Upload
dinhnguyet
View
216
Download
2
Embed Size (px)
Citation preview
Cessnock Water SupplyUpgrade
Community workinggroup # 3
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 2
Meeting overview
Agenda
• objectives
• applying the non cost criteria to the proposed sites
• eliminating sites based on the non cost criteria
~ supper served ~
• Hunter Water’s method for applying cost
• applying the cost component to the remaining sites
• way forward - work to be undertaken to reach a preferred site
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 3
Tonight’s objectives
• present the non-financial criteria results
• present the cost application rationale
• identify the shortlisted sites
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 4
Project drivers
• this project is the first of a 4 stage upgrade in response to the2006/07 Department of Planning’s Lower Hunter RegionalStrategy. This report identified specific projected growth aroundCessnock - 21,000 lot connections by 2031.
• objectives of stage 1 aim to:
• improve the current water network by eliminating pressureissues within the area
• address the projected growth in the area
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 5
Applying non cost criteria
• individual site assessments were undertaken with eachproperty owner
• each site was scored against the agreed non cost criteria
• a summary of each site assessment has been captured inthe report provided
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 6
Summary graph of non cost criteria
Sites that score lower than 60 will therefore be discounted.
-
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
We
igh
ted
Sc
ore
(/1
00
%)
Site
1A
Site
1B
Site
2
Site
3A
Site
3B
Site
4
Site
5
Site
6
Site
11
Site
12
Site
13
Site
16
Site
21
Site
22
Site
23
Site
24
Site
25
Site
26
Site
27
Proposed Reservoir Site
Cessnock water supply - stage 1 - reservoir site selection analysis
SOCIAL (40%)
ENVIRONMENTAL (20%)
DESIGN (40%)
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 7
Summary graph of non cost criteria
-
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
Weig
hte
d S
co
re (
/100%
)
Site
1A
Site
1B
Site
2
Site
3A
Site
3B
Site
4
Site
5
Site
6
Site
11
Site
12
Site
13
Site
16
Site
21
Site
22
Site
23
Site
24
Site
25
Site
26
Site
27
Proposed Reservoir Site
Cessnock water supply - stage 1 - reservoir site selection analysis
SOCIAL (40%)
ENVIRONMENTAL (20%)
DESIGN (40%)
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 8
Site 6
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 9
Key findings of short listed sitesSite 3a
•visual impact – 4 propertyowners (500m)•proximity to vineyard -<50m
•access easement -extensive
Disadvantages
•property operations -minimal impact on current andfuture operations
•submerge structure – 4m
•visual impact – > 400m fromroad
•vegetation clearance – Nil
•endangered ecologicalcommunities – no impact.
•lead-in main length -~3.6km
•submerge structure –4mAdvantages
SOCIAL (40%)Good 29.20%
ENVIRONMENTAL (20%)Good 17.00%
DESIGN (40%)Satisfactory 23.60%
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 10
Key findings of short listed sites
Site 3b
•visual impact – < 300m fromroad•proximity to vineyard -<50m
•access easement -extensive
Disadvantages
•property operations -minimal impact on current,potential impact on futureoperations
•submerge structure – 4m
•visual impact – 3 propertyowner (500m)
•vegetation clearance – Nil
•endangered ecologicalcommunities – no impact.
•lead-in main length -~4km
•submerge structure –4mAdvantages
SOCIAL (40%)Satisfactory 22.00%
ENVIRONMENTAL (20%)Good 18.00%
DESIGN (40%)Satisfactory 24.80%
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 11
Key findings of short listed sites
Site 6
•vandalism – high•endangered ecologicalcommunities – extensive
•vegetation clearance –extensive
•access easement -extensive•lead-in main length -~7.1kmDisadvantages
•property operations – noimpact
•submerge structure – 4m
•visual impact – no impact
•submerge structure –4m
Advantages
SOCIAL (40%)Good 38.12%
ENVIRONMENTAL (20%)Poor 6.00%
DESIGN (40%)Poor 19.20%
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 12
Key findings of short listed sites
Site 21
•proximity to vineyard -<50m
access easement -extensiveDisadvantages
•property operations -minimal impact on current,potential impact on futureoperations
•submerge structure – 4m
•visual impact – 0 propertyowner (500m)•visual impact – > 400m fromroad
•vegetation clearance – Nil
•endangered ecologicalcommunities – minimalimpact.
•lead-in main length -~4.8km
•submerge structure –4m
Advantages
SOCIAL (40%)Good 30.88%
ENVIRONMENTAL (20%)Satisfactory 13.60%
DESIGN (40%)Satisfactory 22.00%
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 13
Key findings of short listed sitesSite 22
•vegetation clearance –extensive
•endangered ecologicalcommunities – extensive.
lead-in main length -~5.7km•access easement -extensiveDisadvantages
•property operations – noimpact on current or futureoperations
•visual impact – existingvegetation conceals
•visual impact – 4 propertyowner (500m) - partial
•submerge structure –4m
Advantages
SOCIAL (40%)Good 31.08%
ENVIRONMENTAL (20%)Poor 7.00%
DESIGN (40%)Good 28.80%
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 14
Key findings of short listed sites
Site 24
•proximity to vineyard -<50m
lead-in main length -~6.4km•access easement -extensive
Disadvantages
•property operations -minimal impact on current,potential impact on futureoperations
•submerge structure – 4m
•visual impact – 1 propertyowner (500m)•visual impact – > 400m fromroad
•vegetation clearance – Nil
•endangered ecologicalcommunities – minimalimpact.
•submerge structure –4m
Advantages
SOCIAL (40%)Good 34.40%
ENVIRONMENTAL (20%)Satisfactory 12.40%
DESIGN (40%)Poor 18.40%
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 15
Key findings of short listed sitesSite 26
•vandalism – high•endangered ecologicalcommunities – extensive•vegetation clearance –extensive
•access easement -extensive•lead-in main length -~5.7km•Potential minesubsidence
Disadvantages
•property operations – noimpact
•visual impact – no impact
•submerge structure –4mAdvantages
SOCIAL (40%)Good 37.00%
ENVIRONMENTAL (20%)Poor 7.00%
DESIGN (40%)Satisfactory 27.20%
Break
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 17
Applying cost to each site
• cost is important in determiningthe feasibility of each site.
• Hunter Water has undertakenpreliminary costing on thecapital construction cost.
• costing around land value andcompensation is yet to bedetermined.
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 18
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000
Co
st
($)
Sit
e 1
A
Sit
e 1
B
Sit
e 2
Sit
e 3
A
Sit
e 3
B
Sit
e 4
Sit
e 5
Sit
e 6
Sit
e 1
1
Sit
e 1
2
Sit
e 1
3
Sit
e 1
6
Sit
e 2
1
Sit
e 2
2
Sit
e 2
3
Sit
e 2
4
Sit
e 2
5
Sit
e 2
6
Sit
e 2
7
S ite Options
Reservoir Sites - preliminary cost estimates
Capital construction cost ($)
Summary graph of costing
$6.0M budget limit
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 19
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
$9,000,000C
ost
($)
Sit
e 1
A
Sit
e 1
B
Sit
e 2
Sit
e 3
A
Sit
e 3
B
Sit
e 4
Sit
e 5
Sit
e 6
Sit
e 1
1
Sit
e 1
2
Sit
e 1
3
Sit
e 1
6
Sit
e 2
1
Sit
e 2
2
Sit
e 2
3
Sit
e 2
4
Sit
e 2
5
Sit
e 2
6
Sit
e 2
7
S ite Options
Reservoir Sites - preliminary cost estimates
Capital construction cost ($)
Cost impact on shortlisted sites
$6.0M budget limit
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 20
• sites 6 and 22 have been eliminated once the cost filter was applied.
• sites remaining have been ranked in order of cost:
1. Site 3a2. Site 3b3. Site 214. Site 245. Site 26
• further work (geotechnical, visual impact study, environmental assessment) will beundertaken on sites 3a, 3b, 21
• Hunter Water will pursue sites 24 and 26 in the event sites 3a, 3b and 21 are deemedunfeasible
Short listed sites
Cessnock Water Supply Upgrade Community Working Group # 3
December 2009 21
Way forward - reaching a preferred site
• further negotiations with short listed property owners will take place - landvalue and compensation will be determined.
• consultation with adjacent property owners will be undertaken
• Preliminary engineering design, geotechnical and environmentalassessments to be undertaken
• visualisation impact studies will be undertaken
• next CWG meeting # 4 – late March 2010 (date TBC)
• meeting minutes:– draft distributed by Thursday 10 December 2009– return comments by Thursday 17 December 2009
• are these dates okay?
Thank you