Coal Mill Firing System

Embed Size (px)

Citation preview

  • 8/8/2019 Coal Mill Firing System

    1/9

    COAL MILL FIRING SYSTEM

    Inderect Firing

    Existing Design : per unit Power Plant of 35 MW (Gross Out Put)

    PC Boiler with Direct Firing

    Boiler Capacity : 35 TPH

    Design NPHR : 3083 kcal /kwh

    Design Coal HHV (AR) : 4.100 Kcal/kwh

    3.083

    Coal flow rate = x 35 TPH

    4.100

    = 26,32 TPH

    Proposed design of NEM has configuration :

    * Direct firing: Each boiler with 3 units of Coal Mills, 2 in operation, 1 standby

    * Mill capacity = 14 TPH each

    Proposed design of REKIN has configuration :

    * In-Direct firing: Two boilers with 3 units of Coal Mills, 2 in operation, 1 standby

    * Mill capacity = 31.4 TPH each

  • 8/8/2019 Coal Mill Firing System

    2/9

    Inderect FiringConstraints :

    1. Ramping Up requirement = 3 % load/ minute

    = 1 MW / minute

    Converted to Coal Consumption during acceleration is =

    NPHR

    = x 1 MW / minute

    Coal HHV

    3.083

    = x 1 Ton / minute

    4.100

    = 0,75 Ton/minute

    a) Ramping Up is From Turn Down Ratio (40 % Load) To 100 % load

    or from 14 MW to 35 MW.

    Rumping Up time 1435 = 21 minutes

    or PC needs = 21 x 0,75

    = 15,75 Ton

  • 8/8/2019 Coal Mill Firing System

    3/9

    b) Ramping Up from inhouse power ( 5 MW) to

    full load (35 MW) :Ramping Up time 5

    35 = 30 menit

    Or PC needs = 30 x 0,75

    = 22,5 Ton

    2) Mill Maintenance :

    Practically Mill need maintenance for 1 shift (8hours) per week (7 days).

    We design spare time for mill maintenance at2 h/day or 14 h/week. So the operating hour is

    (24 2) h/day = 22 h/day

  • 8/8/2019 Coal Mill Firing System

    4/9

    Mill Sizing

    Indirect Firing for PC Boiler Mill Configuration follow this scheme :

    Boiler

    1

    Boiler

    2

    321

    Coal Mill

    Pulverised coal

    Bin 2

    Pulverised coal

    Bin 1

    PC

    Feeder BPC

    Feeder A

    PC

    Feeder APC

    Feeder B

    NOTE :

    Coal Mill Run 2 unit

    Stand by 1 unit

  • 8/8/2019 Coal Mill Firing System

    5/9

    Coal Consumption

    2 units Boiler Ramp-up to Full-Load= 2 x 26,32 TPH

    = 52,64 TPH at PC Coal

    2 Units Boiler Ramp up 5MW to 35MW

    = 2 x 22,5 ton/ 30minutes= 45 ton/30minutes

    Coal taken from PC bins during ramp up for 2 unit boiler is :

    52,64= 45 ton/30minutes - ton/30 minutes

    2

    = 18.68 ton / minutes

  • 8/8/2019 Coal Mill Firing System

    6/9

    Mill Sizing

    Mill configuration: 3 units, 2 operation, 1 standby Minimum mill capacity of 13,15tph is needed.

    After ramp-up two mills will run to fill the PC bins of 18,68 ton whilesupplying boiler operation.

    Coal needed from PC bin each boiler will be

    18,68 ton

    = 9,34 ton

    2

    PC bin is design to have retention time of 6 hours so that theminimum bin capacity is 60 ton/unit boiler.

    Maximum time to fill PC to bin after ramp-up is 1 cycle of cement

    plat start-up cycle, ie. 300 minutes or 5 h. So, based on 24h continues operation the minimum coal mill

    capacity is 26.32 + (9.34/5) or 28.2 tph

  • 8/8/2019 Coal Mill Firing System

    7/9

    Mill Sizing

    Mill configuration: 2 units with 2 operation Based on 24h continues operation the minimum coal

    mill capacity is 26.32 + (9.34/5) or 28.2 tph

    Mill Maintenance :

    Practically Mill need maintenance for 1 shift (8 hours)per week (7 days).

    We design spare time for mill maintenance at

    2 h/day or 14 h/week. So the operating hour is

    (24 2) h/day = 22 h/day

    Coal Mill Size:24/22 x 28.2 tph = 30.75 tph

    So the minimum coal mill capacity is 30.75 tph

  • 8/8/2019 Coal Mill Firing System

    8/9

    Mill Sizing

    Indirect Firing for PC Boiler Mill Configuration follow this scheme :

    Boiler

    1

    Boiler

    2

    21

    Coal Mill

    Pulverised coal

    Bin 2

    Pulverised coal

    Bin 1

    PC

    Feeder BPC

    Feeder A

    PC

    Feeder APC

    Feeder B

    NOTE :

    Coal Mill Run 2 unit

    Stand by 0 unit

  • 8/8/2019 Coal Mill Firing System

    9/9

    Equipment List

    1. Coal Mill = 2 x 31 TPH

    2. Raw Coal Silo = 2 x 150 Ton (5h retention)3. PC Bins = 2 x 60 Ton

    4. PC Feeder = 4 x 15 TPH

    5. Safety Equipment (CO2 inert) for 2 unit Boiler.