐country system at the Three County Fairgrounds at Old Ferry Road. It
traverses through residential and agricultural land and goes through the East Levee before discharging to the
Historic Mill River. The north‐flowing drain line (Day Avenue Brook) ranges in size from 12 to 42 inches in
diameter. It originates at Lincoln Avenue and travels cross‐country through an old streambed until the
intersection of Marshall and Crosby Streets. At the intersection of Crosby Street and the Norwottuck Rail Trail,
the drain line converges with a drain line from the industrial park, and then crosses under Interstate Route 91,
discharging to the Connecticut River at Damon Road via the MassDOT 42‐inch diameter collapsed pipe
The peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events for each sub‐drainage area can
be found on Table B.1 in Appendix B. The pipe capacity analysis for existing conditions found that several pipes
are under capacity, as shown on the tables in Appendix C. The results of the pipe capacity analysis are discussed
in greater depth in the following section.
2.3.1.3 Preliminary Review of Alternatives
To address flooding that occurs in the floodplain area between Bridge Street and Route I‐91, including the
Fairground area, CDM considered three alternatives.
1. Create a flood storage area upstream of the East Levee near Pomeroy Terrace. This area currently floods
when the 24‐inch system is above capacity. Preliminary modeling indicates that the proposed flood storage
area would have a surface area of approximately three acres and a 25‐year storm maximum stage depth of
3.5 feet. However, this alternative was eliminated from consideration because a field investigation of the
area by Northampton staff indicates that the proposed flood storage area location is a wetland, as shown on
Figure 3.1. CDM has received permission from permitting agencies in Massachusetts in the past to enhance
the flood storage capabilities of wetlands as a measure to protect properties from extreme flooding;
however, the Massachusetts Department of Environmental Protection prefers that this not be done.
Stormwater detention/retention basins are generally designed to protect wetland areas, not to use them as
basins.
2. Collect stormwater runoff from sub‐drainage areas 2 and 4 and route the flows north through the existing
cross‐country drainage system to the existing MassDOT 42‐inch diameter pipe that discharges to the
Connecticut River. The additional flow to the north‐flowing drainage system from areas 2 and 4 is 40 cfs.
The pipe capacity analysis under existing conditions indicates that the 42‐inch diameter pipe is undersized
and needs to be a 66‐inch diameter pipe. Similarly, the cross‐country pipes from Lincoln Avenue to Marshall
Street are undersized under existing conditions and need to be replaced with a 18‐inch to 36‐inch diameter
drains. Construction of this replacement drainage system would require obtaining easements from all the
private property owners abutting the pipe. CDM also considered directing the flows from areas 2 and 4 to
Bridge Street. However, Bridge Street is a busy state road (Route 9), whose ground elevation is nearly 10
feet higher than the ground elevation of the cross‐country pipe. Thus, because of the differences in the
ground elevations, it would be difficult to convey flows to the existing 42‐inch diameter pipe via gravity
flow.
Section 2 Existing Conditions
2‐9
106678‐80349‐03‐11
3. Redirect flows from the Three County Fairgrounds, and sub‐drainage areas 1, 2, and 3 to Old Ferry Road,
through the airport, to the Connecticut River in order to address the flooding in the floodplain area. An
alternative alignment is directing flows to Old Ferry Road, then to Cross Path Road, discharging at the
Connecticut River. The total flow collected is 90 cfs and requires a 48‐inch diameter pipe. The pipe
alignment from Old Ferry Road to Cross Path Road remains on all public roads, avoiding the need for
easements at the airport, but it is longer than the pipe alignment through the airport. Both alignments
create a new discharge to the Connecticut River. Despite the logistical and permitting considerations
associated with this alternative, it achieves the objective of reducing the flooding to the agricultural land
adjacent to Pomeroy Terrace, while still continuing to provide flows to the existing wetland located adjacent
to the levee.
As previously stated, the pipe capacity analysis indicates that the existing MassDOT 42‐inch diameter pipe that
discharges to the Connecticut River needs to be upsized to a 66‐inch diameter pipe. Calculations indicate that
the 48‐inch diameter pipe serving the industrial area just upstream of this pipe should be upsized to a 60‐inch
diameter pipe. Similar to the commercial area upstream of Church Street in the King Street area, there are
opportunities in this industrial area to install on‐site stormwater BMPs to reduce peak stormwater discharges.
CDM recommends that the property owners in the industrial park manage stormwater on‐site with BMPs to
reduce flows instead of upsizing the existing 48‐inch diameter pipe. CDM does recommend that the MassDOT
upsize the existing 42‐inch diameter outfall to a 66‐inch diameter pipe when they repair the pipe in the near
future. Repairing the existing 42‐inch diameter pipe and using the existing parallel 24‐inch diameter pipe does
not provide sufficient capacity to convey the calculated flows.
The pipe capacity analysis indicates that other sections of the Bridge Street/Meadows area drainage systems
need to be upsized to convey future build‐out flows. In sub‐drainage area 12, the existing 12‐to 18‐inch
diameter cross‐country system needs to be replaced with 18‐ to 36‐inch diameter pipes. However, given that
this system is located in a former streambed, obtaining sufficient cover for those pipes may be difficult. Twin
pipes or alternative box culvert or oval pipe systems may need to be used here. In sub‐drainage area 9 the
existing system in Williams Street needs to be replaced with 18‐ to 24‐inch diameter pipes. The 24‐inch
diameter pipe at the downstream end of the Williams Street Brook needs to be upsized to a 42‐inch diameter
pipe from the outfall at the Historic Mill River to just upstream of Hockunam Road and then upsized to a 30‐inch
diameter pipe to just upstream of Montview Avenue. See Section 3.2.3 for a discussion of the recommended
plan and preliminary cost estimate.
2.3.2 Elm Street Brook/Florence Area
2.3.2.1 Site Inspection and Area Description
Area Description
The Elm Street Brook watershed includes a mixture of rural/lightly developed land and moderate density
development including: a large portion of the Florence downtown area, residential areas, Cooley Dickinson
Hospital, Northampton High School (NHS), and Smith Vocational and Agricultural High School. The brook enters
a closed drainage system at the MassDOT property on Locust Street and at the Northampton High School and
ultimately discharges to the Mill River. Flooding currently occurs at the intersection of Elm Street, Milton Street
and Riverside Drive, along and south of Elm Street west of this intersection, Nutting Avenue, and at the
intersection of Milton Street and Ormond Drive. The flooding causes these roads to become impassable at
times. The drainage system is shown on Figure 2.3.
MILL RIVER
MILL RIV
ER
U
CC
L
B
A
S
Z
W
Q
N
M
V
G
T
X
J
R
P
H
I
BB
EE
O
Y
AA
K
D
DD
C
F
E
12’’
10’’
8’’
15’’
10’’
12’’
24’’
8’’
12’’
12’’
12’’
10’’
12’’
24’’
10’’
8’’
8’’
6’’
8’’
10’’
12’’
15’’
10’’
10’’
6’’
10’’
24’’
8’’
18’’
18’’
12’’
18’’
10’’
12’’
10’’
8’’
6’’
10’’
12’’
15’’
12’’
18’’
15’’
48’’
10’’
24’’
12’’
10’’
36’’
12’’
10’’
10’’
18’’
12’’
15’’
12’’
12’’
10’’
30’’
10’’
12’’
36’’
15’’
24’’
8’’
12’’
15’’
10’’
8’’
12’’
8’’
18’’
18’’
10’’
36’’
15’’
12’’
12’’
10’’
8’’
12’’
18’’
12’’
10’’
24’’
12’’
10’’
4’’
15’’
15’’
18’’
8’’
10’’
36’’
12’’
15’’
12’’
12’’
12’’
12’’
12’’
20’’
12’’
18’’
10’’
12’’
10’’
12’’
8’’
10’’
8’’
8’’
8’’
12’’
12’’
10’’
18’’
12’’
12’’
18’’
8’’
8’’
18’’
12’’
10’’
12’’
15’’
15’’
21’’
15’’
8’’
8’’
12’’
10’’
12’’
10’’
10’’
8’’
18’’
18’’
15’’
12’’
12’’
12’’
15’’
12’’
12’’
12’’
8’’
12’’
12’’
12’’
24’’
12’’
12’’
12’’
8’’
8’’
10’’
15’’
12’’
12’’
12’’
12’’
8’’
12’’
21’’
12’’
12’’
24’’
8’’
30’’
12’’
12’’
15’’
12’’
48’’
10’’
15’’
8’’
12’’
12’’
12’’
24’’
12’’
24’’
18’’
12’’
12’’
12’’
15’’
18’’
10’’
12’’
10’’
12’’
8’’
10’’
12’’
12’’
10’’
10’’
8’’
12’’
8’’
8’’
12’’
8’’
10’’
15’’ 10’’
10’’
15’’
15’’
24’’
27’’
12’’
24’’
8’’
12’’
12’’
10’’
12’’
15’’
21’’
15’’
12’’
15’’
18’’
12’’
10’’
18’’
12’’
10’’
15’’
12’’
30’’
15’’
10’’
12’’
18’’
15’’
12’’
12’’
15’’
21’’
12’’
10’’
12’’
12’’
21’’
18’’
12’’
10’’
12’’
12’’
15’’
12’’
15’’
10’’
8’’
12’’
12’’
10’’
12’’
15’’
12’’
15’’
12’’
12’’
33’’
12’’
18’’
18’’
15’’
137
177
275
187
255
177
285
265
167
187
275
196
246
206
265
216
187
295255
167
285
196
246
246
285
187
265
206
275
275
295
255
167
246
187
216
275
236
196
187
305
196
216
265
226
236
295
255
196
246
196
275
167
246
187
246
236
206
236
216
314
167
206
157
255
246
285
255
285
196
236
196
177
187
275
305
196
236
275
216
265
147
324
324
295
206
305
137
157
187
206
157
236
167
285
206
334
157
187
226
265 147
255
196
177
275
167
236
275
255
137
157
265
206
167
206
255
275
255
275
275
157
147
206
246
246
177
246
314
255
216
206
265
236
295
206
196
187
265
226
167
324
216
246
314
226
285
255
226
216
236
305
206
216
295
ASP
ENLA
NE
BRIDGE ROAD
ELMSTREET
PIN
ES
ED
GE
DR
IVE
GA
RF
IELD
ST
RE
ET
FED
ER
AL
ST
RE
ET
NORTH
ELM
STREET
BARDWELLSTREET
ST
RA
W A
VE
NU
E
AS
PE
N L
AN
E
LOCUSTSTREET
NORTHMAINSTREET
ASPENLANE
NO
RT
H E
LM S
TR
EE
T
NO
RT
HM
AP
LE
ST
RE
ET
NO
RT
H E
LM
ST
RE
ET
VERNO
NST
REET
SH
ALL
OW
BR
OO
K D
RIV
E
HATFIE
LD S
TREET
WARDAVENUE
KEAR
NEY
FIEL
DR
OAD
ELM STREET
JAC
KS
ON
ST
RE
ET
WASHINGTO
N
PLACE
ST
ILS
ON
AV
EN
UE
NO
RTH
ELM
ST
RE
ET
WARNER STREET
NORTH ELMSTREETBRANCH
NO
RT
H E
LM
ST
RE
ET
NO
RTH
ELM
STREE
T
CH
ES
TN
UT
ST
RE
ET
PROSPECT
STREET
ELM
ST
RE
ET
DRYADS
GREEN
EXTENSIO
N
PINESTREET
CH
ILD
S P
AR
K R
OA
D A
ELM
STR
EE
T
ARLINGTON
STREET
GOLDENCHAINLANE
PROSPECT STREET
PARADIS
E RO
AD
PAR
KS
TR
EE
T
NO
RTH
ELM
ST
RE
ET
PINES
EDGE
DRIVE
HATFI
ELD S
TREET
BURNCOLT
ROAD
KIMBALL STREET
MARCCIRCLE
DRYADS GREEN
CH
ES
TN
UT
ST
RE
ET
COSMIAN
AVENUE
SANDERSONAVENUE
BRIDGE ROAD
FR
AN
CIS
ST
RE
ET
DANA STREET
GLEASON ROAD
MAIN STREETFLORENCE
CO
OKE
AVE
NU
E
PLYMOUTH STREET
MA
PL
E S
TR
EE
T
LOCUST
STREET
DANA STREET
WARRENSTREET
OAK
STREET
CHILDS PARK ROAD B
CALVINTERRACE
PR
OS
PE
CT
AVE
NU
E
BR
AT
TO
NC
OU
RT
NO
RTH
ELM
STREE
T
HIG
HM
EA
DO
WR
OA
D
SMITH SCHOOLSERVICEROAD
NORTH ELM
STREET
HO
LLY
WO
OD
HE
IGH
TS
BRIDGEROAD
CLO
VE
RD
ALE
ST
RE
ET
MEADOW
STREET
HA
WT
HO
RN
LAN
E
LIBE
RT
Y
ST
RE
ET
KIN
GA
VE
NU
E
LAD
D
AVE
NU
E
ST
ER
LIN
G R
OA
D
TR
INIT
Y R
OW
NO
RT
H E
LM S
TR
EE
T
FLOR
EN
CE
RO
AD
MA
RY
JAN
ELA
NE
FR
AN
CIS
ST
RE
ET
FED
ERA
L STR
EE
T
HO
LLY
WO
OD
HE
IGH
TS
LAURELRIDGEDRIVE
WOOD
AVENUE
BEACONSTREET
HIGH STREET
WILLOWSTREET
SU
N H
ILL
DR
IVE
CO
OK
E AV
EN
UE
BLACKBERRYLANE
KE
YE
S S
TR
EE
T
PAR
KS
TR
EE
T
MAINSTREET
FLORENCE
NONOTUCK STREET
CAROLYN
STREET
EMILY
LANE
WIL
DE
R P
LAC
E
ALLISON STREET
VERONA STREET
GARFIELDAVENUE
ELM STREET
PLY
MO
UT
H A
VE
NU
E
MAPLE
STR
EET
ELMSTREET
RIDGEWOODTERRACE
HATFIELD S
TREET
FORBES
AVENUE
KENSINGTO
N
AVENUE
FAIR
FIE
LD A
VE
NU
E
SU
MN
ER
AV
EN
UE
ORMOND DRIVE
TAYLOR STREET
FR
AN
KLI
N S
TR
EE
T
DICKINSON
STREET
PROSPECTHEIGHTS
MANDELLE ROAD
PINESTREET
JEWETT STREET
STRAWBERRYHILL
DEPOT STREET
HAROLD STREET
RIVE
RS
IDE
DR
IVE
HIN
CK
LEY
ST
RE
ET
MU
RP
HY
TE
RR
AC
E
MA
PLE
ST
RE
ET
NE
W S
TRE
ET
HASTINGS
HEIGHTS
LEENO
TERRACE
CH
ILD
S P
AR
K R
OA
D A
POWELLSTREET
SHEFFIELD LANE
CLA
IRE
AV
EN
UE
DA
NA
ST
RE
ET
HIG
H M
EAD
OW
RO
AD
HO
WE
S S
TR
EE
T
BA
KE
R H
ILL
RO
AD
NONOTUCK STREET
LEX
ING
TON
AVE
NU
E
WEST CENTER STREET
PIO
NE
ER
VALL
EY
DR
IVE
MEADOWBROOK
DRIVE
EMILY LANE
MA
SSA
SO
ITST
REE
T
PINE
STREET
JAMES AVENUE
HAT
FIE
LD S
TR
EE
T
HIGH STREET
GLEASON ROAD
WO
OD
LAW
N A
VE
NU
E
PILGRIM DRIVE
HIN
CK
LEY
ST
RE
ET
MIL
TON
ST
RE
ET
CLEMENT
STREET
SOU
TH
MA
IN
STREE
T
GR
AN
DV
IEW
STR
EE
T
SMITH SCHOOL DRIVE
ARLINGTON
STREET
CH
ES
TN
UT
ST
RE
ET
RIVERSIDE DRIVE
WINSLOW
AVENUE
TERRACE LANE
LAN
DY
AV
EN
UE
DENNISTON PLACE
MO
UN
TAIN
STR
EE
T
BE
RK
SH
IRE
TE
RR
AC
E
NO
RFO
LKAV
EN
UE
HO
SP
ITA
L R
OA
D
RO
E A
VE
NU
E
RIDGEWOODTERRACE
NO
RW
OO
D AV
ENU
E
NU
TT
ING
AVE
NU
E
KEAR
NEY
FIE
LD R
OAD
CHILDS PARK ROAD B
WARNER
STREET
MANN TERRACE
WASHIN
GTON
AVENUE
NO
RT
HM
AP
LES
TR
EE
T
MIDDLESTREET
HARRISO
N AVENUE
FEDERAL
STREET
MA
PLE
WO
OD
TER
RAC
E
MAYNARD R
OAD
BOTTO
M RO
AD
FO
X F
AR
MS
RO
ADLA
KE
ST
RE
ET
CH
ILD
S PA
RK
RO
AD C
HIL
LCR
ES
T D
RIV
E
MEADOWBROOKDRIVE
WI L L O W
L A KE
N SH I C
E P
ON
D
Brough
tons
Brook
Elm St. Brook
SANDY H I
LL
B ROO K
Broughtons Brook
KING ST BROOK
SANDY HIL L
BROOK
Broughtons
Brook
Bro
ugh
tons
Br ook
Broughtons
Brook
Broughtons Brook
Brou g ht o
ns
Bro ok
PINE BROOK
Brou
ghto
ns Broo
k
Broughtons Brook
Elm St. Brook
Broughtons
Brook
Br ought ons Brook
PINE BROOK
\\camgissvr1\Projects\M_Billings\Northampton\mxd\ElmSt_DrainageArea_Map.mxd SCC July 2011
91
91
Drain Pipe
Drain Lateral
Culvert
Drainage Channel
Detention/Retention Basin
LegendDrainage Area Boundary
Area Prone to Flooding
Drain Manhole
Catch Basin/Inlet
Stormwater Outfall
Stormwater Pumping Station
City of NorthamptonStormwater and Flood Control System
Assessment and Utility Plan
Figure 2.3Elm Street Brook/Florence Drainage Areas
Contour
Parcel Boundary
Building
DEP Wetlands
Wetlands (MassGIS) 350 0 350 700175
Feet
Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)
Section 2 Existing Conditions
2‐11
106678‐80349‐03‐11
Field Inspection
On Wednesday, December 22, 2010 CDM conducted a field survey of the Elm Street Brook drainage system.
The stormwater retention pond located adjacent to Federal Street, south of the Northampton High School
athletic fields, is fed by a 36‐inch high density polyethylene (HDPE) drain pipe originating on Elm Street. The
retention pond was found to need some routine maintenance to remove some of the vegetation in the pond.
Elm Street Brook (Brook) crosses underneath Federal Street and empties into the Mill River through a channel
that is about 10 feet wide and 4 to 5 feet deep. The box culvert under Federal Street is in poor condition.
Headwalls on both sides show advanced degradation; the concrete has chipped away to expose a significant
amount of rebar.
At the intersection of Elm and Milton Streets the Brook is conveyed via 36‐inch and 48‐inch culverts under Elm
Street and the high school grounds, re‐emerging south of the track. No blockages were present during the time
of inspection, however some large branches were found in the downstream manhole near the high school
parking lot.
Upstream of the 36‐inch and 48‐inch culverts, Elm Street Brook flows along the northern side of Elm Street. The
stream is well established and is migrating very close to Elm Street, exposing existing gas lines. Upstream of this
section, the brook veers off away from Elm Street towards the Smith Vocational and Agricultural High School’s
land. This area was assessed for the potential location of a stormwater management basin.
The Brook crosses under Route 9 through a culvert and meanders upstream through an area that is generally
heavily wooded and undeveloped.
2.3.2.2 Existing Conditions Hydraulic Model
The Elm Street Brook area watershed is approximately 690
acres and is primarily a moderately dense residential area with
small areas of industrial and business development, as well as a
special conservancy district. The
watershed also includes the Smith Vocational and Agricultural
High School, Cooley Dickenson Hospital and NHS. Sub‐drainage
area delineations and drainage systems are shown on Figure
2.3.
The drainage system for the Elm Street Brook area watershed
consists of an extensive network of closed pipes and open
channels, as shown on Figure 2.3. Most of the sub‐drainage areas (totaling approximately 535 acres) drain to an
open channel located along the north side of Elm Street. This channel crosses under Elm Street in 36‐ and 48‐
inch diameter culverts at NHS. The 36‐inch culvert conveys flows to a detention basin on school property, which
outlets under Federal Street to a channel that discharges to the Mill River. The 48‐inch culvert under the playing
fields daylights into an open channel on school property that flows under Federal Street, discharging to the same
channel as the outlet from the detention basin.
The peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events for each sub‐drainage area can
be found on Table B.2 in Appendix B. The pipe capacity analysis for existing conditions found that several pipes
are under capacity, as shown on the tables in Appendix C. The results of the pipe capacity analysis are discussed
in greater depth in the following section.
Photo 2.2 Elm Street Brook
Section 2 Existing Conditions
2‐12
106678‐80349‐03‐11
2.3.2.3 Preliminary Review of Alternatives
Flooding at Elm Street near Nutting Avenue is the primary flooding issue in this drainage area. CDM considered
three alternatives to alleviate flooding in these areas.
1. Construct flood storage area just downstream of the dirt road on the Smith Vocational and Agricultural High
School property. The drainage area tributary to the flood storage area is very large – 478 acres. Preliminary
modeling indicates that the surface area of the flood storage area would need to be correspondingly large,
32 acres, with a four‐foot design flow depth, to have a significant effect on reducing downstream flows. A
flood storage area of this size is not feasible at this site.
2. Eliminate the 18‐inch pipe discharge to Elm Street Brook at the intersection of South Main Street and Elm
Street, and upsize the existing pipe in Federal Street to convey an additional 32 cfs. The pipe capacity
analysis under future build‐out conditions for this alternative indicates that the existing 18‐inch diameter
pipe at the discharge point to the Mill River needs to be upsized to a 54‐inch diameter pipe. This alternative
was eliminated because approximately 2,600 feet of pipe in Federal Street needs to be upsized and will not
provide relief of the localized flooding along Elm Street.
3. Modify the Elm Street Brook channel to provide relief at the location of flooding. Analysis of the Elm Street
Brook channel adjacent to Elm Street indicates that its capacity at its narrowest point is approximately 90
cfs. The narrowest section of the channel is closest to the street and results in flooding of Elm Street when
it overtops. The 10‐year storm peak rate of runoff entering the channel at this location is 270 cfs. The
channel is an environmental resource area that permitting agencies will want to preserve. Any
improvements to enlarge the channel to convey more flow must preserve the channels natural path and
characteristics. An alternative to enlarging the brook is to install a 7‐foot by 4‐foot box culvert in Elm Street
to convey brook overflows to Milton Street. A weir structure installed in the channel can redirect the
overflows into this culvert. The existing drainage system in Elm Street will tie into this system. The existing
12‐ inch diameter pipe in Milton Street will be replaced with a 48‐inch diameter pipe from Elm Street to
Federal Street. The box culvert will tie directly into this pipe and any surcharging will back up into the Elm
Street Brook channel and flow into the existing 36‐ and 48‐inch culverts that cross under Elm Street. In
Federal Street, the existing 18‐inch diameter pipe will be upsized to a 48‐inch pipe and convey flows west to
a new discharge point.
A new 72‐inch diameter pipe will be constructed from Federal Street and go through a parking lot,
discharging upstream of existing wetlands adjacent to the Mill River. A new discharge point to the Mill River
protects the existing channel and abutters between Federal Street and the Mill River from flooding. The
proposed discharge pipe size is 72 inches to accommodate future flows from Federal Street as part of
needed future upgrades to the drainage system. Installing a new pipe at Milton Street provides relief at the
source of flooding near NHS and will also reduce flows to the detention basin at the high school. Milton
Street is scheduled for full‐depth reconstruction, making it more practical to install a new pipe in Milton
Street and in a shorter section of Federal Street, rather than constructing nearly 2,600 feet of new pipe in
Federal Street.
The pipe capacity analysis for the major drain lines in the Elm Street Brook area indicates that several pipes need
to be enlarged to accommodate 10‐year 24‐hour peak rates of runoff. In Federal Street, from Warner Street to
the proposed new 72‐inch diameter discharge point, it is recommended the existing system be replaced with
new pipes ranging in diameter from 24 to 48 inches. In addition, in Federal Street, from Vernon Street to the
existing outfall to the Mill River, the existing 10‐inch diameter pipe needs to be upsized to a 36‐inch diameter
pipe. Within sub‐drainage area F, from High Street to Straw Avenue, the existing drainage system should be
Section 2 Existing Conditions
2‐13
106678‐80349‐03‐11
replaced with a new system with diameters ranging from 12 to 36 inches. See Section 3.2.4 for a discussion of
the recommended plan and preliminary cost estimate.
2.3.3 King Street/Market Street/Downtown Area
2.3.3.1 Site Inspection and Area Description
Area Description
The two main trunk lines in the King Street system (i.e., King Street and Market Street Brook systems) have an
interconnection at Main Street (Rte. 9) underneath the railroad bridge. This interconnection was inspected by
CDM and City staff. It was confirmed that the old culvert (carrying sanitary and storm flows) located in the
Fitzwilly’s Pub parking lot was abandoned and a new diversion structure constructed in Main Street. The King
Street main trunk line enters the diversion structure as a 66‐inch pipe and exits the structure as a 60‐ inch pipe.
A 36‐inch relief pipe in the diversion structure connects to the Market Street Brook system.
The downtown King Street area has two main drain lines. The King Street drain line conveys stormwater runoff
from the highly developed commercial area along Route 5 (King Street) and discharges to the Historic Mill River
bed. The Market Street Brook drain line (discussed above) originates along the existing abandoned railroad bed
in the vicinity of North Street, between Woodmont Road and Highland Avenue, and it discharges to the Historic
Mill River bed. The two drainage systems are connected to each other through a diversion structure located on
Main Street. These drainage systems are shown on Figure 2.2. The section of Main Street under the railroad
bridge and State Street from just north of Main Street to Summer Street are prone to localized flooding.
Field Inspection
On Tuesday December 7, 2010 CDM conducted a field survey of the King
Street area drainage system.
There are two drainage systems, both of which discharge to the Historic
Mill River bed: a 60‐inch circular concrete pipe located under the
railroad bridge off Hockanum Road, and a 66‐inch circular concrete pipe
located behind the condominiums on Randolph Place near the bikeway.
The river bed has significant sediment accumulation in areas; however,
the outfalls had less than 20 percent sediment at the end of the pipes
and look to be in good condition.
The field crew met with DPW staff to discuss some specific areas
where localized flooding had occurred in a recent storm. These areas
were the North Street underpass between Market and King Streets,
condominiums on Gothic Street, and State Street at Stoddard Street.
On North Street, two catch basins at the low point of the underpass
directly connect to the old Market Street Brook culvert and flooding
may be due to the need for more frequent catch basin maintenance or
additional grate.
Photo 2.4 60‐in Outfall at Hockanum Road
Photo 2.3 66‐in Outfall at Randolph Place
Section 2 Existing Conditions
2‐14
106678‐80349‐03‐11
Stoddard Street is experiencing flooding from backwater coming from the wetland behind Stop & Shop. Heavy
beaver activity has caused water to pool upstream of the wetlands sediment trap and migrate through
homeowners’ yards into the street along the side of the bikeway.
State Street had been observed with large puddles during high‐intensity downpours.
2.3.3.2 Existing Conditions Hydraulic Model
The King Street area watershed is approximately 397 acres and is a mixture of industrial, business and urban
residential districts. Business and residential development is dense, and includes sections of downtown
Northampton. The highly impervious business district is generally centered along King Street. This drainage
area also includes portions of the Smith College campus. Sub‐drainage area delineations and the King Street
area drainage systems are shown on Figure 2.2. The King Street/Market Street area sub‐systems are identified
by letters and the Bridge Street/Meadows area sub‐systems are identified by numbers on this figure.
The King Street closed drainage system consists of two main lines, with the overall drainage area nearly equally
divided between the two systems. The King Street drain line ranges in size from 12 inches to 66 inches in
diameter. It follows King Street to Merrick Lane, and then travels down Strong Avenue, Pearl Street and
Pleasant Street before discharging to the Historic Mill River bed.
The Market Street Brook drain line originates along the existing abandoned railroad bed in the vicinity of North
Street, between Woodmont Road and Highland Avenue. It generally follows the railroad bed to Hockanum
Road, before discharging to the Historic Mill River bed. It begins as a 36‐inch diameter pipe and then gradually
increases in size through a varying series of circular, box and arch pipes. The approximate maximum equivalent
diameter in the system is 82 inches. Upstream of the Market Street Brook closed drainage system, there is a
series of open channels that conveys stormwater runoff from the industrial park to the Market Street Brook
system. Additionally, there is a private 12‐inch closed drainage system that originates from a rear section of
retail businesses along King Street, which also ties into the upstream end of the Market Street Brook system. At
the intersection of Main Street and Strong Avenue, there is a diversion structure in the King Street system that
diverts flows to the Market Street system via a 36‐inch diameter pipe.
The peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events for each sub‐drainage area can
be found on Table B.3 in Appendix B. The pipe capacity analysis for existing conditions found that several pipes
are undercapacity, as shown on the tables in Appendix C. The results of the pipe capacity analysis are discussed
in greater depth in the following section.
2.3.3.3 Preliminary Review of Alternatives
Within the King Street area, Church Street is currently prone to localized flooding. The pipe capacity analysis
indicates that the existing 21‐inch diameter pipe in this street cannot adequately convey flows under existing
and future build‐out conditions during a 10‐year 24‐hour storm event. A 36‐inch diameter pipe along the entire
street length is needed to relieve flooding on Church Street.
Upstream of Church Street, the King Street system is slightly undersized for a 10‐year 24‐hour design storm
(there is an existing 30‐inch drain and a 36‐inch drain is needed). There are opportunities on largely impervious
commercial properties in this area to manage stormwater on‐site with Best Management Practices (BMPs), such
as bioretention street planters, rain gardens, green roofs and porous pavement. A recommended alternative to
upsizing the pipe from 30 to 36 inches is to install these types of BMPs to reduce rates and volumes of
stormwater runoff to the drainage system in this section of King Street. If the proposed stormwater utility
program described in Section 5 is adopted, property owners can be provided the option of receiving credit and
Section 2 Existing Conditions
2‐15
106678‐80349‐03‐11
reducing the cost of their utility bills for installing BMPs that reduce stormwater runoff and improve the water
quality of receiving waters.
Downstream of Church Street, it is recommended that the King Street system be upsized to a 48‐inch diameter
pipe at Church Street and gradually increased to a 72‐inch diameter pipe at Trumbull Road. These pipes were
sized assuming that BMPs are not installed in the upstream retail properties.
In State Street near Trumbull Road, the pipe capacity analysis indicates that a 36‐inch diameter pipe is needed to
alleviate flooding that currently occurs near Trumbull Road. Upstream of the 36‐inch diameter pipe, it is
recommended the existing 10‐inch lateral system that ties into State Street be upsized to 12‐ to 24‐inch
diameter pipes. In sub‐drainage area M (see Figure 3.1), it is recommended the existing 12‐inch diameter
system be replaced with a new system that ranges from 12 to 18 inches in diameter. The existing 24‐ to 36‐inch
diameter pipe in Trumbull Road should be replaced with a new system that ranges from 48 to 54 inches in
diameter.
Downstream of Trumbull Road to the diversion manhole, the pipe capacity analysis indicates that the existing
48‐ to 66‐inch diameter pipe in King Street needs to be upsized to a 78‐inch diameter pipe. The pipes
downstream of the diversion manhole are adequate to convey flows and do not need to be upsized.
In general, the Market Street Brook system has nearly sufficient capacity to convey flows associated with the 10‐
year 24‐hour storm event to the Historic Mill River bed; however, upstream of Bridge Street, the pipes are in
poor structural condition, which may contribute to flooding problems. Upstream of North Street, the pipe
capacity analysis indicates that the 48 inch diameter equivalent system described in Section 2 is adequate to
convey flows. However, the 1981 North Industrial Park Drainage Study prepared by Almer Huntley (“Almer
Huntley report”) on this system noted that the overall condition of this section of pipe is poor. Between Bridge
Street and North Street, Almer Huntley was not able to inspect the pipe because the manholes were not
accessible. They did inspect the pipe just downstream of North Street and just upstream of Bridge Street, and
found the condition to be poor. In these areas, the Almer Huntley report documented longitudinal cracks and
missing bricks and stones. Between North Street and Bridge Street, the average equivalent pipe diameter is 44
inches and CDM’s pipe capacity analysis indicates that a 48‐inch diameter pipe is needed to adequately convey
flows. Thus, given the poor condition of the existing system and the lack of sufficient capacity in some sections
of the system, CDM recommends replacing the 44‐ and 48‐inch diameter equivalent pipes with a 48‐inch
diameter pipe. Repairing and upsizing this section of pipe will reduce the localized flooding that currently occurs
at North Street.
Downstream of Bridge Street, Almer Huntley found the existing Market Street Brook system to be in good
condition. However, an inspection is recommended to confirm the current condition. The pipe continues to be
a composite of pipe diameters, shapes and materials, such as a brick box with a brick arch roof and a wooden
plank floor. CDM’s pipe capacity analysis indicates that from Bridge Street to the outfall at the Historic Mill River
bed the Market Street Brook system has the capacity to convey future build‐out flows and, thus, it is not
recommended that this section of pipe be upsized.
The drainage system associated with Market Street currently ties into the Market Street Brook system at Bridge
Street. The system begins as a 12‐inch diameter pipe near Walnut Street and gradually increases to a 24‐inch
diameter pipe at Bridge Street. The pipe capacity analysis indicates that the drainage system in Market Street is
insufficient to convey flows during a 10‐year 24‐hour storm. It is recommended that the system be replaced
with a 24‐inch diameter pipe beginning at Walnut Street and gradually increased to a 48‐inch diameter pipe
towards Bridge Street.
Section 2 Existing Conditions
2‐16
106678‐80349‐03‐11
Photo 2.5 Swale behind Austin Circle
Sub‐drainage area D shown on Figure 3.1 is currently served by a private 12‐inch diameter drainage line that
connects into the Market Street Brook drainage system. The feasibility of re‐routing this drainage line to the
King Street system was considered in the future build‐out analysis. Modeling indicates that redirecting flows
from sub‐drainage area D from the Market Street Brook system to the King Street system would have a minor
effect on either system. For the 10‐year 24‐hour storm event, it accounts for only 3 and 4 percent (6 to 8 cfs) of
the total flows to the King Street and Market Street Brook systems, respectively. Thus, if one or both systems
are enlarged, the drainage system from sub‐drainage area D could be conveyed in either system.
Overall, the King Street/Market Street business district is highly impervious and is likely to see extensive
redevelopment over the next 10 to 20 years. This is a potential area for incorporating green infrastructure/Best
Management Practices (BMPs), such as green roofs, porous pavement and bioretention systems in the form of
street planters and rain gardens, during redevelopment. In areas where soils are not conducive for infiltration
(i.e., clay) these BMPs can still provide stormwater treatment prior to discharge to the storm drain system via an
underdrain system. See Section 3.2.5 for a discussion of the recommended plan and preliminary cost estimate.
2.3.4 Austin Circle/Ryan Road Area
2.3.4.1 Site Inspection and Area Description
On Wednesday, December 22, 2010 CDM conducted a field survey
of the Ryan Road area. Between Austin Circle and the elementary
school on Ryan Road, there is a drainage ditch that periodically
overtops and floods into the backyards and basements of residents
living on Austin Circle. This flat ditch receives storm flows from
Ryan Road school, Ryan Road, and the area north of Ryan Road, in
the vicinity of the Matthew Drive area. Further downstream in the
channel, the build‐up of sediment is occurring at the culvert
crossings at Brierwood Drive and Acrebrook Drive. These sections
of channel are in need of sediment removal.
Matthew Drive is also affected by drainage problems. The top of the
hill above Matthew Drive has a perched pond that at the time of
inspection had no freeboard and was discharging to a seasonal
streambed which flows down the hill, through a resident’s yard,
onto the street and into a catch basin.
The culverts under Brierwood Drive and Acrebrook Drive show
evidence of significant sediment build‐up resulting from ponding
and slow flow velocities through this area. The drainage system is
shown on Figure 2.4. The drainage ditch between Austin Circle
and the elementary school, as well as the low‐lying grassed area
along Ryan Road on the school property, are prone to flooding.
2.3.4.2 Existing Conditions Hydraulic Model
The Ryan Road area watershed is approximately 121 acres and is a medium density residential area. Most of the
area north of Ryan Road is wooded and undeveloped land, with the exception of one housing subdivision and a
shooting range. This wooded area contains a small natural pond that overflows down the hill, causing erosion
on a property at the corner of Matthew Drive and Gregory Lane. The Ryan Road Elementary School is located
within this drainage area. Sub‐drainage delineations and drainage systems are shown on Figure 2.4.
A1
D
G
B
A2
A3
RYAN ROAD
OVERLOOK DRIVE
ACREBROO
K DRIVE
BRIE
RW
OO
D D
RIV
E
BRO
OK
SID
E CIR
CLE
WO
OD
S R
OA
D
SPRUCE HILL AVENUE
DEERFIELD DRIVE
PIONEER KNO
LLS
AUSTIN CIRCLE
GILR
AIN TER
RAC
E
MAT
THE
W D
RIV
E
BIRCH HILL ROAD
LON
GV
IEW
DR
IVE
PEN
CA
SAL D
RIV
E
BEATTIE
DR
IVE
ALAMO COURT
HOLLY COURT
HIC
KOR
Y D
RIV
E
GOLDEN DRIVE
GREGORY L
ANE
TARA CIRCLE
CA
HIL
LAN
E T
ER
RA
CE
FO
RE
ST
GL
EN
DR
IVE
SUMMERFIELD STREET
BR
OO
KS
IDE
CIR
CLE
314
324
334
344
403
383
374
413
423
364
354
305
433
275
452
295
285
462
393
442
393
314
285
423
305
413
442
305
285
275
393
354
324
275
364
275
295
295
285
364
295
285
374
344
334
275
314
295
285
305
305
295
305
433
314
383
285
393
18’’
15’’
24’’
10’’
60’’
16’’
12’’
8’’
30’’
48’’
18’’
12’’
12’’
12’’
12’’
12’’
12’’
12’’
15’’
12’’
15’’
12’’
12’’
15’’
12’’
10’’
12’’
12’’
12’’
18’’
15’’
10’’
12’’
12’’
12’’
12’’
12’’
12’’
12’’
18’’
12’’
12’’
12’’
12’’
12’’
12’’
18’’
8’’
12’’
12’’
12’’
15’’
\\camgissvr1\Projects\M_Billings\Northampton\mxd\RyanRoad_DrainageArea_Map.mxd JD 11/21/2011
Drain Pipe
Drain Lateral
Culvert
Drainage Channel
Detention/Retention Basin
LegendDrainage Area Boundary
Area Prone to Flooding
Drain Manhole
Catch Basin/Inlet
Stormwater Outfall
Stormwater Pumping Station
91
91
City of NorthamptonStormwater and Flood Control System
Assessment and Utility Plan
Figure 2.4Austin Circle/Ryan Road
Drainage Areas
Contour
Parcel Boundary
Building
DEP Wetlands
Wetlands (Delineated by City)
Wetlands (MassGIS) Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)
150 0 150 30075
Feet
Section 2 Existing Conditions
2‐18
106678‐80349‐03‐11
Approximately 45 acres of the area north of Ryan Road are routed through the two detention basins associated
with the housing subdivision. The remaining northern area sheet flows to Ryan Road. Stormwater runoff from
the area north of Ryan Road and from the elementary school building and parking lots is collected in a 15‐inch
diameter pipe that crosses the elementary school property and discharges upward through a grate that is
adjacent to an open channel that runs through the backyards of residences on Austin Circle. Most of the
remaining drainage area sheet flows directly to this channel. Local street drainage associated with Brierwood
and Acrebrook Drives discharges directly into 36‐inch diameter culverts located under these streets.
The peak rates of runoff during 2‐, 10‐, 25‐, and 100‐year 24‐hour storm events for each sub‐drainage area can
be found on Table B.4 in Appendix B.
2.3.4.3 Preliminary Review of Alternatives
Three alternatives were considered for Ryan Road to address the drainage ditch that periodically overtops and
floods into the backyards and basements of residents living on Austin Circle.
1. Install a new street drainage system that intercepts the existing 15‐inch diameter pipe that crosses Ryan
Road with a 30‐inch diameter relief pipe in Ryan Road. This system would convey flow to Brierwood Drive
and then down Brierwood Drive, discharging just upstream of the 36‐inch diameter culvert in Brierwood
Drive. A variation of this alternative is intercepting the 15‐inch diameter pipe with a 30‐inch diameter relief
pipe and crossing diagonally across the elementary school’s athletic fields, discharging just upstream of the
36‐inch culvert. This alternative conveys flows from the drainage area north of Ryan Road. It increases the
peak flow at the culvert from 21 to 37 cfs, causing an increase in the hydraulic grade line at the culvert by
approximately one foot. The 36‐inch diameter culvert would need to be increased in size to lower the grade
line, which would increase peak rates of runoff to downstream properties.
2. Upsize the 15‐inch diameter pipe across the elementary school property to a 30‐inch diameter pipe to
convey runoff from a 25‐year storm event, and provide channel improvements in the channel adjacent to
Austin Circle. The improved conveyance of flow through the 30‐inch pipe will result in a downstream
increase in the hydraulic grade line at the Brierwood Drive culvert. Thus, this alternative and the first
alternative do not effectively address the flooding problems that residents of the Austin Circle currently
experience. The Brierwood Drive culvert acts as a control and the headwater backs up into the channel, a
condition the first two alternatives will exacerbate because of the increased flows to the culvert.
3. Create a flood storage area just upstream of the Brierwood Drive culvert and use the culvert as the outlet
control for the flood storage area. With a surface area of approximately 1.3 acres, the flood storage area
has a total depth of four feet (25‐year storm maximum stage plus one foot of freeboard). A 24‐inch
diameter pipe will intercept the 15‐inch diameter pipe at Ryan Road and convey runoff from the drainage
area north of Ryan Road diagonally across the athletic fields to the flood storage area. The 15‐inch diameter
pipe will continue to convey runoff from the elementary school to the existing channel, which will discharge
into the flood storage area. This alternative lowers the hydraulic grade line by approximately 0.8 feet,
resulting in less water backing up into the channel. It also reduces flows downstream of the culvert by 13
cfs during a 2‐ year 24‐hour storm event. The City performed a wetlands survey along the drainage ditch in
September 2011. The wetlands survey indicates that there are bordering vegetated wetlands along the
alignment of the ditch. The flood storage area has been located to not impact these wetland areas.
4. This alternative is a variation of Alternative #3. Because of the high degree of imperviousness of the school
and the short time of concentration, the runoff from the school was calculated to be 19 cfs for the 25‐year
storm. The existing 15‐inch diameter pipe would convey this flow to the channel. However, a channel to
convey a flow of this magnitude would have a top width of approximately 26 feet. Thus, instead of installing
Section 2 Existing Conditions
2‐19
106678‐80349‐03‐11
a 24‐inch diameter pipe from Ryan Road across the athletic fields to the flood storage area, the 15‐inch pipe
through the school property would be upsized to a 30‐inch pipe to collect and convey flows from the
drainage area north of Ryan Road and from the elementary school, and then turn easterly at the
southeastern corner of the elementary school, crossing the fields, to the flood storage area. This option
significantly reduces the flow to the channel to approximately 10 cfs. The channel would have a total depth
of 3 ft and a top width of 21 ft.
For all four alternatives, channel improvements are recommended to improve conveyance of flows. Currently,
the channel between the Brierwood Drive culvert and Acrebrook Drive culvert is not well‐defined and it is
recommended that a better defined channel be created. The channel along Austin Circle needs to be cleaned to
remove brush and other debris. It is noted that theses channels are on private property, have no easements to
the City and were created by the developer for these subdivisions. See Section 3.2.6 for a discussion of the
recommended plan and preliminary cost estimate.
2.4 Flood Control Systems 2.4.1 East Levee Description
The East Levee flood control system is an earthen fill levee and three concrete flood walls, with a total length of
approximately 4,950 feet and a maximum height of approximately 23 feet. The width of the crest is about 10
feet with an 8‐foot‐wide gravel surface and grass‐covered edges. The crest of the levee was constructed at an
elevation of about El. 131.6 to El. 131.3 NAVD88.
As shown on Figure 2.1, the earth embankment starts at the intersection of Pomeroy Terrace and Hancock
Street, continues southeasterly and crosses Ventures Field Road. Beyond the Ventures Field Road crossing, the
embankment bends and the alignment extends southwesterly and crosses Hockanum Road and meets the
Northampton Flood Control Pumping Station at the Old Mill River. From the pumping station, the earth
embankment bends and crosses the Boston & Maine railroad tracks and then Route 5. Concrete retaining
walls/abutments are constructed at the railroad crossing and the highway crossing and function as stop‐log
structures during a potential flood event. Stop‐logs are stored in corrugated metal storage houses constructed
next to the crossings. The earth embankment extends westerly beyond Route 5 approximately 500 feet where
the embankment is in contact with the natural earth high ground.
Design and record drawings show that the core of the embankment is constructed with a random soil material.
The embankment material river‐side of the core is an impervious clay‐like blanket material, and a sandy pervious
material is shown land‐side of the core. Based on the record plans, most of the river‐side slope of the levee was
presented as a 2.5 horizontal: 1 vertical (2.5H:1V) slope, and a 3H:1V slope at the segment between Ventures
Field Road and Hockanum Road. Most of the land‐side slope of the levee was shown to be a 2H:1V slope, and a
3H:1V slope at the segment between Ventures Field Road and Hockanum Road.
A toe drain system consisting of 8‐inch to 15‐inch porous concrete pipe in gravel bedding filter trenches exists
below grade along most of the embankment toe of slope. Intermittent manholes are installed to service the toe
drain system. The toe drain system collects the seepage water through the levee fill and discharges to the
stormwater collection system.
2.4.2 West Levee Description
The West Levee flood control system consists of earthen fill levee segments and a concrete flood wall, with a
total length of approximately 2,300 feet. Based on the record plans, the crest of the levee segments is shown to
be generally 10 feet wide and grass‐covered. The crest of the levee segment north of West Street was
Section 2 Existing Conditions
2‐20
106678‐80349‐03‐11
constructed at elevations ranging from El. 145.5 to El. 144.8 ft NAVD88. The crest of the levee segment south of
the bridge of the former railroad crossing was constructed at an elevation of about El. 139.1 NAVD88. The
embankment is approximately 16 feet high.
The system begins at high ground near Paradise Pond just northeast of the Paradise Pond Dam, and adjacent to
College Lane on the property of Smith College (Figure 2.1). The embankment extends southerly, parallel with the
east bank of the Mill River for about 1,100 feet to the crossing at West Street. A concrete “T” flood wall extends
southerly from West Street to the current bike path bridge crossing, formerly the New York, New Haven &
Hartford Railroad. The concrete flood wall is about 450 feet long and contacts the stone abutment of the bridge
of the former railroad. Most of the length of the wall is about 10 feet above ground surface with a top elevation
of about El. 140 NAVD88. The top of the wall and stop‐log structure at the West Street south curb is about El.
145.3 NAVD88 to match the elevation of the levee and stop‐log retaining wall at the north curb. A concrete flood
wall and an earth embankment with slight curvature extend from the former railroad crossing abutment in a
southerly direction about 900 feet to the natural earth abutment and high ground at Hebert Avenue. This last
earth embankment segment serves as a dam, which permitted the Mill River to be diverted into the Diversion
Canal.
Based on the record drawings, the river‐side slope of the northerly levee segment is shown as a 2.5H:1V slope.
The levee segment south of the flood wall was built with a 3H:1V slope to the end at Hebert Avenue. The slope
surface is protected with a one‐foot layer of hand‐placed riprap. Most of the land‐side slope of the levee is
shown to be a 2H:1V slope.
A toe drain system consisting of 8‐inch to 10‐inch porous concrete pipe in filtered trenches exists below grade
along most of the embankment toe of slope. Intermittent manholes are installed to service the toe drain system.
The construction of the Northampton Flood Control Pumping Station at the East Levee involved the diversion of
the Mill River, which originally flowed through the City. Flows originating from the upstream Mill River were
diverted into the new diversion canal, which begins at the southern portion of the West Levee and directs flow
to the old Connecticut River Ox Bow, currently called Ox Bow Lake. The diversion route made it necessary to
close Grove Street and to build a new bridge with a drop structure where the canal crosses South Street.
Downstream of the drop structure, the canal bottom is about 35 feet wide, with 3H: 1V side‐slopes. The bottom
and side slopes are lined with stone riprap. The canal extends about 8,000 feet beyond the end of the drop
structure to the discharge point at Ox Bow Lake.
2.4.3 East and West Levee Inspection
On December 22, 2010, CDM, accompanied by a representative from the City, performed a general visual
inspection of the levee system. A separate, more detailed inspection and evaluation of the levee system is
currently being performed by others for the USACE.
In general, the levee systems were found to be in very good condition. Only isolated areas were noted to have
deficiencies that would usually be corrected with normal maintenance practices. In general, the deficiencies
included:
1. A few trees and thick brush growing near the toe of the river‐side slopes of the levee and at the river‐side
face of the concrete flood wall at isolated areas;
2. Ruts, small depressions on the crest of the earth embankments;
3. The grass on the crest of the earth embankments worn by foot traffic exposing bare soil to potential
erosion;
Section 2 Existing Conditions
2‐21
106678‐80349‐03‐11
4. Isolated area of missing riprap on the slope of the diversion channel near the end of the West Levee; and
5. Potential clogging of the toe drain system as reported by recent USACE inspection.
Recently, the USACE has inspected the levees on two separate occasions: September 18, 2009 and on December
10, 2010/January 14, 2011.
The 2009 inspection found the levees to be in a “Minimally Acceptable” condition, meaning that no deficiencies
were identified that would prevent the system from performing as intended during a flood event. The report
noted deficiencies that included:
1. Heavy vegetation, including large bushes, trees, and tall grass, growing on and along the toe of slope of the
levees;
2. Heavy vegetation, including trees, growing in the riprap channel banks of the diversion canal;
3. Sections of the levee crown and slope with little to no sod cover due to pedestrian traffic;
4. Areas of riprap along the levee toe have been displaced;
5. Animal burrows on the crown and slope of the levee;
6. Vegetation and sediment in the intake pond at the pump station.
Similarly, the 2010/2011 inspection found the levees to be in a “Minimally Acceptable” condition. The report
noted the same deficiencies as those found during the 2009 inspection. The inspection also found some spalling
occurring on the concrete flood walls. The USACE has required that deficiencies be repaired by January 2013 or
2014, depending on the item.
2.4.4 East/West Levee Recommended Improvements
Based on the visual inspection of the East and West Levees performed by CDM, we recommend the following
activities that improve the overall conditions of the levees, but do not alter the current design.
Cut and clear trees and thick brush on the levee and at least 15 feet beyond the abutments and at the toe
of the levee. This is the current (new) USACE requirements. The removal of the trees greater than four
inches in diameter and any planned excavation of roots should be designed by a qualified levee/dam
engineer. Holes should be filled with low‐permeability fill on the river‐side slope and compacted fill on
the land‐side slope.
Remove burrowing animals and backfill holes with compacted fill. Alternatively, flowable fill could be
used to fill the hole. The material may have to be rodded to force the mix further into the hole. After the
mix is installed, the upper 6 in. +/‐ of the hole should be backfilled with soil and seeded to promote grass
growth
Repair areas of sparse vegetation and small depressions on the crest and land‐side slope by establishing a
healthy stand of grass to prevent future erosion. Continue to monitor for new bare spots, and maintain
grass since the crest of the levee system is used for hiking/walking by the public.
Potential clogging of the toe drain system at the land‐side toe of the embankments should be
investigated, and sediment should be removed from the toe drain pipe and manholes.
Section 2 Existing Conditions
2‐22
106678‐80349‐03‐11
Remove the salt shed located against the land‐side face of the concrete flood wall of the west levee
system at the physical plant property of Smith College.
Update the Operation and Maintenance Manual to include inspection schedules, annual training, and
operational and maintenance procedures required to ensure satisfactory operation of the levee system
to reduce the potential for deterioration to the facility.
When flood control levee system accreditation is required, follow the general guidelines outlined in the
memo in Appendix A in accordance with CFR 65.10.
These recommendations will require design by a professional engineer, application for applicable permits, and
construction by a contractor experienced in levee repair. CDM also recommends the following activities be
undertaken on a regular or yearly basis.
Regular maintenance activities should be performed at least twice a year or as conditions warrant from
the Spring to Fall seasons to control and limit growth of vegetation on the levee and the banks of the
diversion canal.
Monitor areas for dislodged riprap, and replace riprap stones to protect exposed embankment soils.
Annual training to responsible staff for erection of flood control stop log structures.
The 2009 and 2010/2011 inspections made similar recommendations for repairing the levees.
Excess vegetation should be removed and vegetative growth controlled in the long term with a
maintenance program.
Sod should be reestablished on the bare areas of the levee crown and maintained.
Animal borrows should be excavated and backfilled, and an animal control program established.
Areas of missing riprap should be replaced with new riprap.
The toe drain system should be inspected by remote camera every five years.
The intake pond at the pump station should be cleared of vegetation.
In addition, the 2010/2011 USACE Report identified several system data gaps that will require extensive
engineering to be completed by January 2014. The most notable system data gaps include:
Recent topographic survey information and comparison to the design height/available freeboard;
Hydraulic and hydrologic analyses of the entire flood control system;
Seepage and slope stability analyses for the dikes, floodwalls and diversion canal;
Settlement analyses for the dike, pumping station, and floodwalls;
Confirmation with additional test boring that the “artificial fill” was removed down to the moderately
impervious formation prior to constructing the dike near Smith College; and
Pipe inspection reports for all pipes that pass through or under the flood control system.
Section 2 Existing Conditions
2‐23
106678‐80349‐03‐11
For flood control projects to be recognized by FEMA on the NFIP maps, adequate evidence must be provided
showing the flood control system provides reasonable assurance that protection from the base flood exists in
accordance with CFR 65.10. The accreditation process with respect to the stability of the earthen embankment
levees and flood walls includes:
A topographic survey of the system to confirm system geometry and the 3‐foot freeboard requirement ;
A subsurface exploration program to evaluate the composition and in‐situ strength of embankment and
foundation materials;
Evaluating erosion protection from currents and/or wave action;
Embankment and foundation stability and seepage analyses of the earthen embankments in accordance
with USACE EM‐1110‐2‐1913, Design and Construction of Levees;
Stability and seepage analyses of the flood walls in accordance with the USACE Phase II Interim Guidance
for Evaluating Existing I‐Walls, dated October 25, 2006; and
Settlement evaluations to assess the potential and magnitude of loss of freeboard.
Several of the system data gaps that have been identified by the USACE are consistent with the data
requirements (shown above) for the accreditation process. Data gap analyses to be completed for the USACE
should also include all scope items that are needed for FEMA accreditation.
2.4.5 Northampton Flood Control Pumping Station – Hockanum Road – Inspection
The Northampton Flood Control Pumping Station was constructed in 1940 by the USACE as part of the
Northampton Flood Control System in conjunction with the Connecticut River Flood Control Project. It is located
on the Old Mill River approximately 1.4 miles upstream of the
confluence with the Connecticut River, and provides flood
protection for a major portion of the City, including the downtown
business district. Stormwater flow during normal river level is by
gravity. The primary function of the pumping station is to pump
stormwater through the levee when the Connecticut River is in
flood stage. The pumping station is currently manually operated
by DPW employees.
The pumping station is a brick building constructed between two
earth embankments of the levee with interconnecting concrete
counterfort flood walls. It houses four pumps: three 48‐inch
propeller pumps that can pump a total of 150,000 gpm, two
powered by gasoline engines and one powered by diesel engine;
and a single 16‐inch Worthington trash pump that is designed to pass up to 6‐inch diameter solids, powered by
an electric motor. When flood stage is reached, stormwater is diverted from the gravity flow chamber to the
pumping chambers using two electrically operated sluice gates. While in operation, the pump inlet chambers
are protected from large debris by two trash racks located upstream of the inlet sluice gate. The pumping
station includes a gasoline fueled emergency standby generator if the main power feeder fails. The standby
generator is sized to provide power for the 16‐inch pump, valve operators and lighting.
Photo 2.6 Northampton Flood Control Pumping Station
Section 2 Existing Conditions
2‐24
106678‐80349‐03‐11
CDM accompanied Northampton staff on field inspections of the Northampton Flood Control and Stormwater
Pumping Stations.
Interviews with DPW staff and inspection of the Northampton Flood Control Pumping Station revealed that
there are only minor imminent mechanical problems with the pumping equipment and the drives. The major
issue at the station is that it is manually operated, and it must be monitored continuously when operating or
when operation may be expected to commence. Other deficiencies noted during the inspection include:
1. Influent Screen Area: Access for a portable mechanical device to reach and clean the upstream face of the
influent screens is poor because of the configuration of the screen structure. In addition, raising and
lowering of the existing screens is a manual operation, and is potentially dangerous to City workers. The
screens are left lowered in place throughout times of the year when the station may need to operate. This
causes debris to be collected, even when pumps are not operating.
2. Sluice Gates: The City workers are concerned that the operators for the main sluice gates may not work
reliably in electric mode. If they fail to work, opening the gates manually will be a lengthy operation for City
workers.
3. Standby Generator: Because of safety concerns, gasoline‐powered standby generators are no longer used;
they are typically fueled by diesel, natural gas, or propane. In addition, current codes no longer allow
standby generators to be cooled by municipal water supplies because of reliability concerns. The City
currently uses its water supply to cool the generator, which could fail during a flooding situation.
In general, the pumping station is over 70 years old and at this advanced age, the City runs the increased risk
that the pumping station will not operate reliably under flood conditions. In addition, because of the age of the
pumping station, the availability of repair parts is questionable. The City runs the risk of having significant
downtime at the pumping station, while the City searches for, or possibly fabricates, repair parts. Thus, CDM
recommends the City take a proactive approach to improve the reliability of the pumping station by
implementing the recommended improvements described in the following section.
2.4.5.1 Recommended Improvements
If the City opts to keep the existing facility and only repair/replace the deficiencies identified during the
inspection to potentially save money, CDM recommends the following activities in order of importance.
1. Replace both of the electric motor‐operated sluice gate operators because of the concerns over their
current reliability.
2. Rework the influent screen area.
a. The existing screens with their hazardous manual operators should be removed.
b. Install a mechanically‐cleaned screen because the screens need to be cleaned frequently during station
operation. The screens should be coarse type, with 3‐to 4‐inch clear openings. Screen width is 8 feet.
c. For reliability, a bypass manually cleaned screen should be provided in case the mechanically cleaned
screen experiences operational problems.
d. The screen area should also be made easily accessible to catch basin cleaning type equipment so that
objects too large for the mechanically cleaned screen can be removed.
Section 2 Existing Conditions
2‐25
106678‐80349‐03‐11
e. Modification of the influent screen structure will require demolition of the existing screen structure and
construction of a new structure.
3. Replace the existing gasoline‐engine‐driven standby generator. The generator should be replaced with a
radiator‐cooled diesel‐engine‐driven generator capable of running all building systems (lights, heat, gate
operators, sump pump, etc.) plus the electric motor‐driven pump. We do not recommend a natural gas
engine because the engine needs to be physically larger than a diesel engine in order to get the required
horsepower, and is therefore more expensive. Also, in a flooding situation, the supply of natural gas may be
cut off, leaving the station inoperable.
4. Replace the existing electric‐motor‐driven pump. Because of its advanced age, it may not operate reliably in
the future. Thus, it should be replaced with a new pump that has the same capacity of the existing 50
horsepower pump.
5. Because of their age, replace the three existing stormwater pumps, including their engine drives and right‐
angle gear drives in‐ kind, with three new diesel‐engine‐driven pumps. Similar to the generator, the
replacement engine drives must be radiator cooled with unit mounted radiators. This will require major
revisions to the ventilation and air handling systems in the building to obtain adequate ventilation air and
exhaust the heated air outdoors.
6. In conjunction with replacement of the pumps, the existing pump discharge piping, isolation valves, and
outlet flap valves should be replaced because the pipe will need to be reworked to align with replacement
pumps.
7. Existing electrical, lighting, and ventilation systems should be replaced because of the age of these systems.
8. Upgrade the pumping station building to meet current accessibility and egress requirements. Implementing
the recommendations listed above, such as replacement of the ventilation system, will result in
modifications to the physical structure of the building. These changes to the building will trigger compliance
with current building codes for accessibility and egress.
9. Assuming the preceding recommendations are implemented, new monitoring and automated control
systems should be provided to allow the station to operate automatically with minimal supervision to
reduce personnel costs for pumping station operation. This task will require replacement or upgrade of
existing level monitors on the Connecticut River side of the dike, as well as in the influent channel and pump
wells. A Supervisory Control and Data Acquisition (SCADA) type panel should be provided to coordinate
monitoring with control of the pumps.
Alternatively, based on a field evaluation of the Northampton Flood Control Pumping Station, CDM recommends
replacing the existing pumping station with an entirely new facility. The new facility will replace the engine‐
driven pumps and standby generator in‐kind with three new diesel engines, right angle gear drives, stormwater
pumps, and one standby generator. Because the pump engines are the only source of power for operation of the
pumps, they will be evaluated as continuous duty application, requiring a high degree of emissions control (EPA
Tier 4). The design of the new facility will need to take into account the potential for increased flows to the
pumping station due to the recommended upgrades in the upstream drainage systems. The cost estimate
provided in this report assumes a new facility.
2.4.6 West Street Stormwater Pumping Station– Inspection
The West Street Stormwater Pumping Station is located on the Mill River, adjacent to the West Street river
crossing. Similar to the Northampton Flood Control Pumping Station, its primary function is to divert
Section 2 Existing Conditions
2‐26
106678‐80349‐03‐11
Photo 2.7 West Street Pumping Station
stormwater that collects behind the levee and flood wall through the levee when the Mill River is in flood stage.
The manually‐operated West Street Stormwater Pumping Station serves a 14.6‐acre area inside the levee that is
a low point for collection of stormwater runoff.
The pumping station is an on‐grade structure, with exterior dimensions of approximately 12 by 9 feet. The
building houses one engine‐driven self‐priming type pump. The pumping station was built after the flood of
1955 in 1957.
The pump is connected to the West Street stormwater collection system by a 6‐inch steel suction pipe that rises
just outside the building from a manhole. The self‐priming pump is a 6‐inch Rex Chainbelt. No rating data plate
could be identified, but its capacity is likely to be approximately 800 to 1,000 gpm. The pump is driven by a
spark‐ignited engine power unit (assembled by Hanlon Waters) fueled by propane. The propane fuel tank is a
300‐lb propane bottle located outside the station.
CDM accompanied Northampton staff on a field inspection of the West Street pumping station.
No obvious deficiencies at the West Street Pumping Station were
observed during the inspection. However, the future reliability of
the pumping station is questionable because it is rarely used.
Near the pumping station, two stormwater collection system
outlets were observed. They discharge into the river, one higher
than the other, and both were built into the retaining wall along
the river bank. Both have cast iron flap valves, which appear to
open freely. The lower of the two flap valves appears to be new,
and uses a resilient seat. However, the seat appears to have
swollen to the point that the flap cannot close onto its seat. The flap
cannot be forced manually to full closure, resulting in flooding of the
stormwater collection system tributary to this flap gate when the river elevation is high. Thus, the leakage may
fully negate the capacity of the pumping station.
Similar to the Northampton Flood Control Pumping Station, this pumping station is manually operated. When
the station must be operated, an operator must be on‐site at all times. Because the pumping station is not
automated, determination of the need to operate the pumping station is dependent upon visual observations of
flooding in the storm system on West Street.
2.4.6.1 Recommended Improvements
The West Street Stormwater Pumping Station does not have the capacity to discharge adequate flow to prevent
flooding of the West Street drainage area. Assuming that utility power is not available during flooding
conditions, a pump at this location should be engine‐driven. Instead of installing a permanent pump at this
location, CDM recommends the City purchase a portable diesel‐engine driven pump with capacity of
approximately 6,000 gpm, which can be brought to the site and set up temporarily for flood control.
2.5 River Erosion 2.5.1 River Road – Mill River
The proposed River Road Retaining Wall/Floodwall improvements are located in the Leeds Village section of
Northampton (see Figure 2.1 and Photo 1.5). Flows from the Mill River have scoured and undercut significant
sections of the wall, and surface runoff has compromised the integrity of the upper portions of the wall. In
Section 2 Existing Conditions
2‐27
106678‐80349‐03‐11
Photo 2.8 Federal Street Flood Wall
Photo 2.9 Roberts Meadow Brook Channel
addition, the Williamsburg sanitary sewer interceptor is located within River Road and is in danger of collapsing
due to river erosion. The City is proposing to remove the existing stone masonry wall and replace it with a cast‐
in‐place concrete retaining wall that will protect the road and sewer from the 100‐year flood event.
2.5.2 Federal Street Flood Wall
The Federal Street retaining wall improvements are proposed along
the Mill River in the vicinity of Vernon Street and Ward Avenue (see
Figure 2.1 and Photo 2.8). The purpose of this project is to protect a
30‐inch sewer interceptor. Erosion is occurring along the sharp bank
angle, which is leading to the exposure of the interceptor.
2.5.3 Roberts Meadow Brook Channel
The Roberts Meadow Brook channel is located between the Lower
Roberts Meadow Reservoir Dam and Reservoir Road in Leeds (see Figure 2.1
and Photo 2.9). The channel is comprised primarily of dry masonry sidewalls
and a naturalized boulder and cobble bottom. High flow events
have resulted in significant erosion of the channel sidewalls, which is
threatening the dwellings and driveways of adjacent private
properties. The City has proposed to extend the floodwall upstream
from the Reservoir Road bridge to the critical area in the channel.
The new floodwall would be a cast‐in‐place concrete retaining wall
with sufficient height to protect adjacent properties from the 100‐
year flood event.
2.6 Current Operational Cost and Funding Levels 2.6.1 Regulatory Compliance
The City is currently complying with all requirements of the 2003 NPDES Phase II permit. The City maintains a
public education and participation program, which includes educational brochures, stormwater education in the
high school, availability of rain barrels, storm drain labeling, outfall monitoring by volunteer groups, household
hazardous waste collection days, and community cleanups. The storm drain maps, with outfalls, have been put
into a Geographic Information System (GIS) and are continuously updated. In 2004, the City approved both the
Illicit Connections and Discharges to the Municipal Storm Drain System Ordinance and the Erosion and Sediment
Control and Post‐Construction Stormwater Management Ordinance. These ordinances are currently enforced.
The City’s street sweeping program sweeps all wards once per year and all streets in the downtown business
district every week from mid‐April to June. The City’s 3,750 catch basins are cleaned once per year, generating
20 tons of debris. In total, the City has spent in excess of $l00,000 annually on implementing the requirements
of this permit.
2.6.2 Stormwater Drainage Operations Staffing
Operation and maintenance activities associated with stormwater drainage operations fall mainly under the
Streets Division and the Sewer/Drain Division. Currently, funds to pay the compensation for sewer and drain
staff are allocated 2/3 from the sewer Enterprise Fund and 1/3 from the General Fund. Compensation for
Section 2 Existing Conditions
2‐28
106678‐80349‐03‐11
overtime is split 50 percent between the enterprise and General Funds. Storm drain materials and equipment‐
related costs are funded through the General Fund.
Generally, the current staffing is as follows:
Streets Division: Three staff spend about half‐time on street sweeping operations.
Sewer/Drain Division: Nine staff provide maintenance activities on the City sewer and drain systems, including
television inspections of drains, cleaning catch basins with a clamshell or vactor truck and infrastructure repairs.
Vehicle Maintenance: One vehicle maintenance staff person is assigned to vehicle maintenance on sweepers
and drain‐related equipment.
Regulatory Compliance: Currently, one part‐time planner is mainly responsible for compliance with the NPDES
Phase II permit. He is assisted by the GIS Coordinator, when compliance requires GIS mapping. Other
engineering and scientist staff may provide technical support as needed. The part‐time planner is funded
through the General Fund. Other technical staff are funded through various Enterprise Funds and the General
Fund.
2.6.3 Flood Control Operations Staffing
Flood control activities are paid for through the General Fund. Labor associated with flood control activities is
paid for through the Sewer Enterprise Fund for straight time and the General Fund for overtime. Staffing for
flood control activities are assigned to the Wastewater Treatment Division. Typically, the staff includes two to
three flood control technicians plus one supervisor. During flooding situations, staff from other departments
participate in flood control activities as needed, such as erecting the West Street flood wall.
3‐1
106678‐80349‐03‐11
Section 3 ‐ Capital Improvements Plan and Operational Budget Requirements
3.1 Introduction This section summarizes the recommended drainage system and flood control improvements plan,
including construction phasing, additional television inspection needs for final design, cost estimates
and schedules. It also includes the following proposed river erosion control projects: River Road
floodwall improvements, Roberts Meadow Brook channel improvements, and Federal Street
retaining wall improvements.
The recommended drainage system improvements have been phased as follows:
Phase 1 and 2 projects – needed to address high priority flooding problems or other issues,
such as pipe collapses; and
Phase 3 and 4 projects – are in areas with less flooding problems, designed to provide capacity
to control 10‐year 24‐hour storm peak rates of runoff.
3.2 Summary of Recommended Plan Figures 3.1 through 3.3 illustrate the recommended plans for each of the project areas. These maps
also provide locations of City‐owned property where there are opportunities for the City to install
stormwater Best Management Practices (BMPs)/green design facilities to reduce stormwater runoff
to drainage systems, improve the water quality of receiving waters and comply with the upcoming
new Environmental Protection Agency (EPA) Municipal Separate Storm System (MS4) permit.
3.2.1 Street Improvement Projects
The DPW maintains a conditional assessment database of all city streets pavement. This pavement
condition database is updated yearly. The purpose of the database is to determine the priority listing
for street work ranging from crack sealing, to asphalt mill and overlay, to full depth reconstruction.
Funding for roadway repair projects is primarily provided by the state under the Chapter 90 program.
Chapter 90 funding provides for the cost of asphalt resurfacing. The construction funding for new
sewer lines that may be needed as part of a street reconstruction project is provided through the
City’s Sewer Enterprise Fund. If new water lines are required, the funding is provided by the Water
Enterprise Fund. Historically, the City has funded drainage improvements through the General Fund,
as determined by the City Council through the capital improvements process. Because of the lack of
available monies in the General Fund, funding for storm drain construction has been extremely
limited. The DPW reports that a $62,000 budget line item for storm drain construction was removed
from the budget in 2010 as part of a DPW budget cut. If a street is identified as a high priority and in
need of reconstruction, and funding is not available for construction of a new drainage system, that
street is removed from the priority paving list. A good example of this funding dilemma is Milton
Street, a street that is desperately in need of reconstruction, but is on hold because of the lack of
funding to install a new drainage system.
Alignment #2New 48" RCP Drain
Alignment #1New 48" RCP Drain
CONNECTICUT RIVER
MILL RIVER
CONNECTICUT RIVERManage StormwaterOn-Site with BMPs
Manage StormwaterOn-Site with BMPs
Northampton Flood ControlPumping Station
West StreetStormwater
Pumping Station
Phase 2 Northampton FloodControl Pumping Station
Phase 1 and 2Levee Improvements
Phase 1 and 2Levee Improvements
Phase 2 Portable StormwaterPumping Station
66"
Nelson/Nygaard Design Charrette Area
Approximate Wetland Boundary Estimated by City
HISTORIC M
ILL RIVE
R
I
Fairgrounds
6’’
12’’
36’’
15’’
12’’
12’’
12’’
6’’
8’’
10’’
36’’
10’’
12’’
8’’
12’’
12’’
12’’
6’’
18’’
12’’
12’’
10’’
14’’
12’’
12’’
12’’
36’’
12’’
24’’
12’’
12’’
12’’
12’’
12’’
12’’
12’’
8’’
12’’
12’’
12’’
12’’
30’’
21’’
12’’
12’’
12’’
10’’
12’’
18’’
12’’
12’’
12’’
12’’
12’’
24’’
12’’
18’’
24’’
12’’
12’’
10’’
12’’
10’’
18’’12’’
15’’
18’’
12’’
10’’
6’’
12’’
6’’
21’’
48’’
15’’
15’’
12’’
15’’
8’’
6’’
36’’
12’’
10’’
12’’
12’’
36’’
12’’
10’’
21’’
6’’
18’’
12’’
54’’
54’’
24’’
18’’
8’’
10’’
14’’
12’’
18’’
15’’
12’’
18’’
24’’
15’’
24’’
36’’
12’’
6’’
12’’
24’’
12’’
30’’8’’
12’’
12’’
18’’
12’’
8’’
36’’
8’’
6’’
18’’
15’’
12’’
18’’
24’’
8’’
36’’
15’’
48’’
15’’
12’’
10’’
16’’
60’’
18’’
18’’
8’’
18’’
12’’
12’’
12’’
15’’
12’’
18’’
12’’
12’’
6’’
24’’
36’’
21’’
42’’
12’’
30’’
18’’
18’’
64’’
12’’
8’’
18’’
18’’
12’’
8’’
12’’
15’’
10’’
18’’
15’’
8’’
15’’
12’’
10’’
18’’
24’’
18’’
12’’
8’’
8’’
18’’
15’’
8’’
12’’
15’’
12’’
21’’
18’’
18’’
18’’
15’’
12’’
21’’
12’’
12’’
30’’
12’’
44’’
8’’
10’’
15’’
12’’
36’’
18’’
10’’
12’’
12’’
60’’10’’
10’’
12’’
12’’
15’’
15’’
10’’
10’’
18’’
15’’
12’’
24’’
8’’
12’’
25’’
36’’
10’’
10’’
8’’
54’’
15’’
66’’
10’’
12’’
12’’
15’’
48’’
6’’
12’’
12’’
54’’
12’’
36’’
12’’
12’’
10’’
10’’
12’’
15’’
15’’
12’’
12’’
10’’
18’’
16’’
12’’
8’’
12’’
12’’
15’’
12’’
10’’
15’’
15’’
12’’
15’’
12’’
8’’
18’’
12’’
10’’
18’’
24’’
12’’
18’’
6’’
10’’
15’’
24’’
24’’
12’’
18’’
30’’
8’’
12’’
10’’
15’’
10’’
15’’
12’’
18’’
12’’
21’’
21’’
10’’
12’’
12’’
24’’
18’’
15’’
15’’
18’’
12’’
10’’
24’’
8’’
12’’
12’’
12’’
12’’
18’’
24’’
36’’
15’’
10’’
12’’
30’’
12’’
15’’
12’’
12’’
24’’12’’
24’’
12’’
8’’
12’’
82’’
12’’
6’’
15’’
10’’
15’’18
’’
48’’
30’’
6’’
15’’
16’’
18’’
12’’
10’’
12’’
12’’
24’’
48’’
36’’
12’’
12’’
12’’
12’’
15’’
66’’
18’’
15’’
12’’
15’’
36’’
15’’
12’’
15’’
12’’
12’’
10’’
24’’
60’’
15’’
15’’
12’’
24’’
6’’
44’’
72’’
24’’
12’’
118
127
118
246
196
177
127
127
157
147
137
147
118
255
137
127
137
118
177
177
118
137
118
118
157
137
127
147
137
147
147
167
137
167
157
118
147
118
127
127
187
137
147
147
118
137
118
118
177
108
147
137
187
127
127
177
118
137
127
108
137
127
137
147
147
118
108
118
275
118
137
147
147
137
118
177
157
127
167
118
127
187
127
137
137
147
127
157
167
118
108
147
127
147
147
127
127
157
137
118
118
118
127
147
147
127
118
157
177
127
108
108
118
196
157
118
127
147
127
118
147
157
118
147
118
137
177
167
265
177
147
127
108
118
167
147
236
118
226
118
216
137
157
167
137
206
137
157
118
118
127
127
137
118
118
HOLYOKE STREET
BRIDG
E STREET
MAIN
STREET
SOUTH STREET
CEMETERY ROAD
HA
MP
TO
NG
AR
DE
ND
RIV
E
CENTERSTREET
ELMSTREET
WE
ST
ST
RE
ET
FRUITSTREET
STA
TE
ST
RE
ET
HOCKANUM ROAD
CONZ STREET
GREEN
STREET
SCHOOLSTREET
PARSONS
STREET
SO
UT
H
ST
RE
ET
NORTH STREET
UNION
STREET
NE
W
SO
UT
H
ST
RE
ET
PR
OS
PE
CT
ST
RE
ET
DAMON ROAD
KIN
GS
TR
EE
T
BARRETTSTREET
FAIRGROUNDSROAD
BR
IDG
ES
TR
EE
TP
OM
ER
OY
TER
RA
CE
BAN
CR
OFT
RO
AD
PRO
SPE
CT S
TRE
ET
ST
AT
ES
TR
EE
T
MO
UN
T T
OM
RO
AD
CO
LLEG
E LA
NE
WILLIA
MS
ST
RE
ET
INDUSTRIAL DRIVE
HE
NS
HA
W A
VE
NU
E
CONZSTREET
TRUMBULL ROAD
BRID
GE
STR
EET
RO
UN
D H
ILL
RO
AD
WARFIELD
PLACE
BELMO
NT
AVENUE
MARSHALLSTREET
ST
AT
E S
TR
EE
T
RA
ILRO
AD
AVE
NU
E
BEDFORD
TERRACE
HAW
LEY
STREET
WO
OD
MO
NT R
OA
D
BARRETTSTREET
FINN STREETFINN
STREET
MUNROESTREET
MONTVIEW AVENUE
NORTH KING
STREET
BRIGHT STREET
HUBBARDAVENUE
CR
ES
CE
NT
ST
RE
ET
KINGSLE
Y AVENUE
RUSSELL STREET
FO
RT
ST
RE
ET
STA
TE
ST
RE
ET
LANE PLANT ROAD
HAM
PTO
N M
AN
OR
DR
IVE
CROSBY STREET
KIN
G
ST
RE
ET
ELM STREET
SHERMANAVENUE
INDUSTRIAL
DRIVEROTARY
WR
IGH
TAV
ENU
E
CR
AF
TS
AV
EN
UE
BAY ROAD
HILLSIDEROAD
CR
OS
SPA
TH
RO
AD
VALL
EYST
REE
T
HAM
PTO
NAV
ENU
E
HAYES
AVENUE
BA
Y R
OA
D
WOODBINE
AVENUE
HIGHLAND AVENUE
CHURCHSTREET
ED
WA
RD
SS
QU
AR
E
PH
EA
SA
NT
HIL
L D
RIV
E
MYRTLE
STREET
SMITH COLLEGE DRIVE
FAIR STREET
PH
EA
SA
NT
HIL
L D
RIV
E
CE
ME
TE
RY
RO
AD
GRAVES
AVENUE
NO
RTH
KIN
G
ST
RE
ET
HENRY STR
EET
IND
USTR
IAL
DR
IVE
SUMMER
STREET WALNUT
STREET
DE
NIS
E C
OU
RT
BATES
STRE
ET
ALD
RIC
H
ST
RE
ET
REVELL AVENUE
DYKE ROAD
CRESCENT STREET
BUTLER
PLACE
NORTHERN
AVENUE
HAMPSHIRE HEIGHTS
KIN
G
ST
RE
ET
BAR
RET
TPL
ACE
KIN
G
ST
RE
ET
RIVER
BANK R
OAD
WOODMONT
ROAD
LINDEN
STREET
MUNROESTREET
KIN
GS
HIG
HW
AY
MAN
HAN
STREET
SERVICE CENTER
CLARK SCHOOL DRIVE
GRANT AVENUE
COLUMBUS
AVENUE
FO
RT
HILL T
ER
RA
CE
PERKINS
AVENUE
HE
BE
RT
AVE
NU
E
BAY ROAD
BRIDGE ROAD
PHILLIPS
PLACE
FAIRVIEWAVENUE
STODDARD
STREET
OLD FERRY ROAD
OLD
FE
RR
Y R
OA
D
CLARK
AVENUE
COOLIDGE AVENUE
GOTHICSTREET
LINCOLN
AVENUE
DAY AVENUE
CHERRY
STREET
ELIZABETH STREET
CR
OS
S PAT
H R
OA
D
OLIVE STREET
HUNTS ROAD
ORCHARD
STREET
FAC
TO
RY
ST
RE
ET
BAY ROAD
KIN
GS
HIG
HW
AY
LYMAN ROAD
CR
OS
SPA
TH
RO
AD
PIN
E B
RO
OK
CU
RV
E
BRADFORD STREET
FAIR STREET
NOOK ROAD
KIN
GS
HIG
HW
AY
STRONG
S RO
AD
SO
UT
H B
RA
NC
H R
OA
D
CR
OS
S P
AT
H
OLD FERRY ROAD
HUNTS ROAD
NOOK ROAD
FAIR
ST
RE
ET
CR
OS
S P
AT
H R
OA
D
AQUAVITAE ROAD
WA
LNU
T TR
EE
S PATH
VEN
TUR
ER
S F
IELD
RO
AD
BRADFO
RD BR
OOK
KING
ST BR
OOK
BRADFO
RD
BROO
K
KIN
G ST
BROO
K
KING
ST BR
OO
K
KING
ST BRO
OK
BRADFORD BROOK
Viaduct
Brook
Barr
ett St
Broo
k
BRADFORD
BROOK
Barrett St Brook
91
91
12’’
66’’
54’’
24’’
48’’
12’’
48’’
12’’
42’’
30’’
12’’
12’’
36’’
42’’
48’’
18’’
12’’
24’’
18’’
78’’
24’’
12’’
72’’
78’’
36’’
12’’
24’’
12’’
12’’
12’’
36’’
18’’
60’’
36’’
24’’
36’’
12’’
18’’
’’
12’’
18’’
48’’
18’’
30’’
12’’
5
5
10
10
5
5
9
9
9
9
5
66
5
5
\\camgissvr1\Projects\M_Billings\Northampton\mxd\KingSt_WilliamSt_Recommendations.mxd JD 11/21/2011
91
91
City of NorthamptonStormwater and Flood Control System
Assessment and Utility PlanFigure 3.1
King Street/Market Street and Bridge Street/Meadows Areas Recommended Plan
Proposed DrainageSystem Improvements
( )Existing Pipe Diameter
Proposed Pipe Diameter24"10"
9’ x 5’ Box
Legend
Drain Manhole
Catch Basin/Inlet
Stormwater Outfall
Stormwater Pumping Station
Contour
Drain Lateral
Culvert
Drainage Channel
Detention/Retention Basin
Drain Pipe
Parcel Boundary
Building
DEP Wetlands
Wetlands (MassGIS)
City of Northampton Property
LeveeDrainage Area Boundary
Area Prone to Flooding
Manage Stormwater On-Sitewith BMPs
400 0 400 800200
Feet
Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)
Phase 2Phase 3Phase 4
Phase 1
New 48" RCP Drain
New 72" RCP Drain
MILL RIVER
Manage StormwaterOn-Site with BMPs
New 7’x4’ Box Drain
NU
TTIN
G A
VE
NU
E
147
Federal Street Retaining Wall Improvements
Weir Structure
10’’
8’’
15’’
10’’
12’’
12’’
12’’
24’’
8’’
12’’
12’’
12’’
10’’
14’’
24’’
12’’
24’’
10’’
8’’
6’’
8’’
12’’
10’’
10’’
6’’
8’’
24’’
8’’
18’’
18’’
12’’
18’’
10’’
12’’
8’’
6’’
12’’
10’’
12’’
15’’
12’’
18’’
48’’
24’’
12’’
10’’
8’’
36’’
12’’
10’’
10’’
18’’
12’’
12’’
15’’
12’’
12’’
12’’
10’’
30’’
8’’
36’’
15’’
24’’
12’’
15’’
10’’
8’’
12’’
8’’
18’’
10’’
36’’
15’’
12’’
10’’
8’’
12’’
10’’
18’’
12’’
15’’
12’’
10’’
12’’
4’’
15’’
15’’
18’’
8’’
10’’
10’’
12’’
15’’
10’’
8’’
12’’
12’’
12’’
60’’
20’’
12’’
18’’
10’’
12’’
10’’
18’’
10’’
12’’
8’’
8’’
8’’
12’’
12’’
10’’
18’’
12’’
12’’
18’’
8’’
18’’
12’’
8’’
10’’
18’’
12’’
15’’
15’’
15’’
15’’
30’’
21’’
15’’
8’’
12’’
10’’
12’’
10’’
8’’
18’’
10’’
24’’
18’’
15’’
12’’
12’’
12’’
15’’
12’’
12’’
12’’
8’’
12’’
12’’
12’’
12’’
8’’
18’’
15’’
12’’
12’’
12’’
8’’
12’’
21’’
12’’
12’’
24’’
8’’
30’’
12’’
42’’
12’’
12’’
48’’
10’’
15’’
8’’
12’’
12’’
12’’
24’’
12’’
12’’
15’’
18’’
12’’
12’’
12’’
15’’
18’’
10’’
12’’
12’’
10’’
8’’
10’’
12’’
8’’
12’’
10’’
12’’
8’’
12’’
8’’
8’’
15’’
10’’
10’’
15’’
12’’
8’’
15’’
24’’
27’’
12’’
8’’
12’’
10’’
12’’
36’’
15’’
21’’
24’’
15’’
10’’
15’’
18’’
12’’
10’’
24’’
18’’
12’’
8’’
10’’
12’’
10’’
15’’
15’’
30’’
36’’
12’’
8’’
15’’
10’’
15’’
12’’
12’’
12’’
15’’
15’’
21’’
12’’
12’’
10’’
12’’
21’’
18’’
12’’
10’’
12’’
12’’
8’’
15’’
12’’
15’’
8’’
12’’
12’’
10’’
12’’
12’’
12’’
33’’
12’’
12’’
18’’
12’’
15’’
236
17
157
285
216
275275
206
255
147
314
265
246
196
206
255
275
285
206
285
295
285
246
206
246
285
265
187
206
187
275
187
137
255
236
196
246
305
324
177
265
226
147
147
236
295
157
255
196
187
196
275
167
246
246
206
246
167
236
167
236
216
314
206
177
137
157
187
255
285
255
285
196
236
177
275
305
196
236
275
216
187
147
265
177
324
324
206
187
157
226
295
137
206
236
167
285
246
334
147
167
157
265
187
255
275
167
255
236
137
275
157
177
265
324
206
167
255
206
314
255
275
275
275
206
246
255
187
196
246
187
295
246
314
206
265
147
236
206
157
187
177
285
196
246
265
216
167
157
226
216
265
255
226
216
236
226
305
206
216
295
WO
OD
LAW
N
AVEN
UE
WO
OD
LAW
N
AV
EN
UE
BANCROFT ROAD
PROSPECT STREET
BRIDGE ROAD
BRIDGE ROAD
BRIDGE ROAD
BARDWELL STREET
GA
RF
IEL
D S
TR
EE
T
FE
DE
RA
L S
TRE
ET
FED
ER
AL
STR
EE
T
FEDERAL STREET
ST
RA
W
AV
EN
UE
LOCUST STREET
LOCUST STREET
NO
RT
H E
LM
ST
RE
ET
NO
RT
H M
AP
LE
ST
RE
ET
ELM STREET
ELM STREET
ELM STREET
VER
NO
N ST
REET
SH
AL
LO
W B
RO
OK
DR
I VE
HATFIELD
STREET
WARD AVENUE
WASHINGTON
PLACE
ST
ILS
ON
AV
EN
UE
WARNER STREET
JAC
KS
ON
ST
RE
ET
NO
RT
H E
LM S
TR
EE
T
CH
ES
TN
UT
ST
RE
ET
CH
ES
TN
UT
ST
RE
ET
HATFIELD STREET
HA
TF
IEL
D S
TR
EE
T
CH
ILD
S P
AR
K R
OA
D A
FR
AN
KLI
N
ST
RE
ET
FR
AN
KLI
N
ST
RE
ET
LOCUST
STREET PR
OS
PE
CT
AV
EN
UE
PR
OS
PE
CT
AVE
NU
E
NONOTUCK STREET
MEADOWBROOK DRIVE
ME
AD
OW
BR
OO
K D
RIV
E
PINE STREET
PINE
STREET
KIMBALL STREET
DRYADS GREEN
SANDERSON AVENUE
BRIDGE ROAD
FR
AN
CIS
ST
RE
ET
DANA STREET
GLEASON ROAD
MAIN STREET FLORENCE
CO
OK
E
AV
EN
UE
PLYMOUTH STREET
BR
AT
TO
N C
OU
RT
PARADISE
ROAD
MAPLE
STREET
HA
WT
HO
RN
LANE
KIN
G A
VE
NU
E
CLO
VE
RD
AL
E S
TR
EE
T
LAD
D AVE
NU
E
WOOD AVENUE
FIFTH AVENUE
BEACON STREET
LAUR
EL RIDGE DRIVE
HIGH STREET
SU
N H
ILL
DR
IVE
MA
RY
JA
NE
LA
NE
BLACKBERRY LANE
KE
YE
S S
TR
EE
TCAROLYN STREET
WIL
DE
R P
LAC
E
ALLISON STREET
BARRETT STREET
VERONA STREET
PLY
MO
UT
H A
VE
NU
E
RIDGEWOOD TERRACE
FORBES A
VENUE
SU
MN
ER
AV
EN
UE
ORMOND DRIVE
TAYLOR STREET
PROSPECT HEIGHTS
JEWETT STREET
HAROLD STREET
RIVERSIDE DRIVE
RIV
ER
SID
E D
RIV
E
RIVERSIDE DRIVE
RIVERSID
E DRIV
E
HIN
CK
LEY
ST
RE
ET
NE
W S
TR
EE
T
POWELL STREET
SHEFFIELD LANE
KENSINGTON AVENUE
MANDELLE ROAD
HO
WE
S S
TR
EE
T
AD
AR
E P
LAC
E
BA
KE
R H
ILL
RO
AD
MA
SS
AS
OIT
STR
EE
T
MA
SS
AS
OIT
S
TR
EE
T
JAMES AVENUE
MU
RP
HY
TE
RR
AC
E
MIL
TON
ST
RE
ET
CL
EM
EN
T S
TR
EE
T
SO
UTH
MA
IN S
TRE
ET
GR
AN
DV
IEW
STR
EE
T
ARLI
NG
TON
ST
REE
T
WILLOW STREET
WINSLOW AVENUE
TERRACE LANE
LAN
DY
AV
EN
UE
DENNISTON PLACE
BE
RK
SH
IRE
TE
RR
AC
E
NO
RFO
LK A
VE
NU
E
RO
E A
VE
NU
E
NO
RW
OO
D AV
EN
UE
NU
TT
ING
AV
EN
UE
MANN TERRACE
WASHIN
GTON A
VENUE
MIDDLE STREET
HARRISO
N AVENUE
MA
PLE
WO
OD
TE
RR
AC
E
MAYNARD R
OAD
BOTTO
M RO
AD
FO
X F
AR
MS
RO
AD
HIL
LCR
ES
T
DR
IVE
PINES
ED
GE
DR
IVE
EMILY LANE
KEARNEY
FIE
LD R
OA
D
HO
LLY
WO
OD
HE
IGH
TS
LIBE
RT
Y S
TR
EE
T
TR
INIT
Y R
OW
ST
ER
LIN
G R
OA
D
FAIR
FIE
LD
AV
EN
UE
CLA
IRE
AV
EN
UE
LEX
ING
TON
AVE
NU
E
MO
UN
TAIN
STR
EET
HO
SP
ITA
L R
OA
D
FLO
RE
NC
E R
OA
D
9
5
9
M IL L R I V E R
M I L L R I V E R
WIL
LO
W L
AK
E
N S H I C
E P
ON
D
Broughtons
Brook
Elm St.
Brook
SANDY HI LL
B ROO K
Broughtons Brook
KING ST BROOK
Broughtons
Brook
Bro
ugh
tons
Brook
Broughtons
Brook
Broughtons Brook
Bro
u g ht o
ns
BrookBr
ough
tons
Broo
k
Broughtons Brook
Elm St. Brook
P IN E BROO K
Broughtons
Brook
Brou ghtons Brook
PINE BROOK
18’’24’’
12’’
36’’
24’’
12’’
24’’
36’’
24’’
12’’
24’’
12’’
12’’
12’’
12’’
30’’
18’’
12’’
12’’
18’’
36’’
12’’
12’’
18’’
12’’
12’’
18’’
48’’
12’’
12’’
24’’
18’’
12’’
18’’
30’’
36’’
12’’
\\camgissvr1\Projects\M_Billings\Northampton\mxd\ElmSt_Recommendations.mxd SCC July 2011
91
91
Legend
350 0 350 700175
Feet
Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)
City of NorthamptonStormwater and Flood Control System
Assessment and Utility Plan
Figure 3.2Elm Street Brook/Florence Area
Recommended Plan
Proposed DrainageSystem Improvements
Phase I
10"
24"Phase 3 ( )
Existing Pipe Diameter
Proposed Pipe Diameter
Drainage Area Boundary
Area Prone to Flooding
Drain Manhole
Catch Basin/Inlet
Stormwater Outfall
Stormwater Pumping Station
Parcel Boundary
Building
DEP Wetlands
Wetlands (MassGIS)
City of Northampton Property
ContourDrain Pipe
Drain Lateral
Culvert
Drainage Channel
Detention/Retention Basin
New 30" RCP Drain
ChannelImprovements
ChannelImprovements
Flood Storage AreaNew 30" RCP Drain
Plug and AbandonExisting Pipe
12’’
10’’
48’’
12’’
18’’
12’’
12’’
8’’
12’’
12’’
15’’
12’’
12’’
12’’
18’’
18’’
10’’
30’’
12’’
12’’
48’’
12’’
12’’
16’’
60’’
12’’
15’’
10’’
12’’
15’’
18’’
12’’
24’’
12’’
12’’
12’’
10’’
12’’
15’’
12’’
12’’
12’’
15’’
12’’
15’’
18’’
442
383
295
314
285
295
324
423
344
413
364
305
393
462
275
275
393275
285
305
433
295
305
423
295
364
314
334
285
354
285
285
285
413
275
393
295
305
374
452
442
383
433
324
423
275
295
295
305
314
393
403
324
314
334
344
BR
OO
KS
IDE
CIR
CLE
MA
TT
HE
W D
RIV
E
RYA
N R
OA
D
RYAN
RO
AD
ALAMO COURT
OVERLOOK DRIVE
BIRCH HILL ROAD
ACREBROOK
DRIVE
AC
RE
BR
OO
K
DR
IVE
BR
OO
KS
IDE
CIR
CLE
TARA CIRCLE
SUMMERFIELD STREET
CA
HIL
LAN
E T
ER
RA
CE
HOLLY COURT
GREGORY LA
NE
BR
OO
KS
IDE
CIR
CLE
HIC
KOR
Y D
RIV
E
OV
ER
LOO
K D
RIV
E
LONG
VIEW
DRIVE
BRIE
RW
OO
D D
RIV
E
PEN
CA
SAL D
RIV
E
GILR
AIN TE
RR
AC
E
PIONEER KNOLLS
WO
OD
S R
OA
D
FO
RE
ST
GL
EN
DR
IVE
DEERFIELD DRIVE
SPRUCE HILL AVENUE
SP
RU
CE
HIL
L A
VE
NU
E
BE
ATTIE
DR
IVE
GOLDEN DRIVE
GOLDEN DRIVE
AUS
TIN C
IRC
LE
AUSTIN CIRCLE
\\camgissvr1\Projects\M_Billings\Northampton\mxd\RyanRoad_Recommendations.mxd JD 11/21/2011
City of NorthamptonStormwater and Flood Control System
Assessment and Utility Plan
Figure 3.3Austin Circle/Ryan Road
Area Recommended Plan
Legend
91
91
Drainage Area Boundary
Area Prone to Flooding
Drain Manhole
Catch Basin/Inlet
Stormwater Outfall
Flood Storage Area
Proposed DrainageSystem Improvements
Phase 2
Drain Pipe
Drain Lateral
Culvert
Drainage Channel
Detention/Retention Basin
Stormwater Pumping Station
150 0 150 30075
Feet
Basemap: PlanimetricsSources: City of Northampton and MassGISCoordinate System: NAD83 Mass. State PlaneMainland FIPS 2001 (feet)
Contour
Parcel Boundary
Building
DEP Wetlands
Wetlands (MassGIS)
City of Northampton Property
Wetlands (Delineated by City)
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐5
106678‐80349‐03‐11
In the future reestablishing an annual budget amount for new drain system construction would allow the DPW
to better prioritize street reconstruction projects because complete funding would be available for paving and
all street utilities. The annual budget would need to be significantly greater than previous budgets in order to
maintain the city stormwater system. This funding would result in an improvement in the management of city
streets and related utilities.
Based on conversations with the City, an annual budget of $500,000 is suggested for construction of new storm
drains or replacement of old drains as part of street improvement projects. This is comparable to the annual
amount budgeted by the City for water line and sewer line improvements.
3.2.2 Municipal Green Infrastructure/Building Project Retrofit/ Capital Allowance
The proposed NPDES permit contains requirements for “Good House Keeping and Pollution Prevention for
Permittee Owned Operations.” The section of the proposed permit has wide ranging requirements that will
involve one‐time capital expenditures and annual maintenance requirements beyond what is currently done.
These requirements include small and large obligations. The following provides some information about the
capital requirements, while the operational requirements are discussed in Section 3.3:
Parks and Open Space: Where waterfowl may congregate and feeding by the public occurs, the City is required
to install educational signage about the threat posed to receiving waters. Pet waste requirements include
preparation and distribution of educational flyers, signage, provision of pet waste bags, and disposal receptacles.
Buildings and Facilities: An inventory of all floor drains in City‐owned buildings must be prepared and all floor
drain connections that are connected to the drain system must be disconnected and piped to the sewer system.
Given the age of many City buildings, many floor drains may not be properly connected to the sewer. The design
and construction of new connections from floor drains to the sewer system will be required.
Vehicles and Equipment: City vehicles with fluid leaks must be stored indoors or in a contained area until
repaired and all vehicle washing must be discharged to the sewer system. Construction of improvements to
DPW facilities and other city facilities may be needed to meet this requirement.
City property and rights of way – retrofits: The draft permit requires the city to construct BMPs on City property
and within right of ways for City streets. These BMPS are to be designed to reduce the frequency, volume, and
peak intensity of stormwater discharges, as well as to reduce pollutant loadings into the drainage system and
receiving waters. The costs associated with these capital projects could be considerable given that the
construction of detention basins, water quality swales, rain gardens, permeable pavement and other capital
intensive BMPs would be required.
Based on conversations with the City, an annual budget of $200,000 is suggested for green infrastructure and
other retrofit construction. This budget is escalated with time in Table 3.6.
3.2.3 Bridge Street/Meadows Area
The recommended Phase 1 Bridge Street/Meadows area drainage improvements (Figure 3.1) consist of
approximately 5,500 feet of new drainage pipe ranging from 48‐ to 66‐inches in diameter. These improvements
include the 48‐inch diameter drain from the Three County Fairgrounds to the Connecticut River and the 66‐inch
diameter Massachusetts Department of Transportation (MassDOT) drain replacement at Damon Road. On‐site
management of stormwater with BMPs is recommended in the industrial area, instead of increasing pipe sizes in
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐6
106678‐80349‐03‐11
that area. Phase 3 improvements consist of 7,500 feet of new drainage pipe, ranging from 12‐to‐42‐inches in
diameter. The preliminary project cost estimate for these improvements is $11,117,000. See Table 3.1 for a
breakdown of these costs.
3.2.4 Elm Street Brook/Florence Area
The recommended Phase 1 Elm Street Brook area drainage improvements (Figure 3.2) consist of approximately
1,900 feet of new 48‐inch diameter drainage pipe and 1,600 feet of 7‐ by 4‐foot box culvert. The recommended
Phase 3 Elm Street Brook area drainage improvements (Figure 3.2) consist of approximately 15,000 feet of new
drainage pipe ranging from 12‐ to 72‐inches in diameter. The Smith Vocational and Agricultural High School is
located on a City‐owned parcel and on‐site management of stormwater with BMPs is recommended at this
location. The total estimated cost for drainage improvements in this area is $19,364,000. See Table 3.2 for a
breakdown of costs and phasing.
3.2.5 King Street/Market Street Area
The recommended Phases 1 and 2 King Street area drainage improvements (Figure 3.1) consist of approximately
5,400 feet of new drainage pipe ranging from 36‐ to 78‐inches in diameter, and 560 feet of 9‐foot by 5‐foot box
culvert in the Historic Mill River. Drainage pipe improvements include replacement of pipes in the Market Street
Brook system from North Street to Bridge Street, and replacement of pipes in King Street. Television inspections
of the drains in the Market Street Brook system upstream of Main Street should be performed during the final
design of improvements in this area to determine the condition of this system and whether it needs to be
replaced.
The recommended Phases 3 and 4 King Street area drainage improvements (Figure 3.1) consist of approximately
7,200 feet of new drainage pipe ranging from 12‐ to 60‐inches in diameter. On‐site management of stormwater
with BMPs is recommended in the retail area along upper King Street instead of increasing pipe sizes in that
area. These BMPs could be required during the planning board approval process or as part of the City’s
stormwater permit program.
On March 14‐16, 2011 Nelson\Nygaard conducted a three‐day design charrette with the City to address bicycle
and pedestrian access, while maintaining levels of vehicle throughput, for portions of King and Main Streets.
The charrette identified the need to reduce King and Main Streets from a four‐lane cross‐section to a two‐lane
cross‐section (also known as a “road diet”) to improve pedestrian and bicycle safety, while also creating several
opportunities for new public spaces.
The road diet also provides several opportunities for the installation of stormwater BMPs on Main and King
Streets. On Main Street, the Nelson/Nygaard study recommended using the additional space to widen sidewalks
to allow outdoor dining, street trees and other vegetation. Opportunities for BMPs on Main Street include
permeable pavers on the sidewalks for infiltration and street planters and bioretention gardens to collect and
treat stormwater runoff from the street. On lower King Street, the study recommended center left‐turn lanes
with vegetated medians. These vegetated medians could be designed as bioretention areas or street planters to
collect and treat stormwater.
On upper King Street, in addition to center left‐turn lanes, the study recommended one‐way cycletracks
constructed at‐grade with the sidewalks, but separated from the sidewalk by a 10‐foot‐wide vegetated strip.
Opportunities for green infrastructure include permeable pavers for the sidewalks, porous pavement for the
cycletracks, bioretention areas in the vegetated strip, and street planters in the vegetated median. All of these
stormwater BMPs will reduce peak runoff to the King Street drainage system and provide treatment of
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐7
106678‐80349‐03‐11
stormwater, improving receiving water quality. It is recommended that pipe capacity improvement design for
the King Street drainage system occur concurrently with modifications to King and Main Streets because
detailed hydrologic/hydraulic analyses associated with the proposed stormwater BMPs may indicate that pipe
sizes smaller than those shown on the recommended plan (Figure 3.1) may be feasible. . The total estimated
cost for drainage improvements in this area is $19,424,000. See Table 3.3 for a breakdown of costs and phasing.
3.2.6 Austin Circle/Ryan Road Area
The recommended Phase 2 Austin Circle/Ryan Road area drainage improvements (Figure 3.3) consist of
approximately 1,300 feet of new 30‐inch diameter drainage pipe, a 1.3‐acre flood storage area, and 1,500 feet of
channel improvements. The total estimated cost for drainage improvements in this area is $4,084,000. See
Table 3.4 for a breakdown of costs.
3.2.7 Flood Control Pumping Station Improvements
Recommendations for the Northampton Flood Control Pumping Station and the West Street stormwater
pumping station are discussed in Sections 2.3.5.1 and 2.3.6.1. For the Northampton Flood Control Pumping
Station, the cost estimate is based on a complete new facility. For the West Street Pumping Station, it is
recommended that the City purchase a portable diesel‐engine‐driven pump with capacity on the order of 6,000
gpm, instead of installing a permanent pump at this location. Pumping station improvements are scheduled for
Phase 2. The total estimated cost for the Flood Control Pumping Station improvements is $23,653,000. See
Table 3.5 for a breakdown of costs and phasing.
3.2.8 Levee Improvements
As discussed in Section 2.3.4, the levee improvements mandated by USACE include repairing areas with ruts,
small depressions, sparse vegetation, and missing riprap, and removing trees and thick brush on the levee and at
least 15 feet beyond the abutments and at the toe of the levee. Regular maintenance activities are also
recommended at least twice a year, or as conditions warrant, to control and limit growth of vegetation on the
levee and the banks of the diversion canal. The USACE has also mandated an engineering evaluation of the
levees to assess data gaps. Levee improvements must be completed by January 2013 or 2014, depending on the
item, as discussed in Section 2.
3.2.9 River Erosion Improvements
The proposed River Road Retaining Wall/Floodwall Improvements are located in the Leeds Village section of
Northampton (See Figure 1.1). Flows from the Mill River have scoured and undercut significant sections of the
wall, and surface runoff has compromised the integrity of the upper portions of the wall. In addition, the
Williamsburg sanitary sewer interceptor is located within River Road and is in danger of collapsing due to river
erosion. The City is proposing to remove the existing stone masonry wall and replace it with a cast‐in‐place
concrete retaining wall that will protect the road and sewer from the 100‐year flood event. This project is
scheduled for Phase 1.
The Roberts Meadow Brook channel is located between the Lower Roberts Meadow Reservoir Dam and
Reservoir Road in Leeds (see Figure 1.1). The channel is comprised primarily of dry masonry sidewalls and a
naturalized boulder and cobble bottom. High flow events have resulted in significant erosion of the channel
sidewalls, which is threatening the dwellings and driveways of adjacent private properties. The City has
proposed to extend the floodwall upstream from the Reservoir Road bridge to the critical area in the channel.
The new floodwall would be a cast‐in‐place concrete retaining wall with sufficient height to protect adjacent
properties from the 100‐year flood event. This project will be performed during Phase 1.
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐8
106678‐80349‐03‐11
The third project improves the Federal Street retaining wall along the Mill River, as shown in Figure 3.2. The
purpose of this project is to protect a 30‐inch sewer interceptor. Erosion is occurring along the sharp bank
angle, which is leading to the exposure of the interceptor. This project will be performed during Phase 2.
3.3 Future Operational Cost Projections Additional operational staff, equipment and funding will be needed to address the maintenance and
replacement needs of the City’s aging drainage infrastructure and to comply with the new requirements of the
pending changes to the NPDES Phase II permit. The proposed NPDES permit has many requirements that will
require both operational and technical staff, as well as new equipment needs. Some of these requirements are
discussed below.
Data Requirements: The Draft NPDES Permit requires the gathering, and in some cases mapping, of an
enormous quantity of data. Much of this information is required in the first two years after permit issuance in
order to perform the analyses required to meet the permit milestones. Northampton has a well‐established
Geographic Information System (GIS), but a significant amount of professional staff time will be required for the
data compilation and analysis.
Proposed Outfall Sampling: The new permit requires sampling 25 percent of each community’s outfalls each
year during both dry and wet weather. The City of Northampton has almost 300 stormwater outfalls that
discharge to various brooks, streams, and rivers, resulting in the need to sample about 75 outfalls two times per
year. These sampling events will require DPW staff labor and sampling equipment to accomplish, as well as
possible laboratory testing fees.
Nitrogen Reduction Requirements and Best Management Practices (BMPs): The Draft NPDES Permit requires
the use of both structural and non‐structural BMPs to ensure water quality standards will be met. The draft
NPDES permit requires a 10 percent reduction in the amount of nitrogen discharged in stormwater. This will be
required since the City is located within the Connecticut River basin and thus ultimately discharges to Long
Island Sound. The construction of many BMPs within the City stormwater system will be required to reduce the
amount of nitrogen discharged. These types of BMPs are stormwater retrofit construction projects that will
require capital funding to accomplish.
Public Education and Outreach: The Draft Permit includes the production and distribution of eight public
education notices, in addition to several ordinances and programs intended to teach the public how to minimize
their impacts on stormwater quality. Professional DPW staff will be required to manage the requirements of the
public education and outreach program.
Catch Basin Inspection and Cleaning: The draft permit requires street sweeping twice per year (spring and fall)
and a catch basin cleaning frequency that ensures that no catch basin will be more than 50 percent full of debris.
Currently, most City streets are swept once per year and only certain catch basins are cleaned on a regular basis.
The City has over 150 miles of paved streets and over 3,750 catch basins. Additional DPW staff and equipment
will be required to meet these new regulatory requirements.
3.4 Estimated Costs and Preliminary Schedule Tables 3.1 through 3.5 present the estimated project costs and projected schedules for construction of the
recommended drainage and flood control facilities. Table 3.6 summarizes the total project costs for the 20‐year
plan.
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐9
106678‐80349‐03‐11
Project costs include estimated construction costs, a 25 percent construction contingency, engineering and
implementation costs. The need for land acquisition and easements was not determined and those costs are
not included. Estimated mid‐points of construction used in the cost estimates vary for each project and are
provided in Tables 3.1 through 3.5.
Table 3.1
Bridge Street/Meadows Area Drainage Improvements Preliminary Project Cost Estimate
Location/Description Pipe
Size (in) Quantity Unit
Unit Cost Depth 0 to 8 ft
Construction Cost
Phase 1
New Drains 48 4,700 lf $670 $3,149,000
66 770 lf $950 MassDOT Project
Headwalls and Riprap Pads (42‐ to 84‐in pipe)
1 ea $80,000 $80,000
Subtotal 5,470 lf $3,229,000
Construction Contingencies (25%) $807,250
Total Construction Cost (April 2011 ENR 9027) $4,036,250
Construction Cost at Mid‐Point of Phase 1 Construction* $4,410,519
Engineering and Implementation Costs (25 %) $1,102,630
Phase 1 Opinion of Probable Project Costs (Rounded) $5,513,000
Phase 3
New Drains 12 3,650 lf $255 $930,750
18 1,225 lf $330 $404,250
24 500 lf $370 $185,000
30 1,300 lf $400 $520,000
36 350 lf $470 $164,500
42 490 lf $635 $311,150
Subtotal 7,515 lf $2,515,650
Construction Contingencies (25%) $628,913
Total Construction Cost (April 2011 ENR 9027) $3,144,563
Construction Cost at Mid‐Point of Phase 3 Construction* $4,483,394
Engineering and Implementation Costs (25 %) $1,120,849
Phase 3 Opinion of Probable Project Costs (Rounded) $5,604,000
Total Opinion of Probable Project Costs (Rounded) $11,117,000
Notes:
Land acquisition/easement costs not included
Costs are April 2011 dollars (ENR 9027)
*Phase 1: Apr '11 to Apr'14, 3% per year; Phase 3: Apr '11 to Apr '23, 3% per year
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐10
106678‐80349‐03‐11
Table 3.2
Elm Street Brook/Florence Area Drainage Improvements Preliminary Project Cost Estimate
Location/Description Pipe Size
(in) Quantity Unit
Unit Cost Depth 0 to 8 ft
Construction Cost
Phase 1
New Drains 48 1,860 lf $670 $1,246,200
New Box Culvert 7‐ft x 4‐ft 1,645 lf $1,200 $1,974,000
Headwalls and Riprap Pads (42‐ to 84‐in pipe)
3 ea $80,000 $240,000
Subtotal 3,505 lf $3,460,200
Construction Contingencies (25%) $865,050
Total Construction Cost (April 2011 ENR 9027) $4,325,250
Construction Cost at Mid‐Point of Phase 1 Construction* $5,164,575
Engineering and Implementation Costs (25 percent) $1,291,144
Phase 1 Opinion of Probable Project Costs (Rounded) $6,456,000
Phase 3
New Drains 12 8,000 lf $255 $2,040,000
18 1,750 lf $330 $577,500
24 1,580 lf $370 $584,600
36 1,200 lf $470 $564,000
48 1,860 lf $670 $1,246,200
72 530 lf $1,000 $530,000
Subtotal 14,920 lf $5,542,300
Construction Contingencies (25%) $1,385,575
Total Construction Cost (April 2011 ENR 9027) $6,927,875
Construction Cost at Mid‐Point of Phase 3 Construction* $10,326,425
Engineering and Implementation Costs (25 percent) $2,581,606
Phase 3 Opinion of Probable Project Costs (Rounded) $12,908,000
Total Opinion of Probable Project Costs (Rounded) $19,364,000
Notes: Land acquisition/easement costs not included Costs are April 2011 dollars (ENR 9027) * Phase 1: Apr '11 to Apr '17, 3% per year; Phase 3 Apr '11 to Apr '24/'25, 3% per year
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐11
106678‐80349‐03‐11
Table 3.3
King Street/Market Street Area Drainage Improvements Preliminary Project Cost Estimate
Location/Description Pipe Size
(in) Quantity Unit Unit Cost Depth 0 to 8 ft
Construction Cost
Phases 1 and 2
New Drains 36 320 lf $470 $150,400
48 2,800 lf $670 $1,876,000
66 420 lf $950 $399,000
72 400 lf $1,000 $400,000
78 1,480 lf $1,300 $1,924,000
New Box Culvert 9‐ft x 5‐ft 560 lf $1,800 $1,008,000
Subtotal 5,981 lf $5,837,400
Construction Contingencies (25%) $1,459,350
Total Construction Cost (April 2011 ENR 9027) $7,296,750
Construction Cost at Mid‐Point of Phase 1/2 Construction* $9,108,690
Engineering and Implementation Costs (25 %) $2,277,170
Phase 1/2 Opinion of Probable Project Costs (Rounded) $11,386,000
Phases 3 and 4
New Drains 12 1,500 lf $255 $382,500
18 950 lf $330 $313,500
24 2,000 lf $370 $740,000
36 1,360 lf $470 $639,200
54 800 lf $740 $592,000
60 630 lf $930 $585,900
Subtotal 7,240 lf $3,253,100
Construction Contingencies (25%) $813,275
Total Construction Cost (April 2011 ENR 9027) $4,066,375
Construction Cost at Mid‐Point of Phase 3/4 Construction* $6,430,309
Engineering and Implementation Costs (25 %) $1,607,577
Phase 3/4 Opinion of Probable Project Costs (Rounded) $8,038,000
Total Opinion of Probable Project Costs (Rounded) $19,424,000
Notes:
Land acquisition/easement costs not included
Costs are April 2011 dollars (ENR 9027)
*Phase 1/2: Apr '11 to Apr'18/'19, 3% per year; Phase 3/4: Apr '11 to Apr '26/'27, 3% per year
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐12
106678‐80349‐03‐11
Table 3.4
Austin Circle/Ryan Road Area Drainage Improvements Preliminary Project Cost Estimate
Location/Description Pipe
Size (in) Quantity Unit
Unit Cost Depth 0 to 8 ft
Construction Cost
Phase 2
New Drains 30 1,300 lf $400 $520,000
Headwalls and Riprap Pads (up to 36‐in pipe)
4 ea $25,000 $100,000
Flood Storage Area 1.3 acre $500,000 $650,000
Channel Improvements 1,500 lf $450 $675,000
Subtotal 2,800 lf $1,945,000
Construction Contingencies (25%) $486,250
Total Construction Cost (April 2011 ENR 9027) $2,431,250
Construction Cost at Mid‐Point of Phase 2 Construction* $3,267,400
Engineering and Implementation Costs (25 percent) $816,800
Opinion of Probable Project Costs (Rounded) $4,084,000
Notes:
Land acquisition/easement costs not included
Costs are April 2011 dollars (ENR 9027)
*Phase 2: Apr '11 to Apr '21, 3% per year
Section 3 Capital Improvements Plan and Operational Budget Requirements
3‐13
106678‐80349‐03‐11
Table 3.5
Flood Control System Improvements Preliminary Project Cost Estimate
Description of Capital Improvement Construction Costs
Phase 1
Levee Capital Improvements $436,000
Levee Certification Allowance $445,000
Subtotal $881,000
Construction Contingencies (25 percent)
Capital Improvements Only $109,000
Total Construction Cost $990,000
Construction Cost at Mid‐Point of Construction* $1,019,700
Phase 1 Opinion of Probable Project Costs (Rounded) $1,020,000
Phase 2
Levee Capital Improvements Allowance $500,000
Flood Control Pumping Station Upgrades $12,000,000
West Street Portable Pumps $400,000
Subtotal $12,900,000
Construction Contingencies (25%) $3,225,000
Total Construction Cost (April 2011 ENR 9207 ) $16,125,000
Construction Cost at Mid‐Point of Construction** $18,106,000
Engineering and Implementation Costs (25 percent) $4,526,500
Phase 1 Opinion of Probable Costs (Rounded) $22,633,000
Opinion of Probable Project Costs (Rounded) $23,653,000
Notes:
Land acquisition/easement costs not included
Costs are April 2011 dollars (ENR 9207 Estimated)
*Mar '12 3% per year
**April 2011 to April 2012 to Apr '18 (levee improvements), '15 (stormwater P.S.),'16 (West St P.S.)
Section 3 Capital Improvement Plan and Operational Budget
3‐14
106678‐80349‐03‐11
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031
Bridge Street/Meadows Phase 1 Improvements $441,000 $5,072,000
River Road Floodwall Improvements $155,000 $1,453,000
Roberts Meadow Brook Channel Improvements $43,680 $502,320
Federal Street Retaining Wall Improvements $120,000 $1,380,000
Elm Street Brook/Florence Area Phase 1 Improvements $516,000 $5,939,000
King Street/Market Street Area Phase 1 and 2 Improvements $911,000 $5,160,000 $5,315,000
Levee Certification $275,000 $275,000
Levee Capital Improvements $280,000 $275,000 $56,000 $647,000
Flood Control Pumping Station Upgrades $1,391,000 $15,998,000
West Street Portable Pumps $46,000 $533,000
Austin Circle/Ryan Road Area Phase 2 Improvements $327,000 $3,757,000
Bridge Street/Meadows Area Phase 3 Improvements $448,000 $5,156,000
Elm Street Brook/Florence Area Phase 3 Improvements $1,033,000 $5,850,000 $6,025,000
King Street/Market Street Area Phase 3 and 4 Improvements $643,000 $3,643,000 $3,752,000
EPA MS4 Permit Requirements Allowance $250,000 $250,000 $250,000 $250,000 $250,000
Annual Allowance for Drainage Infrastructure $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Municipal Green Design/Construction Allowance $258,000 $265,000 $273,000 $281,000 $290,000 $299,000 $307,000 $317,000 $326,000 $336,000 $346,000 $356,000 $367,000 $378,000 $389,000 $401,000 $413,000 $426,000 $438,000 $452,000
Total Costs per Year $1,761,680 $3,961,320 $6,151,000 $3,115,000 $18,087,000 $7,769,000 $7,347,000 $6,132,000 $1,153,000 $4,593,000 $1,294,000 $7,045,000 $6,717,000 $7,546,000 $4,532,000 $4,653,000 $913,000 $926,000 $938,000 $952,000
Grand Total $95,586,000
Planning/Operations
Design
Construction
YearProject Description
Table 3.6
Summary Project Cost Schedule
Section 3 Capital Improvement Plan and Budget Operational Requirements
3‐15
106678‐80349‐03‐11
3.5 Project Prioritization Construction phasing of the recommended drainage and flood control improvements will depend upon the
City’s availability of funding to implement these improvements. Twenty‐year bonds will likely be issued to
accomplish the projects. Section 5 uses the costs summarized in Section 3.4 above, assuming issuance of 20‐
year bonds, to evaluate creation of a Stormwater and Flood Control Utility to fund the recommended
stormwater and flood control improvement projects, as well as annual maintenance of drainage infrastructure
and permitting requirements.
The highest priorities are flood control, street improvements, the Bridge Street/Meadows area, which includes
the Fairgrounds, and the Elm Street Brook area where chronic flooding limits access to the area around
Northampton High School. As discussed above, the recommended drainage system improvements consist of
two types of projects:
Phase 1 and 2 projects – needed to address high priority flooding problems or other issues, such as pipe
collapses
Phase 3 and 4 projects ‐ designed to provide capacity to control 10‐year 24‐hour storm peak rates of runoff in
areas with less significant flooding problems
Table 3.7 provides a preliminary prioritization ranking system for the drainage and flood control projects that
can be used by the City for future stormwater and flood control system asset management using the City’s
VUEworks program. The prioritization ranking system includes a list of key qualitative (non‐cost) and
quantitative (cost) assessment criteria used to screen each project. Each project is rated based on key
assessment criteria, and the criteria is assigned weighting factors to account for varying degrees of importance.
It is recommended that the matrix be re‐evaluated every few years to determine whether it would be more
beneficial to re‐order project priorities.
Section 3 Capital Improvement Plan and Budget Operational Requirements
3‐16
106678‐80349‐03‐11
Table 3.7 Stormwater Capital Improvement Projects – Prioritization Ranking Summary
5.0% 10.0% 2.5% 10.0% 15.0% 22.5% 25.0% 10.0%
Watershed Improvement Nature of Problem Sys
tem
Des
ign
Cap
acity
(ye
ar)
Cos
t (E
ngin
eerin
g D
esig
n,
Per
mitt
ing
&
Con
stru
ctio
n)
Pro
ject
aff
ects
pa
rcel
s in
F
EM
A
flood
plai
n
Acr
es I
mpa
cted
Fac
ility
C
apac
ity
Env
ironm
enta
l Q
ualit
y
Acc
ess
&
Eas
emen
ts
Con
nect
ion
to
City
-Pla
nned
P
roje
cts
Con
stru
ctab
ility
Roa
dway
s/P
rop
erty
Flo
oded
To
tal C
ost
Sco
re
Bridge Street/Meadows Area48" drain from 3C Fairgrounds to Connecticut River, 66" drain replacement at Damon Road. (Phase 1) Flooding at Fairgrounds and lower Williams Street 10
$5,513,000YES 5 4 0 4 5 4 5 3 4.250
Elm Street Brook/Florence AreaInstall weir structure and box drain in Elm Street, new drain in Milton and Federal Streets, and new outfall from Federal Street to Mill River. (Phase 1)
Flooding along Elm Street, particularly at the intersection of Milton Street. 10
$6,085,000NO 4 4 0 4 4 3 5 3 3.825
King Street/Market Street Area
48" drain in Market Street Brook from North Street to Bridge Street, 36" drain in Market Street, 66" to 78" drain in King Street from North Street to Main Street, 9' x 5' box culvert in Old Mill River. (Phase 1 and 2)
Drainage systems do not accommodate 10-year storm
10
$11,386,000
NO 4 3 0 3 4 2 3 5 3.100
Austin Circle/Ryan Road AreaCreation of a Flood Storage Area, installation of 24" drain, and improvements to existing channel.
Flooding along existing channel25
$3,225,000No 2 4 5 3 0 3 5 2 3.050
Bridge Street/Meadows AreaUpsize all pipes <12" to 12" pipes, upsize cross-country drainage system near Coolidge Avenue, upsize pipes in Pomeroy Terrace, upsize pipes in Williams Street. (Phase 3)
Drainage systems do not accommodate 10-year storm10
$6,456,000No 3 5 0 2 1 1 5 3 2.775
Elm Street Brook/Florence Area
Upsize all pipes <12" to 12" pipes, upsize pipes in Federal Street, North Elm Street, Locust Street, Stitson Avenue, High Street, Straw Avenue, Fox Farms Road, Bridge Road, Strawberry Hill Street, and Chestnut Street. (Phase 3)
Drainage systems do not accommodate 10-year storm
10
$12,908,000
No 3 4 0 4 1 3 2 5 2.775
King Street/Market Street AreaUpsize all pipes <12" to 12" pies, upsize pipes in Upper King Street, Walnut Street, State Street, Trumbull Avenue and Church Street. (Phase 3 and 4)
Drainage systems do not accommodate 10-year storm10
$8,038,000No 3 2 0 4 2 2 3 4 2.650
LEGEND: Ranking Based on Quantifiable Data
Notes:(1) Costs that occur annually - MS4 permitting, drainage infrastructure, and municipal green design projects - are not included in this table.(2) Capital projects that are subject to a FEMA grant - River Road floodwall improvements, Roberts Meadow Brook channel improvements and Federal Street retaining wall improvements - are not included in this table.(3) Levee accreditation not included because subject to FEMA scheduling.
Project Affects Parcels in FEMA Floodplain
4‐1 10678‐80349
Section 4 – Environmental Permitting
4.1 Introduction Section 3 presented the recommended plans for the King Street/Market Street Area, Bridge
Street/Meadows Area, Elm Street Brook/Florence Area, Austin Circle/Ryan Road area drainage areas,
to be designed, permitted and constructed in four phases, as well as the Northampton flood control
system and river erosion recommended improvements.
These anticipated projects can proceed as standalone projects. Hence each phase of the work in
each watershed and the flood control improvements will be designed, permitted and built separately.
Following are the anticipated environmental permits and approvals for each watershed for Phases 1
through 4, and for the flood control and river erosion improvements:
Location
Federal Approvals
State Approvals Local
Approvals
USACE Permit
NPDES Permit
MEPA Water Quality
Certification
CH. 91 License
Order of Conditions
Phase 1 and 2
King Street/Market Street Area
X X X X
Bridge Street/Meadows Area
X X X X X X
Elm Street Brook/Florence Area
X X X X X
Austin Circle/Ryan Road Area
X X X X X
Phase 3 and 4
King Street/Market Street Area
X X X X
Bridge Street/ Meadows Area
X X X X
Elm Street Brook/Florence Area
X X X X
Flood Control Projects X X X X
River Erosion Projects X X X X
Section 4 Environmental Permitting
4‐2 10678‐80349
In addition, the new pump engines and emergency standby generator for the replacement Flood Control
Pumping Station will need to obtain Installation Compliance Certification as part of the MassDEP Environmental
Results Program.
During preliminary design the proposed improvements will be evaluated to determine what permits and
approvals are needed and a strategy to effectively navigate the approval process will be prepared. A “permitting
plan” will be incorporated into the preliminary design report for each project.
4.2 Description of Applicable Permits There are a number of federal, state and local permits required to implement the drainage improvements.
Because city drainage systems are linked to, or incorporate water courses and wetlands, e.g. Elm Street Brook
and the Connecticut River, permits and approvals will be required to work in or adjacent to these resources.
The following identifies federal, state and local permits/approvals required to work in or adjacent to regulated
natural resources.
4.2.1 Federal Permits/Approvals
4.2.1.1 Clean Water Act, Section 404
Section 404 of the Clean Water Act (CWA) regulates the discharge of dredged or fill materials into the Waters of
the U.S., including adjacent wetlands. Any discharge of dredged or fill material into Waters of the U.S. and/or
adjacent wetlands to prosecute drainage improvements, will require approval from the U.S. Army Corps of
Engineers (USACE) in accordance with Section 404 of the CWA.
In Massachusetts, the USACE issued a General Permit (GP) to streamline the permitting process. The GP
establishes three categories of review: Category I involves a pre‐discharge notification but no formal review by
the USACE provided all applicable GP conditions are met; Category II activities require screening by the USACE
for compliance with GP conditions; and, an Individual Permit is required for large‐scale projects (e.g., those
altering more than 1 acre of vegetated wetland or landfill bank) which do not meet the terms and general
conditions of the GP based on concerns for the aquatic environment or for other factor of the public interest.
Section 10 of the Rivers and Harbors Act
Section 10 of the Rivers and Harbors Act of 1899 (Section 10) requires approval from the USACE to place fill or
construct structures in Navigable Waters. Note, the Massachusetts GP was issued pursuant to Section 404 of the
CWA and Section 10 of the Rivers and Harbors Act of 1899. Therefore, review for work subject to Section 10 is
the same as described above for Section 404 of the CWA.
Executive Order 11988 (E.O. 11988), Protection of Floodplains
E.O. 11988 directs that federal actions (i.e. federal funding or approvals) occurring within floodplains must be
performed so as to avoid adverse impact to the floodplain, and to minimize potential harm and to restore and
preserve the natural and beneficial values of the floodplain.
This requirement is addressed by the USACE concurrent with their review pursuant to CWA Section 404,
described above. Floodplain associated with the Connecticut River will be altered during construction, including
excavation and refill. Preliminary design calculations have indicated that there will be no net loss of floodplain
storage capacity. This will be confirmed during future design work.
Section 4 Environmental Permitting
4‐3 10678‐80349
Executive Order 11990 (E.O. 11990), Protection of Wetlands
E.O. 11990 directs that federal actions (i.e. federal funding or approvals) occurring within a federal jurisdictional
wetland must be performed so as to minimize the destruction, loss, or degradation of wetlands. This
requirement is addressed by the USACE concurrent with their review pursuant to Section 404 of the CWA
described above.
4.2.1.2 Federal Endangered Species Act of 1973
Section 10 of the Endangered Species Act (ESA) is designed to regulate a wide range of activities affecting plants
and animals designated as Endangered or Threatened, and the habitats upon which they depend. With some
exceptions, the ESA prohibits activities affecting these protected species and their habitats unless authorized by
a permit from the U.S. Fish and Wildlife Service (USFWS) or the National Marine Fisheries Service (NMFS).
Permitted activities are designed to be consistent with the conservation of the protected species.
The ESA makes it unlawful to import or export; deliver, receive, carry, transport, or ship in interstate or foreign
commerce in the course of a commercial activity; sell or offer for sale in interstate or foreign commerce; take
(includes harm, harass, pursue, hunt, shoot, wound, kill, trap, capture, or collect any wildlife within the United
States); take on the high seas; possess, ship, deliver, carry, transport, sell, or receive unlawfully taken wildlife;
remove and reduce to possession any plant from areas under Federal jurisdiction; maliciously damage or destroy
an endangered plant on areas under Federal jurisdiction; and, remove, cut, dig up, or damage or destroy any
endangered plant in knowing violation of any State law or regulation or in the course of a violation of a State
criminal trespass law. These prohibitions apply to live or dead animals or plants, their progeny (seeds in the case
of plants), and parts or products derived from them.
Section 7 of the ESA requires Federal agencies to consult with the USFWS to ensure that actions they fund,
authorize, permit, or otherwise carry out will not jeopardize the continued existence of any listed species or
adversely modify designated critical habitats.
The presence or absence of federally protected species will be determined during preliminary design.
4.2.1.3 National Pollutant Discharge Elimination System (NPDES) – Construction General Permit
The NPDES Construction General Permit (CGP) authorizes stormwater discharges from construction activities
that result in a total land disturbance of equal to or greater than one acre, where those discharges enter Waters
of the United States or a municipal separate storm sewer system (MS4) leading to Waters of the United States
subject to the conditions set forth in this permit. The proposed drainage and flood improvement projects will
alter more than 1 acre of land and stormwater will be discharged to the Waters of the U.S.; therefore,
compliance with the CGP is required.
Pursuant to the requirements of the CGP, the project proponent, or designee, will prepare a Storm Water
Pollution Prevention Pollution Plan (SWPPP) to document stormwater control measures during the construction
periods for the projects. Following completion of the SWPPP, the proponent or designee will complete and
submit to EPA a Notice of Intent to discharge stormwater.
4.2.2 State Permits/Approvals
4.2.2.1 Certificate from the Executive Office of Environmental Affairs (MEPA Approval)
The Massachusetts Environmental Policy Act (MEPA) requires the review and evaluation of certain large‐scale
projects to describe the environmental impact and requires that permit granting agencies identify feasible
Section 4 Environmental Permitting
4‐4 10678‐80349
measures to mitigate potential environmental damage. The MEPA Regulations (301 CMR 11.00) establish
thresholds, a procedure, and time line for a two‐tiered review process, which generally proceeds as follows: the
project proponent submits an Environmental Notification Form (ENF) to the Secretary of Environmental Affairs
(Secretary). A twenty day public comment period follows during which time the Secretary receives comments
from the public and agencies, and holds a site visit and consultation session. Up to ten days following the close
of the comment period, the Secretary issues a Certificate stating whether an Environmental Impact Report (EIR)
is needed and what the scope of the EIR should include, if required. If no EIR is needed the state permitting
agencies can issue the required permits and the project can go forward. Please note, MEPA approval is not
required before an Order of Conditions is issued by a local Conservation Commission. If an EIR is required, it is
prepared by the proponent and submitted to the Secretary. The EIR is reviewed and commented on at both
Draft and Final stages by the public, state agencies, the Secretary, and the MEPA Unit. After completion of
review the Secretary issues a Certificate approving the project.
Approximate time required to file an ENF is about two to four weeks. The approximate agency review time is
five weeks (including the public comment period). Approximate time to complete the EIR process is dependent
upon the time needed to prepare the EIRs, but it is normally completed in twelve to twenty four months.
4.2.2.2 Massachusetts Wetlands Protection Act (M.G.L. c.131, s.40; 310 CMR 10.00)
The Massachusetts Wetlands Protection Act (MWPA) regulates alteration of state‐ defined wetland resource
areas and the Massachusetts Wetlands Protection Regulations (310 CMR 10.00) identify wetland resource areas
subject to protection and present the regulations for work in these wetland resource areas. Although a state
law, the MWPA is administered at the local level by the municipal Conservation Commission. Areas known to be
subject to protection at this time, based on Mass GIS datasource and City investigations, are shown on the
recommended plan figures, and along the Connecticut, Mill and Old Mill Rivers.
A Notice of Intent (NOI) will be prepared and submitted to the Northampton Conservation Commission for
activities within areas subject to protection under the Massachusetts Wetlands Protection Act.
4.2.2.3 Massachusetts Rivers Protection Act (Ch. 258 of the Acts of 1996; 310 CMR 10.58)
The Rivers Protection Act protects perennial rivers, streams, brooks, etc., in the Commonwealth and is enacted
through Section 10.58 of the Massachusetts Wetlands Protection Regulations. It establishes a 200‐foot wide
Riverfront Area that extends horizontally on both sides of perennial waterways. In certain urban areas, the
Riverfront Area is only 25 feet wide. The Connecticut, Mill and Old Mill Rivers are perennial rivers and have an
associated 200‐foot wide Riverfront Area.
Because the Rivers Protection Act is administered through the Wetlands Protection Regulations, the NOIs for the
projects, described above, will address compliance with the Rivers Protection Act.
4.2.2.4 401 Water Quality Certification Program (314 CMR 9.00)
Section 401 of the Clean Water Act requires that states certify that federal actions will not prevent the
attainment of state water quality criteria. The proposed projects will involve work in the Connecticut, Mill and
Old Mill Rivers and associated wetlands, thereby requiring a permit from the USACE per Section 404 of the Clean
Water Act. Consequently, a Water Quality Certification is required from the MassDEP per 314 CMR 9.00. For
minor impact projects [projects that alter less than 5,000 square feet of federal and state jurisdictional wetlands
and/or involve dredging less than 100 cubic yards of material and receive an Order of Conditions (wetlands
permit) per the Massachusetts Wetlands Protection Act] no individual Water Quality Certification is needed. For
projects that exceed those thresholds, an Individual Water Quality Certification is needed from the MassDEP.
Section 4 Environmental Permitting
4‐5 10678‐80349
Massachusetts Stormwater Regulations: Recent revisions to 314 CMR 9.00 establish stormwater standards as a
regulatory requirement. These standards were developed to regulate the quantity (flow) and quality of
stormwater runoff from project sites. The proposed drainage and flood control improvements will require
stormwater runoff control features and will need to comply with the standards to the maximum extent
practicable. These provisions are reviewed by the Conservation Commission pursuant to the WPA and MassDEP
via WQC application review.
4.2.2.5 Massachusetts Endangered Species Act (M.G.L c.131A; 321 CMR 10.00)
The Massachusetts Endangered Species Act (MESA) prohibits the "take" of any rare plant or animal species listed
as Endangered, Threatened, or of Special Concern by the Massachusetts Division of Fisheries & Wildlife (MDFW).
"Take" is defined in the Act as to harass, harm, pursue, hunt, shoot, hound, kill, trap, capture, collect, process,
disrupt the nesting, breeding, feeding or migratory activity of an animal or to collect, pick, kill, transplant, cut or
process a plant. Drainage improvements are located with estimated habitats and will involve work in the
Connecticut, Mill and Historic Mill Rivers, which are also mapped as habitat for protected aquatic species.
When projects involve MESA review and also require approval pursuant to the Massachusetts Wetlands
Protection Act, MESA review can be initiated by submitting the NOI (wetland permit application) to MDFW.
Through this joint review, the MDFW will determine whether a Take Permit is needed.
4.2.2.6 Waterways Licensing Program (M.G.L. Chapter 91; 310 CMR 9.00)
The Waterways Licensing Program was formally established in 1866 with the passage of M.G.L. Chapter 91.
Chapter 91 jurisdiction extends to the mean high water mark of tidal water bodies and the ordinary high water
mark of non‐tidal water bodies, and also includes "filled tidelands.” A Waterways License will be required for
placement of fill or structures below ordinary high water line, of the Connecticut, Mill and Historic Mill Rivers.
4.2.2.7 Environmental Results Program (310 CMR 7.26[42:43])
Under the Environmental Results Program (ERP), operators of new engines and new emergency engines are
required to certify to MassDEP that they are complying with the environmental protection requirements that
apply to the new engines. Operators complete the Installation Compliance Certification Form, which has three
sections. The first section identifies the facility and contact information. The second part is a series of questions
about whether the facility is following applicable environmental requirements. The last part is the certification
statement. The certification needs to be completed within 60 days of starting operation.
4.2.3 Local Permits/Approvals
4.2.3.1 Wetlands Protection Act and City Ordinance
The Massachusetts Wetlands Protection Act and Regulations were established to protect wetland resource areas
because of the valuable functions wetlands provide such as: protection of public and private water supply;
protection of groundwater supply; flood control; storm damage prevention; prevention of pollution; protection
of land containing shellfish; protection of fisheries; and protection of wildlife habitat. Authorization is required
from the municipal Conservation Commission for any work in and adjacent to protected wetland resource areas
as described above.
In addition to the state law, the City adopted a wetlands protection ordinance to augment wetland protection.
The work subject to the ordinance will be addressed in a single joint application (NOI) to address both state and
local requirements.
Please note, additional local approvals may be required by local Zoning Board of Appeals for work with the
floodplain, Planning Board Review, and authorization to connect to municipal drainage systems. Since this
Section 4 Environmental Permitting
4‐6 10678‐80349
project is currently in the conceptual design stage, evaluation of these permitting requirements is beyond the
scope of this document. These issues will be evaluated in their entirety as needed.
4.3 Conclusion The proposed drainage improvement, flood relief and river erosion improvement projects will require work in
regulated resources, e.g. rivers and wetlands, and thus meeting applicable statutory and regulatory
requirements is a critical project component during the preliminary design phase. A program‐specific permitting
plan will be developed to identify anticipated project impacts to regulated resources; permit thresholds;
required permits; suggested measures to mitigate anticipated impacts; and a strategy and schedule to apply for
environmental permits and approvals.
5‐1 106678‐80349‐03‐11.docx
Section 5 ‐ Stormwater and Flood Control Utility
5.1 Introduction Below is a summary of the drivers and main objectives of this section, a brief overview of the
approach and methodology used in developing this report and a summary of the key findings.
5.1.1 Objectives
The City of Northampton (the “City” or “Northampton”) has actively begun to evaluate the funding
needs to maintain the City’s flood control and stormwater infrastructure. As part of this evaluation,
the City requested that Camp Dresser & McKee Inc. (CDM) assess the option of implementing a
stormwater and flood control utility by developing a financial framework and stormwater fee that
could be used to recover costs incurred by the utility. To provide the City with an understanding of
how Stormwater and Flood Control Utility fees are structured, we have developed the following
information:
A planning level budget for the Stormwater and Flood Control Utility, which includes stormwater‐
related expenses currently funded through the sewer rate and General Fund, as well as
anticipated capital improvements.
An analysis of Geographic Information System (GIS) data and application of a standard industry
methodology to determine the City’s equivalent residential unit (ERU) based on impervious area.
A financial model that combines budgetary data with GIS/ERU data to develop a stormwater fee
and assess its impact on typical customers.
A discussion on some of the important policy considerations that are important to take into
account when developing a Stormwater and Flood Control Utility and the associated fees.
The remainder of this section will present the results of this evaluation.
5.1.2 Stormwater Utilities in Other Communities
In order to provide the City with a basis of comparison for stormwater and flood control utility
implementation practices, CDM developed a comparison table which provides information on
population, organizational structure, staffing needs, budget/funding activities funded by the utility
and rates/fees. The table has two sections. The first section of the table reviews stormwater utilities
in New England. The second section reviews stormwater utilities across the country. This
comparison has been compiled using information from the EPA, planning commissions and CDM
client experience. The following is a list of sources and follow up documents that can be used to gain
additional detail on stormwater utility implementation:
Section 5 Stormwater and Flood Control Utility
5‐2
106678‐80349‐03‐11.docxSection 5_050212.docx
Table 5.1
Stormwater Utilities in Other Communities
New England Comparisons
Municipality Population Organizational Structure Staffing Needs Budget/Funding Activities Funded Rates/Fees
Newton, MA 85,000
Stormwater Management Program within DPW
Full‐time engineer and four laborers
$1.149 million (2011)
Operations: stormwater engineer, pollution prevention, water quality sampling, corrective actions, personnel training, public education and outreach.
Capital improvements: drainage improvements, sediment removal, culvert replacement and pump station rehab.
Originally, annual uniform rate: $25 residential and $150 commercial. Recently switched to ERU charge of $25 per unit annually, through water and sewer bills.
Reading, MA 25,000 Enterprise Fund
3 ½ equivalent laborers allocated to utility, 10% of DPW director, 10% of business supervisor and 10% of health administrator. 25% of accounting/finance clerk.
$540,350 (2007)
Operations: street sweeping, vacuum truck rental, materials and supplies, consulting fees and staffing.
Capital improvements: GIS mapping, drainage improvements, river restoration, street sweeper, vacuum truck and dump truck.
ERU charge of $39.84 annually, billed through water and sewer bills.
South Burlington, VT 16,000 Stormwater Management Department, DPW
4 DPW laborers/engineers and 10% city planner.
$1.250 million (2007 estimate)
Operations: legal services, consulting fees, water quality monitoring, permitting, equipment and maintenance.
Capital improvements: upgrades to culverts, retention ponds, drainage and catch basins, GIS services and infrastructure maintenance.
ERU charge of $54 annually, through the water district.
Lewiston, ME 42,000 Enterprise Fund N/A $2.2 million (2011 estimate)
Operations: billing and collections, street sweeping, catch basin cleaning, drainage repairs and general O&M.
Capital improvements: GIS Mapping, pipe renewal and replacement, stormwater infrastructure maintenance.
ERU charge of $40 for single‐family and $60 for duplex, annually. All other customers, $40 base rate and .045 cents per sq. feet of impervious area above 2,900 sq. feet.
Chicopee, MA 55,000 Stormwater Utility Bureau, DPW N/A N/A N/A ERU charge of $100
Westfield, MA 41,000 Stormwater Utility, Special Revenue Fund
Operations: labor, catch basin cleaning, street sweeping, illicit discharge detection and elimination, stormwater control device monitoring and inspection, water quality programs and monitoring, billing and administrative costs.
Capital improvements: engineering, design, financing and construction costs for new facilities or improvement of existing facilities.
$20 flat fee for residential and impervious area‐based fee for non‐residential: $0.045 per square foot impervious surface, with a $100 minimum and $640 maximum
Section 5 Stormwater and Flood Control Utility
5‐3
106678‐80349‐03‐11.docxSection 5_050212.docx
Table 5.1 (con’t)
Stormwater Utilities in Other Communities
United States Comparisons
Municipality Population Organizational Structure Staffing Needs Budget/Funding Activities Funded Rates/Fees
Lancaster, PA 500,000 Enterprise Fund (planning level) N/A $1.832 million (2011 estimate)
Operations: public education and outreach, illicit discharge detection and elimination, construction site runoff control, street sweeping, catch basin cleaning, GIS mapping and stormwater management staff training.
Capital Improvements: N/A
ERU charge of $16.53 (planning stages)
Bellevue, WA 117,000 Part of Utilities Department
45 to 50 full time equivalent employees
$10 million (2004)
Gross Area and Intensity of Development, $120 annually
Charlotte/Mecklenburg County, NC
1,500,000 County Utility with inter‐governmental agreements
105 full time equivalent employees
$85 million
Flat rate for single‐family residential with ERU basis for other customer classes. Rates vary by location.
Tulsa, OH 392,000 Part of Public Works
$12‐$14 million (2002)
Impervious area/ERU basis $42 annually.
Louisville/Jefferson County Metropolitan Service District, KY
Part of Sewer District
600 full time equivalent employees (includes sewer)
$26.7 million (2006)
Flat rate for single‐family residential. Impervious area/ERU basis for other2. $56.40 annually.
Sarasota County, FL 340,000 County Utility 120 employees $20 million (2005) Assessments vary by geographic location.
Griffin, GA 25,000 City Department, with shared DPW Director
15 full time staff $1.2 million (2000)
Operations: personnel and benefits, contracted services, supplies, debt service
ERU charge of $35.40 annually.
Union, OH 6,400
Program within DPW
7 hourly employees $75,000 Operations: storm drain maintenance, catch basin cleaning
Flat Fee System (Impervious area was too complex for a small community)
Annual Cost:
Residential: $36
Commercial: $72
Industrial: $108
Fort Collins, CO 109,000
Program within the Utility Department
25 full time equivalent staff, some staffed are shared and some exclusive to the stormwater program
$7.2 million (2000)
Operations: storm drain maintenance and repair, water quality improvement, new construction development reviews, floodplain management and design of relevant capital projects.
Each parcel is charged a basin fee rate, which varies by geographic location and takes into account on‐site detention reduction factor and a runoff coefficient for each parcel
The runoff coefficient uses a formula that takes into account the percentages of impervious area, pervious area and semi‐pervious area on a per parcel basis
Valparaiso, IN 25,000 Department of Stormwater Managment
No full time employees, only reimburses City staff for labor on stormwater related business
$520,000 (2000) Operations: collection, disposal and drainage of stormwater.
ERU of $36, with multiplier for impervious area, which is broken into 6 ranges, the largest of which charges $1,152 annually for impervious area > 160,000 sq. feet
Section 5 Stormwater and Flood Control Utility
5‐4 106678‐80349‐03‐11.docx
1. Assessment of Stormwater Financing in New England, Charles River Watershed Authority, March 30, 2007.
2. Guidance for Municipal Stormwater Funding, National Association of Flood and Stormwater Management
Agencies, January, 2006.
3. How to Create a Stormwater Utility, Pioneer Valley Planning Commission, November 13, 1998.
4. Stormwaterfinance.urbancenter.iupui.edu, Center for Urban Policy and the Environment.
5. Utility Stormwater Survey, Black & Veatch, 2010.
6. South Burlington Stormwater Utility, Stormwater Credit Fee Manual, Hoyle, Tanner & Associate, Inc.s and
AMC Earth & Removal, Inc., February, 2006.
5.1.3 Methodology
To develop the analysis of a separate Stormwater and Flood Control Utility, stormwater‐related costs currently
being funded through the General Fund and Sewer Utility were identified through discussions with the City.
Based on these discussions, the portion of General Fund and Sewer Utility costs attributable to stormwater were
allocated to the Stormwater and Flood Control Utility. Having combined these costs with anticipated capital
improvements outlined in Section 3, CDM developed revenue requirement projections for the Stormwater and
Flood Control Utility and paired our financial projections with impervious area parcel data to determine a rate
per “ERU”.
The results of this analysis are compiled in this report, the goal of which is to provide the City with the necessary
information to make an informed decision on how it could implement a Stormwater and Flood Control Utility in
order to equitably recover the costs of collecting and treating stormwater through a separate rate. Given this
objective, we focused on three sequential tasks in our analysis, which are as follows:
1. Estimated Stormwater and Flood Control Utility revenue requirements
2. Assessed the City’s impervious surface area and used it to develop an ERU‐type billing system
3. Calculated a rate per equivalent unit and summarized the impact the rate would have on typical customers
This analysis uses FY 2011 as the base year for the projections. The City would not anticipate implementing the
Stormwater and Flood Control Utility within the remainder of the fiscal year. However, it is shown as a basis for
the projections to indicate how the rate would be calculated under the most current expense period.
5.1.4 Key Findings
Should the City choose to implement a stormwater utility, CDM recommends using an ERU fee, which we believe
will most appropriately distribute the costs of the stormwater system. This is an equitable approach that
depends on impervious area, but simplifies the billing system and GIS data requirements needed for
implementation. Under the ERU system, residential units would be assigned one billing unit per dwelling unit,
up to a three‐family unit. Therefore, a single‐family would be assigned one billing unit; a duplex, two billing
units; and a three‐family, three billing units. Larger residential units (i.e. more than three units) and non‐
residential parcels would be assigned billing units based on the amount of parcel impervious area to the
equivalent residential unit amount which CDM has estimated for purposes of this analysis to be 2,671 square
feet (full calculation is shown in Table 5.8). This approach equitably allocates the costs of the system, since
customers with more impervious area create a greater burden on the system and thus should be responsible for
more of the costs.
Section 5 Stormwater and Flood Control Utility
5‐5 106678‐80349‐03‐11.docx
The resulting stormwater fee from an ERU approach is shown in Table 5.2.
Table 5.2
Proposed FY 2012 Equivalent Residential Unit Stormwater Fee Schedule
Classification Billing Units ERU Rate per ERU
Single‐family 1 1.00 $66.63
2‐Family 2 2.00 $133.26
3‐Family 3 3.00 $199.90
Classification Impervious
Area ERU Rate per ERU
Large Residential 10,821 4.05 $269.95
Commercial/Industrial with 1,000 sq. feet of IA 1,000 0.37 $24.95
Commercial/Industrial with 10,000 sq. feet of IA 10,000 3.74 $249.46
Commercial/Industrial with 100,000 sq. feet of IA 100,000 37.44 $2,494.58
A common concern about the implementation of a stormwater and flood control fee is the impact to
commercial and industrial customers, which typically have a higher proportion of impervious area than small
residential customers. Additionally, in some cases, commercial users who do not discharge significant levels of
wastewater may have a significant level of impervious surface area. The shifting cost burden can be difficult for
businesses to appropriately budget for. If the City is concerned about the effect of stormwater and flood control
fees on certain customer classes, there are certain measures that can be taken to mitigate their impact, such as
stormwater management credits, phased implementation, or continuing to recover a portion of stormwater and
flood control costs through the General Fund.
5.2 Stormwater and Flood Control Utility Implementation Considerations
Despite increasing state‐wide interest in Stormwater and Flood Control Utility creation as a means to effectively
manage permit requirements and equitably distribute the cost of stormwater impacts, the concept is still
relatively new to the world of flood control and pollution management. Implementing stormwater utilities is a
significant undertaking and, unfortunately, the lack of existing utilities serves to limit the number of examples
that can be used in assessing best practices. Given those limitations, this section combines information from
existing utilities, planning documents and CDM’s experience in helping clients to establish stormwater utilities, in
order to assist the City in its evaluation of creating a new utility.
5.2.1 Stormwater and Flood Control Utility Background
The establishment of stormwater utilities is a concept that has achieved growing popularity in the United States
since the mid‐1970s. The fundamental basis for the Stormwater and Flood Control Utility is that as the amount
of impervious area increases on a parcel, the amount of runoff from that parcel increases proportionately.
Therefore, the amount a parcel owner is charged is related to its impervious area. The impervious area charge is
an equitable funding mechanism, since charges assessed to each parcel of land are based upon usage of the
drainage system..
Section 5 Stormwater and Flood Control Utility
5‐6 106678‐80349‐03‐11.docx
The average impervious area per dwelling unit for residential land use categories is typically designated as the
“base unit” for the utility fee structure. The base unit represents the impervious area discharge potential of the
average residential dwelling and its associated lot. It can be based upon all residential development (including
multi‐family), on single‐family residential development only, or a combination to encompass smaller residential
developments. For this analysis, the average impervious area of the base unit is calculated by summing the
impervious area for smaller residential parcels (defined as structures less than four units) and dividing by the
total number of dwelling units within those structures. This basic unit is referred to as an equivalent residential
unit (ERU).
Under this approach, large residential properties (greater than three units), and non‐residential parcels are billed
based on the amount of impervious area on the parcel relative to the ERU amount. For example, if a commercial
parcel has four times as much impervious area as the base ERU unit, the commercial site would be billed four
times the residential flat fee.
During the initial history of stormwater utilities, it was relatively expensive to develop the necessary parcel
information to determine billing units and assign billing units to specific parcels. It frequently required hand
measuring parcels and conducting samples of residential parcels to estimate the ERU. However, as GIS
technology has improved, the costs of developing and implementing utilities have declined. Many municipalities
now include impervious area as a layer within their GIS and it is possible to determine, with a high level of
accuracy, the impervious cover on each parcel.
Due to the declining costs and increasing ease with which impervious area can be mapped, some utilities now
bill customers individually based on the actual amount of impervious area on the parcel regardless of whether
the property is residential or non‐residential. The result is that each parcel or customer’s fee is based on its
impact on the municipal system making the stormwater charge more consistent with other utility charges (i.e.,
water, sewer, electric). The main obstacle to this approach is developing the detailed GIS impervious area maps,
which despite technological advancements, still requires a significant effort, specifically in instances of “open
polygons”. A common example of this is a driveway, which GIS applications have difficulty delineating, relative
to something like a roof, which is a closed polygon.
5.2.2 Structural Considerations
The first step towards creating a Stormwater and Flood Control Utility is generally drafting appropriate language
as part of an ordinance. The City Council would typically approve the ordinance to establish the utility. Some
general guidelines to consider include:
Citing the existing legal authority to establish the Stormwater and Flood Control Utility
Showing evidence of the need to create the Stormwater and Flood Control Utility, and the processes
required for its creation
Creating the utility in a way that ensures consistency with local, state, and federal guidelines
The ordinance should explicitly define the role and purpose of the utility, as well as the utility’s ability to charge
and collect fees. It should further establish the process by which the stormwater fees and charges are set,
including the methodology behind the calculation and any potential exclusions for parcels such as undeveloped
land or municipal properties. The ordinance should also detail any credits that are available and the process by
which a resident could appeal a charge. We suggest the City begin reviewing existing stormwater ordinances in
other communities, as well as the City’s Sewer Utility ordinance, as a basis for its own stormwater ordinance.
Section 5 Stormwater and Flood Control Utility
5‐7 106678‐80349‐03‐11.docx
5.2.3 Public Education and Involvement
The City should consider developing a public education program designed to educate the community on the
reasons behind creating a Stormwater and Flood Control Utility, highlighting the negative impacts of stormwater
pollution. Public support for the utility may make it easier to implement the fees and charges necessary to fund
the utility. Educating the public on the basics and the impact of pollutants in stormwater may also have the
effect of creating a change in behavior and encouraging better stormwater management practices from
residents and businesses.
The City should identify the amount available to allocate towards public education and outreach, and formulate
activities it believes will be most effective for public consumption. Examples of activities include distributing
flyers or press releases outlining the role and purpose of the Stormwater and Flood Control Utility, incorporating
the basics of stormwater into school curriculum, and/or hosting public events. As a planning level estimate,
CDM has included a $20,000 line item for public education into its incremental budget in the revenue
requirement subsection.
In defining the steps for public education and acceptance for the creation of a Stormwater and Flood Control
Utility, it is important to define the message the City wants to convey to the public, and the means by which to
convey it in an effective manner. Generally, before the creation of the utility, the focus of public outreach is to
describe the utility and its general functions and to justify the need for a separate stormwater fee. For the City,
the message would most likely highlight the environmental and health impacts of stormwater pollutants and
requirements to remain in compliance with permit guidelines.
A common method to facilitate public education is through the distribution of flyers and educational packets,
incorporating stormwater information into school curricula, public hearings or press releases, inserts that
accompany water and sewer bills outlining the need for a Stormwater and Flood Control Utility, and/ a
dedicated website with stormwater education. Given that the City has decided to establish the utility as a
standalone enterprise utility, establishing a separate page on the City website dedicated to the Stormwater and
Flood Control Utility may be useful, with information on why the utility is being established, and a justification
for the stormwater and flood control fee. The site could also contain links to various web resources that
facilitate public education on the topic. See the website for the South Burlington, VT stormwater utility that
provides detailed information about their utility (sburlstormwater.com).
In conjunction with educating the public on the need for the new Stormwater and Flood Control Utility and fee,
it could also be useful to highlight behaviors that would encourage stormwater pollution prevention. Part of the
education process for the acceptance of the utility creation will include showing the public the negative impacts
of stormwater pollution, consistent with the EPA NPDES Phase II requirements, so the City may consider using
that opportunity to provide the public with ways they can help reduce stormwater pollution. It would be useful
to continue this sort of public outreach on an ongoing basis after the creation of the Stormwater and Flood
Control Utility and the implementation and acceptance of the fee.
5.2.4 Management and Budgeting
Another key aspect to creating a Stormwater and Flood Control Utility is determining how the utility is to be
managed. A new Stormwater and Flood Control Utility would operate as a stand‐alone enterprise utility, which
means that the utility would have its own separate budget with line item expenses, and the stormwater charges
would be set annually to directly offset these expenses.
Section 5 Stormwater and Flood Control Utility
5‐8 106678‐80349‐03‐11.docx
5.2.4.1 Budgeting
The City worked with CDM to identify the staffing and budgetary needs to operate the Stormwater and Flood
Control Utility. In order to develop planning level estimates, CDM worked with the City to allocate stormwater‐
related expenses from the General Fund and Sewer Utility. In addition to this, CDM developed incremental
Stormwater and Flood Control Utility costs. These are operation and maintenance (O&M) costs that will be
required to operate the City’s Stormwater and Flood Control Utility and meet permit requirements.
CDM also provided the Stormwater and Flood Control Utility with a capital improvements plan (CIP), which is
included in revenue requirement projections and must be considered in the budgeting process. In addition to
the CDM‐prepared CIP, the City may need to consider making some additional capital outlays, such as additional
street sweepers and maintenance vehicles, as it moves forward with its Stormwater and Flood Control Utility
implementation. As the City gains a better understanding of the operating costs and capital needs for the
Stormwater and Flood Control Utility, these estimates will need to be adjusted to more accurately reflect the
true cost of service.
5.2.4.2 Billing
The City will need to establish an appropriate and functioning billing system in order to ensure billing accuracy
for the stormwater fee. A common practice is to include the stormwater charge as part of an already existing
municipal bill (e.g. water and sewer). It is generally assumed that the municipality would have a master file of
accounts through some computerized billing program, so the most reasonable way to incorporate the charge is
to populate the master file with the relevant information pertaining to the stormwater charge.
A potential issue with the implementation of this rate structure that the City would need to consider is land
areas not connected to other municipal utilities. One example of this is parcels that have private wells and
septic systems. Another example is vacant parcels, which do not have utility services. The City has over 2.7
million square feet of undevelopable impervious land area, and another 4.2 million square feet in impervious
area with unknown classification. If the City were to include the stormwater charge as part of another utility bill
and incorporate the same customer listing, it would omit the vacant land.
An alternative approach to billing would be to include the stormwater fee as part of the property tax bill. All
taxable property listings would be accounted for, so a property would not need to have municipal utility service
in order to be included for the fee. However, this approach creates a similar but separate issue – the exclusion
of tax‐exempt properties. Exempt (municipal, colleges, etc.) impervious area totals around 16.2 million square
feet, and would not appear on the tax rolls or receive a property tax bill. The City will need to assess the billing
issues associated with the new stormwater fee and determine the appropriate course of action.
A third approach would be to conduct stand‐alone utility billing. However, CDM recommends against this
practice, as it would be redundant with current services and would add an additional layer of administrative
costs to the utility. For this reason, a stand‐alone billing approach is rarely used by stormwater utilities.
5.2.5 Funding Options
There are a variety of rate/fee mechanisms for recovering Stormwater and Flood Control Utility revenue
requirements. As we have developed this report, based on discussions with the City, we have taken an ERU
approach. We have included this section on funding options for the purpose of providing the City alternative
approaches to the one proposed in the report, as well as providing an understanding of why the ERU was used
as the cost recovery method in this report.
Section 5 Stormwater and Flood Control Utility
5‐9 106678‐80349‐03‐11.docx
In large part, rate/fee setting principles focus on the equity of cost recovery. Equity refers to setting rates at a
level that generates adequate revenue to fund revenue requirements, while also aligning to recover the actual
cost of service to operate and maintain the system.
Some of the general methodologies for stormwater rate and fee setting utilized by other communities include:
uniform charges based on property type, rates based solely on impervious area, a combination of impervious
and gross area, impervious area and percent of impervious area, gross property area and intensity of
development, and runoff factors. In addition to the various rates and fees, the City may also choose to recover
stormwater costs through the General Fund, which is largely what it does at present. A brief analysis of these
types of rate and fee structures follows.
Uniform charge/flat fee based on property type ‐ Each property is defined as either residential or non‐
residential, and charged a uniform fee based on customer class. This structure has the benefit of being easy to
understand and easy to implement, as it only requires analysis of property data with a residential or non‐
residential designation for each property. The main shortcoming is that it does not necessarily match the rate
with a property’s impact on the stormwater system. For example, a small retail store with a total of 1,000
square feet would be paying the same non‐residential uniform charge as a large commercial building with a
property size of 100,000 square feet. Recently, the City of Newton, MA switched from this rate structure to an
ERU‐based structure for its stormwater system to more closely match the rates with a customer’s burden to the
system.
Rates based solely on impervious area ‐ This is a common approach for stormwater utilities, as it is simple to
understand, easy to calculate and readily justifiable to the public. The underlying principal of an impervious area
fee is that the more impervious area a property has, the larger the impact it has on the stormwater system.
Thus, it should have a proportional charge to its impact on the system. This structure is used with a calculated
charge per ERU for small residential customers based on the average impervious area for that class category.
Larger residential and commercial customers are charged based on actual impervious area as a multiple of the
rate per ERU. This is the rate structure we recommend for the City, and the detailed calculations and description
of this structure are in Section 5.4 of this report.
Rates based on impervious area and gross area ‐ Impervious area and gross area are both included in this
methodology based on the logic that all land area has some impact on the stormwater system. Setting the
stormwater fee involves allocating either a percent distribution between impervious area and gross area, or a
detailed cost of service that allocates costs to one or the other. A benefit of this rate structure is the implicit
decision to charge underdeveloped land, which expands the base for distributing the costs among the
community residents. One deterrent to implementing this approach is equitably determining the allocation
factors used and effectively educating customers on the methodology.
Impervious area and percentage of impervious cover ‐ Users are charged a rate per 100 square feet, which is
defined by the percentage of impervious area to gross area on a property. The rates are generally set as
increasing in a percentage range (e.g. 0‐15%, 15‐20%, etc.), with the idea being that the more impervious area
on a property, the greater the burden. This rate structure is currently used by the City of Denver, CO.
Gross area and intensity of development ‐ An intensity of development factor is assigned to properties to
estimate the amount of impervious area per parcel. The calculation can be as simple as taking a parcel’s gross
area and multiplying it by the factor. Cincinnati, OH, for example, assigns a factor of zero to undeveloped land
up to a factor of 0.85 for commercial customers. A potential benefit of this structure is employed by Bellevue,
WA, in which a small rate is assessed to undeveloped properties, allowing for some cost recovery from
Section 5 Stormwater and Flood Control Utility
5‐10 106678‐80349‐03‐11.docx
undeveloped lands. The justification follows the same logic as the impervious and gross area rate structure – all
land contributes to the stormwater system, and so should be assessed some charge.
Runoff factor ‐ This structure aims to apply a set of factors to parcels generally in land use categories in order to
account for the amount of stormwater estimated during a storm event. It is similar to the intensity of
development factor, however it is usually considered a better gauge of the amount of actual stormwater by land
use type, but more difficult to describe and justify to the public.
5.2.6 Stormwater Credits
The impact to customers with large amounts of impervious area can often be significant, relative to their current
costs incurred through General Fund taxation. While a stormwater fee is the most equitable means for
recovering stormwater costs, relative to charging for the behavior and conditions that create stormwater runoff,
in some cases, it may be considered over burdensome to certain users in the system. There are several methods
that can be used to help control costs for these users, including phasing in stormwater fees, or providing users
with stormwater credits. This subsection focuses on the latter of the three alternatives.
As discussed in Sections 2 and 3, credits or exemptions can be used to incentivize certain practices or to provide
relief from utility fees based on specific types of land uses. Stormwater utilities typically provide credits in two
circumstances. The first is when a property owner has put in place stormwater controls that provide relief
beyond what may have been required as a condition of property development. The second is for properties that
can demonstrate that they have mitigated their impact on the municipal stormwater infrastructure through
improved stormwater treatment practices, whether it is a reduction in quantity or improvement in water quality
of stormwater runoff.
Some examples of practices where stormwater credits may be applied are:
Detention ponds
Stream buffers and filters
Green rooftops
Conservation of natural areas in new development
Reforestation
Low income credits for residential customers proving financial hardship
In addition to stormwater treatment practices, some utilities and municipalities also provide credit related to
stormwater education, as well as for stormwater systems that are separate from the municipal system, but have
been required to comply with MS4 permitting requirements.
In order to implement a stormwater credit system, it is necessary to develop a well‐defined set of guidelines and
procedures to govern them. The City must define the types of credits they can offer and the specific criteria for
meeting the credit requirements. Some examples of specific criteria that may be necessary to develop are
determining a minimum contiguous area for conservation areas, determining the minimum distance for a buffer
zone, setting a maximum gradient for filters and buffers and determining the maximum amount of fee reduction
for a given credit.
It is also necessary to support the credit program through a permitting process that requires application,
certification and follow‐up inspections to ensure the credit continues to be maintained and valid. Relative to
Section 5 Stormwater and Flood Control Utility
5‐11 106678‐80349‐03‐11.docx
the application process it is necessary to develop the appropriate paperwork and maintain administrative staff
to manage the process. For certification and inspection, the City must also maintain staff that is capable of
evaluating the structural and environmental aspects of stormwater controls. Should the City seek to develop a
stormwater credit program, there are numerous examples and guidelines present to help guide this process.
In Section 3, CDM identified locations in the recommended plan where retail, commercial and industrial
businesses should implement on‐site stormwater BMPs to reduce flows to the drainage system. These
businesses have a significant amount of impervious area and will pay comparatively higher fees; thus, to reduce
their burden, they would benefit from a stormwater credit program such as the one discussed in this section.
5.3 Projected Revenue Requirement The purpose of this section is to project the revenue requirement for the City’s hypothetical stormwater utility.
In general, the revenue requirement is calculated by adding operations and maintenance expenses, existing and
anticipated debt service, cash funded capital expenditures, and netting miscellaneous revenue. Since the
stormwater utility would have no miscellaneous revenue associated with it, the revenue requirement is simply
the total of the allocated O&M expense and debt service on stormwater capital.
The City identified both direct and indirect operating expense items that were applicable to operating the
stormwater system.
5.3.1 General Assumptions
In order to project the stormwater expenses, a set of assumptions were used in this analysis. CDM believes the
assumptions to be reasonable and prudent for the purposes of the analysis. Key assumptions are as follows:
Projections are based on the City’s FY 2011 Revised Budget and FY 2012 Department Request;
Operations and maintenance costs are inflated at 3.0 percent annually. This includes personnel and
overtime expenses;
Energy‐related costs are inflated at 5.0 percent annually;
The entirety of the operating expenses currently covered in the General Fund related to flood control would be allocated to the stormwater utility;
General operations and maintenance expenses currently covered in the General Fund related to storm
drains would be allocated to the stormwater utility. One‐third of the personnel costs would be covered by
the stormwater utility, with the exception of overtime which is split 50/50;
Since no indirect cost allocation currently exists for the stormwater utility, the allocation schedule is
assumed to follow the schedule currently used for the sewer fund. The major exception is indirect costs for
PILOT, which have been excluded from the allocation to the stormwater utility.
Capital outlays are not assumed to be funded as part of the stormwater utility;
The City currently has $250,000 in authorized borrowing not yet spent. It is assumed that this amount will
be bonded as General Obligation (GO) debt for stormwater‐related projects in FY 2012;
The capital projects in the proposed CIP are inflated to the mid‐point of construction, and are assumed to be
financed through GO bonds (i.e. no cash funded capital projects);
Section 5 Stormwater and Flood Control Utility
5‐12 106678‐80349‐03‐11.docx
GO debt is assumed issued at a rate of 5.5 percent with an amortization period of 20 years. Cost of issuance
is assumed to be 1 percent;
Stormwater utility personnel are assumed to have a fully loaded salary, including benefits, of $50,000
annually;
Municipal Separate Storm Sewer System (MS4) permit compliance staff at the stormwater utility are
assumed to have a fully loaded salary, including benefits, of $60,000; and
Rental rates for stormwater utility vehicles have been calculated based on the 10‐year amortization period
for the cost of the vehicle, plus a 10 percent markup for mileage costs.
5.3.2 Operations and Maintenance Expenses
O&M expenses for the Stormwater and Flood Control Utility have been broken into two categories. The first is
incremental O&M costs, which are new costs that will be incurred by the utility to meet MS4 compliance costs.
The second category is the cost allocations presently incurred by the City that are being transferred to the
Stormwater and Flood Control Utility.
5.3.2.1 Incremental O&M
Incremental expenses have been determined based on discussions with the City and best estimates for
stormwater implementation costs. Incremental costs included in the analysis are as shown in Table 5.3.
Monitoring and MS4 compliance staff have been included based on estimates from CDM. Per discussions with
the City, two O&M staff have been included for catch basin cleaning, street sweeping and vactor operations, a
billing clerk has been added to handle additional billing administrative responsibilities and an expense line item
has been added for public outreach. Additional equipment, including a street sweeper, part‐time use of a vactor
truck and a vehicle for catch basin cleaning, have been included to support these O&M activities. A $20,000
increase in energy expenses has also been assumed to support these activities.
Table 5.3
Projected Incremental O&M
2011 2012 2013 2014 2015 2016
Monitoring $100,000 $103,000 $106,090 $109,273 $112,551 $115,927
MS4 Staff $60,000 $61,800 $63,654 $65,564 $67,531 $69,556
O&M Staff $100,000 $103,000 $106,090 $109,273 $112,551 $115,927
O&M Vehicle $2,877 $2,963 $3,052 $3,144 $3,238 $3,335
Vactor Truck $19,927 $20,525 $21,141 $21,775 $22,428 $23,101
Street Sweeper $29,891 $30,788 $31,711 $32,663 $33,643 $34,652
Billing Clerk $50,000 $51,500 $53,045 $54,636 $56,275 $57,964
Public Education $20,000 $20,600 $21,218 $21,855 $22,510 $23,185
Energy Costs $20,000 $20,600 $21,218 $21,855 $22,510 $23,185
Total $402,695 $414,776 $427,219 $440,036 $453,237 $466,834
Section 5 Stormwater and Flood Control Utility
5‐13 106678‐80349‐03‐11.docx
5.3.2.2 Allocated O&M
The stormwater operating expenses have been separated into five categories: Overtime, Flood Control, Storm
Drains Personnel, Storm Drains O&M, and Indirect Costs. The detailed allocation factors from both the General
Fund and the indirect cost schedule are listed in the General Assumptions (Section 5.3.1). It should be noted
that within this allocation are the salaries of key staff members, including engineering, administrative services
and key management personnel.
Table 5.4 summarizes the operating expense allocation for each category, and the total eligible for cost recovery
through the stormwater and flood control fee. These amounts do not include capital outlay. Of total O&M
expenses, incremental expenses account for slightly less than 30 percent of total O&M.
Table 5.4
Stormwater O&M and Capital Outlay by Category, FY 2011 ‐ FY 2016
2011 2012 2013 2014 2015 2016
Existing Budget Allocations
Overtime $23,000 $23,000 $23,690 $24,401 $25,133 $25,887
Flood Control $32,625 $32,625 $33,884 $35,194 $36,559 $37,980
Storm Drains Personnel $109,397 $109,639 $112,928 $116,316 $119,805 $123,399
Storm Drains O&M $54,050 $54,050 $55,672 $57,342 $59,062 $60,834
Indirect Costs $848,465 $933,870 $961,886 $990,743 $1,020,465 $1,051,079
Total Allocated O&M $1,067,537 $1,153,184 $1,188,059 $1,223,995 $1,261,024 $1,299,178
Incremental O&M $402,695 $414,776 $427,219 $440,036 $453,237 $466,834
Total Allocated O&M Expenses $1,470,232 $1,567,960 $1,615,279 $1,664,031 $1,714,261 $1,766,013
5.3.3 Debt Service Expenses
Table 5.5 summarizes the debt service for the Stormwater and Flood Control Utility. The existing debt service is
associated with the $310,000 GO bond issue in FY 2007 related to Ridgewood Terrace Reconstruction, and the
$100,000 GO debt issue in FY 2011 pertaining to drainage projects. The City has $250,000 in authorized
borrowing remaining on the most recent drainage improvement spending, which for the purposes of this
exercise is assumed to be bonded in FY 2012 for general drainage system improvements and included in the
anticipated debt service. Anticipated debt service also includes the proposed CIP, $95.6M in capital spending on
the stormwater system over the next 20 years. For the purposes of these projections, no cash funded capital
projects assumed.
Section 5 Stormwater and Flood Control Utility
5‐14 106678‐80349‐03‐11.docx
Table 5.5
Debt Service
2011 2012 2013 2014 2015 2016
Existing Debt Service $48,340 $54,644 $41,944 $38,684 $37,484 $35,474
Anticipated Debt Service $0 $69,850 $316,548 $789,821 $1,337,643 $2,048,693
Total Annual Debt Service $48,340 $124,494 $358,492 $828,505 $1,375,127 $2,084,167
5.3.4 Revenue Requirement
Table 5.6 shows the anticipated revenue requirement for the Stormwater and Flood Control Utility through FY
2016.
Table 5.6
Revenue Requirement
2011 2012 2013 2014 2015 2016
O&M $1,470,232 $1,567,960 $1,615,279 $1,664,031 $1,714,261 $1,766,013
Existing Debt Service $48,340 $54,644 $41,944 $38,684 $37,484 $35,474
Anticipated Debt Service $0 $69,850 $316,548 $789,821 $1,337,643 $2,048,693
Revenue Requirement $1,518,572 $1,692,454 $1,973,771 $2,492,536 $3,089,388 $3,850,180
Figure 5.1
Revenue Requirement (thousands)
$‐
$500
$1,000
$1,500
$2,000
$2,500
$3,000
$3,500
$4,000
$4,500
2011 2012 2013 2014 2015 2016
O&M Existing Debt Service Anticipated Debt Service
Section 5 Stormwater and Flood Control Utility
5‐15 106678‐80349‐03‐11.docx
5.4 Parcel Analysis and Equivalent Residential Unit Calculation 5.4.1 Impervious Area
In determining a stormwater and flood control fee, it is necessary to separate out impervious area data for the
City by land use characteristics. In undertaking this task, CDM used existing GIS information made available by
Mass GIS to generate a sorted list of impervious area by land use. The intent of this analysis is to understand the
impervious area characteristics in the City and in turn the financial impact of assessing impervious area‐based
stormwater and flood control rates on a permanent basis.
In conducting its analysis, CDM sorted available GIS data into four main categories: Residential,
Commercial/Industrial, Tax Exempt, and Other (which includes categories such as agricultural, forestation and
recreational). The summary of this data is shown in Table 5.7 and displayed graphically in Figure 5.2.
Table 5.7
Total Impervious Area and Parcel Count by Classification
Customer Classification Impervious Area (square feet)
Residential 28,595,854
Commercial/Industrial 21,336,871
Tax Exempt 16,191,191
Other 1,641,422
Total Impervious Area 67,765,338
Section 5 Stormwater and Flood Control Utility
5‐16 106678‐80349‐03‐11.docx
Figure 5.2
Total Impervious Area and Parcel Count by Classification
Section 5 Stormwater and Flood Control Utility
5‐17 106678‐80349‐03‐11.docx
5.4.2 Equivalent Residential Unit Calculation
In order to assess the potential impact of incorporating a stormwater fee with an ERU structure, it was necessary
to determine the impervious area per equivalent residential unit (ERU). The base ERU for this analysis is defined
as the average impervious area per ERU for small residential structures up through three‐family units.
Determining average impervious area per ERU required matching the residential categories within the
Massachusetts Department of Revenue land use codes with estimates on dwelling units. Based on data
provided by the City, Northampton contains 9,600 units defined as either single‐family, two‐family, or three‐
family (Table 5.8). Based on the total number of residential accounts, the average impervious area per unit is
approximately 2,671 square feet for small residential customers.
Table 5.8
Distribution of Dwelling Units, Impervious Area and ERU Calculation
ERU Calculation
Impervious Area (sq. ft. thousands)
Single‐Family1 21,315
Two‐Family 3,551
Three‐Family + 829
Total 25,696
Number of Units (thousands)
Single‐Family1 7.3
Two‐Family 1.8
Three‐Family + 0.5
Total 9.6
Number of Units (thousands)
Total Impervious Area 25,696
Total Units 9.6
Equivalent Residential Unit (sq. ft.) 2,671
1 Includes condominiums and mobile homes
The next step in developing a stormwater fee is to determine the number of ERUs in each of the remaining
customer classes. This includes: commercial/industrial, tax exempt, large residential and other customers. This
data was compiled by totaling the amount of impervious area within each category and dividing it by the
average amount of impervious area per small residential dwelling unit (i.e. the ERU). Table 5.9 below reflects
the calculations determining the dwelling units for the other customer classes.
Section 5 Stormwater and Flood Control Utility
5‐18 106678‐80349‐03‐11.docx
Table 5.9
Number of Billing Units by Customer Classification (Non‐Residential)
Non‐Residential Customers Area Square Feet Impervious
(Total)
Number of Equivalent Residential Units
(thousands)
Commercial/Industrial 21,336,871 8.0
Tax Exempt 16,191,191 6.1
Large Residential3 2,900,131 1.1
Other 1,641,422 0.6
3Large residential is defined as apartments with 4 dwelling units or more.
5.4.3 Estimated Total Billing Units
Adding the large residential and non‐residential equivalent residential units to the number of small residential
units provides a total residential equivalent for billing units. Table 5.10 summarizes the total equivalent
residential billing units by customer type.
Table 5.10
Billing Units by Customer Type
Customer Class Billing units (thousands)
Small Residential 9.6
Large Residential 1.1
Commercial/Industrial 8.0
Tax Exempt 6.1
Other 0.6
Total 25.4
5.5 Calculation of Stormwater and Flood Control Fee This section evaluates the impact of funding the City‘s Stormwater and Flood Control Utility. A stormwater fee
recovers the costs associated with stormwater management, based on the amount of impervious area contained
on each parcel. The fundamental basis for this approach is that there is a direct relationship between impervious
area and stormwater runoff (i.e. the more impervious area there is on a parcel, the greater the amount of runoff
from that parcel). Therefore, the amount a parcel is charged using a stormwater and flood control fee is related
to the quantity of impervious area. A significant benefit of this approach is that it equitably distributes
stormwater costs, in the sense that parcel owners are charged proportionally, relative to their cost imposed on
the system.
Prior to the availability and use of GIS, the ability to maintain a database of parcel and impervious area was
cumbersome and costly. Due to this implementation barrier, the trade‐off of more equitably distributing
stormwater related costs has typically been outweighed by its complexity, even though these costs are closely
Section 5 Stormwater and Flood Control Utility
5‐19 106678‐80349‐03‐11.docx
tied to impervious area. However, with the advent of GIS technology, the process of implementing a
stormwater fee has become significantly less burdensome and is no longer cost prohibitive.
Furthermore, a stormwater and flood control fee provides the benefit of more equitably distributing the costs
associated with stormwater management and flood control. This in turn has a significant benefit, in that by
aligning the means with which stormwater treatment costs are recovered with the characteristics of customers
that create the service requirement, it provides incentive for customers to improve stormwater management
practices.
Having shown the calculations for developing the ERU in the previous section, the following subsections will
provide the basis for the stormwater fee calculation and the financial impact.
Given projected revenue requirements and ERUs, CDM developed a stormwater fee which would be assessed to
customers based on impervious surface area. In order to illustrate the impact of the fee, a set of representative
customer classes has been developed. These customer classes are hypothetical and have been created to
provide means by which the City can measure the impact across customer classes. The representative customer
types examined are as follows:
Single‐family residence;
Two‐family residence;
Three‐family residence;
20‐unit apartment (Large Residential);
Commercial property with 1,000 square feet of impervious area;
Commercial property with 10,000 square feet of impervious area; and
Commercial property with 100,000 square feet of impervious area.
The base rate per ERU is calculated by dividing the annual revenue requirement by the total calculated ERUs of
25,400. The necessary revenue to fully fund the baseline Stormwater and Flood Control Utility shown in Table
5.11 is $1.692 million in FY 2012. Dividing the projected revenue requirement by the total number of ERUs
would yield a rate of $66.63 per ERU for FY 2012.
Table 5.11
Projected Annual ERU Charge
2011 2012 2013 2014 2015 2016
Revenue Requirement $1,518,572 $1,692,454 $1,973,771 $2,492,536 $3,089,388 $3,850,180
Residential Charge per ERU $59.79 $66.63 $77.71 $98.13 $121.63 $151.58
Using the ERU system, parcels with larger amounts of impervious area are charged proportionally higher costs to
offset their cost burden on the system. For example, a commercial customer with 100,000 square feet of
impervious area would be charged approximately $2,495 in order to account for the cost of stormwater that the
parcel contributes to the system. The impact of these rates on the various customer classes is shown in Table
5.12.
Section 5 Stormwater and Flood Control Utility
5‐20 106678‐80349‐03‐11.docx
Table 5.12
Comparison of Impacts for Standard Customer Types, FY 2012
Classification Billing Units ERU Rate per ERU
Single‐Family 1 1.00 $66.63
Two‐Family 2 2.00 $133.26
Three‐Family 3 3.00 $199.90
Classification Impervious
Area ERU Rate per ERU
Large Residential 10,821 4.05 $269.95
Commercial/Industrial with 1,000 square feet of IA 1,000 0.37 $24.95
Commercial/Industrial with 10,000 square feet of IA 10,000 3.74 $249.46
Commercial/Industrial with 100,000 square feet of IA 100,000 37.44 $2,494.58
Table 5.13 summarizes the total revenue expected from general customer classes for FY 2011. It can be seen
that the revenues generated by customer class are directly proportional to the billing units, and in turn the
impervious area of each customer class.
Table 5.13
Expected Revenue per Customer Class, FY 2012
Classification Billing units (thousands) Approximate Revenue
Small Residential 9.6 $639,668
Large Residential 1.1 $73,295
Commercial/Industrial 8 $533,056
Tax Exempt 6.1 $406,456
Other 0.6 $39,979
Total 25.4 $1,692,454
5.6 Recommendations As the City evaluates the option of developing a Stormwater and Flood Control Utility, and as a means for
meeting revenue requirements, it will need to consider not only the impact of its chosen cost recovery
mechanism, but also issues related to equity and behavioral incentives. Relative to the equity of its stormwater
and flood control rate structure, the City should seek to align its cost of serving customers as closely as possible
with the charge assessed to those customers. Using this criterion, a stormwater and flood control fee will
accurately reflect the likely cost burden imposed by individual customers as stormwater runoff is closely tied to
impervious area. Relative to behavioral incentives, a stormwater and flood control fee based on impervious area
creates a price signal for stormwater customers as to the cost associated with stormwater runoff and flood
control. This directly encourages customers and new developers to find ways to minimize stormwater impacts.
Section 5 Stormwater and Flood Control Utility
5‐21 106678‐80349‐03‐11.docx
Should the City choose to move forward with implementing a stormwater and flood control fee, given its current
stormwater‐related costs, anticipated capital costs and the City’s geographic characteristics, we have projected
the City’s current stormwater charge for FY 2012to be $66.63. Given the anticipated growth in the stormwater
charge over time, should the City be interested in mitigating the impact of the stormwater and flood control fee
on customers with high impervious area, it can seek to either maintain a portion of the stormwater costs on
sewer rates or implement a stormwater credit program.