Building the Future
Current Activities this Week:
Mass Excavation:
Backfilling of on-grade seating is ongoing in Area 3.
Site Utilities:
Storm Sewer Installation (Line 6000) is nearly complete
on the east side of France Family Drive. Sanitary Sewer
Line E is underway.
Foundations:
Area 3 Field Level – Foundation installation continues on
the east side of the site.
Concrete Flatwork:
Area 1 – Slab-on-grade is placed at field level to
Column line 15. Concourse Level Slab-on-Metal deck is
in place to Column line 6.
Structural Steel Erection:
Area 1 – Main Canopy Truss Erection is ongoing (Seq 1-8).
Area 3 – Steel erection in Sequence 3-2 is complete.
Installation of metal deck is ongoing in Sequence 3-2.
Precast Concrete:
Area 2 – Precast erection is ongoing and is currently set
to Column Line 13.
Underground MEP:
Electrical for Electrical Room 01.12.01 is ongoing.
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 8.11.2010
Re: Wizards Stadium Project
Update – Week of
8.9.2010
Area 3 – Installation of Storm Line 6000 inlet
boxes is complete on the east side of France
Family Drive.
Area 2 – Precast erection is ongoing at the
south elevation. Currently being placed
between Column Lines 12.4 - 13.
Field Level Area 3 – Foundation walls for
Elevator Pit 1 have been placed.
Building the Future
MEP Rough-in:
Area 2 – Shallow electrical and plumbing rough-in is
ongoing. Ductwork installation on Suite and Press Levels
are ongoing. Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection Mains are being installed on
Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Concourse, Suite and Press
Levels are ongoing.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas G and H.
Area 1 Concourse Level – Picture framing is nearly complete
for south concourse buildings. Layout for north buildings
are ongoing.
Projected Activities occurring next Week:
Mass Excavation:
Backfilling of foundations areas will continue in Area
3.
Site Utilities:
Installation of the Storm Line 6000 on the East Side (France
Family Drive) of the site will be complete. Sanitary Sewer
installation will begin at locations where Storm Line 6000
is complete.
Deep Underground MEP:
Deep Plumbing installation has started in Area 3.
Foundations:
Area 3 Field Level – Foundation installation will continue.
Concrete Flatwork:
Area 3 Concourse Level – Concrete placement for Slab-on
Metal Deck will continue.
Area 1 – Shot of the West Building from the
east concourse.
Field Level Area 1 – Masonry is ongoing at
the Field Level.
Area 1 – Canopy truss erection is ongoing
and is currently set to Column Line 21.
Building the Future
Area 1, 2 and 3 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Structural Steel Erection:
Decking/Detailing of Structural Steel in Sequence 3-2 will
continue.
Erection of the Canopy Trusses will continue in
Sequence 1-8.
Underground MEP:
Deep underground plumbing will continue in Area 3.
MEP Rough-in:
MEP Rough-in at Suite and Press Levels will continue.
Ductwork installation on Press Level will continue. Fire
Sprinkler mains and branch line installation will continue on
Suite Level.
Metal Stud Framing:
Area 1 – Metal stud framing for Concourse, Suite and Press
Levels will continue.
Roof Level Area 1 – Installation of the West
Building roof has started. Protection board
and vapor barrier installation seen here.
Area 1 – Stair 6 installation is ongoing and is
currently erected to Suite Level.
Building the Future
Additional Photos:
Press Level Area 1 – Ductwork installation
has started.
Field Level Area 2 – Precast header installed
at Southeast Truck Drive.
Concourse Level Area 1 – Southwest Terrace
Area concrete installation is nearly
complete.
Roof Level Area 1 – Mechanical Unit roof
curbs have been set.
Area 1 – Shot (looking west) of the canopy
trusses at Column Lines 22 and 23.
Suite Level Area 1 – Installation of fire
sprinkler mains are ongoing on Suite Level.