4
Building the Future Current Activities this Week : Mass Excavation : Backfilling of on-grade seating is ongoing in Area 3. Site Utilities : Storm Sewer Installation (Line 6000) is nearly complete on the east side of France Family Drive. Sanitary Sewer Line E is underway. Foundations : Area 3 Field Level – Foundation installation continues on the east side of the site. Concrete Flatwork : Area 1 – Slab-on-grade is placed at field level to Column line 15. Concourse Level Slab-on-Metal deck is in place to Column line 6. Structural Steel Erection : Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8). Area 3 – Steel erection in Sequence 3-2 is complete. Installation of metal deck is ongoing in Sequence 3-2. Precast Concrete : Area 2 – Precast erection is ongoing and is currently set to Column Line 13. Underground MEP : Electrical for Electrical Room 01.12.01 is ongoing. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 8.11.2010 Re: Wizards Stadium Project Update – Week of 8.9.2010 Area 3 – Installation of Storm Line 6000 inlet boxes is complete on the east side of France Family Drive. Area 2 – Precast erection is ongoing at the south elevation. Currently being placed between Column Lines 12.4 - 13. Field Level Area 3 – Foundation walls for Elevator Pit 1 have been placed.

Construction Update 08-11-2010

Embed Size (px)

Citation preview

Page 1: Construction Update 08-11-2010

Building the Future

Current Activities this Week:

Mass Excavation:

Backfilling of on-grade seating is ongoing in Area 3.

Site Utilities:

Storm Sewer Installation (Line 6000) is nearly complete

on the east side of France Family Drive. Sanitary Sewer

Line E is underway.

Foundations:

Area 3 Field Level – Foundation installation continues on

the east side of the site.

Concrete Flatwork:

Area 1 – Slab-on-grade is placed at field level to

Column line 15. Concourse Level Slab-on-Metal deck is

in place to Column line 6.

Structural Steel Erection:

Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8).

Area 3 – Steel erection in Sequence 3-2 is complete.

Installation of metal deck is ongoing in Sequence 3-2.

Precast Concrete:

Area 2 – Precast erection is ongoing and is currently set

to Column Line 13.

Underground MEP:

Electrical for Electrical Room 01.12.01 is ongoing.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 8.11.2010

Re: Wizards Stadium Project

Update – Week of

8.9.2010

Area 3 – Installation of Storm Line 6000 inlet

boxes is complete on the east side of France

Family Drive.

Area 2 – Precast erection is ongoing at the

south elevation. Currently being placed

between Column Lines 12.4 - 13.

Field Level Area 3 – Foundation walls for

Elevator Pit 1 have been placed.

Page 2: Construction Update 08-11-2010

Building the Future

MEP Rough-in:

Area 2 – Shallow electrical and plumbing rough-in is

ongoing. Ductwork installation on Suite and Press Levels

are ongoing. Plumbing rough-in is ongoing on Suite and

Press Levels. Fire Protection Mains are being installed on

Suite Level.

Metal Stud Framing:

Area 1 – Metal stud framing for Concourse, Suite and Press

Levels are ongoing.

Masonry:

Area 1 Field Level – Masonry wall installation is ongoing

in Areas G and H.

Area 1 Concourse Level – Picture framing is nearly complete

for south concourse buildings. Layout for north buildings

are ongoing.

Projected Activities occurring next Week:

Mass Excavation:

Backfilling of foundations areas will continue in Area

3.

Site Utilities:

Installation of the Storm Line 6000 on the East Side (France

Family Drive) of the site will be complete. Sanitary Sewer

installation will begin at locations where Storm Line 6000

is complete.

Deep Underground MEP:

Deep Plumbing installation has started in Area 3.

Foundations:

Area 3 Field Level – Foundation installation will continue.

Concrete Flatwork:

Area 3 Concourse Level – Concrete placement for Slab-on

Metal Deck will continue.

Area 1 – Shot of the West Building from the

east concourse.

Field Level Area 1 – Masonry is ongoing at

the Field Level.

Area 1 – Canopy truss erection is ongoing

and is currently set to Column Line 21.

Page 3: Construction Update 08-11-2010

Building the Future

Area 1, 2 and 3 Field Level – Installation of on-grade seating

risers and intermediate stairs will continue.

Structural Steel Erection:

Decking/Detailing of Structural Steel in Sequence 3-2 will

continue.

Erection of the Canopy Trusses will continue in

Sequence 1-8.

Underground MEP:

Deep underground plumbing will continue in Area 3.

MEP Rough-in:

MEP Rough-in at Suite and Press Levels will continue.

Ductwork installation on Press Level will continue. Fire

Sprinkler mains and branch line installation will continue on

Suite Level.

Metal Stud Framing:

Area 1 – Metal stud framing for Concourse, Suite and Press

Levels will continue.

Roof Level Area 1 – Installation of the West

Building roof has started. Protection board

and vapor barrier installation seen here.

Area 1 – Stair 6 installation is ongoing and is

currently erected to Suite Level.

Page 4: Construction Update 08-11-2010

Building the Future

Additional Photos:

Press Level Area 1 – Ductwork installation

has started.

Field Level Area 2 – Precast header installed

at Southeast Truck Drive.

Concourse Level Area 1 – Southwest Terrace

Area concrete installation is nearly

complete.

Roof Level Area 1 – Mechanical Unit roof

curbs have been set.

Area 1 – Shot (looking west) of the canopy

trusses at Column Lines 22 and 23.

Suite Level Area 1 – Installation of fire

sprinkler mains are ongoing on Suite Level.