Citizens Charter No. 06
Name of Office : ENVIRONMENTAL IMPACT ASSESSMENT MGT. SECTION – CLEARANCE AND PERMITTING DIVISION
ENVIRONMENTAL MANAGEMENT BUREAU 5
Frontline Service : ISSUANCE OF ENVIRONMENTAL COMPLIANCE CERTIFICATE (ECC) – EPRMP
Schedule of Availability of Service : 8:00 AM – 5:00 PM, MONDAY – FRIDAY
Who may Avail of the Service : PROPONENTS OF PROJECTS THAT SIGNIFICANTLY AFFECTS THE QUALITY OF THE ENVIRONMENT
How to Avail of the Service : MANUAL APPLICATION TO EMB V REGIONAL OFFICE
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
1
Inquire for the ECC
Application
(For existing/expansion)
Provide the checklist of requirements
and the outline of report to be
submitted (EPRMP)
Myla M. Gueta Divine R. Seming
Engineer III EMS II
Ralph O. Chavez Aaron Buena-Agua
EMS I EMS I
1 hour
- Environmental Performance
Report and Management Plan
(EPRMP) outline
- Letter of application
- Zoning certification/ Area
clearance/ Locational
clearance (MPDC/ MGB/
HLURB)
- Certified photocopy of TCT/
OCT/ TD (proof of
ownership)
- Vicinity and/or Location map/
Topographic map
- Plans and details of project
installation
- Certification from concerned
LGU’s (Brgy. Capt. And
Mayor)
- Pofile/ Bio-data of the
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
EPRMP Preparer
- Accountability statement of
project Proponent and
Preparer
- ECA Certification from
CENRO
- PEMAPS
- Geographical Coordinates
(all documents in three sets)
2
Submission of
ECC requirements
Evaluation of submitted report and
other requirements
(If incomplete, return the application to
the client)
(If complete, prepare Revenue
Monitoring Form)
Myla M. Gueta Divine R. Seming
Engineer III EMS II
Ralph O. Chavez Aaron Buena-Agua
EMS I EMS I
2 hours
Procedural Screening
Fee : 300.00
Database Mgt. Fee
: 1,000.00
Processing Fee
: 1,700.00
PhP 3,000.00
===========
Processing Fee : 1,700.00
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
3
Pay for the appropriate
amount to the cashier.
Copy the OR # and date paid to the
attached checklist of requirements.
(Let the client forward the application to
the Records Section)
Myla M. Gueta Divine R. Seming
Engineer III EMS II
Ralph O. Chavez Aaron Buena-Agua
EMS I EMS I
1 hour
Revenue Monitoring Form/
Order of Payment
4
The client will submit
the application to the
Records Section.
Receive and record application and
forward to Clearance and Permitting
Division Receiving Clerk
Ma. Anna Habana
Records Officer
15 Minutes
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
5
Received and Record documents and
forward to Chief, CPD
Mary Anne F. Caceres
Admin Aide
15 Minutes
6
Endorse to Chief, EIAMS for
assessment.
Henry A. Lopez
C, CPD
10 Minutes
7
Assess and Forward to EIAMS Staff
for substantive review
Anthony I. Viñas
C, EIAMS
15 Minutes
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
8
Initial substantive review of the
submitted ECC application and
endorsed to PEMU for site verification
Myla M. Gueta Divine R. Seming
Engineer III EMS II
Ralph O. Chavez Aaron Buena-Agua
EMS I EMS I
2 days
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
9
Conduct site verification, prepares
report and forwards site verification
report to CPD
PEMU
Rey A. Monreal Nanette A. Tidon
Albay Sorsogon
Lilian D. Ornido Jasmin V. Rieza
Camarines Sur Camarines Norte
Ma. Joana Salazar Goldwyn Ceasario
Deleon
Catanduanes Masbate
5 days
Site Verification Report
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
10
(If there’s no adverse findings, the case
handler prepares the Environmental
Compliance Certificate for approval)
(If found with derogatory findings, the
case handler prepares a Letter Directive
and impose penalty if there’s any.)
Myla M. Gueta Divine R. Seming
Engineer III EMS II
Ralph O. Chavez Aaron Buena-Agua
EMS I EMS I
1 hour
3 days
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
11
The client receives and
comply the requirements
stipulated in the issued
Letter Directive.
The case handler verifies the
correctness/ completeness of the
compliance and prepares ECC.
Myla M. Gueta Divine R. Seming
Engineer III EMS II
Ralph O. Chavez Aaron Buena-Agua
EMS I EMS I
4 days
Compliance to the Letter
Directive
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
12
Final Substantive review of the
application and affix initial to
Environmental Compliance Certificate
(ECC) and forward to Chief, CPD for
recommendation.
Anthony I. Viñas
C, EIAMS
4 days
ECC
13
Recommends approval/denial of the
Environmental Compliance Certificate
Henry A. Lopez
C, CPD
5 days
ECC
14
Review recommended action and
forward to the Regional Director for
approval/denial/revision.
Charito V. Milañez
Sr. EMS/HEA
2 days
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
15
Approves/denies Environmental
Compliance Certificate (ECC)
EVA S. OCFEMIA,
PhD, CESO IV
Regional Director
5 days
ECC
16
ORD staff forwards to CPD Clerk the
approved ECC/denial letter
Charito V. Milañez
Sr. EMS
10 Minutes
17
ORD staff forwards to CPD Clerk the
approved ECC/denial letter
Kriztyll Kaye N. Bermeo
ORD Staff
10 Minutes
No. CLIENT ACTIVITY EMB ACTION OFFICE/ PERSON RESPONSIBLE/
LOCATION
DURATION
(Max. of 30
working days)
DOCUMENTARY
REQUIREMENTS
AMOUNT OF FEES
(G)
[A] [B] [C] [D] [E] [F]
18
CPD Clerk records and forwards the
approved ECC/denial letter to case
handler for recording/data base.
Mary Anne F. Caceres
Admin Aide
10 Minutes
19
If denied, the application will be
returned to the client together with a
denial letter.
If approved, the client shall be notified
on the approved ECC, required to have
the ECC notarized, discuss the
conditions stipulated in the approved
ECC and released the ECC.
Myla M. Gueta Divine R. Seming
Engineer III EMS II
Ralph O. Chavez Aaron Buena-Agua
EMS I EMS I
1 day
Approved ECC