Conchas Dam and Lake US Army Corps of Engineers Operations Division Albuquerque District Office Public Meeting 17 June 2013 US Army Corps of Engineers BUILDING STRONG ®

Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Conchas Dam and Lake

US Army Corps of Engineersy p gOperations DivisionAlbuquerque District Office

Public Meeting17 June 2013

US Army Corps of EngineersBUILDING STRONG®

Page 2: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Plan for evaluating seepage from three remaining service and emergency gatesservice and emergency gates

Difficulty setting bulkhead gate for other three conduitsDifficulty setting bulkhead gate for other three conduits Evaporation is 5 to 8 times more than seepage NM State Police underwater camera is being repaired and g p

should be available in July Results from the camera will assist with planning efforts

for possible divers to evaluate options for successfullyfor possible divers to evaluate options for successfully setting the bulkhead gates

Schedule for divers is largely dependent upon funding and g y p p gwhen they are available (soonest might be winter 2013-14)

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 3: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Conchas Reservoir ElevationTop of Dead Pool 4155.00

Assume: 2012 inflow, seepage = 6.5 cfsActual data to 12 Jun 2013

Big Mesa pump 9 ft under barge (Jul 2014)

NMSP pump (Jan 2014 Elev 4150.00)

g p p g ( )

(Elev 4147.55)

Big Mesa pump under barge (Feb 2016)

(Elev 4139.55)

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 4: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

South Boat Ramp Refocused efforts on South Ramp Challenge is flat slope 7% to 7.5% Expect CatEx by 24 Jun Extend concrete ramp ~60 ft to water Use “JR Landing Mats” for ~60 ft temp

boat ramp below the water Won’t be completed by 4 Jul Asking for 10-12 volunteers Sign up at the Project Office Unsafe to extend temporary ramp

b d i iti l 60 ft ( 7% l )beyond initial 60 ft (< 7% slope)

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 5: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Status of the Adobe Belle

Expect CatEx in July for roof and water line repairs/replacement If funds are available, expect to award contracts for both in August Plan to make repairs to sewage system in the winter of 2013-14 Other repairs to damaged adobe walls, walkways, electrical system

etc., will be made as needed and funds are available The earliest the Adobe Belle will be ready to issue a solicitation for

a concessionaire lease is spring 2014

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 6: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Status of the Southside Lodge

Gates have been installed to minimize vandalism and ATV access Operations is evaluating the alternatives report from the Walla

W ll Di t i t (SME f hi t i t )Walla District (SME for historic assets) Walla Walla will also complete a structures inventory in spring 2014 Both reports, and recommended course of action, will be submitted

to SHPO (State Historic Preservation Office) for final approval The soonest final approval from SHPO will be obtained is likely late

summer 2014 The soonest funding “might” be available will be late 2014 Update from Vic Harp on possible outsourcing to a non-profit

veteran’s organizationg If a non-profit organization can’t be found, and there are no viable

alternative uses, the Lodge will likely be demolished

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 7: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Completed & On-going Southside Recreation Area Work

12 foot extension of South Boat ramp last summer Opened gate to allow shoreline access for land based recreation Installed 5 campground shelters Extensive shoreline cleanup (560 tires and 20 tons of misc debris) Mowing and campground cleanupg pg p Removed dead and down trees and other vegetation Volunteers are watering trees, collecting trash, maintaining

campground, promoting water safety awareness, etc.campground, promoting water safety awareness, etc. Replaced barriers with gates

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 8: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Planned Southside Recreation Area Work

~60 foot permanent extension of South Boat ramp to water’s edge ~60 foot temporary South Boat ramp under the water Plant native drought tolerant trees Repair water lines in the campground Replace information sharing bulletin boards at boat ramp and p g p

campground Install 8 additional campground shelters (funding?) Install two permanent vault toilets at the campground (funding?)Install two permanent vault toilets at the campground (funding?) Extend mid-ramp to the parking lot (funding?)

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 9: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Shoreline Management Approvals in Flowage Easement

O ti i d l i h li t li f k Operations is developing a shoreline management policy for work by private land owners in the flowage easement

Until that policy is finalized, Operations will evaluate requests for work by private land owners on a case-by-case basis Approval from USACE Operations Division USACE has right to flood No habitable structures Any constructed features must not impact reservoir operations 404 Permit required for disturbing soil below 4201.0 ft

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 10: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

Irrigation Intake Channel Sediment Removal Project

Agreements exist between USACE, Reclamation, and Arch Hurley Conservancy District (AHCD) for O&M of the water delivery system from Conchas Dam

Channel has never been cleaned out Low lake levels make this an opportune time

t l t th h lto clean out the channel Approvals obtained and work began 10 Jun Reclamation is ahead of schedule and should

complete removing 5000 cu yds by 20 Juncomplete removing ~5000 cu-yds by 20 Jun Once work is complete, AHCD intends to wait

until the reservoir reaches ~4161.5 ft before taking water by gravity flow for irrigationtaking water by gravity flow for irrigation

Agreements do allow AHCD to pump water between 4155.0 ft and 4161.5 ft, however they are not in a position to do so at this time

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST

Page 11: Conchas Dam and Lake - United States Army...Actual data to 12 Jun 2013 Big Mesa pump 9 ft under barge (Jul 2014) NMSP pump (Jan 2014 Elev 4150.00) gpp g( ) (Elev 4147.55) Big Mesa

US Army Corps of EngineersContact Information

Karl MartinChief, Lakes and Assets Branch505-342-3144505 342 [email protected]

Steve PetersonLake Manager, Conchas [email protected]

Conchas Lake:

http://www.spa.usace.army.mil/Missions/CivilWorks/Recreation/ConchasLake.aspx

Click "Attention Conchas Lake Enthusiasts“ for the latest updates

BUILDING STRONG®CORNERSTONE OF THE SOUTHWEST