City of Waverly Capital Project Sheet Project Title: 1st Street SW & Trail Project Description: From West Bremer Avenue to 7th Avenue S.W. including Trail in South Riverside Park from 7th Avenue S.W. to Fire Station area. Projected Construction Year: 2005 - 2006 Total Project Cost: $524,000 PROJECT FINANCING Cash on Hand: Intergovernmental: $175,000 Transfers In: Interest: GO Bonds: $249,000 S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT $100,000 L.O.S.T. Cash T.I.F. Cash TOTAL SOURCES: $524,000 Yes No Funding for this project impacts debt capacity. X Funding for this project impacts property tax levy. H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 1st Street SW & Trail

Project Description: From West Bremer Avenue to 7th Avenue S.W. including Trail in South Riverside Park from 7th Avenue S.W. to Fire Station area.

Projected Construction Year: 2005 - 2006

Total Project Cost: $524,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: $175,000Transfers In:Interest: GO Bonds: $249,000S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT $100,000L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $524,000

Yes No

Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 2: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: Water Main 10th Avenue Loop

Project Description: Installation of water main from near Waverly Light & Power's load station to near 4th Street SW. Project included some sewer main on 10th Ave. SW and water main crossing of 4th St. SW near 29th Ave. SW

Projected Construction Year: $212,000

Total Project Cost: $212,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $212,000

$212,000

Yes No

Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 3: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: LEC Center

Project Description: Reconstruction of Bremer-Waverly Law Enforcement Center

Projected Construction Year: 2004 - 2005

Total Project Cost: $1,150,607

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $1,150,607

Yes No

Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$1,150,607

Page 4: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: WPC Plant / Sanitary Sewer (3 years)

Project Description: Project involves the replacement of the screening mechanism at at the main lift station, pipe digester gas to a new replacement boiler system and perform other misc. work to upgrade sludge pump controls and improve external digester piping.

Projected Construction Year: 2005 - 2006

Total Project Cost: $250,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $250,000

Yes No

X Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$250,000

Page 5: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: WPC Plant / Sanitary Sewer (3 years)

Project Description: Replace the secondary digester covers.

Projected Construction Year: 2006 - 2007

Total Project Cost: $250,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In: $250,000

Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $250,000

Yes No

Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 6: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: WPC Plant / Sanitary Sewer (3 years)

Project Description: To be determined after facility plan is updated.

Projected Construction Year: 2008 - 2009

Total Project Cost: $250,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In: $250,000

Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $250,000

Yes No

X Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 7: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 1st Street NW & Bremer Intersection

Project Description: Reconstruction of northwest corner of intersection.

Projected Construction Year: 2006 - 2007

Total Project Cost: $75,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash $75,000

TOTAL SOURCES: $75,000

Yes No

X Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 8: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 39th Street SE Reconstruction

Project Description: Rebuilding the 39th St. SE roadway as an urbancurb-and-gutter sectionpast the residentially developed areas and as a rural-ditched roadway through the agricultural sections.

Projected Construction Year: 2005 - 2006

Total Project Cost: $432,342

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $432,342

$432,342

Yes No

Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 9: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 1st Avenue SE Parking Lot

Project Description: The reconstruction of the municipal parking lot in the north half of the block between 2nd and 3rd St. NE, south of 1st Ave. NE.

Projected Construction Year: 2005 - 2006

Total Project Cost: $204,635

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $204,635

Yes No

Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$204,635

Page 10: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: Sanitary Sewer Extension (Copper Ridge Phase 2)

Project Description: The construction of 1,000 feet of sanitary sewer main to primarily service the Copper Ridge Second Addition.

Projected Construction Year: 2005 - 2006

Total Project Cost: $75,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In: $75,000

Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $75,000

Yes No

x Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 11: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: Kohlmann Park

Project Description: New fountain and new play equipment.

Projected Construction Year: 2005 - 2006

Total Project Cost: $253,763

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $253,763

$253,763

Yes No

X Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 12: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: Public Services Facilities Improvements

Project Description: Construction of a new Public Services Facility.

Projected Construction Year: 2007 - 2008

Total Project Cost: $1,000,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $1,000,000

Yes No

X Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$1,000,000

Page 13: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: Fire Station Improvements / Ladder Truck

Project Description: Construction of new fire station and fire museum and purchase of new ladder truck.

Projected Construction Year: 2006 - 2007

Total Project Cost: $4,040,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

$4,040,000

TOTAL SOURCES: $4,040,000

Yes No

Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 14: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 1st Avenue NE Parking Lot

Project Description: Reconstruction of parking lot located nearMauer Eye Center.

Projected Construction Year: 2006 - 2007

Total Project Cost: $200,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash $200,000

TOTAL SOURCES: $0

Yes No

Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 15: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: SE Waterloop River Crossing

Project Description: Looping the water main in SE Waverly

Projected Construction Year: 2008 - 2009

Total Project Cost: $750,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $750,000

$750,000

Yes No

X Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 16: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 9th Avenue NW

Project Description: Reconstruction of 9th Avenue NW

Projected Construction Year: 2006 - 2007

Total Project Cost: $250,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $250,000

$150,000

$100,000

Yes No

Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 17: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 4th Avenue & 11th Street SW Reconstruction - 2007

Project Description: The reconstruction of 4th Ave. SW from 16th St. SW to 11th St. SW and the reconstruction of 11th St. SW from 4th Ave. SW to 2nd Ave. SW

Projected Construction Year: 2007 - 2008

Total Project Cost: $400,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $400,000

Yes No

X Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$100,000

$300,000

Page 18: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 5th Avenue SW - (4th to 8th)

Project Description: The reconstruction of 5th Ave. SW from 4th St. SW to 8th St. SW

Projected Construction Year: 2008 - 2009

Total Project Cost: $250,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $250,000

$100,000

$150,000

Yes No

X Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 19: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 5th Street NW (Bremer to 5th Avenue)

Project Description: The reconstruction of 5th St. NW from West Bremer Ave. to 5th Ave. NW

Projected Construction Year: 2009 - 2010

Total Project Cost: $275,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. Cash

$175,000T.I.F. Cash

TOTAL SOURCES: $275,000

Yes No

Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$100,000

Page 20: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 2nd Avenue SW

Project Description: The reconstruction of 2nd Ave. SW from the railroad track to 16th St. SW.

Projected Construction Year: 2010 - 2011

Total Project Cost: $300,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. Cash

$200,000T.I.F. Cash

TOTAL SOURCES: $300,000

Yes No

Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$100,000

Page 21: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of Waverly

Capital Project Sheet

Project Title: 218 Business from Burger King to Dairy Queen

Project Description: The reconstruction of 4th St. SW from 8th Ave. SW to West Bremer Ave.

Projected Construction Year: 2009 - 2010

Total Project Cost: $2,000,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $2,000,000

$1,000,000

$1,000,000

Yes No

Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 22: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 218 Business - Hy-Vee to Wal-Mart Area

Project Description: The widening and dividing of 4th St. SW from 13th Ave. SW to the entrance of Waverly Tire.

Projected Construction Year: 2008 - 2009

Total Project Cost: $4,000,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds:L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $4,000,000

$2,000,000

$2,000,000

Yes

X

X

No

Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 23: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: Wartburg / Waverly Sports And Wellness Center

Project Description: Construction of indoor wellness center.

Projected Construction Year: 2007 - 2008

Total Project Cost: $6,000,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $6,000,000

Yes No

Funding for this project impacts debt capacity.

X Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$3,200,000

$2,800,000

Page 24: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: Cedar Lane Reconstruction - South Leg

Project Description: The reconstruction of Cedar Lane from 2nd Ave. NE to Brown Lane.

Projected Construction Year: 2008 - 2009

Total Project Cost: $300,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $300,000

$300,000

Yes No

Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 25: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: Dry Run Sanitary Sewer Interceptor

Project Description: The construction of sanitary sewer main within the Dry Run. The limits to be determined by the Sanitary Sewer Capacity Analysis Study.

Projected Construction Year: 2008 - 2009

Total Project Cost: $2,000,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: $2,000,000

L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $2,000,000

Yes

Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

Page 26: City of Waverly Capital Project Sheetagendas.waverlyia.com/documents/public/City Council...City of Waverly Capital Project Sheet Project Title: WPC Plant / Sanitary Sewer (3 years)

City of WaverlyCapital Project Sheet

Project Title: 10th Avenue E: 4th St. SW to 8th St. SE

Project Description: The extension fo 10th Ave. from 4th St. SW to 8th St. SE.

Projected Construction Year: 2008 - 2009

Total Project Cost: $2,000,000

PROJECT FINANCING

Cash on Hand:

Intergovernmental: Transfers In:Interest: GO Bonds: S/A Bonds: Revenue Bonds: L.O.S.T. Bonds: RUT L.O.S.T. CashT.I.F. Cash

TOTAL SOURCES: $2,000,000

Yes No

X Funding for this project impacts debt capacity.

Funding for this project impacts property tax levy.

H:\Capital Improvement Plan\2006 Capital Improvement Plan.xls

$2,000,000