32
PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 1 CMS Module Testing Issues Perspective from a large scale production project Anthony Affolder (for the UCSB module testing group)

CMS Module Testing Issues

Embed Size (px)

DESCRIPTION

CMS Module Testing Issues. Perspective from a large scale production project Anthony Affolder (for the UCSB module testing group). Talk Overview. Review current CMS testing procedures Assorted observations from limited testing experience on CMS components - PowerPoint PPT Presentation

Citation preview

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 1

CMS Module Testing Issues

Perspective from a large

scale production project

Anthony Affolder

(for the UCSB module testing group)

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 2

Talk Overview• Review current CMS testing procedures • Assorted observations from limited testing

experience on CMS components• Outline UCSB module testing program

Personnel, equipment, and infrastructure

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 3

CMS Testing Overview• Review current CMS testing procedures

Ensure understanding of testing prior to arrival at FNAL/UCSB– Reproduction of hybrid tests on arrival

Make sure any systematic failures in production techniques/materials found as early as possible

– M800 pre-production first chance to produce large quantities (>20) of single type of modules

– Need to be able to track time development of faults

• Answer open questions before full scale production Need of burn-in of hybrid/optical systems components Finalization of production procedure Finalization of testing procedure

– Both fault finding and module qualification

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 4

Tests Prior to Arrival at FNAL/UCSB

• APV Chip Testing (1 minute) Voltage stressing (6 sec) Basic Functionality

– Pedestal

– Calibration Injection (2 MIP)

– Pipeline

• FHIT-Industrial Testing (1 minute) Connectivity Basic Functionality

– Pedestal

– Calibration Injection (2 MIP)

– Noise

• Strasbourg ?????

• CERN-Pitch adaptor bonding (20 minutes) Basic functionality

– Pedestal

– Noise

– Calibration Injection (2 MIP) Capacitive pulsing pitch adaptor Thermal cycle to –20 C

– Repeat test Warm to room temperature

– Repeat test

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 5

Testing Concerns• Hybrids tested only ~1-20 minutes

Concern about infant mortality problems

• Hybrids not completely characterized Calibration circuit only tested at one injection point Pipeline pedestal/noise not thoroughly measured

• Requirements not consistent between sites Pedestal cuts changes between test stands On-chip common mode subtraction “feature” makes noise

characteristics of open/saturated channels unpredictable

• We are attending CMS tracking week to address issues Motivate requirements on fault finding/performance issues Continuation of bringing CDF/D0 production experience to

CMS

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 6

Test System Grounding Issues

• PC, DAQ/ARC, LV supplies, and HV supply share common ground Leads to less than predictable results

• Suggest that a common-mode noise standard made With on-chip common mode subtraction removed (inverter off) Allows for more uniform testing results

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 7

Lower Noise Requirements

Sensor-Sensor Open Visible

Improving grounding until common mode noise less than ~0.5 ADC in peak mode/ inverter off allows the use of raw noise as a powerful tool for finding opens, including the location

•Sensor-Sensor•Pitch Adaptor-Sensor•APV-Pitch Adaptor (???)

Seen by Charge Injection

TOB Module 83

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 8

Upper Noise Requirements

• High noise only affects signal efficiency (clustering)

• Use physics (radioactive sources/collision data) to determine cut value Expect values to be different

for different systems

SVX

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 9

Gain Measurement• Multi-point gain measurements

have many advantages More stable More uniformity between chips

– Tighter Cuts

Shows non-linearities Shows non-uniformities

within chip

Gain Scan (0.5-3.0 MIP)

(2 MIP injected)/2

TOB Module 83

TOB Hybrid

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 10

Noise Chip Edge Wings

Increase in noise at chip edges But only in a few pipeline cells pipeline scan=latency scan

Deadtimeless effect!! Fairly easy to reduce/avoid

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 11

UCSB Short-term Testing Plan

• Characterize hybrid (+PA) on arrival Basic functionality, gain scan, and deep test (ARC)

• Re-characterize module on completion of construction Basic functionality, gain scan, deep test, and IV curves

(ARC)

• Vienna cold box test fraction of modules (DAQ) Acts as ~24 hour module burn-in

– Identifies mechanical/bond/electrical weaknesses prior to production of large number of modules

– Reduces reworking of rod/retrofitting of modules

• Rod assembly/characterization/burn-in (when parts and test setups available)

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 12

Testing personnel at UCSB• Professors

Joe Incandela Claudio Campagnari David Stuart

• Post-docs Anthony Affolder Patrick Gartung (UC-Riverside)

• Graduate Students Steve Levy Shawn Stromburg +1-2 starting this summer

• Electrical Engineering Support Sam Burke

• ESE Master Student Anuroop Gupta

(Database/programming)

• + Assorted Undergraduates and Techs (during full production)

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 13

Current UCSB Testing Setup

• Clamshell(UCSB) Plastic stand-offs

– 2 Locating Pins

Kapton Extension Cables(UCSB)

– Easy connection/disconnection

Solid mounting of DAQ equipment

• 1 ARC Controller + 1 ARC FE• LV & HV Power Supplies• Dry Air• Clamshell

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 14

Testing Facilities

• High Bay (Ground floor) Rod assembly/burn-in Convenient access to loading

dock

• Clean Room (5th floor Physics) Adjacent to production area Module tests

– Fault finding and deep tests Module burn-in station Visual inspection table

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 15

Safety Protocols• LV

OVP,OCP

• HV Crowbar Protection

• Electrostatic Protection Ground mats on tables and

floors Heel straps Combo tester at clean room

entrance Touch tester at each station

(Artist Rendition)

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 16

Testing Conclusions• Slight modification of testing program would lead to

more uniform and consistent fault finding between different sites/systems Reduce rework performed on completed rods

• Location of opens can be identified by combination of noise and internal calibration measurements Useful for rod burn-in fault finding

• Increase in noise at chip edges likely deadtimeless effect We are willing to study more thoroughly

• We have the manpower and the experience necessary to aid in development of the testing program while performing module quality assurance measurements

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 17

Backup Slides• EVERYTHING AFTER THIS IS BACKUP

SLIDES

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 18

Possible Rod Burn-in Issues • LED systems may be necessary for discovery of

“high current” pinholes and location of opens In current rod burn-in plan, no LED systems available Would necessitate new techniques to locate “high

current” pinholes and opens– New sensor qualification tests, backplane pulsing, lower

common mode noise, etc.

• Burn-in at module stage provides important information on this issue LED tests still available Until rod components arrive this is not an issue

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 19

Example of DAQ/ARC Differences

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 20

On-chip common mode subtraction

• Inverters share common point Current flows between channels

• Regular channel noise: 2raw

2-cm2

• Opens/saturated channel noise: 2raw

2+cm2

• Depending on cm, open channel have higher/lower noise

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 21

Deadtimeless Scan (ISL)• Issue two triggers with varying

time separation Pattern of commands should

include complete set of commands, measurements, resets, etc.

Measure pedestal and noise at each unit of trigger separation

• With ISL, every command, chip change of state, and data readout caused pedestal shifts Would guess similar effect

causing wing– May also be related to PC

controller

• Removed with DPS at CDF

(Time Between Triggers)

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 22

Calibration Injection Test• Enhance pulse shape information with gain measurement

Measure pulse heights at 6-13 calibration injection setting between 0-3 MIPs using internal calibration and fit

Require gain between Glow and Ghigh

– Gain uniformity specification???

Require 2<2cut (2 based on noise measurement and knowledge

of calibration circuit)– Finds non-linear charge response and gain non-uniformities within

chip

• Relatively simple to include in ARC software

• Only moderately increases testing time

• Calibration is fairly sensitive to environment/grounding

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 23

Test System Grounding Issues (1)Module Testing Final PS System

PC

LV -5V

-5V

ARC Controller

HV+HV

Sensor

Hybrid

ARC FE

2.5V

1.25

V

GROUND LOOPS!!!

GROUND LOOPS!!!

LV

HV+HV

Sensor

Hybrid

HVGND

GND+1.25V+2.5V

DOH

AOH

Command And Data CableOptical Cables

Patc

h Pa

nel/

Inte

rcon

nect

Bus

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 24

CDF Module Burn-in Experience

• Significant number of pinholes created during burn-in (even after 5 hours running) L1- 0.166% of strips L3- 0.052% of strips L4- 0.033% of strips ISL-0.0071% of strips

• 7 additional pinholes created during data-taken L7 burnt-in at depletion voltage

– All others burnt-in with over-voltage

• Early module burn-in in CMS will indicate pinhole creation rate and effect on rod rework rate

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 25

Noise Measurements• Lower noise requirements optimized to detect faults in production

Very loose low noise requirement at hybrid level– Noise only changes from ~0.6~0.4 for completely dead pre-amplifier

– 20% requirement will fail good channels Hybrid at UCSB tests better with shaper current set to zero

Tighter low noise requirements at module/rod level– Can identify open types/location

Sensor-Sensor:~1.2 ADC

PA-Sensor: ~0.7 ADC

Chip-PA:~0.5 ADC

• Upper Noise requirement set by effect on signal efficiency Noise sets channel’s thresholds in clustering Effect is module type dependent

– Larger signal and wide pitch minimizes effect on noise on TOB Determine by source/cosmic testing

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 26

Pedestal Tests (Current)• Wafer Probing

Average Pedestal: 67.1– 50 <P < 90 ADC Cut

• FHIT (Industrial Tester) Average Pedestal:~90

– ±20% Cut:~72<P<108

• ARC Average Pedestal:~110

– ±20% Cut:~88<P<132

• DAQ Average Pedestal:~170

– ±20% Cut:~146<P<194-40 -30 -20 -10 0 10 20 30 40

DAQ

ARC

FHIT

WaferProbing

Pedestal Difference Cut (ADC)Pedestal Requirement vary by as much as 70%

•Try to develop common test based on detector performance•Different requirements for different sub-detectors

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 27

Hybrid Gain Measurement(1)

• Hybrid Tests on steel plate Large pickup effects cause large 2 when 0 MIP point included 2 fairly good when excluding zero

– Noise of calibration circuit not yet included

0-3 MIPs 0.5-3 MIPs

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 28

Bias Ring Voltage

Voltage conversion assumes old resistor values in bias return circuit (22K,100

With new resistor values (2.2K, 681need ~120 A for regular pinholes need >300 mA for “high current” pinholes

New Leakage Current (A) Necessary With New Resistor Values

LED Pinhole Tests

May cause damage to sensors!!!

(Torsten Franke)

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 29

Gain Measurements (2)

Zero point offset

Low gain

High gain

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 30

R(22 kO)

• LED pinhole test characteristics will change with bias return line modification

Resistance on hybrid (22k,100)(2.2k,683)

LED Pinhole Test

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 31

Test model(1)• Add hybrid qualification prior to pitch adaptor bonding

Thorough understanding of hybrids by adding more pipeline and gain measurements

• Make requirements/calculation algorithms consistent through testing process Wafer Probing FHITStrasburg Pitch Adaptor Bonding Module

Construction Rod Construction/burn-in– Allows for the reproduction of bad channel lists

– Eases tracking of fault creation

• Motivate requirements for fault finding and on silicon tracker performance Noise Occupancy Signal Efficiency Signal Resolution

PMG Jan. 24 2002 CMS Module Testing Issues-Anthony Affolder Slide 32

Test model(2)• Improve system’s noise in order to use as powerful tool

Identification of location of opens

• Modify deep tests Suggest different bad channel cuts specific to component type tested Remove all percentage requirements (relative to average) Replace with fixed requirements

• Use cooling box as module burn-in until shown unnecessary Reduces reworking during rod assembly Adds important information about necessity of LED tests for the finding of

some pinholes and opens locations Demonstrates if hybrid burn-in necessary