namma metroConstruction challenges
A circular railway of 57.9 km metro system on two corridors
Phase-I 12.9 km - Rajajinagar to Jayanagar
Phase - II 11.2 km-Hudson Circle to Krishnaraja puram.
Phase III
Phase IV
*INTRODUCTION
CLIENT : BANGALORE METRO RAIL COROPORATION LIMITEDCONSULTANT: RITES
L&TS SCOPE : REACH -III - 3 STATIONS REACH- IV -3 STATIONS
*INTRODUCTION
*METRO ROUTE MAP
East West Corridor : 18.10 kmsNorth-South Corridor : 24.20kmsTotal : 42.30 kmsElevated : 32.85 kmsAt grade (at ground level) 00.65 kmsUnder ground 08.80 kmsGauge standard gaugeTraction 750 v Dc third railNo of stations 39(31 elevated,8 Ug) Travel time 33/44 mins (end to end)Head way 4 mins at start ; later 3 mins
CHALLENGES IN NAMMA METRO CONSTRUCTION:
Traffic volume & diversion Deep excavation (6 m from road level)Local Public issues / Project Affected PeopleExisting utilitiessafetyEnvironmental aspects Space constraints (Stacking ,Transporting &Erection Of Precast Girder) Media Focus (Increased spot lights ) Quality of skilled labour
Challenge: 1.Traffic Volume & Diversion
Safety of public & workmenProductivity Progress
Both the footpaths are demolished and Constructed for temporary road6M6M12MSTAGE 1
6M6MSTAGE 1EXISTING PATHWAY TO BE DEMOLISHEDERCT THE BARRICATIONMAKE THE TEMPORARY ROADPIER
L&T TRAFFIC MARSHALS ENGAGED WITH SIGNAL TORCH (FLUORESCENT LIGHT) AT NIGHT SHIFT BLINKER LIGHTS
Challenge 2 : Deep Excavation
Challenge: 3 Project affected people
a) Pre-construction stage Land acquisition/litigation
b) Construction stage, Noise pollution Air pollution Traffic diversion Utility diversion Working hours
Challenge: 4 Existing utilities
Identification of utilities
Interfacing with various agencies ( Govt / Non Govt) (BBMP,BWSSB,BESCOM,KPTCL,BSNL etc)
Challenge 5: safety
Safety
Pep talk conducted for Traffic Marshals and Workmen
Traffic signage and painted Hard barricading boards with Reflective ballet postsBallet post
Challenge 6: Environmental aspects
Some of the environmental components considered under this are
Trees Air pollution Noise levels Soil erosion and pollution Disposal of excavated soil and debris Maintaining of roads/Drainages
Challenge : space constraints
ImpactsCasting ,stacking& transportationErection scheme
Stacking ,Transportation & Erection Of Precast Girder
A major concern with girder erection is the security and stability of the superstructure
During all phases of erection with respect to construction conditions, wind loads and construction loads.
Stacking of the girders until the erection part comes & delivery of precast concrete girders to the site
Erection of precast girders with the traffic flow.
Erection Methodolgy for R4 06082009.pptTaking the above things in consideration L&T made a detailed erection scheme.
ResourceChallenge 9 : Quality of skilled labour
*******************