Ceramic Tiles, Terrazzo Tiles and Mosaics MethodStatement
Home Management Template Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement
Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement
This procedure outlines the system of control and inspections to be adopted for the fixing on site of tiles
and mosaics.
PROJECT: PROJECT NAME
Search our site
Join Our Email Listing
keep yourself Updated
Type and hit enter
SECTION:
FINISHING
DATE OF ISSUE
Dec. 2012
SUBJECT: BY:
QA/QC ENGINEER
Ceramic Tiles, Terrazzo Tiles And Mosaics Method Statement APPROVED BY:
QEHS MANAGER
ACTION VERIFY
1. SCOPE
This procedure outlines the system of control and inspections to be
adopted for the fixing on site of tiles and mosaics.
2. PROCEDURE
.1 A method statement shall be prepared and approved. It
shall include:
Project
Manager
Project
Engineer
Store-
Method
Statement
Sample
approval
Instructions
Videos Gallary
Lesson 8 part1 The goldenrule ofestimatingmanpower isthePRODUCTIVITY
Name Email
Sign Me Up!
We hate spam just as much as you
i) Acceptance conditions for laying e.g. maximum moisture
content of substrate, levelness, soundness, cleanliness,
environment.
ii) Surface preparation and bonding e.g. bonding agent,
bed mix proportions, adhesives.
iii) Specific requirements with regard to setting out,
alignment of joints and cutting.
iv) Method of protecting finished work.
v) Source documents for tiles, adhesive
.2 A sample of tiles shall be prepared on the wall in accordance
with the specifications laid down in the contract and approved by the
Consultant.
.3 Storage of tiles:
i) Tiles shall be delivered to site palletised, on a clean
hard surface free from contamination by mud or surface
water.
ii) Ensure that manufacturers instructions in respect of
storage conditions of adhesives are strictly followed.
.4 The Project Director/Manager or his designate will confirm that
materials are in compliance with contract specification requirements.
.5 In the case of internal wall tiling, work will not proceed until all
concealed conduits, pipes, electrical cables and boxes etc. that
penetrate the tiling have been fixed securely in position and making
good is complete. Obtain written clearance from MEP Co-ordinator
that all their works in that area is clear for taking up the tiling work.
keeper
Project
Manager
Project
Engineer
FINI/05/A
FINI/05/A
PROJECT: PROJECT NAME Ref No. FINI/05
Planning Engineer on
YouTube
Recent Questions
and Answers
Usage of MS Excel File
Format Converter to
Convert Lotus WK4
Extesion Type Files to
MS Excel XLS Type
Format
Primavera P6
Professional
Resource Leveling
Question
Estimate manpower
PAGE 2 OF 3
SECTION:
FINISHING
DATE OF ISSUE
Dec. 2012
SUBJECT: BY:
QA/QC ENGINEER
CERAMIC TILES, TERRAZZO TILES AND MOSAICS APPROVED BY:
QEHS MANAGER
ACTION VERIFY
.6 Site operatives must observe the following while fixing tiles in
addition to the specifications laid down in the contract document.
i) In the case of internal wall tiles, the setting out course or
layout course is established.
ii) The level and events of the wall surface should not
exceed the allowable tolerance as specified in the contract.
Any such defect should be rectified before proceeding
further.
iii) While setting out for floor tiling, establish a datum level
for the finished floor and control the overall level of the
finished floor by means of series of spot levels. The Site
Engineer will involve Consultants representative while fixing
levels.
iv) Avoid cutting tiles as far as possible. If cutting cannot
be avoided locate cut tiles where they will be least
Gen.
Foreman
Gen.
Foreman
FINI/05/A
FINI/05/A
requirmnet
Ask what you want here
Concrete
Pavings
Method
Statement
February 14,
2014
Men and
Women
abbreviations
Mr., Mrs.,
Miss and Ms
February 11,
2014
Ceramic
Tiles,
Terrazzo
Tiles and
Mosaics
Method
Statement
February 10,
2014
Download
Planning
noticeable, if in doubt refer to specification.
v) The sequence of fixing tiles shall be as follows unless
specified otherwise in the contract:
Floor tiles from the centre of room
Internal walls Upward from the setting out course up to
the specified height (in case of false ceiling) otherwise
from top and downwards up to starting level.
External walls always from top to bottom covering one
horizontal strip after another but preferably to be done in
bays.
vi) The mortar or adhesive is spread on the surface using a trowel or
blade in thin layers as specified.
vii) Before placing the next tile take care to allow correct
joint width by placing the correct spacers in all corner joints.
viii) Do not start joint grouting work till tiles are properly
fixed to the surface. Normally the time period varies between
24 hrs to 48 hrs.
.7 Protection and Cleaning:
i) Protect external tiling and mosaics from rain and sun
until the bed and joints have set. Continue the protection for
the period specified.
PROJECT: PROJECT NAME Ref No. FINI/05
PAGE 3 OF 3
SECTION:
FINISHING
DATE OF ISSUE
Dec. 2012
Engineers
Preparation
Course for
Free
February 9,
2014
PROJECT
PERFORMANCE
REPORT
February 9, 2014
Batching Of
Concrete
Method
Statement
February 8,
2014
Home Categories Q & A Jobs Chat Paid Services Contact Us
0
0
Share
0
Like
Share
SUBJECT: BY:
QA/QC ENGINEER
CERAMIC TILES, TERRAZZO TILES AND MOSAICS APPROVED BY:
QEHS MANAGER
ACTION VERIFY
ii) Do not allow tiling and mosaics to be wetted in shower
bath areas for the period as specified, until the bedding and
joints have set and hardened.
iii) Do not permit any traffic at all on the flooring till the tiles
are set afterwards permit light foot traffic only.
iv) For general protection spread white no-staining saw
dust over the floor but not earlier than the period during
which grout is hardened.
0
PROJECT: PROJECT NAME SITE NO.:
CERAMIC TILES, TERRAZZO TILES AND MOSAICS Sheet No.
SUBCONTRACTOR: CLIENT
SECTION OF WORK ____________________________LOCATION _________________
STAGE
ITEMChecked
by
DATE
PREPARATION
1. Method statement approved.
PE
2. Materials to specification (including suitability of
adhesive).
SE
3. Check storage condition of materials. SK
4. Establish line and level. SU
5. Check moisture content of substrate. GF
6. Liaise with MEP section for completion of their
works.
PE/MEP
7. Acceptance of substrate
GF
8. Sample area acceptable.
PE
APPROVAL TO PROCEED WITH LAYING
QA/QC
INSTALLATION
9. Check setting-out
SU
10. Check line and level.
SU
11. Check mixing, colour and application of grout.
GF
12. Check sequence of fixing tiles.
SE
APPROVAL TO PROCEED
QA/QC
POST 13. Check initial cleaning of work. GF
INSTALLATION 14. Check protection applied correctly. GF
APPROVAL TO PROCEED
CM
CM Construction Manager, QA/QC Quality Assurance/Quality Control, PE Project Engineer, SE Site
Engineer, SU Surveyor, GF General Foreman, SK Storekeeper
Download Ceramic Tiles, Terrazzo Tiles and Mosaics Method Statement
Word template:Ceramic Tiles, Terrazzo Tiles and Mosaics Method
Statement
Share it now!
0
Share
0
About the author
Hany Ismael is a Civil Engineer BSc, Project Management Professional certified PMP, MSc student at
Liverpool University, involved in construction projects since 11 years, and working as a Planning
Manager. He likes to share Project Management Information and follow the rabid update of Project
Management Tools such as Primavera and Excel. Google
0
LikeShare
February 10, 2014 By Hany Ismael Management Template Leave a comment
ceramic tiles method statement Mosaics terrazzo tiles
Planning
Engineer
Twitter Facebook Google
Comments
Click on a tab to select how you'd like to leave your comment
Men and Women abbreviations Mr., Mrs., Miss and Ms
Download Planning Engineers Preparation Course for Free
Related posts
Concrete Pavings
Method Statement
February 14, 2014
Download
Planning
Engineers
Preparation
Course for Free
February 9, 2014
PROJECT
PERFORMANCE
REPORT
February 9, 2014
Batching Of
Concrete Method
Statement
February 8, 2014
BORED PILING
METHOD
STATEMENT
February 7, 2014
HUMAN
RESOURCE PLAN
February 5, 2014
Courses
Authorized PMP
online training
PMBOK5 Only 110$
Preparation Course for
Planning Engineers
Excel Online Course:
Microsoft Excel for
Engineers
:
Ask Question
Excel
Other
primavera
Project Management
Posts Calendar
February 2014
M T W T F S S
Jan
1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28
Search Our Website
Type and hit enter
PlanningEngineer.Net Project Management Planning Discussions Planning Using Primavera Management Template
Excel in Planning