Executive Summary

Contract Number 07-01

General Contractor Western Water Constructors

Contract Bid Amount $35,550,000.00

Change Orders to Date 1

Pending/Anticipated Change orders 6 items

Notice to Proceed October 8, 2007

Original Contract Time 910 calendar days

Working Days Elapsed 116

Working Days Remaining 794

Milestone 1 (CCT & EPS) July 29, 2009

Milestone 2 (All other work) March 6, 2010

Rain days – Accepted to date 7 of 50 included within contract time

Contract Change Order(s) Time Extension 0

Final Completion Date April 5, 2010 Work Progress during January 2008 by Area or System: 1. General:

Western Water maintained the Storm Water Pollution Prevention Plan best management practices (BMPs). Western Water has submitted rain event inspection forms for the record. Western Water has continued routine weekly safety tailgate meetings, weekly safety checks, as well as the monthly safety audit performed by their safety officer. Reports of all these activities have been submitted for the record. Western Water conducted a Confined Space Entry safety class. This was coordinated with CMSA’s confined space program and Western Water has adapted their program to follow the more stringent guidelines. During this month Western Water has also submitted the revised Baseline schedule and monthly project photographs as required. The quarterly update of the “Dear Neighbor” letter was prepared for distribution. The website and progress photos were added to this update. A “First Scoop” drawing was held on January 23. With the help of the contractor’s operators, two CMSA staff members will operate an excavator and scoop dirt for the excavation work in the chlorine contact tank area, which is expected to occur in early February. On January 31, CMSA, Carollo, Harris & Associates, and Western Water representatives attended a half-day partnering session. All parties reviewed and re-established project goals.

2. Polymer Facility: Western Water has formed the walls for the sump pump and drain and the walls of the facility, backfilled and compacted aggregate base under the bottom slab. The bottom mat rebar was placed for the base slab. The electricians ran their conduit lines within the base slab area, prior to the concrete placement. The shoring for the sump area with the protective barrier fence remains within the roadway. Western Water also ran two 3-inch polymer lines, one 3-inch reclaimed water line and one 3-inch potable water line from the stubbed locations to the connection points in the Grit Chamber.

3. Gallery A & B Improvements, including Grit Chamber 3

Western Water continued work on the fire protection water line and began installation of the fire hydrant adjacent to the Headworks Building.

4. Primary Clarifiers 6 & 7

Subcontractor Condon-Johnson staged their storage van and rebar cages for the secant pile retaining wall along the plant road in the area of the new primary clarifiers.

5. Chlorine Contact Tanks 5 & 6 Subcontractor Stroer & Graff investigated and resolved the accident issue at the beginning of January. New safety goals were set for no injuries on the project. Stroer & Graff were allowed to continue installation of the shoring system in the chlorine contact tank and effluent pump station area. The beam installation is expected to be complete in early February and excavation of the area will begin shortly thereafter.

6. Effluent Pump Station

The activity in this area was the same as the activity in the chlorine contact tank area noted above.

7. Secant Retaining Wall and other Site improvements Subcontractor Condon Johnson began installation of the reinforced and unreinforced piles. Condon-Johnson completed the installation of the majority of the unreinforced piles within the first two weeks of January. This work involves drilling a hole to the required depth into the bedrock and filling it with unreinforced controlled low strength concrete. They also began installation of the reinforced piles between the unreinforced piles. This work involves drilling a hole to the required depth into the bedrock, placing a cylindrical reinforcing steel cage into the hole, then placing a large steel beam within the cylindrical rebar cage to within six inches of the bottom depth of the hole and filling the hole with plasticized concrete. The welding of Nelson Studs on the steel beams for the reinforced piles is on-going.

8. Review Item Summary

Please see attached RFI and Submittal logs in Section 3 for details of the following items. The majority of the certified payroll documents was received at the end of the month and will be reviewed and returned in early February.

Review Items Total Received to Date

Number Received in

January

Number Returned / Reviewed in January

RFIs 39 13 16 Submittals 163 40 41 Certified Payroll 65 22 2

9. Change Order Summary

Change Type & No. Description Cost Approved/Pending

Contract Change Order No. 001

One-time relocation of PG&E gas Line $0.00 Approved

Request for Quotation No. 001 / COR No. 002

Rotary Aeration Blower Roots 412 $5,333.70 Pending

Request for Quotation No. 002 / COR No. 004

Revise Headwall No. 001 at Polymer (Credit) -$2,000.00 Pending

Change Order Request No. 008

Additional Rebar at Sluice Gate Opening $800.00 Pending

Change Order Request No. 008

Additional Rebar at Pilaster Connections $900.00 Pending

Change Order Request No. 001

Delete Lightweight Backfill under manholes -$460.00 Pending

Change Order Request No. 003

Replacement of Broken Scum Cleanout $253.00 Pending

Change Order Request No. 002

Vehicle Incident requiring truck repair $1,400.00 Pending

Change Order Request No. 009

Pipe saddle in lieu of “T” in gallery TBD Pending

Change Order Request No. 005

Delete ship’s ladder on fuel tank TBD Pending

Change Order Request No. 006

Shared Partnering Costs per Contract TBD Pending

The pending items noted above will be negotiated and incorporated into contract change orders in February or March 2008.

10. Apprentices There has only been one apprentice on the project site for a short period. Apprentices will begin working once the crews become larger and more of the heavy construction begins. This is expected in March-April of 2008.

Work Activities planned for February 2008: • Continuation of Storm Water Pollution Prevention Plan • Place concrete slabs and walls at polymer facility with electrical conduits • Place reinforced concrete in Grit Chamber 3 area and complete Grit Chamber 3

improvements • Complete the installation of the pile and lagging shoring in the chlorine contact tank

(CCT) and effluent pump station area. • Begin excavation and off-haul of dirt from chlorine contact tank and effluent pump

station area. • Continue installation of the secant pile retaining wall, reinforced piles. • Complete installation of fire hydrant adjacent to Headworks Building. • Submittals provided for review

Wet Weather Improvements January 2008Photos taken 01.30.2008

Progress Photo 01 - Outfall Area Progress Photo 02 – View west at Chlorine Contact Tank; Shoring installation in progress

Wet Weather Improvements January 2008Photos taken 01.30.2008

Progress Photo 03 – Shoring installation at Chlorine Contact Tank & Effluent Pump Station Area

Progress Photo 4 – Shoring installation –looking East

Wet Weather Improvements January 2008Photos taken 01.30.2008

Progress Photo 05 – View East from Solids Handling Building – Shoring installation

Progress Photo 06 – View West from Solids Handling Building; Drill Rig bench and ramp

Wet Weather Improvements January 2008Photos taken 01.30.2008

Progress Photo 07 – Reinforced Secant Pile Retaining Wall Beams installed

Progress Photo 08 – Drill rig, crane, and steel reinforcing beams for secant pile retaining wall (east view)

Wet Weather Improvements January 3008Photos taken 01.30.2008

Progress Photo 09 – Polymer Facility Area (northwest view from HeadworksBuilding)

Progress Photo 10 – Polymer facility rebar and concrete forms for bottom slab (west view from Headworks Building)

Wet Weather Improvements January 2008Photos taken 01.30.2008

Progress Photo 11 – Detail: Drilling dewatering well at southwest corner of chlorine contact tank area

Progress Photo 12 – Detail: Sodium Bisulfate line at chlorine contact tank

CMSA - Wet Weather Improvement

Job No:Project No: Page:Page: 1 of 11 of 1

Date: 1/31/2008061-0491.0107-01

Open Requests for Information

Status Request Dated Responded RequiredIssueRFI Number From To TitleChange

Central Marin Sanitation Agency

1/22/2008 1/25/2008On Sheet S-9.5, Detail 2, the drawing show a typicalcantilevered parapet wall detail for the Chlorine ContactTanks. We propose to shorten the length of the hooksshown on the attached drawing. This will allow us tohave our wall forms unobstructed by these dowels. Wepropose to have hook lengths shorten as shown onAttachment A and similar to Detail AB on Sheet S-5.6 atthe Primary Clairifiers.

Thank you,

OPN00032 WESTWATR HARRIS Cantilevered ParapetReinforcement

1/31/2008 2/6/2008On sheet M-9.5 of the drawings typical detail S200 notesthat concrete will be chipped and hammered out anoversized hole in order to recover existing rebar andplace and grout a wall spool for the 16 inch 3 water pipeline to pass through the existing Chorine Contact TankWalls.

We propose to core drill a 20 inch hole for the 16 inchpipe. For each of the three interior walls we propose touse 1 link seal grouted in on both sides with 10,000 lbsgrout. For each of the two exterior walls we propose touse 2 link seals grouted in on both sides and betweenusing 10,000lbs grout. This is our recommendation.

Thank you

OPN00039 WESTWATR HARRIS CCT 1-4 Modifications16-Inch 3W

Report r_a_rfi_03_harris

Item No.

CMSA - Wet Weather Improvement

Open Submittal Log - Sorted by Submittal No.

Project No:Job No: 061-0491.01

07-01 Page:Date: 1/31/2008

1 of 2

Submittal TitlePackage Rev. FinishRequired

Status Rcvd. Sent Return Forward BICLatest Dates

Central Marin Sanitation Agency

111 Baseline Schedule01324-1.06-B 01324 002 OPN 1/30/2008 2/1/2008 HARRIS

158 Secant Pile Retaining Wall02339-1.05-Cap 02339 001 OPN 1/22/2008 1/23/2008 CAROLLO

032 Drilled Concrete Piers02467-1.04 A-K 02467 003 R&R 12/21/2007 12/24/2007 1/4/2008 WESTWATR1/18/2008

161 Chlorine Contact Tank Rebar03200-1.05-CCT 03200 001 OPN 1/28/2008 1/28/2008 CAROLLO

155 Class CE Mix Design03300-1.05-CE 03300 001 R&R 1/15/2008 1/17/2008 1/24/2008 WESTWATR1/25/2008

154 Class A - Trial Batch Data Mix 979603300-1.05-G 03300 001 OPN 1/15/2008 1/17/2008 CAROLLO

157 Metal Grating & Ladder Shop Dwg05500-1.03-B 05500 001 R&R 1/17/2008 1/17/2008 1/24/2008 WESTWATR1/25/2008

099 Metal Fabrications - Grating05500-1.03-B.3 05500 001 R&R 11/20/2007 11/27/2007 11/30/2007 WESTWATR12/3/2007

160 FRP Fabrications - Grating06611-2.02 GRT 06611 001 R&R 1/22/2008 1/23/2008 1/25/2008 WESTWATR1/28/2008

133 Steel Doors & Frames08110-1.03 08110 001 OPN 1/3/2008 1/4/2008 CAROLLO

133 Door Hardware - data & schedule08710-1.03 A&B 08710 001 OPN 1/3/2008 1/4/2008 CAROLLO

118 GromanRupp Model T6A3S-B Pump11312F-1.05-A 11312F 001 R&R 12/18/2007 12/18/2007 1/9/2008 WESTWATR1/10/2008

118 Spare Parts List11312F-1.11.B 11312F 001 R&R 12/18/2007 12/18/2007 1/9/2008 WESTWATR1/10/2008

118 US Motors Model H15P3B11312F-2.11.B 11312F 001 R&R 12/18/2007 12/18/2007 1/9/2008 WESTWATR1/10/2008

150 Progressing Cavity Pumps11312I-1.05 11312I 001 OPN 1/10/2008 1/11/2008 CAROLLO

131 Submersible Sump Pumps (EPS)11312K-1.05 11312K 001 R&R 1/3/2008 1/3/2008 1/25/2008 WESTWATR1/28/2008

162 Horizontal End Suction Pump w/O&M11312O-1.05A 11312O 001 OPN 1/29/2008 1/29/2008 CAROLLO

117 FRP Launders13120-1.03-A 13120 001 R&R 12/18/2007 12/18/2007 1/14/2008 WESTWATR1/15/2008

117 FRP Launders - Drawing B1013120-1.03-A 1 13120 001 R&R 12/18/2007 12/18/2007 1/14/2008 WESTWATR1/15/2008

117 FRP Launders - Drawing B1113120-1.03-A2 13120 001 R&R 12/18/2007 12/18/2007 1/14/2008 WESTWATR1/15/2008

117 FRP Launders - Drawing B1213120-1.03-A3 13120 001 R&R 12/18/2007 12/18/2007 1/14/2008 WESTWATR1/15/2008

117 FRP Launders - Drawing B1313120-1.03-A4 13120 001 R&R 12/18/2007 12/18/2007 1/14/2008 WESTWATR1/15/2008

117 FRP Launder Sample13120-1.03-B 13120 001 R&R 12/18/2007 12/18/2007 1/14/2008 WESTWATR1/15/2008

117 FRP Launders - Warranty13120-1.06 13120 001 R&R 12/18/2007 12/18/2007 1/14/2008 WESTWATR1/15/2008

151 Metal Building System13122-1.04 13122 001 OPN 1/10/2008 1/15/2008 CAROLLO

116 Polyethylene Storage Tanks13208-1.04 13208 R&R 12/13/2007 12/14/2007 1/9/2008 WESTWATR1/10/2008

163 Above Ground Fuel Storage Tank13209-1.04 13209 001 OPN 1/29/2008 1/30/2008 CAROLLO

135 Flow Field Inst. Magnetic Flowmeter13422-2.03 13422 001 OPN 1/29/2008 1/29/2008 CAROLLO

132 Pre-Action Automatic Sprinkler Syst13931-1.10 ABD 13930 001 R&R 1/3/2008 1/4/2008 1/21/2008 WESTWATR1/23/2008

034 Butterfly Valves15112-1.04A-C.1 15112 R&R 10/24/2007 10/24/2007 11/13/2007 WESTWATR11/13/2007

140 Quick Connect Hose Coupling15120-2.14 A-E 15120 R&R 1/3/2008 1/4/2008 1/17/2008 WESTWATR1/18/2008

145 Heat Tracing Cable15772-001 15772 001 R&R 1/3/2008 1/4/2008 1/17/2008 WESTWATR1/18/2008

128 Ductwork Accessories15820-2.02 15820 001 R&R 1/3/2008 1/3/2008 1/17/2008 WESTWATR1/18/2008

129 Type 1, Down Blast Centrifugal Roof15830-2.01 15830 001 R&R 1/3/2008 1/3/2008 1/28/2008 WESTWATR1/29/2008

129 Type 2, Up-Blast Centrifugal Roof15830-2.02 15830 001 R&R 1/3/2008 1/3/2008 1/28/2008 WESTWATR1/29/2008

129 Type 3, In Duct Fan15830-2.03 15830 001 R&R 1/3/2008 1/3/2008 1/28/2008 WESTWATR1/29/2008

149 Cooper B22 Channel16050-001 16050 001 NEW WESTWATR

149 Cooper Channel Nuts and Hardware16050-002 16050 001 OPN 1/9/2008 1/10/2008 CAROLLO

149 Screw Connection Terminal Blocks16050-003 16050 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Plug-in Style Terminal Blocks16050-004 16050 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Nameplates - Adhesive Backing16050-005 16050 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Warning Signs16050-006 16050 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Raceway Labels16050-007 16050 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Detectable Underground Tapes16050-008 16050 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Copperbonded Ground Rods16062-001 16062 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Ground Conductor16062-002 16062 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Christy G5 Ground rod Box16062-003 16062 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Shrink Dot Matrix Markers - 2.02.B16075-001 16075 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Markers TLS 2200 - 2.02.C16075-002 16075 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Heat Shrink Markers - 2.02.D16075-003 16075 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

Report r_sb_01_c_01

Item No.

CMSA - Wet Weather Improvement

Open Submittal Log - Sorted by Submittal No.

Project No:Job No: 061-0491.01

07-01 Page:Date: 1/31/2008

2 of 2

Submittal TitlePackage Rev. FinishRequired

Status Rcvd. Sent Return Forward BICLatest Dates

Central Marin Sanitation Agency

149 Raceway ID SS - 2.0316075-004 16075 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Type TC Wire- 2.02.A&B16123-001 16123 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Typw TC Inst. Cable - 2.03.A&B16123-002 16123 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Terminal Products16123-003 16123 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Cable Pulling Lubricant - 2.06.C16123-004 16123 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Noalox Anti-Oxident Compound16123-005 16123 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Allied GRS Conduit - 2.01.A16133-001 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Luquidtight Flex Conduit - 2.01.B16133-002 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 PVC GRS Conduit - 2.01.C16133-003 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Schd 80 PVC Rigid Conduit - 2.01.D16133-004 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Misc. Electrical Fittings- 2.02.A16133-005 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Appleton Conduit Bodies - 2.02.B16133-006 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 XJG Expansion Joints - 2.02.C16133-007 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 XD Expan/Deflec. Coupling - 2.02.D16133-008 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Conduit Seals - 2.02.E16133-009 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 PVC Coated Couplings - 2.02.F16133-010 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 PVC/SS pipe Straps - 2.02.G & H16133-011 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Metal Framing Channels 2.02.I16133-012 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Wall Seals16133-013 16133 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 FS/FD Indoor Cast Boxes - 2.02.B16134-001 16134 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 FS/FD Outdoor Cast Boxes - 2.02.C16134-002 16134 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Single Gang Boxes/Covers - 2.03.A16134-003 16134 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Double Gang Boxes/covers - 2.03.B16134-004 16134 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 SS 4X Enclosures - 2.05.A16134-005 16134 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Submersible Cast Boxes - 2.05.B16134-006 16134 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Miscellaneous Fasteners16134-007 16134 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 NEMA12 Enclosure - 2.02.A16135-001 16135 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 NEMA 4 Enclosure - 2.02.B16135-002 16135 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 NEMA 4 Emclosure Wall - 2.02.B16135-003 16135 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 NEMA 7 Enclosure - 2.02.C16135-004 16135 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 15 A 240 V Plugs/Receptacles - 2.0416140-004 16140 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 480 V Plugs/Recepticles - 2.0516140-005 16140 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Surge Suppresion Recepticles - 2.0616140-006 16140 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 UPS Receptacles - 2.0716140-007 16140 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Local PB Motor Control Sta. - 2.0816140-008 16140 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Al Control Enclosures - 2.08.D16140-009 16140 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Pilot Devices - 2.0916140-010 16140 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008

149 Cord connector Grips - 2.1016140-011 16140 001 R&R 1/9/2008 1/10/2008 1/21/2008 WESTWATR1/22/2008