Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Composite power system reliability evaluation: Italian perspective
June 12, 2018
NERCComposite
Resource Adequacy and Transmission Reliability Planning
webinar
R. Calisti, M. V. Cazzol, G. Ceresa, E. Ciapessoni, D. Cirio, A. L’Abbate, G. Migliavacca
Outline
Reliability & adequacy New needs & challenges Approaches and tools in the Italian and European context Conclusions
2
Reliability
• Reliability of a power system refers to the probability of its satisfactory operation over the long run. It denotes the ability to supply adequate electric service on a nearly continuous basis, with few interruptions over an extended time period. (IEEE/CIGRE Joint Task Force on Stability Terms and Definitions, IEEE Tr. PS, VOL. 19, NO. 2, 2004)
• Reliability, in a bulk power electric system, is the degree to which the performance of the elements of that system results in power being delivered to consumers within accepted standards and in the amount desired. The degree of reliability may be measured by the frequency, duration, and magnitude of adverse effects on consumer service. (NERC)
• System adequacy of a power system is a measure of the ability of a power system to supply the load in all the steady states in which the power system may exist considering standard conditions. (ENTSO‐E)
3
Reliability
Reliability can be addressed by considering two basic functional aspects of the power systems:
• Adequacy—The ability of the electric system to supply the aggregate electrical demand and energyrequirements of the end‐use customers at all times, taking into account scheduled and reasonablyexpected unscheduled outages of system elements.
• Security—the ability of the power system to withstand sudden disturbances such as electric short circuits or non‐anticipated loss of system components.
4
Context: On‐line / real‐time When missing: Risk of widespread disturbances
Context: Planning, operational planning, quasi on line When missing: Controlled disconnections
Approaches
5
Generation only Generation + transmission(«composite»)
Deterministic
Probabilistic
Total load
Peak load
Max credible simultaneousoutages of…
G G+T
Monte Carlo simulation
Direct computation
Load scenarios
Availability status of… G G+T State enumeration becomes unfeasible
due to combinatorial explosion
Monte Carlo allows to deal with large numbers of stochastic variables and sequential events
Approaches
6
Generation + transmission(«composite»)
Non sequential
SequentialLoad scenarios
Availability status of… G G+T
Load scenarios
Availability status of… G G+T
Hydro status
Other quantities with sequential constraints: generator output (e.g. ramp rate), weather
correlations, …
Each simulated hour isindependent of the others
Monte Carlo simulation
Indices
• Loss Of Load Expectation (LOLE)– expected number of hours per year for which the available generation capacity is insufficient to cover the demand
• Loss Of Load Probability (LOLP)– likelihood of encountering loss of load = LOLE / 8760 hours
• Expected Energy Not Supplied (EENS)– amount of electricity demand (MWh) that is expected not to be met by generation in a given year
• Expected Energy Not Produced (EENP)– amount of electricity from Variable Energy Resources VERs (MWh) that is expected not to be fed into the grid due to system issues in a given year
7
Paradigm shift
8
https://www.sma‐italia.com/prodotti/referenze/montalto‐di‐castro.html
• VERs act as «base load» plants• DG currently «uncontrolled»• Conventional generation (including thermal) supplies the «residual», «net» load
https://www.nasa.gov/offices/oct/images/nasa‐derived‐northern‐power‐100‐wind‐turbines‐operating‐in‐italy
Paradigm shift
99
Net load demand in Italy on bank holidays , source TERNA
June 6 October 10
https://www.sma‐italia.com/prodotti/referenze/montalto‐di‐castro.htmlhttps://www.nasa.gov/offices/oct/images/nasa‐derived‐northern‐power‐100‐wind‐turbines‐operating‐in‐italy
Adequacy issues
10
Source: ENTSO‐E Mid‐Term Adequacy Forecast 2017
Summer Peak Load variation 2015/2014: +13% !!
Yearly demand variation 2015/2014: +2%
Heat wave on the electric energy demandItaly, July 2015
summer
winter
Variability
11
Extreme weather phenomenaEnergy & Power are different stories
Cold spell + low VER generation + outage of some nuclear plants
France, Jan/Feb 2017
Spatially correlated issues
Exceptional conditions, Adequacy alarm: unusual dispatch & import conditions(help by neighbors)
Persistence of low VER generation over wide areas
Are hydro (reservoir/pumped storage) resources enough to meet the demand? 13
2 wind falls, each lasting a week
Average wind power capacity factor is 7% in Finland and Sweden, and 9% in Norway Their respective annual are 20%, 30%, and 22%
Source: European Commission METISStudy S04, “Generation and System Adequacy Analysis”, Jan. 2016
Performances required to conventional generation
• Provide more reserve and cope with VER volatility
14
Ramping rates, startup time, minimum up/down time, minimum output power
Source ENTSO‐E MAF 2017
Risk of losing controllable capacity
15
Generation Capacity at risk of being mothballedImportance of good input information
Source ENTSO‐E MAF 2017 Absolute [MW] and relative [% of the thermal generation capacity]
Grid congestion
VER impact on the grid:new and diverse power flow patterns, is the grid ok?
16
Source: TERNA
Overgeneration
Caused by… Grid capacity constraints + reserve needs
Summary of weather-related impacts
• Load (temperature)• Wind• PV • Hydro
• Grid capacity (DLR)• Grid availability (extreme events)
17
Short term
Long term(seasonal)
Source ENTSO‐E Summer outlookwinter review 2017
More topics to be put into adequacy evaluations…
• Maintenance programs
• Resilience aspects– Withstand disturbances, especiallymultiple outages in an area due to extreme weather phenomena
– Recovery
18
Opportunities• Making transmission more flexible :
– PST– HVDC– FACTS
• Taking advantage of distributed resources:– Demand response– Distributed storage– EV and V2G
• Moreover, technologies such as…– Dynamic Line Rating (DLR) allows to operate lines at higher capacity when ambient conditions allow so
– High Temperature Low Sag (HTLS) OHL allow to increase line capacity with reducedrights‐of‐way
19
Resulting modeling needs for adequacy analyses
• Sequential simulation• Long‐term model (time series) of primary energy sources• Model of storages
• Unit commitment with minimum power output, minimum up/down time, ramp rates
• Grid components: power flow control devices
• Gridmodel: full AC
20
Modeling needs
21
Grid size
Time period (days, months, years)
Injection model LoadVERStorage Conventionalgeneration
Trade‐off needede.g. zonal vs. nodal analyses
Weather model
Grid modellinear DC vs. non linear AC Components (PST, FACTS…) Availability
Tools in use at the Italian TSO
22
• GRARE (Grid Reliability and Adequacy Risk Evaluator) owned by Terna, developed by CESI, • Reliability and economic operational capability using probabilistic Monte Carlo analysis
SAMPLING
Zonal representation Nodal representation
Deterministic (single year simulation)
Probabilistic (multiple year simulation)(non sequential Monte Carlo)(sequential Monte Carlo)
EXPANSION SELECTION
ADEQUACY(linear DC modeling)
ADEQUACY(non‐linear AC modeling)
TECH
NO‐ECO
NOMIC
ASSESSMEN
T
Research Tools @RSE
23
Zonal representation Nodal representation
Deterministic (single year simulation)
Probabilistic (multiple year simulation)(non sequential Monte Carlo)(sequential Monte Carlo)
PREESP ESPAUT
MTSIM
sMTSIM+
EXPANSION SELECTION
ADEQUACY(linear DC modeling)
ADEQUACY(non linear AC modeling)
TECH
NO‐ECO
NOMIC
ASSESSMEN
T
REMARK+
REMARK
ACRE
ACRE+
Research Tools @RSE
24
RES data generation
Transmission Expansion
ESPAUT“ESPansione AUTomatica”
“Automatic expansion” procedure to select the optimal reinforcement plan within a set of grid expansion alternatives to
fulfill a network development plan over a long term period
25
Transmission ExpansionESPAUT
Definition of the reinforcement plan
Candidates for the target year
Optimal reinforcement for the target year
Optimal reinforcement for intermediate years
0 1 … Target year
Commissioning year of reinforcements
26
COMPLEX AND LARGE DIMENSION PROBLEM (MIP)
Example: 6 scenarios generation/loadbase case + 27 contingencies
206 candidates750 nodes930 links
170 generators
477000 variables (206 binary)423000 constraints
1385000 non null elements
PREESPPRE‐ESPAUT
Generation and load curvespreparation through the resolutionof an optimisation problem of a
simplified grid with detailed model of storage, DSM, electric vehicles, before full grid implementation by
ESPAUT
Transmission ExpansionESPAUT
27
LCHF111MSEF111
MORF111VLVF111
LONF111 MOUF111
CHEF111
MERE111 MASN111
VIGF111
HOUF111
GRAE111COUE111
TOUF111 ROUF111ARGF111
TERF111
DOMF111
VERF111CORF111DISF111
DAMF111
MEZF111
AVOF111
LQUF111LOUF111
PENF111
GATF111
LREF111
AVEF111HASO211 MANF111
LHVF111
DEEL111
WLAO211
WIAO211
WJ1O211 WJ2O211SU5O211
SU6O211
WYLL111PENL111
WF1O211
WF2O211
WF3O211CODO211
KISO211SU2O211
MULLINGAR
ENNIS
TURLOUGHHILL
THURLES
-ON- HILLGILRA ARVA
KINNEGAD
BALLYBEG
NENAGHARDNACRUSHA
CHARLESLAND
BALLYRAGGET
ORIO211
CKMC111
HUNC111BALC111WOOC111
DUNC111
MAYC111
ARKC111LAOC111
BA1C211
WEMB111
CAVA111-211CASTLEBAR
GALWAY
LANESBORO
CLOON
IKERRIN
DALTON
CAMUS
TYNAGH
FLAA111-411
CASA111-411 SHAA111-411
OLDB111-411
MONB111-211 KELC111
WHRW211
LAMF111
CHEF111
MEES111
HENS111
DODS111
ZWOS111
WARF111
GEES111MAVS111
SIZM111
PEWL111
BOLN111
LOVN111
DOGK112
DRXK111 YORK111
NORM112
NORM113
WALM111 NORM111
BRFM111
GRAN111
DIES111
DISS111
NORTHERNIRELAND
ISL0211
WS10211
WS20211
WS50211
ARG0211
WS40211
WS30211FAGH111
FWIH111
BRDH111
WIG0211 SOL0211
WNAO211
SU4O211
GRNH111HARJ111
HUTL111HUSL211
SU8O211
MANQ211
SU7O211
SHANKILLCUNGHILL
BUNBEG
TIEVEBRACK
SRANANAGH
*
KIN0211
OMAD111-211
STRD211
COOD211COLD211
MAGD211
TURD111-211
CACD211 KELD211BAFD211
TAND211
LOUA211BALA211
LEAD111-411
CATA111-411
SLIA111-411BELA111-211-411 SRAA111-411
HAND211GOLA111-411
WIRW211
WJNW211 WKNW211
MORH211-111
FORH113 FORH112FORH111
MOSH111-211
PETH111-211
STEJ111 HAWJ111
LACJ111
QUEL111
DOGK111
DOGK113
THRK111 HORK111 HORK112
MESS111
DIEZ111 WEDZ111
KASU111
HANU111
SELN111NURN111
TRAL111WF4O211
CASL211
PEMM111
BR1O211BR2O211
ALVN111
INDN111 LAGN111ABHN111
EXTN111
SWAM111WALM111
SCIN211
WIWO211
DOON
MALLOW
CHARLEVILLE
BANDONDUNMANWAYBRINNY
DUNGARVAN
KILB111-211
KILBARRY
OUGHTRAGH
TRALEE
CLASHAVOON
CULLENAGH
TIPPERARYKILLONAN
GLENLARA
CROSS
PROSPECT
COOMAGEARLAHY
CLAHANE
COOMACHEOBVKB111WF5O211
SU2O211
GLAO211
ARKO211
GREC111
LODC211KILC111
KNOB111
CAHC111
AGHB111
KN1B111-411TARB111-211WGRW211
THSK111
DRSK111
NOSM111
COCH111 TORH111
STSJ111
BSUE111
NSUS111
MESE111
WESZ111
KSSU111DSUU111
GSUZ111
DASH211-221
HUEH111-221
AUCH211-221
DOUH211-221
MYBH211-221
INVH111
BEAH111-211
MD1B111-211
TRIA111-411
ENND111-411
TASB111-211
CAML111
TREL111LEGL111
BOSN211
TKNK111
RCBK111DUDK111
SHHK111DOCK111
TKSK111
BICM111
LOAN111
GRGM111
GUFM111
COSN111
THAN111
WERK111
HUGK111
WALO211
WDUO211
BAIM111
BRBU111
MEPZ111AV1W211
AV3W211
AV2W211
OUGB211
CROB211
AF4W211
AF3W211
AF2W211
AF1W211
OBEZ111
GRNZ111KUSZ111
LIPZ111
HNEZ111
GIEZ111
BROZ111
NEHZ111
GROZ111
HAMZ111
LANZ111
WAHZ111WEHZ111
FRAF111
NETS111
GERZ111
Transmission ExpansionESPAUT
1472 Candidates (ROW potential reinforcements)
Example of ESPAUT application: the case of Ireland
(Source: Eirgrid)
28
Medium‐Term Simulator of a day‐ahead zonal market (DAM)• system‐wide energy evaluations (i.e. fuel consumption)• emission evaluations (CO2 and other pollutants)• hourly clearing price throughout the year• Simplified linear DC Optimal Power Flow minimizing the energy price
• variable (fuel, O&M) costs• environmental costs• hourly bid‐up of each unit
• transmission modeled by an inter‐zonal equivalent system with HVAC (via PTDF) andHVDC
• planning modality allowing to consider additional interconnection capacity betweenthe market zones
Adequacy MTSIM
• MTSIM provides also the possibility of including innovative technologies: HVDC PST/FACTS Storage DSM/DR• MTSIM providesmain outputs for techno‐economic assessments: Hourly zonal generation dispatch Dispatch cost Inter‐zonal flow transits Load shedding (EENS) RES curtailment CO2 emissions Hourly zonal marginal costs/prices Fuel consumption
AdequacyMTSIM
• Represents the Monte Carlo evolution of MTSIM• Variable RES (solar, wind) generation is simulated at eachiteration
• «Stochastic Unit Commitment» algorithm to define UCaccounting for uncertainty in residual load forecast
• Reserve requirements included in the UC
31
AdequacysMTSIM+
Pan‐European zonal model (2030) Pan‐European zonal model (2050)GridTech EU30+ study
32
Hourly zonal generation dispatch Dispatch cost Inter‐zonal flow transits
Load shedding (EENS) RES curtailment (EENP)
CO2 emissions Hourly zonal marginal
costs/prices Fuel consumption
MTSIM Medium-Term Simulator of day-ahead zonal market
Pan‐European zonal model (2050)GridTech EU30+ study
33
Hourly zonal generation dispatch Dispatch cost Inter‐zonal flow transits
Load shedding (EENS) RES curtailment (EENP)
CO2 emissions Hourly zonal marginal
costs/prices Fuel consumption
MTSIM Medium-Term Simulator of day-ahead zonal market
• Simplified linear DC Optimal Power Flowminimizing operation costs
• Inter‐zonal equivalent system with HVAC (via PTDF)and HVDC
• UC and ramp limitations• Storage, DR• Planning modality• “Stochastic” version: UC performed considering
VER uncertainties
over 2030 S0 (base)
Planning modality application results (2030)
Planning modality application results (2050)
MTSIM results examplesGridTech EU30+ study
34
REMARK“ REliability & MARKet ”
Adequacy analysis on composite G&T systems based on zonal market structure
• Grid limitations and constraints that affect the economic system dispatch
• Simplified linear DC Optimal Power Flow minimizing operation costs
• Non sequential (REMARK+: sequential )
• Social Welfare (Consumers/Producers Surplus, congestion rent) • LMP, dispatch costs, CO2 emissions, Joule losses (ex‐post)
• Typical reliability parameters: EENS , LOLP, LOLE, as well as Expected Energy Not Produced (EENP)
35
• Power system model features:– Detailed model of the network: nodes, HVAC and HVDC lines, transformers, PSTs, generators, loads
– Nodal loads, characterised by yearly profile– Grid representation by simplified DC load flow equations– OPF objective: maximisation of Social Welfare – Geographic system/market zones subdivision– Generation: fixed (predefined profile), random variable, dispatchable
AdequacyREMARK & REMARK+
36
AdequacyREMARK
Statistical probabilistic analysis: “non‐sequential Monte Carlo” methodA sample, representative of the hourly system configurations at a target year, is randomlygenerated as a combination of:
– unavailability of lines, transformers, generators – maintenance schedules for generators– predefined profiles of load demand and non‐dispatchable generation (also for hydro reservoir
plants)– statistical profile of wind generation
37
4 OPFs are simulated with a different granularity of transmission system representation to determine the
additional costs due to market and grid constraints
N O R D
C E N T R O S U D
S U D
C E N T R O N O R D
S IC IL IA
G R E C IA
E S T E R O N O R D
C E N T R O S U D
S U D
C E N T R O N O R D
S IC IL IA G R E C IA
E S T E R O
N O R D
C E N T R O S U D
S U D
C E N T R O N O R D
S IC IL IA G R E C IA
E S T E R O E S T E R O
N O R D
C E N T R O N O R D
C E N T R O S U D
S U D
S IC IL IA G R E C IA
+
N O R D
C E N T R O S U D
S U D
C E N T R O N O R D
S IC IL IA G R E C IA
E S T E R O
+
1) Single area 2) Zonal market system
3) Zonal market system + interconnections
4) Zonal market system + whole grid
REMARK
38
AdequacyREMARK+
Statistical probabilistic analysis: “sequential Monte Carlo” method
The Monte Carlo method is tasked to feed the yearly system dispatch simulation via the datafeatured by random elements:• the hourly states of system components• the hourly expected production (wind, PV)
Each Monte Carlo run generates a deterministic problem that simulates the optimal yearly systemdispatch, to be calculated via optimisation.
MONTE CARLO SEQUENTIALITY
More precise storagemodeling
Higher complexity
39
ACRE
“ Alternating Current REliability”ASSESSMENT OF SPECIFIC SYSTEM DISPATCH CASES VIA
AC OPTIMAL POWER FLOW (OPF)
o Full AC Optimal Power Flowo Complete grid model (AC load flow equations)
o Objective functiono total cost minimisationo active losses minimisation
o Cost curveso quadratico linear
40
Sequential ACRE+: o Mixed AC/DC gridso HVDC LCC and VSC modelingo Storageo FACTSOngoing development
New indices:
o Levels of active power losses on transmission lines.o Levels of reactive power losses on transmission lines.o Levels of voltage amplitudes on load nodes and distribution interface nodes.o Levels of utilisation of capacitors banks and shunt reactors.o Limits of currents accounting for active and reactive power flows.o Levels of utilisation of subsystems (cables, lines and/or meshed grids) operated in
HVDC.
AdequacyACRE
41
AdequacyACRE+
o Mixed AC/DC gridso HVDC LCC and VSC modelingo Storageo FACTSo ...o Sequential Monte Carlo method
o Problem complexity: limit number of hours in a sequenceo Ongoing development
42
AMaChaStochastic Analysis with Markov Chains
AMaCha 1 ‐ analysis AMaCha 2 ‐ generation
43
Markov
•Model parameters
PCA‐1
• Production of n series of new states• Resizing of state series into data series
• Correlated data
STL‐1
• Data with seasonal behaviors
STL
• Input data: time series of power production from wind and solar generators
PCA
• Deseasonalized data, without trend and without annual, seasonal, daily seasonality
• Uncorrelated data • Transformation of data into system states
Markov• Model parameters
Security issues• Short circuit power• Voltage control • Inertia• Frequency regulation• Negative load seen from HV substations• Congestions• …
44
VER generators connected via power electronics do not sensibly contribute to short circuit currentNeed for frequency
regulation resources
Source TERNA
Some highlights from ENTSO-E Mid-term Adequacy Forecast 2017
• Extreme climate conditions impact• Common standards needed: data, models, metrics• Reliable generation plan from utility (mothballing, maintenance schedule)
• Coordinated studies needed • Probabilistic assessment of the residual load
45
https://www.entsoe.eu/outlooks/midterm/
Conclusions
• Adequacy evaluations more and more relevant due to VER penetration• Key modeling aspect: weather correlations; sequential studies• Key organisational aspect: study coordination• Different approaches for different objectives(model complexity vs. computation performances)
• Do not forget security
46 Source ENTSO‐E MAF 2017
Thank you for your attention
Questions?
47
diego.cirio@rse‐web.it
CONFIDENTIALRESTRICTEDPUBLIC INTERNAL
Pierre Henneaux – June 12, [email protected]
Probabilistic composite power system adequacy assessment in transmission planning
5
PUB
LIC
Chapter 1 Motivations
Chapter 2 Methodologies & tools
Chapter 3 Examples
Chapter 4 Conclusions
CONTENTS
Probabilistic composite power system adequacy assessment in transmission planning 6
Motivations
8Probabilistic composite power system adequacy assessment in transmission planning
PUB
LIC
Two-step approach1. Adequacy of the generation system
— Deterministic (e.g. capacity margin) or probabilistic (e.g. LOLE) criteria
— Single-area or multi-area analyses
2. Adequacy of the transmission system— Deterministic analysis
— Specific set of states analyzed, e.g. peak load and off-peak load (“extreme cases”)
— The transmission system must be able to supply the load while satisfying operational constraints (including security constraints – e.g. N-1 events)
13
MotivationsTraditional way to ensure power system adequacy
Probabilistic composite power system adequacy assessment in transmission planning
PUB
LIC
Limitations— Adequacy issues might be due to multiple contingencies, not covered in the deterministic analysis related to the
transmission system— If massive integration of renewable energy sources, difficulty to represent their variability
• Generation system might be adequate, but bottlenecks hampering the load supply can occur in the grid
13
MotivationsTraditional way to ensure power system adequacy
Probabilistic composite power system adequacy assessment in transmission planning
F. Montoya et al., "Renewable energy production in Spain: A review", Renewable and Sustainable Energy Reviews, 2014.
PUB
LIC
Ability to consider combinations of multiple failures in the generation and transmission systems
Ability to consider numerous load/generation patterns
13
MotivationsNeed for a probabilistic composite power system adequacy assessment
Probabilistic composite power system adequacy assessment in transmission planning
Lead not only to system-wide indices (e.g. EENS), but reveal also buses with an insufficient level of adequacy and main bottlenecks in the grid
Methodologies & tools
9Probabilistic composite power system adequacy assessment in transmission planning
PUB
LIC
Analytical methods not practicable for composite adequacy assessment— (Optimal) power flow analysis needed to estimate the potential load shedding in each case
— Major difference compared to pure generation adequacy assessment!• Load shedding = difference between the load and the available generation in case available generation < load
State enumeration: quickly lead to a combinatorial complexity when multiple contingencies are considered
Monte Carlo simulation— Even if several drawbacks (e.g. a large number of samples might be needed to reach a satisfying accuracy),
most relevant approach for composite adequacy assessment up-to-now
— “Easy to implement”
13
Methodologies & toolsWhy Monte Carlo simulation?
Probabilistic composite power system adequacy assessment in transmission planning
PUB
LIC
Non-sequential Monte Carlo simulation— Relevant when no (or weak) temporal interdependencies between system states
— Independent analysis of each state
Sequential Monte Carlo simulation— Necessary when strong temporal interdependencies between system states (e.g. presence of storage), or
when frequency and duration of load shedding events are needed
— Positive correlation between successive system states → more samples needed to reach the same accuracy, compared to a non-sequential Monte Carlo simulation
— Computationally more challenging → nested optimization loops (e.g. annual and weekly optimization)
Methodologies & toolsNon-sequential and sequential Monte Carlo simulation
Probabilistic composite power system adequacy assessment in transmission planning 9
System state sampling Optimal Power Flow Load shedding
Possible multi-step approach to avoid the formal resolution of a OPF when not necessary
Sampling of load, of RES, of generators’ availability, and of
transmission elements’ availability
PUB
LIC
Generation adequacy— LOLE/LOLH
• Reference values, independent of the size of the system → benchmark possible
Transmission adequacy— PLC (Probability of Load Curtailment)
• Not meaningful index: tends towards 1 for very large systems (or when a large number of weakly dependent systems are considered jointly) → benchmark not possible
— EENS (Expected Energy Not Supplied)?• Meaningful value, but dependent on the size of the system → benchmark difficult
— AIT (Average Interruption Time)• Defined as the ratio between the EENS and the average load in the system (interpreted as the equivalent duration of the loss of all
load during average load conditions)
• Normalization by the load → benchmark possible
• No standard, but statistical data available for some countries
Methodologies & toolsIndicators
Probabilistic composite power system adequacy assessment in transmission planning 10
PUB
LIC
Methodologies & toolsAIT for some European Countries
Probabilistic composite power system adequacy assessment in transmission planning 11
Variability, but typical order of magnitude: a few minutes
PUB
LIC
SCANNER
— Software tool developed by Tractebel
— Implement both non-sequential and sequential Monte Carlo simulation methods
— Double aim: adequacy assessment & production cost simulation
— DC power flow
— Non-sequential version: 1986
— Sequential version: 2012
— Used in numerous studies for clients all around the world
Other tools with similar approaches: Antares (RTE), GRARE (CESI), REMARK (RSE), etc.
Methodologies & toolsTools
Probabilistic composite power system adequacy assessment in transmission planning 12
Examples
Probabilistic composite power system adequacy assessment in transmission planning10
PUB
LIC
13
ExamplesCôte d’Ivoire (Ivory Coast)
Probabilistic composite power system adequacy assessment in transmission planning
322,462 km2
24,842,117 hab.9.5 TWh/year
PUB
LIC
Transmission master plan 2030
13
ExamplesCôte d’Ivoire (Ivory Coast)
Probabilistic composite power system adequacy assessment in transmission planning
PUB
LIC
Optimal selection and phasing of reinforcements— Deterministic quasi-steady-state security analysis
— Deterministic dynamic security analysis (EUROSTAG)
— Probabilistic composite power system adequacy assessment (SCANNER)
13
ExamplesCôte d’Ivoire (Ivory Coast)
Probabilistic composite power system adequacy assessment in transmission planning
Year EENS (GWh) AIT (min)2015 74 4077
2020 0.7 28
2025 0.4 11
2030 0.5 11
PUB
LIC
13
ExamplesDjibouti
Probabilistic composite power system adequacy assessment in transmission planning
23,200 km2
810,179 hab.377 GWh/year
PUB
LIC
Need to reinforce the transfer capacity between two substations (Lac Assal and Tadjourah)
Two main possibilities meeting the deterministic reliability criteria— Single-circuit 230kV line
— Double-circuit 63kV line
Best choice?
13
ExamplesDjibouti
Probabilistic composite power system adequacy assessment in transmission planning
?
?
PUB
LIC
Comparison of— Investment costs
— Transmission network losses
— Future potential development
— Contribution to adequacy (probabilistic evaluation)
Chosen solution: double-circuit 63kV line
13
ExamplesDjibouti
Probabilistic composite power system adequacy assessment in transmission planning
PUB
LIC
13
ExamplesRomania
Probabilistic composite power system adequacy assessment in transmission planning
238,397 km2
19,638,000 hab.48.3 TWh/year
PUB
LIC
Computation of standard key adequacy indicators for the generation and the transmission system— Analysis of the impact of increasing
frequency reserves to deal with renewable variability
Identification of situations leading to load shedding
Identification of weak points in the grid?— Beyond the N-1 analysis (critical N-k
contingencies)
13
ExamplesRomania
Probabilistic composite power system adequacy assessment in transmission planning
Conclusions
Probabilistic composite power system adequacy assessment in transmission planning22
PUB
LIC
Massive integration of renewable energies lead to variability of power flows in the grid Fundamental to consider in a couple way the generation system and the transmission system in
adequacy analyses— Generation might be available, but at the wrong place
Tools for composite power system adequacy assessment exist and have been used for several decades in various countries— Based mainly on non-sequential Monte Carlo simulations
Redesign of the tools to consider temporal interdependencies— Methodological questions about the way to consider storage and uncertainty
Conclusions
Probabilistic composite power system adequacy assessment in transmission planning 23
12-June-2018
An Integrated Solution for Reliability
Assessment Applied to the Transmission
Planning of Electric Power Systems
Tito Inga-Rojas
BC Hydro, Canada
Outline
2
BC Hydro Quick Facts
Transmission Planning Tasks
Integrated Solution for Reliability Assessment
MECORE1 - Tool for Composite System Reliability
Evaluation
Wrap Up
1 Reliability Assessment of Electric Power Systems Using Monte Carlo Methods
Roy Billinton, Wenyuan Li, Plenum Press, New York 1994
3
BC Hydro Quick Facts
North American Bulk Power System
WECC
BC Hydro
BC
Providing customers
with reliable,
affordable and clean
electricity throughout
BC, safely
4
BC Hydro Quick Facts (2017)
A commercial crown corporation owned
by the province of BC
Provides 4,000,000 customers with
reliable power. Residential customers
pay the third lowest rates in North
America
98.4% clean electricity generated in BC
30 Hydro Plants, 79,000+ kms of T&D
lines and 300+ substations (500kV -
12.5kV)
11,869MW generating capacity
10,194 MW peak demand
EPA with 114 IPPs with total capacity of
4800MW (non firm), 717MW wind gen.
Planned, built & operated to NERC
MRS standards
Transmission Planning Tasks
5
Adding reliability assessment to the traditional deterministic criteria
in each of these tasks provides an essential framework for optimized
asset investment justifications
Integrated Solution for Reliability Assessment
6
BCH has several in-house software tools for reliability assessment. These
tools are integrated into RSIP (Reliability Software Integrated Package).
Assists planners in performing reliability evaluation of generation,
transmission, substation and distribution systems and comparing alternatives
of capital investments.
Speeds up the preparation of reliability data, load curves and other
information and create tables and charts of results for comparisons
Contains a database of all data including outage data, equipment attributes,
load curves, substation one-line diagrams, and power flow cases
Has an intuitive and user friendly interface for data input, control and output
of results
Integrated Solution for Reliability Assessment
7
• MECORE: composite generation and
transmission system reliability
• MCGSR: power source system reliability
• SDREP: substation and distribution system
reliability
• NETREL: general engineering system reliability
(fault tree or series/parallel network reliability)
• MEANLIFE: mean life and standard deviation of
station equipment
• SPARE: station equipment reliability
assessment for aging failure and spare analysis
• PLOSS: power loss (MW and MWh) evaluation
Integrated Solution for Reliability Assessment
8
MECORE – Tool for Composite Reliability
Evaluation
Monte Carlo simulation and Enumeration approach for COmposite system
Reliability Evaluation. It was initially developed at the University of
Saskatchewan and later enhanced at BC Hydro2
Used to assess:
composite generation and transmission reliability,
generation reliability in a composite system, or
transmission reliability in a composite system
It calculates several indices that can be utilized to compare different planning
alternatives from a reliability point of view
It has an intuitive user interface that allows easy data entry, application control
and results presentation for comparison of alternatives and sensitivity analysis.
2 Reliability Assessment of Electric Power Systems Using Monte Carlo Methods
Roy Billinton, Wenyuan Li, Plenum Press, New York 1994
9
Basic concepts and methods of MECORE
10
Load
Time
(hr)
100%
70%
8760
Multi-step Model of the
Annual Load Curve
Load Priority Levels Load Pattern Types
Load follows shape
of the load curve
Load is kept flat
Flowchart of MECORE
11
Monte Carlo
simulation technique
OPF model for corrective actions
Yes
Yes
Yes
No
No
No
Linearized load flow method
• Multi-step load model
• Network reduction
• Reliability data
• Study scenarios
• Control options
Compile reliability indices
Unavoidable load curtailments
Number of simulation samples
Reliability Indices Calculated by MECORE
12
Most Used
EENS
EDC
PLC
Expected Energy Not
Supplied (MWh/yr)
Expected Damage
Cost (K$/yr)
Probability of Load
Curtailments
Other Indices IEEE Suggested
ELC
ENLC
EDLC
ADLC
EDNS
Expected Load
Curtailments (MW/yr)
Expected Number of Load
Curtailments Index (#/yr)
Expected Duration of Load
Curtailments (hr/yr)
Average Duration of Load
Curtailments (hr/outage)
Expected Demand Not
Supplied (MW)
BPII
BPECI
BPACI
MBECI
SI
Bulk Power Interruption
Index (MW/MW – yr)
Bulk Power Energy
Curtailment Index (MWh/MW-yr)
Bulk Power Supply Average
MW Curtailment Index
(MW/disturbance)
Modified Bulk Energy
Curtailment Index
Severity Index
(System Minutes/yr)
13
Composite Reliability Evaluation – Example
Option 2 Option 1
Option 3
Option 6 Option 5
Option 4
Control Options
14
Average Reliability Data (BCH and CEA)
15
Load Curve Retrieval
16
Load Curve
17
Output Summary Selection
18
Summary Results
19
Wrap Up
20
The purpose of reliability assessment is to add one more dimension to
enhance the transmission planning process rather than to replace the
traditional deterministic criteria.
Utilities need to develop processes, indices and have comprehensive
data collection schemes and tools for reliability assessment. This
includes training for planners and budgets for implementation.
BC Hydro has implemented an integrated software solution for
reliability assessment that is applied when needed to each of its
transmission planning tasks.
References
21
• Roy Billinton and Wenyuan Li, Reliability Assessment of Electric
Power Systems Using Monte Carlo Methods, Plenum Press, 1994
• Wenyuan Li, Probabilistic Transmission Planning, IEEE and Wiley, 2011
• Wenyuan Li, Risk Assessment of Power Systems – Models, Methods, and Applications, IEEE and Wiley, 2005
• Roy Billinton and Ronald N Allan, Reliability Evaluation of Power Systems, Pitman Publishing, 1984
• Roy Billinton and Ronald N Allan, Reliability Evaluation of Engineering Systems: Concepts and Techniques, Pitman Publishing, 1983
• Applied Reliability Assessment in Electric Power Systems. Edited by Roy Billinton, Ronald N Allan, Luigi Salvaderi, IEEE Press, 1991
BC Hydro: technical reports and published papers
Probabilistic Models for Manitoba Hydro’s Transmission Asset Planning, Investment and Management
B. BagenSystem Planning Department, Manitoba Hydro, Canada
June 12, 2018
A presentation to the NERC Composite Resource Adequacy and Transmission Reliability Planning Webinar
OutlineIntroductionSystem Reliability and Risk Model (SRRM) SRRM‐AC SRRM‐DC SRRM‐ST SRRM‐RD SRRM‐SC (Under Development) SRRM‐TS (Research Stage)
Closing Comments
Introduction (Manitoba)
Introduction (Manitoba Hydro)
A Crown Corporation and a vertically integrated utility providingservices for over 500,000 electricity and 250,000 gas customers.A total generating capacity about 5700 MW produced mainly by15 hydroelectric stations, and 2 gas stations.The backbone of Manitoba Hydro transmission is the twoNelson River Bipolar HVDC Systems referred to as BP I and BP II.A new Bipolar HVDC System referred to as BP III is underconstruction and will be in‐service in October 2018
Introduction(Manitoba Hydro’s Probabilistic Planning Philosophy)Contingency Selection: use a subsystem based approachto limit the contingencies/disturbances to be evaluated ina manageable way
Contingency Evaluation: Take advantage of thecalculation accuracy of widely used commercial programfor power flow, transition stability and short circuitanalysis if possible
Reliability Indices Calculation: Use efficient computingtechniques such as the breadth‐first search algorithm, therecursive invocation method and parallel computing tofacilitate the evaluation process.
5
Introduction(Manitoba Hydro’s Probabilistic Planning Strategy) Short‐Term (1‐5 Years)Problem solving/model development oriented for exampledevelop system model in MARS (Achieved)
Mid‐Term (5‐10 Years)Application/result oriented for example using commercialor in‐house programs to help decision‐making process (InProgress)
Long‐Term (>10 Years)A new theory and knowledge oriented for exampledeveloping new models and techniques using traditionalreliability assessment methods and/or other new approaches(In progress)
Introduction(Manitoba Hydro’s Probabilistic Planning Practices)MARSAnnual Planning Reserve Margin AssessmentNERC Biannual Probabilistic AssessmentAssessment of Major Projects and Their Alternatives
System Reliability Risk Model (SRRM‐AC, SRRM‐DC, SRRM‐ST,SRRM‐RD and SRRM‐SC)Transmission Capital PrioritizationAC Network PlanningHVDC PlanningRemote Generation Planning
7
Introduction(Transmission APIM: Current Practice)
Project Justification
Project Approval
Project Prioritization
Introduction(Transmission APIM: Past/Current Practice)
Project Portfolio Spreadsheets (data from SAP)
Capital Budget Ranking Tool
Capital Performance Working Group
Prioritized Project Plan(≈10 years)
Targets Determined by Executive Committee
System Reliability Risk Model (ΔEUE)
Introduction(Transmission AIPM: Evolving Capabilities )
Capital Performance Working Group
Prioritized Project Plan(20 years)
Targets Determined by Executive Committee
System Reliability Risk Model (ΔEUE)
AIPM Analytics
Asset Condition Assessment
Scores
Other Models
SRRM‐AC(General)
A composite system reliability evaluation model
State selection uses the analytical contingency enumerationapproach
State evaluation uses AC power flow (PSS/E)
11
SRRM‐AC (Sub‐system)
12
SRRM‐AC (Inputs/Outputs)
13
Major InputsSystem topology (PSS/E Cases)Study Area (Boundary)Load Data (PL and LDC)Equipment Reliability DataSystem Specific Data (tapped lines, SPS, common‐mode,corridor)
Major OutputsEUE/ΔEUE and risk costContributions to ΔEUE
SRRM‐AC (Examples)
14
A variable 5‐year window evaluationScenarios with and without projects (ΔEUE)SUPK, SUOP and WIPK operating conditionsMost up‐to‐date PL and LDC informationLast 8 years’ statistics for equipment reliability dataTapped lines, SPS and common‐mode outagesThe evaluation results of 6 projects will be presented as examplesP1: Addition of a new 230 kV line (125 km)P2: Sectionalizing new line of P1 to create a new 230/66 kV station and movesome of the load in the area to the new stationP3: Addition of a new 115 kV line (75 km), adding a new 115/66 kV station (2transformers) and moving some of the load in the area to the new stationP4: Addition of a new 230 kV line (70 km) and capacitor banks to provide voltagesupport in the area P5: Addition of a new 230/66 kV station (2 transformers) and moving some ofthe load in the area to the new stationP6: Addition of a new 230/66 kV bank to increase firm capacity of the station
15
Line 7
Bus 4
Line 1Bus 2
Bus 6
Bus 1
Line 12
Line 2
115 kV System
Bus 5
Bus 3
Line 9
Line 3
Line 6
Line 11
Line 4
Line 5
Line 10
Line 8Bus 7
SRRM‐AC (Examples: P1 and P2)
16
SRRM‐AC (Examples: P1 ΔEUE, Line 12)
0
10
20
30
40
50
60
70
80
90
100
Year 1 Year 2 Year 3 Year 4 Year 5
∆EUE (MWh/year)
17
SRRM‐AC(Examples: P1 and P2 ΔEUE, Line 12 and Station 7)
0
500
1000
1500
2000
2500
3000
3500
4000
4500
Year 1 Year 2 Year 3 Year 4 Year 5
∆EUE (MWh/year)
Line 12
Line 12+Station 7
3500
3600
3700
3800
3900
4000
4100
4200
4300
4400
Year 1 Year 2 Year 3 Year 4 Year 5
∆EUE (MWh/year)
18
SRRM‐AC ( Examples: Project 1 EUE Contributions)
0
500
1000
1500
2000
2500
3000
3500
Line 8 Bank 1 Bank 2 Bank 3 Bank 4 Bank 5 Bank 6 Bank 7 Line 6
EUE Co
ntrib
ution (M
Wh/year)
Contingency
Year 1
Without Project
With Project
0
5
10
15
20
25
30
35
40
Bank 2 Bank 3 Bank 4 Bank 5 Bank 6 Bank 7 Line 6
EUE Contribution (MWh/year)
Contingency
Year 1
Without Project
With Project
19
SRRM‐AC ( Examples: Project 1 EUE Contributions)
0
500
1000
1500
2000
2500
3000
3500
EUE C
ontribution (M
Wh/year)
Contingency
Year 5
Without Project
With Project
0
10
20
30
40
50
60
70
80
EUE Co
ntribu
tion
(MWh/year)
Contingency
Year 5
Without Project
With Project
20
SRRM‐AC (Examples: Average ΔEUE)
44
4078
885
60
797
70
500
1000
1500
2000
2500
3000
3500
4000
4500
P1 P2 P3 P4 P5 P6
Average An
nual Red
uctio
n in EUE
(MWh/Ye
ar)
P1 alone offers minimal reliability benefit to the system (1).The reliability impact of P2 (including both Line 12 and Station 7)are significant (10).The reliability benefit of P3 highly depends on the reliability levelof the new line‐Line 7 (6).The reliability benefit of P5 is significant (10).Minimal reliability benefit can be achieved from Projects 4 and 6and these projects may be deferred (1).
21
SRRM‐AC (Examples: Summary)
A probabilistic evaluation model for HVdc systemState selection uses the analytical contingency enumerationapproachState evaluation use capacity sufficiency
22
SRRM‐DC (General)
23
Converter Transformer
Valve Group
Smoothing Reactor
DC Line
Sending End
Receiving End
Bipole I
Bipole II
SRRM‐DC (HVdc System Components)
Sending End
Receiving End
Converter Transformer Smoothing
ReactorDC Line
Valve Group
Filter
Filter
Filter
Synchronous Condensers
SRRM‐DC (Reliability Data for HVdc Schemes)HVdc component and system reliability data are available from various sourcesfor example:Equipment Manufactures (Design phase): ABB, Siemens and AlstomPublished Industry Standard: IEEE Standard 500‐Reliability DataIndustry Experience (Operational Phase): CEA and CIGRE Reports.Manitoba Hydro has supported the activities of both CEA and CIGRE for datacollection and submitted data on the Nelson River HVdc system since early1970’s.
Statistics on HVdc system reliability can be broadly classified into twocategories as:Line related outages: DC line, Smoothing ReactorsTerminal related outages: Valve Group, Pole and Bipole
24
SRRM‐DC (Basic Modeling Technique)It is not realistic to analyze a complex engineering systems like HVdc schemes ina single step instead the system is modeled as a network of smaller sub‐systems.A reliability model for a particular HVdc system can be developed based onfailure mode and effect analysis:Outages of valve group controls, converter transformers, valves and switchingequipment that cause a loss of transmission capability equal to that of a valve groupcan be combined into a single reliability block representing a valve group by suitablecombination of their reliability models in series or parallel using the networkreduction technique.Similarly, outages of pole control equipment, d.c. filters, smoothing reactors andtransmission lines that result in a loss of capability equal to a pole capacity can becombined into a single pole element reliability model.Failures of main station control, a.c. filters, reactive power supply equipment (suchas synchronous condensers), transmission lines or ground electrode cause a loss ofcapability equal to that of a bipole can be lumped into a bipole reliability model.
Note: The HVdc system model developed using the above technique can beeasily incorporated into composite system reliability assessment.
25
SRRM‐DC (Basic Modeling Technique‐Reliability Diagram)
26
Load
Valve Group
Pole Station
Pole line
Pole Station
Valve Group
Bipole Station
Bipole Line
Generation
SRRM‐DC (Basic Modeling Technique‐Equivalent Reliability Diagram)
27
Load
Valve Group
Pole
Bipole
Generation
SRRM‐DC (Example‐Assumptions)
28
The generating system feeding into the HVdc transmissionsystem is 100% reliable with a capacity equal to the maximumcapacity of the HVdc system.All DC components are represented by two‐state modelsNo transmission lossesLoad is 100% factor equal to the maximum transmission capacityThe capacities associated with HVdc transmission system are asfollows:
Bipole I Bipole II
Valve Group 278 Valve Group 500
Pole 834 Pole 1000
Bipole 1668 Bipole 2000
SRRM‐DC (Example‐Component Outage Statistics)
29
Bipole I Bipole II
Component FOR r Component FOR r
Valves and controls 0.021 1.82 h Valves and
controls 0.0156 24 h
ConverterTransformers 0.01 6 m w/o spare
6 d w spareConverter
Transformers 0.01 6 m w/o spare6 d w spare
Pole‐Station 0.000325 0.52 h Pole‐Station 0.00096 1.2 h
Pole Transmission
line0.000085 0.20 h
Pole Transmission
line0.00017 0.5 h
Smoothing Reactor 0.00007 24 h Smoothing
Reactor 0.0066 6 m w/o spare6 d w spare
Pole DC line 0.00048 7 days Pole DC line 0.00048 7 days
Bipole Station 0.000025 0.19 h Bipole Station 0.000185 0.6 h
Bipole DC line 0.00038 7 days Bipole DC line 0.00038 7 days
SRRM‐DC (Example‐Scenarios Evaluated)
30
Case 1: Base CaseCase 2: Spare smoothing reactor on Bipole IICase 3: Spare smoothing reactor and converter transformer onBipole IICase 4: Spare smoothing reactor and converter transformer onBipole II and spare converter transformer on Bipole ICase 5: 100% Reliable HVdc
SRRM‐DC (Example‐Base Case COPT)
31
State Number State Capacity (MW) Probability1 3668 0.733379143
2 3390 0.139788552
3 3168 0.076589129
4 3112 0.011102056
5 2890 0.014598566
6 2834 0.002017872
7 2668 0.015765682
8 2612 0.001159423
9 2556 0.000158699
10 2390 0.003005078
11 2334 0.000210733
12 2278 4.83E‐06
13 2168 0.000718817
14 2112 0.000238664
15 2056 1.66E‐05
16 2000 0.000360017
17 1890 0.000137013
SRRM‐DC (Example‐Base Case COPT)
32
State Number State Capacity (MW) Probability18 1834 4.34E‐05
19 1778 5.04E‐07
20 1668 0.000531788
21 1612 1.09E‐05
22 1556 3.41E‐06
23 1500 3.76E‐05
24 1390 0.000101364
25 1334 1.98E‐06
26 1278 1.04E‐07
27 1112 8.05E‐06
28 1056 1.56E‐07
29 1000 7.74E‐06
30 834 1.46E‐06
31 778 4.73E‐09
32 556 1.15E‐07
33 500 3.53E‐07
34 278 3.50E‐09
35 0 2.61E‐07
SRRM‐DC (Example‐Reliability Indices Calculations)
33
Annual Expected Energy Generated (EEG)
Annual Expected Energy Transmitted (EET)
Annual Expected Energy Curtailed (EEC)
8760max CEEG
n
iiiPCEET
18760
EETEEGEEC
SRRM‐DC (Example‐Results)
34
Case EEG (GWh/yr) EET (GWh/yr) EEC (GWh/yr)
1 32123 31067 10562 32123 31175 9483 32123 31342 7814 32123 31480 6435 32123 32123 0
Closing Comments
35
Relative values (∆EUE) versus absolute values. Energy related index such as ∆EUE can easily be translated into a monetaryvalues. For now MH is focusing on the physical aspect of power system in reliabilityassessment, MH will consider the impact of cyber aspect as well in the future. The number of influencing factors on power system risk assessment increasesconsiderably into the future, resulting from expected changes in the powerindustry such as smart‐grid initiatives, increased utilization of variable energysources, penetration of electric vehicles, distributed generation, storagetechnologies and demand response programs. Electric power utilities need to make relevant and necessary changes to thecurrent risk assessment approaches and practices, and new models andtechniques are needed to be developed in order to deal with those structuraland technological changes in the power industry. Big data and machine learning could play a crucial rule in future powersystem reliability assessment.
36
© 2018 Electric Power Research Institute, Inc. All rights reserved.
Anish Gaikwad, EPRIPr. Project Manager
Nick Wintermantel, Astrape ConsultingPrincipal
NERC Webinar on Composite Resource Adequacy & Trans. Reliability Planning
2018 June 12
Composite Reliability Analysis using Probabilistic Tools - Linking Probabilistic Resource Adequacy & Transmission Reliability Tools
2© 2018 Electric Power Research Institute, Inc. All rights reserved.
Outline
Conceptual background
Overview of the tools used
Case studies
Proposed future work
Reference: EISPC Case Studies Report (https://pubs.naruc.org/pub.cfm?id=536DCE1C-2354-D714-5175-E568355752DD)
3© 2018 Electric Power Research Institute, Inc. All rights reserved.
Resource Adequacy & Production Costing Tools. Most use probabilistic techniques.
Transmission Planning Tools. Most are deterministic in nature, very few use probabilistic methods (only for power flow analysis).
The premise of the work is to link probabilistic resource adequacy and probabilistic transmission planning tools for comprehensive reliability assessment.
4© 2018 Electric Power Research Institute, Inc. All rights reserved.
Resource Adequacy & Production Costing Tools Aim to simulate how generators on a given system are likely to operate
over a specified length of time, usually at least one year.
Most of them use probabilistic approaches
Various levels of detail on– Generator characteristics– Load forecasts– Variable generation forecasts– Ancillary services– Transmission– Fuel prices– Energy limits on hydro– Outage rates & maintenance schedules– Area interchange
5© 2018 Electric Power Research Institute, Inc. All rights reserved.
Resource Adequacy & Production Costing ToolsStudies are performed for hourly or sub-hourly analysis
Models could be “zonal” or “nodal”– Zonal models do not capture detailed transmission representation– Nodal models capture the impact of transmission congestion &
associated rescheduling of generationHowever, transmission deliverability is not robustly assessed
– No full AC power flow is availableCommercially available tools
– SERVM, PROMOD IV, PLEXOS, ProMaxLT, UPLAN, PSO, AURORA, GE MAPS
– SERVM was used for the case studies described later
6© 2018 Electric Power Research Institute, Inc. All rights reserved.
Probabilistic Transmission Reliability Tools Full representation of the transmission system along with generation
systemAll the modern tools have full AC power flow solutionCan’t typically analyze hourly scenarios due to computational burdenVery few tools use probabilistic approaches TransCARE was used for the studies described later
Name Power Flow Approach
Contingency Selection Approach
Availability
TransCARE from EPRI
AC and DC State enumeration Commercially available
SIEMENS PTI PSSE’s Reliability Assessment Module
AC and DC State enumeration Commercially available
NH2 from CEPEL (Brazil)
AC and DC Monte Carlo Not known
MECORE DC Hybrid analytical and Monte Carlo
No, used in-house at BC Hydro
7© 2018 Electric Power Research Institute, Inc. All rights reserved.
Thousands of views of future to account for uncertainties
Simulate hourly production costs for the study year (8760 hours) using SERVM
Select a few hours using various criteria (for e.g. high load hours, MW on outage)
for which no EUE is reported
Build network cases for the selected hours
Perform probabilistic reliability analysis in TransCARE or PSS/E to analyze impact
of transmission constraints
Approach to Linking the Two Analyses Research questions to address:
– Which scenarios to pick from SERVM?
– What is the incremental Expected Unserved Energy (EUE) due to transmission unreliability?
– Can we extrapolate results for a few hours to the entire (8760) load duration curve?
– What other risk-based indices, in addition to EUE can be used for analysis?
– How scalable the approach is for practical interconnections (ISO-wide or for a vertically integrated utility)?
8© 2018 Electric Power Research Institute, Inc. All rights reserved.
An Overview of SERVM
9© 2018 Electric Power Research Institute, Inc. All rights reserved.
SERVMSERVM has over 30 years of use and development
Probabilistic hourly and intra-hour chronological production cost model designed specifically for resource adequacy and system flexibility studies Takes into account all unit constraints: ramp rates, startup times, minup/mindown times, etc. Commitment decisions on the following time intervals allowing for recourse Week Ahead Day Ahead 4 Hour Ahead, 3 Hour Ahead, 2 Hour Ahead, 1 Hour Ahead, and Intra-Hour Load, Wind, and Solar uncertainties at each time interval (decreasing as the prompt hour
approaches)
SERVM calculates both resource adequacy metrics and costs
10© 2018 Electric Power Research Institute, Inc. All rights reserved.
SERVM Applications Resource Adequacy Loss of Load Expectation Studies Optimal Reserve Margin Operational Intermittent Integration Studies Penetration Studies System Flexibility Studies
Effective Load Carrying Capability of Energy Limited Resources Wind/Solar/Demand Response/Storage
Fuel Reliability Studies Gas/Electric Interdependency Analysis Fuel Backup/Fixed Gas Transportation Analysis
Transmission Interface Studies
Resource Planning Studies Market Price Forecasts Energy Margins for Any Resource System Production Cost Studies Evaluate Expansion Plans/Environmental Decisions/Retirement Decision
11© 2018 Electric Power Research Institute, Inc. All rights reserved.
SERVM Framework Capture Uncertainty in the Following Variables Weather (35 years of weather history) Impact on Load and Resources (hydro, wind, PV, temp derates on thermal resources) Economic Load Forecast Error (distribution of 5 points) Unit Outage Modeling (1000s of iterations) Fuel Price and Availability Regulatory Uncertainty
Multi-Area Modeling – Pipe and Bubble Representation
Total Base Case Scenario Breakdown
x =
175Load Scenarios
x 100Unit Outage Draws
= 17,5008760 Hour Simulations
35Weather Years
(Equal Probability)
5LFE Points
(Associated Probabilities)
175Load Scenarios
(Associated Probabilities)
12© 2018 Electric Power Research Institute, Inc. All rights reserved.
An Overview of TransCARE
13© 2018 Electric Power Research Institute, Inc. All rights reserved.
TransCARE - Tool for Assessing Transmission Reliability
Up to 10 Power Flow
Cases
Outage Data
StudySettings
Frequency, Duration,
Expected Values of:
Overloads
Voltage Violations
Load Curtailment
System islanding
Reliability indices can be calculated at system level, bulk load points, or for individual components
Load Shapes & Duration or Probabilities
TransCARE is a research grade tool. Other than PSS/E Reliability Module and TransCAREno viable tools are available
14© 2018 Electric Power Research Institute, Inc. All rights reserved.
TransCARE at a Glance• PSS/E .sav or PSLF .epc• Up to 75K buses, 112,500 circuits• Up to 10 different power flow cases
Network Information
• Enumeration, as well as user defined can be analyzed• Outage of up to 5 lines and 4 units per contingency• Protection & Control Group
Contingencies
• Unit margin• Participation factor• Full economic (not fully tested)
Generation Dispatch
• Forced outage rate/year and duration per outage• Common mode outage stats (if used)• % split between interruptible, firm, & critical load
Outage Stats
• For breaker-to-breaker contingencies• Automatically places breakers for evaluation (beta version)Protection & Control Groups
• Up to 11 elements out (5 gen, 6 lines)• Reports system prob., load loss, gen. tripping, ckt. Tripping, islands, redispatch info.Cascading Analysis
• System/bus/asset reliability indices, load loss indices, bus load loss summary, remedial actions summary
• Database feature for easy data processingReporting
15© 2018 Electric Power Research Institute, Inc. All rights reserved.
TransCARE: Input/Output FilesLoad Flow
Data
Generator
Data
Generator
Outage
Common Mode
Outage
Must Run
Contingencies
Circuit/PCG
Outage
Load Curve
DataBus
Characteristic
Network
Adjustments
TransCARE
INPUT FILES
Group I - Base case resultsGroup II - Input data filesGroup III - Contingency ranking reportsGroup IV - Contingency solution reportsGroup V - System failure reportsGroup VI - Reliability indices reportsGroup VII - PCG reports
REPORT FILES:
7 GROUPS
16© 2018 Electric Power Research Institute, Inc. All rights reserved.
Reliability Assessment using Siemens PTI PSS/E – Process
17© 2018 Electric Power Research Institute, Inc. All rights reserved.
Case Study 1 – Composite Reliability Analysis Using Roy-Billinton Test System
18© 2018 Electric Power Research Institute, Inc. All rights reserved.
RBTS – Case Setup 6 buses, 9 transmission lines, 230 kV transmission system185 MW peak load, 240 MW
installed capacity, 11 unitsLoad duration curve is shown:
0
20
40
60
80
100
120
140
160
180
200
125
250
375
410
0512
5615
0717
5820
0922
6025
1127
6230
1332
6435
1537
6640
1742
6845
1947
7050
2152
7255
2357
7460
2562
7665
2767
7870
2972
8075
3177
8280
3382
8485
35
MW
Hour of Year (Sorted by Load)
19© 2018 Electric Power Research Institute, Inc. All rights reserved.
RBTS – Study Summary SERVM was used to create multiple load-generation scenarios– Out of this, 50 scenarios were selected– For each scenario, a power flow case was
developed (a total of 50 power flow cases)
For each scenario, a corresponding list of contingencies involving generation and transmission components was generated
For each case, the contingencies were run in TransCARE along with remedial actions
For each scenario, EUE was computed
A non-linear curve was fit to the data. The formula was extrapolated to the entire load duration curve
Capacity deficiency in SERVM – 9MWh/yr
Total network related EUE based on TransCARE analysis – 123MWh/yr
20© 2018 Electric Power Research Institute, Inc. All rights reserved.
RBTS – Key Takeaways
EUE was found to be significantly correlated to load levelThe approach computes two separate EUEs
– Generation deficiency in SERVM (9MWh)– Network related EUE (123 MWh)
The case study illustrated that resource adequacy modeling that assumes perfect deliverability within a balancing authority may be ignoring a significant portion of possible reliability events.
21© 2018 Electric Power Research Institute, Inc. All rights reserved.
Case Study 2 – Composite Reliability Analysis Using TVA System
22© 2018 Electric Power Research Institute, Inc. All rights reserved.
Probabilistic Economic Analysis –Probabilistic Production Costing Analysis Using SERVM Study 2015, 2020, 2025, and 2030
Capture uncertainty in the following variables by stochastically simulating many scenarios with 1000s of iterations Weather (33 years of weather history) Impact on Load Impact on Intermittent Resources Economic Load Forecast Error (distribution of 7 points) Unit Outage Modeling (1000s of iterations) Multi-state Monte Carlo Frequency and Duration Multi-Area Modeling Neighbor Load and Resources Fuel/CO2 Forecasts
Total Scenario Breakdown: 33 weather years x 3 LFE x 3 Fuel CO2 Scenarios = 297 scenarios for each year Total Iteration Breakdown: 297 scenarios * 10 unit outage iterations = 2,970 iterations for each year
23© 2018 Electric Power Research Institute, Inc. All rights reserved.
TVA Case Study Setup 20 scenarios were picked for the case study (6 are shown in the figure)
For each scenario, a power flow case was developed
For each scenario, 3000 contingencies were developed using Monte Carlo simulation– Contingency depth was limited to
9 components (both generator and transmission elements)
27,000
28,000
29,000
30,000
31,000
32,000
33,000
34,000
35,000
36,000
0 2 4 6 8 10 12 14 17 19 21 23 25 27 29
TVA
Load
Lev
el
Hour of Year
24© 2018 Electric Power Research Institute, Inc. All rights reserved.
TVA Case Study Analysis SERVM runs by themselves did not indicate any generation adequacy problemsSome correlation exists
between load level and system problemsOverall, about 20,000
contingencies resulted in problems– About 2200 resulted in load
loss
0
500
1,000
1,500
2,000
2,500
25,000 27,000 29,000 31,000 33,000 35,000
Cou
nt o
f Con
tinge
ncie
s W
ith
Syst
em P
robl
ems
TVA Load Level (MW)
The assumption of perfect delivery of power is likely not reasonable.
25© 2018 Electric Power Research Institute, Inc. All rights reserved.
TVA Case Study Analysis
Positive correlation between forced MW outage and system problemsOnly 30% - 50% of contingencies with < 500 MWs forced offline resulted
in system problems. A much larger 60% - 90% of contingencies with 1,500 MW to 2,000 MW
forced offline resulted in system problems
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 500 1,000 1,500 2,000 2,500
Perc
enta
ge o
f Con
tinge
ncie
s w
ith
Syst
em P
robl
ems
Generation Forced Offline (MW)
26© 2018 Electric Power Research Institute, Inc. All rights reserved.
TVA Case Study – EUE by Load LevelNot a strong correlation
between load level and EUE– Many contingencies could not
be solved in TransCARE and their contribution to EUE could not be assessed
The linear curve was extrapolated for the TVA load duration curve– 1128 MWh for the entire year
0
2,000
4,000
6,000
8,000
10,000
12,000
25,000 27,000 29,000 31,000 33,000 35,000
EUE
(MW
h)
TVA Load Level (MW)
Even with this approximate analysis, it is evident that potential reliability problems due to transmission unreliability need to be considered
27© 2018 Electric Power Research Institute, Inc. All rights reserved.
TVA Case Study – EUE by Load LevelEUE/contingency is shown on the 2nd Y-axisHigher load level corresponds to higher EUE/contingency
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
15,000
17,000
19,000
21,000
23,000
25,000
27,000
29,000
31,000
33,000
35,000
0 500 1,000 1,500 2,000 2,500 3,000 3,500
EUE
(MW
h)
TVA
Load
Lev
el
Hour of Year
Load
EUE
28© 2018 Electric Power Research Institute, Inc. All rights reserved.
Future Work
Expand on the concepts developed in the two case studies through more thorough case studies– Plan to work with NERC on new case studies
– How many scenarios should be considered? Is the answer system dependent?
– How to make the process of power flow case creation more efficient?Manual, time consuming process
– Provide guidance on when to perform composite reliability assessments
29© 2018 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity