CMS Tracker Week, CERN, 24-28 Oct 2005
26 Oct 2005CMS Tracker Week - Module ProductionSalvatore Costa - Catania
Report from
Module BondingWorking Group
Salvatore CostaUniversità di Catania and INFN – Sezione di Catania
26 Oct 2005CMS Tracker Week - Module Production 2 Salvatore Costa - Catania
Outline
1. Pull Test results
2. Open issues
3. Some peculiar failures
CMS Tracker Week, CERN, 24-28 Oct 2005
26 Oct 2005CMS Tracker Week - Module ProductionSalvatore Costa - Catania
Global review of Module bonding quality
that is,
Module Pull Test results
26 Oct 2005CMS Tracker Week - Module Production 4 Salvatore Costa - Catania
# Modules Pull Tested
26 Oct 2005CMS Tracker Week - Module Production 5 Salvatore Costa - Catania
Mean pull forces
26 Oct 2005CMS Tracker Week - Module Production 6 Salvatore Costa - Catania
Mean pull forces
26 Oct 2005CMS Tracker Week - Module Production 7 Salvatore Costa - Catania
StDev/Mean of pull forces
26 Oct 2005CMS Tracker Week - Module Production 8 Salvatore Costa - Catania
StDev/Mean of pull forces
CMS Tracker Week, CERN, 24-28 Oct 2005
26 Oct 2005CMS Tracker Week - Module ProductionSalvatore Costa - Catania
Open issues
CMS Tracker Week, CERN, 24-28 Oct 2005
26 Oct 2005CMS Tracker Week - Module ProductionSalvatore Costa - Catania
TEC Backplane HV Connection
A Bonding and Gantry joined operation
1. Review of established practices in EU and US
2. Preparation for it in Italy
26 Oct 2005CMS Tracker Week - Module Production 11 Salvatore Costa - Catania
TEC Backplane HV Connection
• New DB Interface with new section
– v. 6.0– v. 6.0_US
26 Oct 2005CMS Tracker Week - Module Production 12 Salvatore Costa - Catania
HV Connection typesConnection type inventory:1. Conductive Glue dots between gold pad and Sensor (at Gantry)2. Conductive Glue reinforcement over gold pad and Sensor (normally at
Gantry, occasionally at Bonding)3. Bonds without encapsulation (at Bonding)4. Bonds with encapsulation (at Bonding)
Current established practice:• EU: 1 + 2 + 3• US: 1 + 4 [existing TOB modules retrofitted]
Reason for reinforcement (EU) or encapsulation (US): Bonds on back are considered at higher risk of being damaged when
modules mounted on rods or petals because people’s attention is focused on front and the back may get neglected.
Slide 13Susanne KyreTracker week, October 2005
Material and Preparation• Sylgard 186 Silicone
Elastomer, 2 part kit, 10:1 mixing ratio (manufacturer: Dow-Corning)
• Mixing cups
• Mixing sticks
• Digital bench scale
• Small vacuum chamber or centrifuge for degassing
Slide 14Susanne KyreTracker week, October 2005
Dispensing Equipment• Pneumatic glue dispenser
with foot pedal and timed pulse option (manufacturer: EFD model: Ultra 1400) www.efd-inc.com
• 3ccm syringe barrel and piston (EFD)
• Smooth-flow tapered tips, gage 20 (EFD)
Slide 15Susanne KyreTracker week, October 2005
Set up Equipment• Base plate (UCSB design), to
hold the module on a module carrier upside down
• Plastic trowel (UCSB design), to spread the encapsulant over the wirebonds and to keep the height of the encapsulant below the maximum height
• Stereo microscope (optional)
Slide 16Susanne KyreTracker week, October 2005
Procedure I• Mix encapsulant, degas the
mixture and fill syringe
• Set pneumatic dispenser to 15 psi and 1 second dispense time
• Set module in carrier upside down onto base plate
• Dispense a line of encapsulant across the width of the wirebonds
Slide 17Susanne KyreTracker week, October 2005
Procedure II• Position the trowel with one
leg on the sensor, one leg on the kapton
• Spread the encapsulant over all 15 wirebonds by sliding the trowel across the bonds
• Once the trowel is past the wirebonds, lift it up and clean it off with a dry tissue paper
Slide 18Susanne KyreTracker week, October 2005
Procedure III• Check that all wirebonds are
covered completely with the encapsulant (this can be done with or without a stereo microscope)
• If necessary apply more silicone and repeat the troweling procedure
• Cure for 24 hours with the backside of the module facing up to avoid beading up of the encapsulant
26 Oct 2005CMS Tracker Week - Module Production 19 Salvatore Costa - Catania
Established EU procedure
M.Krammer:
no bond encapsulation experience in
EU TEC community: use conductive glue reinforcement
All tests OK
This procedure is now officially requested by TEC to Italy
26 Oct 2005CMS Tracker Week - Module Production 20 Salvatore Costa - Catania
…Except for R4S modules…
…because:
26 Oct 2005CMS Tracker Week - Module Production 21 Salvatore Costa - Catania
26 Oct 2005CMS Tracker Week - Module Production 22 Salvatore Costa - Catania
26 Oct 2005CMS Tracker Week - Module Production 23 Salvatore Costa - Catania
26 Oct 2005CMS Tracker Week - Module Production 24 Salvatore Costa - Catania
How is Back bonding going?
• Aachen: Vibration test of backplane HV bonds: with additional glue near bonds, but bonds bare, in one module some bonds broke, in another module no bonds broke. In modules with encapsulated bonds, none broke.
• Strasbourg: Bonded (in hole) 16 modules electrically OK• Vienna: Bonded (in hole) 80 modules previously front-
bonded, using special supports that hold module carrier all around: sensors not supportedNo problems.
• Hamburg: Not started yet since the backplane jigs are not done before next week. For the last weeks have reinforced the glue connection on the backplane with conductive glue, for some modules where this had not been done before at the Gantries.
26 Oct 2005CMS Tracker Week - Module Production 25 Salvatore Costa - Catania
Recipe for TEC Mod prod in Italy
At the end of the Bonding Meeting, I conveyed its outcome at the Gantry Meeting…
– Bari has agreed to use conductive glue under HV pad when assembling modules
– Bari has agreed to place conductive glue reinforcement over the “top” of the T-shaped pad
– Bonding centers will bond “in the hole” without encapsulation
CMS Tracker Week, CERN, 24-28 Oct 2005
26 Oct 2005CMS Tracker Week - Module ProductionSalvatore Costa - Catania
Some peculiar
Module failures
26 Oct 2005CMS Tracker Week - Module Production 27 Salvatore Costa - Catania
Some recent peculiar Module failures
• IV failures:– Affect modules not randomly in time, but in concentrated clusters: Recently: 5/53 in Aachen, 4/36 in Catania Had also been seen at least in Catania and Padova in the past.
• Seen (in Catania) first TIB module where gold layer on HV pad on back is peeling away. – May drag away the bonds with it– Module will be declared faulty Repair center
• Since Sep we see many TIB PA’s where bonds would stick with unusually high parameters, or would not stick at all, in one or more of these locations: – Pads 1-2, 27-30, 738-741, 767-768 – Seen in: Bari, Catania, Padova. – Suspect bad PA metallization in those (symmetric!) spots