CONFIGURATION MANAGEMENT PROCESS
Version 2.2
TT/CMMI/SUP/CMP
Private and Confidential
No part of this publication may be reproduced or distributed in any form or by any means, or stored in a database or retrieval
Configuration Management Process
Reference No Version Page No
TT/CMMI/SUP/CMP 2.2 2/20
Amendment Record
Version No Changes / Remarks Prepared By Approved By Releas
e
Date
2 Update Process Ho Kian Ping Daryl Choo 18/11/2015
2.1 Update process to align with ISMS
Ti Hooi Suan Daryl Choo 01/08/2017
2.2 Added definition of work product, CI
Ti Hooi Suan Daryl Choo 25/01/2018
Configuration Management Process
Reference No Version Page No
TT/CMMI/SUP/CMP 2.2 3/20
TABLE OF CONTENTS
Page no
CONFIGURATION MANAGEMENT PROCESS ........................................................................................ 4
1.0 PURPOSE AND SCOPE ........................................................................................................................................... 4
2.0 GLOSSARY.............................................................................................................................................................. 4
3.0 ROLES AND RESPONSIBILITY................................................................................................................................... 5
4.0 PROCESS FLOW DIAGRAM ................................................................................................................................... 7
5.0 LIST OF PROCEDURES ........................................................................................................................................... 12
6.0 PROCEDURE DESCRIPTION ................................................................................................................................. 13
6.1. Prepare CM Plan ....................................................................................................... 13
6.2. Setup CM Environment ............................................................................................. 14
7.0 MEASUREMENT ..................................................................................................................................................... 19
8.0 TAILORING OPTIONS ........................................................................................................................................... 20
9.0 QUALITY RECORDS .............................................................................................................................................. 20
Configuration Management Process
Reference No Version Page No
TT/CMMI/SUP/CMP 2.2 4/20
Configuration Management Process
1.0 Purpose and Scope
The purpose of this Configuration Management (CM) process is to
establish and maintain integrity of work products using configuration
identification, configuration control, configuration status accounting,
and configuration audits.
CM activities include:
• Preparing CM Plan
• Placing identified configuration items (CI) into repositories
• Tracking and controlling changes of CI(s)
• Maintaining configuration records
• Performing configuration audits
2.0 Glossary
Abbreviation Description
CC Configuration Controller
CCB Change Control Board
CI Configuration Item
CM Configuration Management
CR Change Request
DAR Decision Analysis & Resolution
PAL Process Asset Library
PD Project Director
PDM Product Manager
PM Project Manager
SA System Analyst
SEPG Software Engineering Process Group
SQA Software Quality Assurance
Configuration Management Process
Reference No Version Page No
TT/CMMI/SUP/CMP 2.2 5/20
Terms Definition
Configuration
audit
An audit conducted to verify that a configuration
item or a collection of configuration items that make
up a baseline conforms to a specified standard or
requirement.
Configuration
baseline
The configuration information formally designated at a
specific time during a product’s or product
component’s
life.
Configuration
control
An element of configuration management consisting
of the evaluation, coordination, approval or
disapproval, and implementation of changes to
configuration items after
formal establishment of their configuration
identification.
Configuration
item
An aggregation of work products that is designated for
configuration management and treated as a single
entity in the configuration management process.
Configuration
identification
An element of configuration management consisting
of selecting the configuration items for a product,
assigning unique identifiers to them, and recording their
functional and physical characteristics in technical
documentation.
Configuration
management
A discipline applying technical and administrative
direction and surveillance to (1) identify and
document the functional and physical characteristics
of a configuration item, (2) control changes to those
characteristics, (3) record and report change
processing and implementation status, and (4) verify
compliance with specified requirements.
Configuration
status
accounting
An element of configuration management consisting
of the recording and reporting of information needed
to manage a configuration effectively.
Work product A useful result of a process. This result can include files,
documents, products, parts of a product, services,
process descriptions, specifications, and invoices. A key
distinction between a work product and a product
component is that
a work product is not necessarily part of the end
product.
Configuration Management Process
Reference No Version Page No
TT/CMMI/SUP/CMP 2.2 6/20
3.0 Roles and Responsibility
CC
• Setup repositories to store CIs and non-CIs.
• Controlling changes to baseline
configuration items.
• Making changes to version control of CI
according to the defined procedure.
• Ensuring backup of CIs and non-CIs.
• Accounting for status of identified CIs and non-
CIs. • Publish periodic reports related to CM for the PM
SA • Ensure developers support CM processes
PM
• Responsible for planning, directing,
controlling, structuring and motivating the
project.
• Ensure adequate CM resources, including CM
tools, are made available.
• Ensure CM requirements, processes, and
practices
• are conveyed to all project members.
CCB • Review all proposed CRs.
• Assess change impacts.
• Review modifications to all documentation.
Head of CCB • Chair the CCB meeting
• Approved/reject CR
SQA • Ensure quality of the process
Configuration Management Process
Reference No Version Page No
TT/CMMI/SUP/CMP 2.2 7/20
4.0 Process Flow Diagram
Prepared Configuration Management Plan
SUPPORT
CC briefs/train the project
SQA reviews the draft CM plan.
Project Manager identifies the Configuration Controller.
Configuration Management Process
Reference No Version Page No
TT/CMMI/SUP/CMP 2.2 8/20
Setup Configuration Management Environment
SUPPORT
CC briefs/train the project team members on the CM
CM environment setup by CC
PM, SQA or SA of the project.
Configuration Management Process
Reference No Version Page No
TT/CMMI/SUP/CMP 2.2 9/20
PAL Repository
SUPPORT
into appropriate repository
CC confirms the submitted work product is configured as
per CM plan.
Project team member notifies
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 10/20
SUPPORT
Change Request Procedure
START
The initiator fills the CR Form (Part A)
PM allocates the project team
member to perform the impact
analysis and update in CR Form
(Part B)
Management reviews and
approved/reject the CR based
on Impact Analysis performed.
END
PM will inform project team
member to precede the
change implementation.
Change Request
Form (Part A)
Change Request
Form (Part B)
Change Request
Form (Part C)
Approved?
Yes
No
PM update the implementation
status.
Change Request
Form (Part D)
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 11/20
PAL
Backup External Hard
Repositories Backup
SUPPORT
Label/tag the backup files
performed per policy
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 12/20
5.0 List of Procedures
1. Prepare CM Plan
2. Setup CM environment
3. Acquire CI and Non CI
4. Change request procedure
5. Repositories backup
6. CM audits and CM reporting
CM Checklist
SUPPORT
Baseline Audit perform by the
Identify the types of audit to
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 13/20
6.0 Procedure Description
6.1. Prepare CM Plan
Entry Criteria 1. Project Initiation Note is issued.
2. Project Manager is assigned to the project.
3. Project members are identified.
Inputs 1. Project Initiation Note
2. CM Plan template
Steps 1. PM identifies CC.
In small project, PM can handle role of CC.
In medium to large projects, CC role may be distributed to
multiple project team members.
2. PM confirms CC has necessary skills to perform the CC role.
PM arranges CC-role based training, if required by SEPG.
3. CC prepares CM Plan.
This involves:
■ Identifying Configuration Items & repositories (refer to CI
Master List)
■ CM related roles & responsibilities
■ Configuration management strategies
■ Backup policy
■ Identifying the composition of CCB. CCB typically
consists of Project Manager, Project Configuration
Controller, SA, PDM, and other relevant stakeholders.
■ Change management procedure
■ Naming & version numbering convention
■ CM Report
■ CM Audit frequency
Guidelines: CI Master List
CM Templates :CM Plan
4. CM Plan is reviewed by SQA using a checklist as per Review
Process and will be baselined.
Review comments are incorporated and verified as per
Review Process
CM Checklist :Checklist for CM Plan Review
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 14/20
5. CC baselines CM Plan. Subsequent changes to CM Plan
are handled using ‘Control Changes to Configuration
Items’ procedure of this process.
6. CC briefs project team members on:
• CM related processes & workflow
• CM repositories
Outputs 1. CM Plan
Exit Criteria 1. CM Plan is baselined after closure of review comments
6.2. Setup CM Environment
Entry Criteria 1. Baselined CM Plan
2. File server for CM.
Inputs 1. Baselined CM Plan
2. CI Master List
Steps 1. CC sets up the following CM environment as required to
implement CM Plan:
• Controlled repository structures
• Security (read/write) access
• Release options
2. CM environment set up by CC at project level is reviewed
by PM, SQA or SA of the project. Issues raised are tracked
to closure.
3. CC briefs project team members on CM environment.
Output 1. CM environment
Exit Criteria 1. CM environment is reviewed and ready for use
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 15/20
6.3. Acquire CI and Non-CI.
*ISMS ISO 27001:2013 Clause 7.5 Documented Information is applicable here.
Entry Criteria 1. CI Master List/ISMS Document Master List updated with
new
CI or Non-CI
Inputs 1. Newly submitted CI or Non-CI
2. CM Plan
Steps 1. Project member notifies CC that the CI is ready to be
baselined.
Baseline means a set of specifications or work
products that: -
■ Has been formally reviewed and agreed on.
■ Which thereafter serves as the basis for
further development
■ Which can be changed only through change
control procedures
2. CC confirms the following:
• Submitted work product is a configuration
item as per CM Plan
• Work product has a unique identifier
• Work product has been reviewed or tested
• Work product follows a defined CI Master List
Guideline : CI Master List, ISMS Document Master List
3. Work product shall be baselined when there is no
defect found.
4. CC checks in the CI/Non-CI into appropriate
repository (depending on development phase)
with the correct name, unique identifier and
version number.
5. CC updates CI List. CC also conducts configuration
status accounting on periodic basis.
CM Template :CI List, CM Plan
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 16/20
6. CC confirms the submitting project member
that the CI/Non-CI has been checked in to the
repository.
Outputs 1. New CI/Non-CI in the Baselined Repository
2. CI List
Exit Criteria 1. CI/Non-CI is checked in the Baselined Repository
2. Updated CI List / ISMS Document Master List
6.4. Control Changes to CI / Change Request Procedure
Entry Criteria 1. When a Change Request is initiated
Inputs 1. Change Request
Steps 1. CR Part A: Initiation The PDM fills the CR Form when there is a request that is
varied from the baselined user requirement. A copy of the
CR form is sent to CC and CC makes an entry in CR
Tracking Register.
CM Forms :CR Form
CM Templates: CR Tracking Register
2. CR Part B: Impact Analysis Once the CR form is registered into the CR Tracking Register
the following steps are performed:
• PM allocates the project team member to perform
the impact analysis who will then update the analysis
content to the CR form (Part B).
• Impact analysis is performed to analyze the impact on
schedules, resources and plans and estimate is made
on the total effort and size required for the change
3. When a CR is in progress and another CR comes up and it is
interdependent to the earlier CR then this “Change on a
Change” situation will be handled by creating the new
change received as a separate CR and would be executed
likewise based on priority as per the defined CR process.
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 17/20
4. CR Part C: Change Request Disposition CCB reviews and approves/rejects the CR based on Impact Analysis performed. If the CR is approved, the CCB shall determine whether the CR is chargeable or not. DAR may be used to determine the decision making.
5. CR Part D: Implementation Status • PM will inform project team member to proceed
with
the change implementation.
• Project team member then makes the necessary
changes.
• The modified CI together with the CR form will
undergo formal review process.
• Project team member informs CC of
completed change request.
6. CC checks in the CI into Baselined Repository with the
correct name, unique identifier and version number.
7. CC updates CR Tracking Register.
8. CC updates CI List
Outputs 1. Chargeable or free CR
2. CR Tracking Register
3. CR Form
4. CI List
Exit Criteria 1. CR is closed
2. CR Tracking Register status is set to “Closed” or “Rejected”
6.5. Repositories Backup
Entry Criteria 1. Source code backup daily
2. Project related documents backup weekly
Inputs 1. Project’s repositories
2. External Hard Disk
Steps 1. PM or CC ensure the backup is performed by System
Engineer
2. Frequency and naming convention of backup is as
defined in CM Plan.
3. The backup external hard disk are labeled with:
■ Type (Source Code, Documents)
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 18/20
■ Date of backup
Outputs 1. Backup External Hard Disk
Exit Criteria 1. Successful backup carried out and verified by PM.
6.6. CM Audits and CM Reporting
Entry Criteria 1 Successful review of CM Plan
2 Project is in execution phase
Inputs 1 CM Plan
2 CI List
Steps 1 CC identifies types of audit to perform in the project.
Audits
performed are:
• Baseline audit which focuses on the product and
work product and is done before an item is base
lined
• Configuration management audit which is
typically performed and focuses on conformance
to the configuration management process and
conforms to the physical characteristics
expected in terms of location, etc.
2 CC determines frequency of each audit to be
performed and documents the frequency in the
Configuration Management plan.
CC also determines the stakeholder responsible to
perform the audits.
• Baseline audit is performed by reviewer
• Configuration management audit is performed by
SQA
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 19/20
3 CC assists SQA in performing audits. Audits are
performed using a defined checklist. Audit results are
documented in QA Audit Report as per Process and
Product Quality Assurance Process.
SQA reports any non-conformances to the Project
Manager.
CC closes any non-conformances found during audit.
Checklist: CM Checklist
Forms: QA Report
Forms: Non-compliance Form
4 CC maintains the latest CM Plan and all
configuration management related records such
as CI List and CR Tracking Register
5 System Engineer performs backup activities.
PM or CC perform random retrieval to check integrity of
the backups.
6 Brief new members of the project on configuration
management and CM tool.
7 SQA conducts Phase End CM audit and sends QA
Audit Report to PM.
Forms: CI List
Forms: QA Audit Report
Output 1 CI List
2 QA Audit Report
Exit Criteria 1 Project is complete
7.0 Measurement
None identified
Configuration Management Process
Reference No Version Page No
FT/CMMI/SUP/CMP 2.2 20/20
8.0 Tailoring Options
Refer to the Process Tailoring Document
9.0 Quality Records
Output / Record Retention Responsibility
CM Plan, CR Form, CR Tracking
Register, CI List, ISMS Document
Master List
Retained by CC until project completion
Retained by PAL for 7 years thereafter
Defect Tracking Logs of CM Plan Retained by CC until project completion
NAS / Cloud storage Retained by CC until project completion
Retained by PAL for 7 years thereafter
~ End of Document ~