Upload
hari-yurismono
View
222
Download
0
Embed Size (px)
Citation preview
8/8/2019 Coal Mill Firing System
1/9
COAL MILL FIRING SYSTEM
Inderect Firing
Existing Design : per unit Power Plant of 35 MW (Gross Out Put)
PC Boiler with Direct Firing
Boiler Capacity : 35 TPH
Design NPHR : 3083 kcal /kwh
Design Coal HHV (AR) : 4.100 Kcal/kwh
3.083
Coal flow rate = x 35 TPH
4.100
= 26,32 TPH
Proposed design of NEM has configuration :
* Direct firing: Each boiler with 3 units of Coal Mills, 2 in operation, 1 standby
* Mill capacity = 14 TPH each
Proposed design of REKIN has configuration :
* In-Direct firing: Two boilers with 3 units of Coal Mills, 2 in operation, 1 standby
* Mill capacity = 31.4 TPH each
8/8/2019 Coal Mill Firing System
2/9
Inderect FiringConstraints :
1. Ramping Up requirement = 3 % load/ minute
= 1 MW / minute
Converted to Coal Consumption during acceleration is =
NPHR
= x 1 MW / minute
Coal HHV
3.083
= x 1 Ton / minute
4.100
= 0,75 Ton/minute
a) Ramping Up is From Turn Down Ratio (40 % Load) To 100 % load
or from 14 MW to 35 MW.
Rumping Up time 1435 = 21 minutes
or PC needs = 21 x 0,75
= 15,75 Ton
8/8/2019 Coal Mill Firing System
3/9
b) Ramping Up from inhouse power ( 5 MW) to
full load (35 MW) :Ramping Up time 5
35 = 30 menit
Or PC needs = 30 x 0,75
= 22,5 Ton
2) Mill Maintenance :
Practically Mill need maintenance for 1 shift (8hours) per week (7 days).
We design spare time for mill maintenance at2 h/day or 14 h/week. So the operating hour is
(24 2) h/day = 22 h/day
8/8/2019 Coal Mill Firing System
4/9
Mill Sizing
Indirect Firing for PC Boiler Mill Configuration follow this scheme :
Boiler
1
Boiler
2
321
Coal Mill
Pulverised coal
Bin 2
Pulverised coal
Bin 1
PC
Feeder BPC
Feeder A
PC
Feeder APC
Feeder B
NOTE :
Coal Mill Run 2 unit
Stand by 1 unit
8/8/2019 Coal Mill Firing System
5/9
Coal Consumption
2 units Boiler Ramp-up to Full-Load= 2 x 26,32 TPH
= 52,64 TPH at PC Coal
2 Units Boiler Ramp up 5MW to 35MW
= 2 x 22,5 ton/ 30minutes= 45 ton/30minutes
Coal taken from PC bins during ramp up for 2 unit boiler is :
52,64= 45 ton/30minutes - ton/30 minutes
2
= 18.68 ton / minutes
8/8/2019 Coal Mill Firing System
6/9
Mill Sizing
Mill configuration: 3 units, 2 operation, 1 standby Minimum mill capacity of 13,15tph is needed.
After ramp-up two mills will run to fill the PC bins of 18,68 ton whilesupplying boiler operation.
Coal needed from PC bin each boiler will be
18,68 ton
= 9,34 ton
2
PC bin is design to have retention time of 6 hours so that theminimum bin capacity is 60 ton/unit boiler.
Maximum time to fill PC to bin after ramp-up is 1 cycle of cement
plat start-up cycle, ie. 300 minutes or 5 h. So, based on 24h continues operation the minimum coal mill
capacity is 26.32 + (9.34/5) or 28.2 tph
8/8/2019 Coal Mill Firing System
7/9
Mill Sizing
Mill configuration: 2 units with 2 operation Based on 24h continues operation the minimum coal
mill capacity is 26.32 + (9.34/5) or 28.2 tph
Mill Maintenance :
Practically Mill need maintenance for 1 shift (8 hours)per week (7 days).
We design spare time for mill maintenance at
2 h/day or 14 h/week. So the operating hour is
(24 2) h/day = 22 h/day
Coal Mill Size:24/22 x 28.2 tph = 30.75 tph
So the minimum coal mill capacity is 30.75 tph
8/8/2019 Coal Mill Firing System
8/9
Mill Sizing
Indirect Firing for PC Boiler Mill Configuration follow this scheme :
Boiler
1
Boiler
2
21
Coal Mill
Pulverised coal
Bin 2
Pulverised coal
Bin 1
PC
Feeder BPC
Feeder A
PC
Feeder APC
Feeder B
NOTE :
Coal Mill Run 2 unit
Stand by 0 unit
8/8/2019 Coal Mill Firing System
9/9
Equipment List
1. Coal Mill = 2 x 31 TPH
2. Raw Coal Silo = 2 x 150 Ton (5h retention)3. PC Bins = 2 x 60 Ton
4. PC Feeder = 4 x 15 TPH
5. Safety Equipment (CO2 inert) for 2 unit Boiler.