    Thursday, August 20, 2015

    Briefing 

     for:

    Briefing 

    on:

    DC  CLEAN  RIVERS PROJECT 

    First  

    Street  

    Tunnel 

    Construction 

    Update 

    and  

    Community  

    Mitigation 

    Measures

    First  

    Street  

    Tunnel  

    Forum/Community  

    Group

    District of Columbia Water and Sewer AuthorityGeorge S. Hawkins, General Manager 

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    2/40

    Tunnel ForumRepresentatives and Alternates

    Location/Group Representative Alternate

    First Street NW Dr. Marilyn Lashley Tomas Encaracion

    Bryant / Channing Streets Renee Peres Philomena FritzFlagler Place Victoria Leonard Pia Brown

     Adams Street Shelly Parker Dianne Barnes

    W Street Joe Levesque Neal Herman

    First and V Streets Angela Ray Theodore Bush and Derrick Jones

    U Street Serita Sanders Jean Marie Thomas

    Thomas St / Rhode Island Ave Chris Von Ferro Vacant

    Local Blogs Scott Roberts Betsy McDaniel

    Government Austin Pearl, ANC 5E Teri Janine Quinn, ANC 5E

    Bertha Holliday, ANC 5E

    Laisha Dougherty, Councilmember 

    McDuffie’s office, Ward 5

    Civic Associations Sherry Howard John MacNeil

     All meetings are open to the public. 2

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    3/40

    Welcome and Introductions

    Meeting Dates for 2015 and 2016

    Two-Month Construction Update at

    Construction Staging Areas (CSAs) Channing Street CSA

     Adams and Flagler CSA First and V CSA

    First and Thomas CSA (Pumping Station)

    Long-Range Construction Schedule

    and Progress

    3

    Update on CommunityMitigation Measures

    Responses to Residents’

    Concerns

    Saturday Work

    Security and Safety withinConstruction Staging Areas

    First and V Streets CSA

    published

    Tree Planting Initiative Project Display Boards at Two

    CSAs

    FEMS Doorway Mural Project

    Next Steps/Save the Date

    Agenda

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    4/40

    MEETING 

    DATES 

    FOR 

    2015 

    AND 

    2016

    Tom Lindberg and John Kennedy, DC Water 

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    5/40

    Meeting Dates for 2015 and 2016

    Discussion Topic Meeting Date* Location

    First Street Tunnel (FST) Project Update January 22, 2015 St. George’s Episcopal Church

    Naming of the Tunnel Boring Machine (TBM) February 26, 2015 First Street Tunnel Project Office

    FST update, TBM Naming Process and Ceremony March 26, 2015 St. George’s Episcopal Church

    TBM Naming Ceremony April 14, 2015 Channing Street CSA

    FST update, TBM naming ceremony, small diameter

    water main project, Doors of Perception murals at

     Adams St CSA

    May 28, 2015 St. George’s Episcopal Church

    Construction Update for Adams Street and Flagler

    Place Residents

    June 10, 2015 Adams Street Construction

    Staging Area

    Proposal to Extend Construction Work Hours June 27, 2015 St. George’s Episcopal Church

    FST Project Update August 20, 2015 St. George’s Episcopal Church

    FST Update and Landscaping and Restoration Plans October 22, 2015 St. George’s Episcopal Church

    FST Hard Hat Site Tour October 24, 2015 Assembly location TBD

    FST Update and Landscaping and Restoration Plans January 22, 2016 St. George’s Episcopal Church

    FST Update and Landscaping and Restoration Plans March 24, 2016 St. George’s Episcopal Church

    5

    * Meeting dates are subject to change.

    There will be no Tunnel Forum meetings in November and December 2015.

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    6/40

    TWO‐

    MONTH 

    CONSTRUCTION 

    UPDATE 

    AT CONSTRUCTION STAGING AREAS

    Scott Hoffman and Thomas March, SKJD

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    7/40

    Channing StreetConstruction Staging Area

    MiningShaft

    ExcavationStockpile

    Electrical/Mechanical

    Site Office

    7

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    8/40

    Channing StreetConstruction Staging Area

    Launch Tunnel Boring Machine, July 2015

    Hard Hat Tour, October 24, 2015 Mining in progress, ongoing – November 2015

    8

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    9/40

    Lucy’s Progress (shown in purple)

    9

    First Street Tunnel

    Channing Street NW

    F i  r  s  t   S  t  r  e e t  NW

    Channing

    Street CSA

    McMillan

    Reservoir 

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    10/40

    Adams and Flagler IntersectionConstruction Staging Area

    Building entrance

    Construction traffic entrance and exit

    CSA

    CWZ

    Road Closed ‒ No thru

    traffic. Local access onlyat intersection of FirstStreet and Adams Street).

     Abbreviations

    CSA ‒ Construction Staging AreaCWZ ‒ Construction Work Zone

    FEMS ‒ Fire and EMS Department

    CSA

    CWZ

    FEMS Access Zone

    4’-wide Pedestrian Sidewalk

    Local Traffic

    10

    14 feet

    55 feet

    Fire department

    ladder truck clearances

    Legend 

       F   l  a  g   l  e  r   P   l

     Adams St

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    11/40

    Adams and Flagler IntersectionConstruction Staging Area

    Shaft excavation completed

    Construction of sewer flume completed  Adams shaft liner 50% complete, finish early

    September 

    Construct near surface structures, started April2015 – ongoing

     Adit excavation and lining, starting September

    2015 Micro Tunnel Boring Machine setup and lining,

    starting November 2015

    11

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    12/40

    Adams and First IntersectionConstruction Work Zone

    Concrete barrier

    with 6-foot-highchain link fence

    8-foot-high chain linkfence all around

    Traffic sand drum

     Adams Street NW 

    12

    N

    Freeze pipes installed at the corner ofFirst and Adams where adit tunnelwill connect to First Street Tunnel.

    Concrete barrier with6-foot-high chain link fence

    Open North-Southsidewalk to pedestrians

        F    i   r   s    t    S    t   r   e   e    t    N    W

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    13/40

    This page intentionally left blank.

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    14/40

    First and V IntersectionConstruction Staging Area

    V Street

       F   i  r  s   t

       S   t  r  e  e   t

    Legend 

    CSA

    CLC

    CSA

    CLC

    4'-wide pedestrian walkway

    FEMS access zone

    Building entrance

    Construction traffic entrance & exit

    CSA ‒ Construction Staging Area

    CLC ‒ Construction Lane ClosureFEMS ‒ Fire and EMS Department

     Abbreviations

    Sidewalk at

    V Street has

    been shiftedto allow FST

    access to

    storm drains

    14 feet

    55 feet

    Fire department

    ladder truck clearances

    Local Traffic

    14

    Currentlyfenced

    Securityfencingin place

    Will notbefenced

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    15/40

    First and V IntersectionConstruction Staging Area

    Completed shaft cast-in-place liner 

    Construction of sewer flume has started Verizon support work completed

    Freeze system and formation completed, adit

    mining started Construct near surface structures, started in

    May 2015 – ongoing

    Continued closure of First and V Streetsintersection

    15

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    16/40

    Plan View of First and V StreetsConstruction Staging Area

     Alley

    Shaft

     Adit

    Chiller Unit for Freeze

     Adit

     A A

    N

    16

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    17/40

    V Street Profile View Adit Construction

    Section B-B

    B

    B

    TBM Tunnel

    Connection to be made after

    TBM tunnel complete

     AlleyStreet Level

    Ventilation Fan 75 HP

    17

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    18/40

    Adit Excavation Cycle (Section A–A)

    Freeze Pipes

    Roadheader Small Loader 

    MuckBox

    Re-establish Freeze Pipe

    Shotcrete support as

    soon as lattice girdersand mesh installed

    Excavation Steps:

    1. Excavation maximum 6 feet, remove freeze pipes

    2. Erect lattice girder and wire mesh

    3. Shotcrete

    4. Re-establish freeze pipe in invert

    Current

    CycleNext

    Cycle

    18

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    19/40

    Equipment to be Used

    Roadheaderbeing fabricated .

    Roadheader finished product.

    Shotcrete plant setup. Roadheader excavating V Street adit.

    19

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    20/40

    Legend CSA

    CLC

    CSA FEMS accesszone

    Building entrance

    Construction traffic entrance and exit

    CSA ‒ Construction Staging AreaCLC ‒ Construction Lane Closure

    FEMS – Fire and EMS Department

     Abbreviations

    First and Thomas IntersectionConstruction Staging Area (Pumping Station)

    14 feet

    55 feet

    Fire department

    ladder truck clearances

    Local Traffic

    20

    30-inch sewer line replaced

    mid-September; restrictedto one lane with flaggers.

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    21/40

    First and Thomas IntersectionConstruction Staging Area (Pumping Station)

    Construct shaft cast-in-placeliner, July 2015 – August 2015

    Freeze system completed andadit formation in progress

    Construct near surface

    structures, started inMay 2015 – ongoing

     Adit excavation and lining,

    starting September 2015

    21

    Excavation of the pumping station dropshaft is complete. Installation of the

    cast-in-place liner is 60% complete.

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    22/40

    Production, Delivery, andPlacement of Concrete

    SKJD makes every effort to schedule concrete pours

    during regular work hours:

    Monday thru Friday, 7 AM to 7 PM; on Saturdays, 9 AM to 5 PM

    However, there have been times at all First Street Tunnel

    construction sites when concrete pours must continue

    beyond normal work hours:

    Concrete plants are independent suppliers and there can be

    problems at the plant, causing delays

    Concrete trucks are independent suppliers traveling on publicroads; traffic congestion and detours can cause delays

    Concrete placement requires all SKJD equipment to be

    completely functioning and fully staffed

    22

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    23/40

    Reported Incident on August 14at Adams Street CSA

    The contractor experienced an equipment problem with the main cranelast Friday evening at the Adams and Flagler Construction Staging Area

    The contractor then mobilized its secondary crane to access the shaft

    The crew in the shaft were detained while the second crane was putinto position

    The main crane began working and the work wrapped up

    These types of activities can and do occur with complex construction

    projects. They are not uncommon, and contingency plans and actionsare in place to address equipment issues, interruptions, and otherdisturbances.

    23

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    24/40

    LONG‐

    RANGE 

    CONSTRUCTION 

    SCHEDULE AND PROGRESS

    Scott Hoffman, SKJD and John Kennedy, DC Water 

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    25/40

    25

    Long-Range Construction Schedule

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    26/40

    Division P – First Street Tunnel

    Progress at-a-Glance as of July 31, 2015; 63% complete

    TBM Mining and Lining

    • Installed temporary ringsand launch frame

    • Started mining throughshaft wall

    • Installed Ring No. 8

    V Street NCS-DC

    • Continue excavating

    • Installing bracingLevels 1 and 2

    • Exposed sewer line

    V Street Adit Tunnel

    • Started Sequential

    Excavation Method(SEM)

    Pump Station – Drop Shaft

    • Continue freeze

    formation at drop shaftand adit

    • Installed rebar, concreteforms and poured invertslab

    • Installed rebar, concrete

    forms and pouredconcrete for CIP LiftNo. 1

    Adams Street – Drop Shaft

    • Finished shaft excavation

    • Installed rebar, concreteforms and poured invertslab

    AS – Diversion Chamber 

    • Continue installing andwelding wales forbracing Levels 1 and 2

    • Demo existing sewer

    pipe and installed flumepipe

    26

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    27/40

    UPDATE 

    ON 

    COMMUNITY MITIGATION MEASURES

    John Kennedy, DC Water 

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    28/40

    Responses to Residents’ Concerns

    Employee parking outside of designated areas

    Ticketed and towed vehicles when identified

    Loud equipment backup alarms and air horns

    Replaced some equipment/vehicle with static alarms and reduced air horn

    usage with buzzer (OSHA requirement)

    Queuing concrete and dump trucks at Construction Staging Areas

    (CSAs)

    Increased awareness to stage trucks at Channing Street CSA

    Loud noise from First and V Streets CSA at night

    Insulated cylinder pressure relief to avoid venting from temperature

    changes

    28

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    29/40

    Responses to Residents’ Concerns

    Metropolitan Police Department officer stationary in patrol vehicle

    Directed officer to periodically foot patrol around CSAs

    Obstructed view around First and V Streets CSA due to sound

    blankets

    Removed some blankets on First Street at the north end of CSA Increased speeding in east alleyway

    Installed collapsible fence, bollards, and additional signage to reduce traffic

    Inadequate lighting at First and V Streets and Adams Street andFlagler Place Construction Staging Areas

    Installed additional perimeter lighting around CSAs

    29

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    30/40

    Saturday work efforts at each of the Construction Staging

     Areas (CSAs) will continue

    Saturday work hours are from 9  AM to 5 PM, and occur as

    weather and the contractor’s schedule allows

    The additional work day is necessary to make up for timelost during delays in the construction schedule (i.e., utility

    relocations, inclement weather conditions, extensive water

    main replacement at Adams Street and Flagler Place)

    If you have questions, please call the First Street Tunnel

    Hotline at 1-844-FST-INFO (1-844-378-4636)

    Saturday Work

    30

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    31/40

    Security and Safety withinConstruction Staging Areas

    The Construction Staging Areas

    (CSAs) house large trucks, construc-

    tion equipment, and tools and havedeep, open excavations

    The CSAs are closed to the public

    Security personnel are onsite duringoff hours

    SKJD has installed security lighting and cameras

    31

    To better ensure your safety and the

    safety of your children and pets, donot enter a Construction Staging Area.

    Fencing signage at First and V Streets CSA.

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    32/40

    First and V Streets CSA published! 

    32

    The First Street Tunnel project

    was shown in an advertisement

    in the August 2015 geotechnical

    magazine, Geostrata

    First and V Streets Construction Staging Areashown in geotechnical periodical, Geostrata.

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    33/40

    DC Water and District Department ofTransportation Tree Planting Initiative

    33Chinese PistacheCrepe Myrtle Magnolia

    Community requested tree planting plan

    DC Water is ready to provide funds to DDOT

    DDOT will work with community members to coordinate plan and determineplanting locations

    DC Water and SKJD will present landscaping and restoration plans in

    October 2015 and will continue discussions through March 2016

    35 native trees to be planted in Bloomingdale

    P j t Di l B d t T

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    34/40

    Project Display Boards at TwoConstruction Staging Areas

    There are currently 17 display boards that provide information

    on the DC Clean Rivers Project and First Street Tunnel

    On Tuesday, August 18, the DC Clean Rivers team installed

    two sets of the display boards on the outer facing fences of

    the Construction Staging Areas. One set each at:

    First and V Streets Construction Staging Area

    First and Thomas Streets Construction Staging Area

    The following pages show where the display boards werepositioned along the fences at both Construction Staging

     Areas

    34

    Di l t Fi t d V St t

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    35/40

    Displays at First and V StreetsConstruction Staging Area (1 of 3)

    35

    V StreetNW

    First Street and V Street NWLooking South

    First Street NW

    Di l t Fi t d V St t

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    36/40

    Displays at First and V StreetsConstruction Staging Area (2 of 3)

    36

    First Street and V Street NWLooking West

    V StreetNW

    First Street NW

    Di l t Fi t d V St t

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    37/40

    Displays at First and V StreetsConstruction Staging Area (3 of 3)

    37

    First Street and V Street NWLooking Northwest

    V StreetNW

    First Street NW

    Displays at First and Thomas Streets

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    38/40

    Displays at First and Thomas StreetsConstruction Staging Area

    38

    First Street and Thomas Street NWLooking West

    Thomas Street NW

    sidewalk 

     patio house

    FEMS Doorway Mural Project at

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    39/40

    FEMS Doorway Mural Project atAdams and Flagler CSA

    39

    The mural painting ofthe doors at Adams and

    Flagler CSA is currentlyunderway

    The first ten doors will becompleted in September 

    The remaining doors, 11thru 31, will be deliveredin October/November 

    Nessar paints a tribute to the environment (left) andDC Water’s Clean Rivers Project logo.

  • 8/20/2019 DC Water 1st Street Tunnel Construction Update 2015 08 20

    40/40

    Next Steps/Save the Date

    Next Tunnel Forum Meeting on Thursday, October 22 at

    7 PM, at St. George’s Episcopal Church

    Save the date: First Street Tunnel hard hat tour day on

    Saturday, October 24 at 10 AM. (Rain date is Saturday,

    November 7). Logistic details to come.

    Topics for next meeting: Landscaping and restoration of

    disturbed areas

    For updates, go to

    www.dcwater.com/firststreettunnel or

    call 1-844-FST-INFO (1-844-378-4636)for First Street Tunnel Construction Issues